A bolted end-plate connection joint of a fabricated concrete beam-column

By installing sleeve plates on steel columns and using a connection method of traction plates and nuts, combined with the limiting mechanism of insert blocks and stops, the problems of difficult quality control and environmental pollution of traditional welding connection methods are solved, realizing fast and stable concrete beam-column connection, improving construction efficiency and building structure safety.

CN121429104BActive Publication Date: 2026-09-04THE SECOND CONSTR OF CHINA CONSTR EIGHTH ENG DIV
2 Cites 0 Cited by

Patent Information

Application Number
CN202511715232.X
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2025-11-21
Publication Date
2026-09-04
Estimated Expiration
2045-11-21

AI Technical Summary

Technical Problem

Traditional concrete beam-column connection methods suffer from problems such as difficulty in controlling welding quality, long construction period, serious environmental pollution, and difficulty in guaranteeing quality, making it difficult to meet the needs of modern prefabricated buildings.

Method used

Sleeve 1 and Sleeve 2 are fitted onto the steel column. The pre-positioning of the concrete assembly beam is achieved through traction plates, screws, and nuts. Combined with the limiting mechanism of insert blocks and stops, a multi-level connection and limiting mechanism is formed to avoid welding operations.

Benefits of technology

It simplifies the construction process, improves construction efficiency, ensures the stability and safety of connections, reduces environmental pollution, and enhances the quality and reliability of building structures.

✦ Generated by Eureka AI based on patent content.
Patent Text Reader

Abstract

The present application relates to the technical field of building construction, in particular to a bolt end plate connecting joint of a fabricated concrete beam column, comprising a sleeve plate one and a sleeve plate two, both of which are sleeved on a steel column, both sides of the steel column are provided with a concrete fabricated beam, the bottom surface of the sleeve plate one is fixed with two groups of traction plates, each group is provided with two traction plates, the two traction plates are inserted into two groove bodies at the end of the concrete fabricated beam, the surface of the traction plate is fixed with a connecting plate, and the surface of the connecting plate is provided with a assembling groove, the sleeve plate one and the sleeve plate two are sleeved on the steel column, the pre-limiting of the concrete fabricated beam is realized through the traction plate, the screw rod and the nut, the operation process is simple and easy to understand, the construction personnel do not need to have superb welding skills, only need to install the parts and tighten the bolts according to a certain order, the connection can be completed, the construction time is greatly shortened, and the construction efficiency is improved.