Deep foundation jet concrete fast slip form construction equipment

By using construction tractors and a sliding formwork system to automatically recover excess concrete and fill depressions, the problems of dust pollution, high rebound rate, and uneven thickness of shotcrete in deep foundation pit construction have been solved, thus improving construction efficiency and quality.

CN119083441BActive Publication Date: 2025-12-26THE 2ND ENG CO LTD OF CHINA RAILWAY 17 BUREAU GRP
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
CN202411508081.6
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-11-06
Publication Date
2025-12-26
Estimated Expiration
2044-11-06

AI Technical Summary

Technical Problem

Existing technologies for shotcreting in deep foundation pit construction suffer from serious dust pollution, high rebound rate, low efficiency, uneven thickness, and unstable quality. They are particularly inconvenient for deep foundation pit operations and cannot effectively recover excess concrete or fill depressions.

Method used

The system employs a construction vehicle and a sliding formwork system, including a drive arm structure and a sliding formwork. The sliding formwork is equipped with a collection ramp, a material retaining trough, a material storage trough, a return trough, and a sand pump, which can automatically recover excess concrete and fill depressions. The sand pump and air valve strips enable the recycling of concrete.

Benefits of technology

It improved the safety and efficiency of deep foundation pit construction, reduced material waste, simplified cleaning work, and ensured wall quality and construction progress.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119083441B_ABST
    Figure CN119083441B_ABST
Patent Text Reader

Abstract

The application discloses a kind of deep foundation pit shotcrete fast slipform construction equipment, it is related to foundation pit construction equipment technical field, including construction locomotive, drive arm structure and sliding formwork, drive arm structure is set in construction locomotive front side, sliding formwork is installed in drive arm structure end, sliding formwork includes outer frame plate, inner plastering flat plate and sand pump, opening is set in outer frame plate, and installation groove one is opened in lower part, inner plastering flat plate is fixedly arranged in installation groove one, and collection inclined plane is opened in inner plastering flat plate middle part, and preformed surface is opened in inner plastering flat plate lower part, and material retaining groove is opened between preformed surface and collection inclined plane.The application is used by construction locomotive to control sliding formwork, so it is more convenient to handle operation to deep foundation pit inner wall surface, and through sliding formwork internal structure can automatically complete excess concrete recycling and recess filling, to greatly improve wall surface quality and reduce subsequent cleaning work.
Need to check novelty before this filing date? Find Prior Art

Description

TECHNICAL FIELD

[0001] The present application relates to the technical field of foundation pit construction equipment, in particular to a deep foundation pit concrete spraying rapid slip form construction equipment. BACKGROUND

[0002] At present, deep foundation pit support mainly adopts support means such as enclosure pile, anchor rod, steel bar mesh and sprayed concrete, and the sprayed concrete is an important link of the support. With the progress of technology, it is usually completed by relying on wet spraying mechanical hand. Although the technology is very mature and the degree of mechanization is very high, there are still some problems that cannot be ignored in practice, which have been bothering technical workers. Mainly manifested in: there is a lot of dust during the sprayed concrete operation, and the working environment is poor; even if the advanced wet spraying equipment is used, it is difficult to get substantial improvement, which seriously threatens the occupational health; the concrete rebound rate is too high during the sprayed concrete operation, which is generally more than 30% under normal circumstances, and the concrete rebound rate is even higher at positions such as soil seepage between enclosure piles, which wastes a lot of concrete materials, increases the engineering cost and cleaning workload, and is not conducive to civilized construction management; the sprayed concrete operation efficiency and the foundation pit excavation speed are not very matched, and when the sprayed concrete thickness is large due to the collapse of soil between piles, multiple and multi-layer implementation is required to reach the design thickness, which occupies a lot of process time, restricts the foundation pit excavation progress and has a certain impact on the overall construction progress; uneven sprayed concrete thickness, difficulty in reaching the standard strength, uneven surface and unstable quality are common quality problems of sprayed concrete operation, which seriously threatens the stability of deep foundation pit.

[0003] The patent document with publication number CN211897733U discloses a troweling device for concrete processing, which comprises a roller frame, a rotating shaft is fixed between the roller frames by welding through a bearing, a roller is fixed on the outer surface of the rotating shaft by welding, a fixed bearing is fixed on the side of the roller frame away from the roller by welding, a connecting rod is fixed on the end surface of the fixed bearing by welding, a scraper is fixed on the bottom surface of the connecting rod by welding, a support plate is fixed on the end of the connecting rod away from the roller frame through a fixed bearing by welding, a plate groove is formed on the side of the support plate away from the fixed bearing, a rolling bearing is connected in the plate groove by rolling, a bolt is fixed on the end surface of the rolling bearing by welding, a nut is threadedly connected with the outer surface of the bolt, a rotating device is arranged on the outer surface of the bolt, and a hand pushing rod is fixedly connected with the rotating device. The troweling device for concrete processing can make the roller frame move upward by driving the rotating device through the hand pushing rod, so that the roller can flatten the uneven concrete.

[0004] The troweling device provided by the above technical scheme can be used for wall concrete troweling, but it is small in size and inconvenient for deep foundation pit operation, and cannot recycle excess concrete or fill recesses, so the use effect needs to be improved. SUMMARY

[0005] The deep foundation jet concrete rapid slip form construction equipment aims to solve the problems of inconvenient deep foundation operation, inability to recycle excess concrete, and inability to fill the recesses, and improve the use effect.

[0006] The application solves the above technical problems through the following technical scheme, and comprises a construction vehicle, a driving arm structure and a slip form, the driving arm structure is arranged on the front side of the construction vehicle, the slip form is installed at the end of the driving arm structure, the slip form comprises an outer frame plate, an inner troweling plate and a sand pumping pump, an installation groove one with an open lower part is formed in the outer frame plate, the inner troweling plate is fixedly arranged in the installation groove one, a collecting inclined surface is formed in the middle part of the inner troweling plate, a reserved surface is formed in the lower part of the inner troweling plate, a material blocking groove is formed between the reserved surface and the collecting inclined surface, a storage groove, an installation groove two and a collecting groove are sequentially formed from top to bottom on the rear side of the inner troweling plate, a collecting opening is formed between the collecting groove and the material blocking groove, a caulking groove is formed between the storage groove and the outer wall on the front side of the inner troweling plate, a backflow groove is formed between the caulking groove and the collecting groove, the sand pumping pump is installed in the installation groove two, and the sand pumping pump is connected with the bottom of the collecting groove and the bottom of the storage groove through pipelines.

[0007] Preferably, at least one caulking opening is formed between the backflow groove and the outer wall on the front side of the inner troweling plate.

[0008] Preferably, a plurality of air flap strips are installed on the inner wall of the backflow groove, and the air flap strips are arranged below the caulking groove and the caulking opening.

[0009] Preferably, an auxiliary material discharging assembly for preventing blockage in the collecting opening is arranged between the outer frame plate and the inner troweling plate, the auxiliary material discharging assembly comprises a roller, a connecting piece and a driving motor, a containing groove is formed at the connection between the collecting opening and the collecting inclined surface, one end of the roller is rotatably installed on the inner wall of the containing groove, a placing groove is formed in one side of the outer frame plate, the driving motor is installed in the placing groove, and the connecting piece is installed at the output end of the driving motor with the small contact surface of the connecting piece being fixedly connected with the roller.

[0010] Preferably, a plurality of pushing pieces are uniformly installed on the edges of the roller.

[0011] Preferably, a variable frequency vibrator is installed on the rear side of the outer frame plate.

[0012] Preferably, the driving arm structure comprises a fixed arm, an adjusting arm, a three-joint block, a first adjusting oil cylinder and a mechanical joint, the fixed arm is fixedly installed on the construction vehicle, the three-joint block is rotationally connected with the fixed arm, the first adjusting oil cylinder is rotationally installed on the fixed arm, one end of the three-joint block is rotationally installed on the output end of the first adjusting oil cylinder, the adjusting arm is fixedly connected with the three-joint block, and the mechanical joint is rotationally connected with the end of the adjusting arm and the outer frame plate respectively.

[0013] Preferably, the driving arm structure further comprises a second adjusting oil cylinder, a hinged seat and a telescopic rod group, the second adjusting oil cylinder is rotationally installed on the end of the adjusting arm, the telescopic end of the second adjusting oil cylinder is rotationally connected with the upper side of the rear side of the outer frame plate, the hinged seat is rotationally connected with the lower side of the adjusting arm and the lower side of the rear side of the outer frame plate respectively, and one end of the telescopic rod group is rotationally installed on the lower side of the adjusting arm and the other end is rotationally installed on the hinged seat.

[0014] Preferably, the outer frame plate and the inner troweling plate are provided with a mounting assembly, recesses are formed on the inner walls of the mounting grooves, key grooves are formed on the sides of the inner troweling plate, the mounting assembly comprises metal positioning blocks and mounting springs, the metal positioning blocks are installed on the inner walls of the recesses through the mounting springs, the metal positioning blocks are clamped in the key grooves, and electromagnetic blocks are installed on the inner walls of the recesses.

[0015] Compared with the prior art, the present application has the following beneficial effects:

[0016] 1、The construction vehicle controls the use of the slipform, so that the deep foundation pit inner wall surface can be conveniently processed and operated, the construction personnel can be protected from dust, the efficiency is high, and the safety is good.

[0017] 2、The excess concrete can be automatically recycled and the recesses can be filled through the internal structure of the slipform, so that the wall surface quality can be greatly improved and the subsequent cleaning work can be reduced.

[0018] 3、The recesses are filled with recycled concrete during use, so that additional materials are not needed, the steps are greatly simplified, and the efficiency of material and wall surface processing is further improved. DETAILED DESCRIPTION

[0019] Figure 1 It is a side view of the present application;

[0020] Figure 2 It is a structure view of the slipform of the present application;

[0021] Figure 3 It is an exploded view of the slipform of the present application;

[0022] Figure 4Figure 6 is a rear view of the inner trowel plate of the present application;

[0023] Figure 5 Figure 7 is a side view of the inner trowel plate of the present application;

[0024] Figure 6 Figure 8 is a perspective view of the present application; Figure 5 Figure 9 is a structural view of the structure at A in Figure 8;

[0025] Figure 7 Figure 10 is a perspective view of the present application; Figure 5 Figure 11 is a structural view of the structure at B in Figure 10;

[0026] Figure 8 Figure 12 is a structural view of the auxiliary material discharging assembly of the present application;

[0027] Figure 9 Figure 13 is a structural view of the corrosion profile of the slip form of the present application.

[0028] Figure 14 is a structural view of the present application;

[0029] Construction vehicle; 2, drive arm structure; 3, three-head connecting block; 4, adjusting arm; 5, slip form; 6, second adjusting oil cylinder; 7, mechanical joint; 8, hinged seat; 9, variable frequency vibrator; 10, fixed arm; 11, telescopic rod group; 12, first adjusting oil cylinder; 13, outer frame plate; 14, inner trowel plate; 15, sand pumping pump; 16, collection slope; 17, reserved surface; 18, material blocking groove; 19, material storage groove; 20, mounting groove two; 21, collection groove; 22, collection port; 23, caulking groove; 24, backflow groove; 25, caulking port; 26, air flap strip; 27, auxiliary material discharging assembly; 2701, roller; 2702, connecting piece; 2703, drive motor; 28, actuating piece; 29, electromagnetic block; 30, mounting assembly; 3001, metal positioning block; 3002, mounting spring; 31, key groove. DETAILED DESCRIPTION

[0030] The above and other technical features and advantages of the present application will be described in more detail below with reference to the accompanying drawings.

[0031] Example One

[0032] This embodiment provides a technical solution: a deep foundation pit jet concrete rapid slip form construction equipment, such as Figures 1-5As shown, including construction locomotive 1, drive arm structure 2 and slip form 5, drive arm structure 2 is arranged in the front side of construction locomotive 1, slip form 5 is installed at the end of drive arm structure 2, through slip form 5, the wall surface after spraying concrete can be smoothed, through construction locomotive 1, slip form 5 can be conveniently moved to the vicinity of the wall surface, through drive arm structure 2, slip form 5 can be driven to move up and down on the wall surface and complete the smoothing operation, slip form 5 includes outer frame plate 13, inner smoothing plate 14 and sand pump 15, outer frame plate 13 is provided with mounting groove one with open lower part, inner smoothing plate 14 is fixedly arranged in mounting groove one, collecting slope 16 is arranged in the middle part of inner smoothing plate 14, and preformed surface 17 is arranged in the lower part of inner smoothing plate 14, when smoothing, the uppermost position of collecting slope 16 is in contact with the concrete on the wall surface and is smoothed, and there is a certain space between collecting slope 16 and preformed surface 17 and the concrete layer, when smoothing, inner smoothing plate 14 can scrape the excess concrete to the position of collecting slope 16, material blocking groove 18 is arranged between preformed surface 17 and collecting slope 16, and the concrete is extruded to material blocking groove 18 with downward movement, storage groove 19, mounting groove two 20 and collecting groove 21 are sequentially arranged from top to bottom at the rear side of inner smoothing plate 14, collecting opening 22 is arranged between collecting groove 21 and material blocking groove 18, the concrete moved to material blocking groove 18 can be recycled to collecting groove 21 through collecting opening 22, so that the excess concrete can be collected, material waste is reduced, and subsequent cleaning work is reduced, caulking groove 23 is arranged between storage groove 19 and the outer wall of the front side of inner smoothing plate 14, backflow groove 24 is arranged between caulking groove 23 and collecting groove 21, sand pump 15 is installed in mounting groove two 20, sand pump 15 is connected with the bottom of collecting groove 21 and the bottom of storage groove 19 through pipelines respectively, through sand pump 15, the concrete collected in collecting groove 21 can be pumped into upper storage groove 19, and when the concrete fills storage groove 19, the excess concrete is discharged from caulking groove 23 through pressure, the concrete can fill the recessed wall surface, when there is no recess, the concrete can flow into collecting groove 21 through backflow groove 24, and then can be circulated.

[0033] As shown in the specific implementation, Figure 5 and Figure 6 at least one caulking opening 25 is arranged between backflow groove 24 and the front side outer wall of inner smoothing plate 14, through caulking opening 25 and caulking groove 23, the recessed part can be filled multiple times, so that the filling is sufficient, similarly, when the concrete passes through the recessed wall surface, it can be filled through the distillation of caulking opening 25, when there is no recess, the concrete can flow into collecting groove 21 through backflow groove 24, and then can be circulated.

[0034] In a specific implementation, a plurality of air flap strips 26 are installed on the inner wall of the backflow groove 24, and the air flap strips 26 are arranged below the filling groove 23 and the filling opening 25. The air flap strips 26 can prevent the concrete from flowing directly downward from the backflow groove 24. When passing through the recess, the concrete can be preferentially discharged through the filling groove 23 and the filling opening 25 under the action of the air flap strips 26 to complete the filling. When there is no recess, the air flap strips 26 can be pushed downward by the pressure above, so that enough space can be formed between the air flap strips 26 and the backflow groove 24 for the concrete to flow downward.

[0035] In a specific implementation, as shown in Figure 5 , Figure 7 and Figure 8 , an auxiliary discharging assembly 27 for preventing blockage in the collection opening 22 is arranged between the outer frame plate 13 and the inner troweling plate 14. The auxiliary discharging assembly 27 includes a roller 2701, a connecting piece 2702, and a driving motor 2703. The connecting part between the collection opening 22 and the collection slope 16 is provided with a receiving groove. One end of the roller 2701 is rotatably installed on the inner wall of the receiving groove. The outer frame plate 13 is provided with a placing groove on one side. The driving motor 2703 is installed in the placing groove. The connecting piece 2702 is installed on the output end of the driving motor 2703 with a large contact surface, and the connecting piece 2702 is fixedly connected to the roller 2701 with a small contact surface. The driving motor 2703 can drive the connecting piece 2702 and the roller 2701 to rotate. When the roller 2701 rotates, the concrete at the collection opening 22 can be continuously pushed into the collection groove 21, thereby preventing blockage. A plurality of pushing pieces 28 are uniformly installed on the edges of the roller 2701. The pushing pieces 28 can further enhance the pushing effect.

[0036] In a specific implementation, as shown in Figure 1 , a variable frequency vibrator 9 is installed on the rear side of the outer frame plate 13. The variable frequency vibrator 9 can facilitate the vibration of the entire slip form 5 during troweling.

[0037] In a specific implementation, the driving arm structure 2 includes a fixed arm 10, an adjusting arm 4, a three-head connecting block 3, a first adjusting oil cylinder 12, and a mechanical joint 7. The fixed arm 10 is fixedly installed on the construction vehicle 1. The three-head connecting block 3 is rotatably connected to the fixed arm 10. The first adjusting oil cylinder 12 is rotatably installed on the fixed arm 10. One end of the three-head connecting block 3 is rotatably installed on the output end of the first adjusting oil cylinder 12. The adjusting arm 4 is fixedly connected to the three-head connecting block 3. The mechanical joint 7 is rotatably connected to the end of the adjusting arm 4 and the outer frame plate 13. The first adjusting oil cylinder 12 can control the three-head connecting block 3 to rotate with the fixed arm 10 as the center, so as to control the adjusting arm 4 and the slip form 5 to move up and down, thereby facilitating the control of the slip form 5 to move up and down on the wall surface.

[0038] In the specific implementation, the driving arm structure 2 further comprises a second adjusting oil cylinder 6, a hinged seat 8 and a telescopic rod set 11. The second adjusting oil cylinder 6 is rotatably installed at the end of the adjusting arm 4, and the telescopic end of the second adjusting oil cylinder 6 is rotatably connected to the upper rear side of the outer frame plate 13. The hinged seat 8 is rotatably connected to the lower side of the adjusting arm 4 and the lower rear side of the outer frame plate 13, respectively. The telescopic rod set 11 is rotatably installed at one end of the lower side of the adjusting arm 4 and at the other end of the hinged seat 8. The telescopic rod set 11 can be controlled to rotate by the telescopic extension of the second adjusting oil cylinder 6, so that the sliding formwork 5 can be always closely attached to the wall surface when moving up and down. When the first adjusting oil cylinder 12 is extended, the second adjusting oil cylinder 6 is retracted. At this time, the adjusting arm 4 and the sliding formwork 5 move downward. The upper half of the sliding formwork 5 is rotatably driven by the second adjusting oil cylinder 6 to rotate the hinged seat 8, and the telescopic rod set 11 is extended and the end thereof is adaptively rotated. When the first adjusting oil cylinder 12 is retracted, the second adjusting oil cylinder 6 is extended. At this time, the adjusting arm 4 and the sliding formwork 5 move upward. The upper half of the sliding formwork 5 is rotatably driven by the second adjusting oil cylinder 6 to rotate the hinged seat 8, and the telescopic rod set 11 is retracted and the end thereof is adaptively rotated. Therefore, the sliding formwork 5 can be always closely attached to the wall surface when moving up and down.

[0039] In this embodiment, the wall surface sprayed with concrete can be smoothed by the construction equipment. The excess concrete can be automatically recycled and the recessed part can be filled by the internal structure of the sliding formwork 5 during smoothing, so as to greatly improve the wall surface quality and ensure the effective use of materials, prevent waste, and smooth the wall surface sprayed with concrete by the sliding formwork 5 during processing. The sliding formwork 5 can be conveniently moved to the wall surface by the construction vehicle 1, and the sliding formwork 5 can be moved up and down on the wall surface by the driving arm structure 2 and can be ensured to be tightly attached to the wall surface. It should be noted that the sliding formwork 5 needs to be operated from the top of the wall surface to the bottom. When the sliding formwork 5 moves downward, the uppermost position of the collection slope 16 contacts and smooths the concrete on the wall surface. There is a certain space between the collection slope 16 and the concrete layer. During smoothing, the inner smoothing plate 14 can scrape the excess concrete to the position of the collection slope 16, and the concrete is extruded to the material blocking groove 18 as it moves downward. The concrete above the material blocking groove 18 can be recycled into the collection groove 21 through the collection port 22, so as to collect the excess concrete, reduce material waste, and reduce subsequent cleaning work. The concrete collected in the collection groove 21 can be pumped into the upper storage tank 19 by the sand pumping pump 15. It should be noted that the storage tank 19 needs to be filled with concrete in the initial stage. The concrete in the storage tank 19 can be discharged from the caulking groove 23 under the action of pressure under the transfer of the sand pumping pump 15. The concrete can fill the recessed wall surface when it passes through the recessed wall surface. When there is no recess, the air flap strip 26 can be pushed downward by the upper pressure, so that enough space can be formed between the air flap strip 26 and the backflow groove 24 for the concrete to flow downward. Then the concrete can be circulated. The caulking port 25 and the caulking groove 23 can be filled for multiple times, so as to ensure sufficient filling, and thus the work of automatically collecting excess concrete and automatically filling recesses can be completed.

[0040] Embodiment Two

[0041] This embodiment is further optimized on the basis of the above-mentioned embodiments. The same technical solutions as above will not be described again. A structure is provided as follows:

[0042] In a specific implementation, as Figure 2 and Figure 9As shown, in a specific implementation, the mounting assembly 30 is arranged between the outer frame plate 13 and the inner plastering plate 14, recesses are arranged on both sides of the inner wall of the mounting groove one, key grooves 31 are arranged on both sides of the inner plastering plate 14 outside the recesses, the mounting assembly 30 comprises a metal positioning block 3001 and a mounting spring 3002, one side of the metal positioning block 3001 is mounted on the inner wall of the recess through the mounting spring 3002, the other side of the metal positioning block 3001 is clamped in the key groove 31, the electromagnetic block 29 is mounted on the inner wall of the recess, through the mounting assembly 30, the mounting between the outer frame plate 13 and the inner plastering plate 14 can be ensured to be stable, and the mounting and dismounting between the outer frame plate 13 and the inner plastering plate 14 can be quickly controlled.

[0043] In use, as shown Figure 9 The metal positioning block 3001 is clamped in the key groove 31 on one side, so that the connection between the outer frame plate 13 and the inner plastering plate 14 can be ensured to be stable, when the inner plastering plate 14 needs to be dismounted, the electromagnetic block 29 is connected with an external power supply, the electromagnetic block 29 can generate magnetism and attract the metal positioning block 3001, so that the metal positioning block 3001 can extrude the mounting spring 3002 and move to the direction of the electromagnetic block 29, when the metal positioning block 3001 is completely moved out of the key groove 31, the inner plastering plate 14 and the outer frame plate 13 are not in a fixed connection relationship, so that the inner plastering plate 14 and the outer frame plate 13 can be dismounted.

[0044] The above is only a preferred embodiment of the present application, which is only illustrative but not limiting of the present application. Those skilled in the art understand that many changes, modifications and even equivalents can be made to the present application within the spirit and scope defined by the claims of the present application, but all will fall within the protection scope of the present application.

Claims

1. A deep foundation jet concrete fast sliding form construction equipment, characterized in that, The utility model provides construction locomotive (1), drive arm structure (2) and slip form (5), drive arm structure (2) is arranged in construction locomotive (1) front side, slip form (5) is installed in drive arm structure (2) end, slip form (5) includes outer frame board (13), inner plastering flat board (14) and sand pump (15), the installation groove one of open -bottomed is set up in outer frame board (13), inner plastering flat board (14) is fixedly arranged in installation groove one, the middle part of inner plastering flat board (14) is set up with collection inclined plane (16), the lower part of inner plastering flat board (14) is set up with reservation surface (17), the reservation surface (17) is set up with material blocking groove (18) between collection inclined plane (16), the rear side of inner plastering flat board (14) is set up with storage groove (19), installation groove two (20) and collection groove (21) from top to bottom in proper order, collection groove (21) is set up with collection port (22) between material blocking groove (18), storage groove (19) is set up with caulking groove (23) between the front side outer wall of inner plastering flat board (14), caulking groove (23) is set up with backflow groove (24) between collection groove (21), sand pump (15) is installed in installation groove two (20), sand pump (15) is connected with the bottom of collection groove (21) and the bottom of storage groove (19) respectively through pipeline.

2. The construction equipment for rapid slip-form of deep foundation pit according to claim 1, characterized in that, At least one caulking port (25) is formed between the backflow groove (24) and the front side outer wall of the inner plastering flat board (14).

3. The construction equipment for rapid slip-form of deep foundation pit according to claim 2, characterized in that, A plurality of air flap strips (26) are installed on the inner wall of the backflow groove (24), and the air flap strips (26) are arranged below the caulking groove (23) and the caulking port (25), respectively.

4. The construction equipment for rapid slip-form of deep foundation pit according to claim 1, characterized in that, An auxiliary material discharging assembly (27) is arranged between the outer frame board (13) and the inner plastering flat board (14) to prevent blockage in the collection port (22), the auxiliary material discharging assembly (27) comprises a roller (2701), a connecting piece (2702), and a driving motor (2703), a receiving groove is formed at the connection between the collection port (22) and the collection inclined plane (16), one end of the roller (2701) is rotatably installed on the inner wall of the receiving groove, a placing groove is formed in one side of the outer frame board (13), the driving motor (2703) is installed in the placing groove, the connecting piece (2702) is installed on the output end of the driving motor (2703) with the small contact surface of the connecting piece (2702) being fixedly connected with the roller (2701).

5. The construction equipment for rapid slip-form of deep foundation pit according to claim 4, characterized in that, A plurality of poking pieces (28) are uniformly installed on the edges of the roller (2701).

6. The construction equipment for rapid slip-form of deep foundation pit according to claim 1, characterized in that, A variable frequency vibrator (9) is installed on the rear side of the outer frame board (13).

7. The construction equipment for rapid slip-form of deep foundation pit according to claim 1, characterized in that, The driving arm structure (2) comprises a fixed arm (10), an adjusting arm (4), a three-head connecting block (3), a first adjusting oil cylinder (12) and a mechanical joint (7), the fixed arm (10) is fixedly installed on the construction vehicle (1), the three-head connecting block (3) is rotatably connected with the fixed arm (10), the first adjusting oil cylinder (12) is rotatably installed on the fixed arm (10), one end of the three-head connecting block (3) is rotatably installed on the output end of the first adjusting oil cylinder (12), the adjusting arm (4) is fixedly connected with the three-head connecting block (3), and the mechanical joint (7) is rotatably connected with the end of the adjusting arm (4) and the outer frame plate (13) at two ends.

8. The construction equipment for rapid sliding formwork of deep foundation pit sprayed concrete according to claim 7, characterized in that, The driving arm structure (2) further comprises a second adjusting oil cylinder (6), a hinged seat (8) and a telescopic rod group (11), the second adjusting oil cylinder (6) is rotatably installed at the end of the adjusting arm (4), the telescopic end of the second adjusting oil cylinder (6) is rotatably connected with the upper side of the rear side of the outer frame plate (13), the hinged seat (8) is rotatably connected with the lower side of the adjusting arm (4) and the lower side of the rear side of the outer frame plate (13) respectively, and one end of the telescopic rod group (11) is rotatably installed on the lower side of the adjusting arm (4) and the other end is rotatably installed on the hinged seat (8).

9. The construction equipment for deep foundation jet concrete fast sliding form according to claim 1, characterized in that, The outer frame plate (13) and the inner smearing plate (14) are provided with a mounting assembly (30), recesses are formed on the inner walls of the mounting groove on both sides, key grooves (31) are formed on both sides of the inner smearing plate (14) and located outside the recesses, the mounting assembly (30) comprises a metal positioning block (3001) and a mounting spring (3002), one side of the metal positioning block (3001) is installed on the inner wall of the recess through the mounting spring (3002), the other side of the metal positioning block (3001) is clamped in the key groove (31), and an electromagnetic block (29) is installed on the inner wall of the recess.

Citation Information

Patent Citations

  • Trowelling device for concrete processing

    CN211897733U

  • Concrete spraying and plastering platform car for tunnel primary support

    CN116792120A

  • Plastering device for house building construction

    CN219993006U