Construction method of tower crane

By using a derrick for segmented dismantling and detailed construction planning, the safety and efficiency issues of tower cranes under site constraints were resolved, achieving stability and cost control for the tower cranes.

CN121894557APending Publication Date: 2026-04-21ZHEJIANG SECOND CONSTR GRP CO LTD
View PDF 7 Cites 0 Cited by

Patent Information

Application Number
CN202610368631.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-03-25
Publication Date
2026-04-21

AI Technical Summary

Technical Problem

Traditional tower crane installation and dismantling are difficult to carry out under site constraints, resulting in compromised safety, low construction efficiency, and high costs.

Method used

The boom tip section of the crane was dismantled in sections using a derrick crane. Combined with a detailed plan for the construction, installation and dismantling of the tower crane foundation, anemometers and obstruction lights were used to ensure safety. The verticality and flatness of the tower body were accurately measured, and attachment devices were set up in a reasonable manner.

Benefits of technology

This improved the safety and efficiency of dismantling operations, reduced costs, and ensured the stability of the tower crane structure and the smooth progress of construction on site.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN121894557A_ABST
    Figure CN121894557A_ABST
Patent Text Reader

Abstract

The invention discloses a construction method of a tower crane, which is applied to the technical field of tower crane mounting and dismounting, and comprises the steps of tower crane foundation construction, tower crane mounting and tower crane dismounting, in the tower crane dismounting process, firstly lowering standard knots, then dismounting most of counterweights, reserving a small amount of counterweights, and mounting a derrick crane on a load-carrying trolley. A derrick mast crane is used for sequentially disassembling a jib tip section to a third jib section of the jib in a segmented mode, after the derrick mast crane is disassembled, a standard section continues to be lowered, an attachment device is disassembled one by one, and a tower body needs to be lowered to the corresponding height before attachment disassembly every time. And finally, the remaining second section of the cargo boom, the balance weight, the balance arm, the arm root section, the rotary assembly, the special section, the climbing frame, the remaining standard section and the remaining basic section are detached. By arranging the derrick mast crane, the problem that a traditional disassembling mode is difficult to implement under the site limitation condition is effectively solved, the site limitation problem is solved, the safety of disassembling operation is further improved, the construction efficiency is remarkably improved, the construction period is shortened, and the construction cost and the labor cost are reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This application relates to the field of tower crane installation and dismantling technology, specifically a tower crane construction method. Background Technology

[0002] Tower cranes, also known as tower hoists, are the most commonly used lifting equipment on construction sites and are an indispensable piece of equipment. Tower cranes are extended (height) section by section (referred to as "standard sections") to lift and transport construction materials such as steel bars, timber, concrete, and steel pipes.

[0003] Traditional tower crane installation and dismantling usually require sufficient space to lower the boom directly to the ground or a designated area. However, this method is difficult to implement when site conditions do not allow it. Furthermore, current tower crane installation efficiency is low, safety cannot be fully guaranteed, and labor and construction costs are high.

[0004] Due to site constraints, the boom tip section to boom root section (i.e., the front end of the boom) of the tower crane cannot be disassembled by the traditional method of lowering the boom section as a whole or directly disassembling the boom section. This makes it difficult to ensure safety during disassembly operations, and the disassembly method is difficult to implement, which reduces construction efficiency, prolongs the construction period, and increases construction and labor costs. Summary of the Invention

[0005] One objective of this application is to provide a construction method for a tower crane that can overcome at least one of the defects in the aforementioned background art.

[0006] To achieve the above objectives, this application provides the following technical solution: a construction method for a tower crane, comprising the following steps: Tower crane foundation construction; Tower crane installation: S1. Install one foundation section and one standard section; S2. Install the climbing frame and jacking system; S3. Install the special section, slewing assembly, and boom root section; S4. Assemble the boom and counterweight on the ground, and sequentially hoist the counterweight, part of the counterweight, boom, and remaining counterweight; S5. Install warning lights and anemometer, and thread the wire rope; S6. Connect the power supply and conduct no-load test run and functional tests; S7. Jack up the tower crane and install the attachment devices in stages; Tower crane dismantling: X1. Inspect the jacking system and rotate the jib to the opening side of the climbing frame; X2. Lower the standard section to the initial dismantling height; X3. Remove most of the counterweight, leaving a small amount; X4. Install the derrick crane on the load trolley, including the fixed lugs, derrick main body, derrick crane lugs, derrick, auxiliary struts, tie rod ropes, and anti-failure tie rod ropes; X5. Use the derrick crane to dismantle the jib section from the tip section to the third section of the jib in sequence; X6. After dismantling the derrick crane, dismantle the attachment devices one by one and continue to lower the standard section. Before each attachment removal, the tower body must be lowered to the corresponding height; X7. Dismantle the remaining second section of the jib, counterweight, counterweight boom, boom root section, slewing assembly, special sections, climbing frame, and the remaining standard and foundation sections.

[0007] Compared to existing technologies, by using a derrick crane to dismantle the jib from the top section to the third section in stages, the traditional dismantling method is effectively solved under limited space conditions. This improves the safety of the dismantling operation, significantly increases construction efficiency, shortens the construction period, and reduces construction and labor costs. Furthermore, detailed and rational planning of each stage of the tower crane's foundation construction, installation, and dismantling helps construction personnel operate according to plan, reducing errors and omissions, improving work efficiency, ensuring the stability of the entire tower crane structure, and guaranteeing the smooth progress of the construction site.

[0008] Preferably, the steps in tower crane foundation construction include: Y1. Excavate the tower crane foundation according to the determined coordinates. Combine the excavation of the cooling tower with the excavation of the earthwork. Use a slope ratio of 1:0.75 for the excavation. Set up warning lines in the construction area during the excavation. Y2. Based on the tower crane design load parameters, construct a slab-type reinforced concrete foundation. The top elevation of the foundation should be consistent with the bottom elevation of the adjacent water tank and a post-cast area should be reserved. Y3. A drainage system should be installed around the concrete foundation soil layer; Y4. Two flat iron bars are led out from the main grounding of the building to the foundation surface, and protruded 200mm to 300mm from the concrete surface. The grounding resistance is required to be ≤4Ω. Y5. Embed fixed legs or sections in the foundation steel mesh, and set a pad or iron stool under the embedded legs to ensure that the installation flatness error is less than 1 / 1000 of the cross-section of the standard section. The exposed size of the anchor foot of the embedded leg is 150mm to 200mm. Y6. Pour concrete and cure it until the concrete strength reaches 1.2MPa before conducting foundation acceptance.

[0009] By setting shims or iron stools, the height and position of the embedded outriggers can be effectively adjusted, ensuring that the installation surface is flat with an error of less than 1 / 1000, meeting high-precision installation requirements. Strict control of flatness also helps in the accurate positioning of subsequent tower crane bases, steel structures, and other components, avoiding structural deformation or stress concentration caused by uneven foundations. The exposed dimension of the embedded outrigger anchor foot is 150mm, ensuring sufficient anchorage length for a firm bond between the anchor and the concrete foundation, enhancing overall connection strength. Sufficient anchorage length helps resist various forces generated during construction and use, such as shear, tension, and torque, thereby improving the stability of the tower crane structure.

[0010] Preferably, step S1 further includes: S11. Lift the base section above the pre-embedded support leg, align the pin hole of the base section with the hole of the pre-embedded support leg, and insert the pin, vertical pin and cotter pin. S12. Lift the standard section above the base section, align the pin hole of the standard section with the hole of the base section, and insert the pin, vertical pin and cotter pin; Step S2 specifically includes: S21. Install the climbing frame platform, ladder, lead-in structure and jacking cylinder in sequence, and carry out overall hoisting after ensuring that the connection is firm. During hoisting, hang the lifting gear on the climbing frame, tighten the wire rope and hoist it. The position of the jacking cylinder is on the same side as the tower steps. Then slowly put the climbing frame on the outside of the tower. S22. Place the climbing claws on the climbing frame onto the steps on the upper part of the base section, and adjust the position of the climbing frame so that the gaps on each side between the climbing guide wheel and the standard section are basically consistent.

[0011] By aligning the lifting cylinder with the tower steps on the same side, lifting operations can be facilitated, ensuring a reasonable direction of force transmission and improving lifting efficiency and safety.

[0012] Preferably, step S5 further includes: S51. When the hinge point height at the base of the boom is greater than 50m, an anemometer can be installed on the top of the tower crane. When the tower crane is used at a height greater than 30m, obstruction lights can be installed, and the distance between the obstruction lights and the beams must be greater than 150m.

[0013] To ensure the safety of tower crane operations at height, the following safety devices must be installed according to their installation height: When the height of the jib root hinge point is greater than 50 meters, an anemometer should be installed on the top of the tower crane in an unobstructed location to ensure that it can issue a stop-work alarm when the wind speed exceeds the working limit; at the same time, when the tower crane is used at a height of more than 30 meters, obstruction lights powered by safe voltage must be installed. Their arrangement should be able to clearly outline the working contour and emit continuous, flashing or rotating red light visible at least 150 meters away to serve as a warning, effectively prevent collision accidents, and ensure the safety of nighttime operations.

[0014] Preferably, step S6 further includes: S61. When the wind speed is ≤3m / s and the tower is unloaded, the verticality of the tower is measured with a theodolite and the error of the verticality is ≤4 / 1000.

[0015] After the tower crane is fully installed, when the wind speed is ≤3m / s and under no-load conditions, the verticality of the tower body should be measured using a theodolite. The verticality error should be ≤4 / 1000 to ensure the stability and safety of the tower crane during subsequent use, and to avoid uneven structural stress or abnormal operation caused by excessive verticality deviation. If the measurement result exceeds the allowable error range, the verticality of the tower body should be adjusted in a timely manner until there is basically no error.

[0016] Preferably, step S7 further includes: S71. The initial independent height of the tower crane installation is determined by the tower crane model. It is finally lifted to the installation height as the cooling tower is constructed. A total of four attachments are set. The height between the first attachment and the ground is greater than the distance between the second attachment and the other attachments. S72. The attachment device is connected to the main chord of the tower body through the attachment frame, and is connected to the connecting base embedded in the cooling tower wall through the attachment rod. The height difference between the attachment frame and the connecting base is allowed to be ≤200mm. S73. When installing the attachment device, a theodolite can be used to check the verticality of the tower body axis. The lateral verticality deviation of the tower body axis above the uppermost attachment is 4 / 1000, and the verticality deviation of the tower body axis below the uppermost attachment is 2 / 1000.

[0017] By accurately measuring the verticality of the tower's centerline, it is possible to ensure that the tower crane maintains a good vertical state during installation and use, avoiding abnormal stress and safety hazards caused by tilting. The verticality deviation of the part below the top attachment is 2 / 1000, because this part is close to the ground and is the foundation and main load-bearing part of the tower crane, and its verticality directly affects the overall stability. The part above the top attachment is allowed a slightly larger deviation of 4 / 1000. Considering the measurement difficulty and structural elastic deformation caused by the increased height, the deviation limit is reasonably set to balance construction difficulty and safety.

[0018] Preferably, step X4 further includes: X41. The fixed lugs of the boom crane are installed on the four corners of the load trolley; X42. Move the load trolley to the first section of the boom and weld at least four boom lugs onto the load trolley. X43. First, fix the load-bearing trolley with steel wire or hemp rope. Then, weld the connecting lugs of the auxiliary support rod and the connecting lugs of the main body of the derrick onto the trolley. The weld grade is level three, and the weld leg height is ≥12mm.

[0019] Welded connections ensure the robustness and reliability of the connection between the boom crane and the load trolley. High-quality welding is the fundamental guarantee for the safe operation of the boom crane, effectively preventing the risk of connection failure and thus greatly enhancing the structural safety and stability of the boom crane installation.

[0020] Preferably, step X5 further includes: X51. Disassemble the boom tip section and the ninth section of the boom; X52. Disassemble the eighth section of the boom, and then disassemble the seventh to third sections of the boom in the same way as disassembling the eighth section of the boom. X53. After the third section of the crane boom has been disassembled, the derrick crane will be disassembled. Specifically, the X52 step also includes: X521. Disassemble the connecting part of the auxiliary support rod, pull up the pole with the two pull arm ropes to make its tilt angle 70°~80°, and then install the auxiliary support rod.

[0021] By using two pull rod ropes to lift the derrick to an angle of 70° to 80°, it is possible to ensure that the auxiliary support rod is in the right position and angle during installation, which facilitates the smooth progress of subsequent dismantling operations.

[0022] Preferably, step X51 further includes: After the X511, auxiliary support rod and derrick are installed, the load trolley is temporarily fixed and the derrick is lifted and pushed to the eighth section of the crane boom. X512. After moving the load trolley to the installation position, use cloth straps and a 2t hoist to fix it at the four rollers of the load trolley and the lower chord of the lifting arm. X513. Use a 4t to 5t hoist as the boom rope, hang the hoist on the upper chord of the crane boom, and connect the other end of the hoist to the boom rod. X514. After the boom rope is installed, add another boom rope to prevent failure. X515. Adjust the angle of the boom lift; X516. Install wire rope guide pulleys on the upper chord of the counterweight boom and lifting boom; X517. First, remove the connecting pin between the lower chord of the ninth section of the boom and the eighth section of the boom, then remove the connecting pin of the upper chord; control the derrick to lower the disassembled boom section to the ground.

[0023] By providing temporary wire or hemp rope and two methods for securing the load-bearing trolley during operation—using a conveyor belt and a 2-ton hoist—the precise position and stability of the load-bearing trolley during the installation of the boom crane and the dismantling of the boom section were ensured. This effectively prevented accidental displacement of the trolley during stress or operation, thus guaranteeing the accuracy and safety of the boom crane operation. Secondly, by adding a fail-safe boom rope, meaning that even if the 5-ton hoist, acting as the boom rope, fails unexpectedly, the fail-safe boom rope can intervene promptly to prevent the boom crane from becoming unstable or falling. This significantly improves the safety of the core dismantling operation and reduces potential accident risks.

[0024] Preferably, step X7 further includes: X71. Before disassembling the second section of the crane boom, first disassemble the load trolley; X72. Use a truck crane to lift the remaining counterweights one by one and place them on the ground; X73. When the hoisting wire rope and the counterweight boom are taut, first remove the connecting pin between the tie rod and the root section of the boom, then slowly lift the boom so that the counterweight boom and the root section of the boom are tilted to the specified angle, and finally remove the connecting pin between the counterweight boom and the boom. X74. When the wire rope of the boom root section is taut, remove the pin, bushing, pin and locking pin connecting the boom root section and the upper support, and then slowly lift the boom root section and place it on the support surface with pads or wooden partition boards. X75. According to the lifting point position during installation, use a crane to lift the slewing assembly, then disassemble the connecting pin and vertical pin between the lower slewing support and the special section, and finally lift the slewing assembly to the ground. X76. Before disassembly, check whether there are cable connections between the special section and adjacent components. Then, use a crane to lift the special section, remove the connecting pin between the special section and the tower body, and lower the special section to the ground with slings. X77. Use a crane to lift the climbing frame, remove the pin between the lifting beam and the lifting cylinder, retract the lifting cylinder to let it hang down naturally, and then slowly lift the climbing frame along the tower body and place it on the ground. X78. Disassemble the standard section and the foundation section in sequence to complete the entire disassembly work.

[0025] By disassembling each remaining structure in a detailed and reasonable sequence, construction workers can operate according to plan, reduce errors and omissions, improve work efficiency, ensure the stability of the entire tower crane structure, and guarantee the smooth progress of construction on site. Attached Figure Description

[0026] Figure 1 A flowchart of the tower crane installation method in a tower crane construction method provided in an embodiment of this application; Figure 2 A flowchart of the tower crane dismantling method in the tower crane construction method provided in an embodiment of this application. Detailed Implementation

[0027] To enable those skilled in the art to better understand the technical solutions of this disclosure, the following detailed, clear, and complete description of this disclosure is provided in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are merely illustrative of this disclosure and are not intended to limit it.

[0028] In the description of this application, the use of "first" and "second" is for the purpose of distinguishing technical features only, and should not be construed as indicating or implying relative importance or implicitly indicating the number of technical features indicated or the order of the technical features indicated.

[0029] Those skilled in the art should understand that in the disclosure of this application, the terms "longitudinal", "lateral", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer", etc., indicate the orientation or positional relationship based on the orientation or positional relationship shown in the accompanying drawings. They are only for the convenience of describing this application and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, or be constructed and operated in a specific orientation. Therefore, the above terms should not be construed as limitations on this application.

[0030] The present application will now be described in further detail with reference to the accompanying drawings, see below. Figures 1 to 2 illustrate.

[0031] This embodiment provides a construction method for a tower crane, the steps of which include: Tower crane foundation construction: Y1. Excavate the tower crane foundation according to the determined coordinates. Combine the excavation of the cooling tower with the excavation of the earthwork. Use a slope ratio of 1:0.75 for the excavation. Set up warning lines in the construction area during the excavation. Specifically, before earthwork excavation, positioning and layout are required. Based on the positioning control points of the excavation area, surveying technicians measure and locate the points before construction. On-site construction personnel determine the tower crane's center point based on the surveying results provided by the surveyors. Construction supervisors monitor the site to prevent off-center or over-excavation. Then, the tower crane foundation is excavated according to the determined coordinates. Combined with the cooling tower earthwork excavation, a slope ratio of 1:0.75 is used for excavation. Warning lines are set up within the construction area during excavation, and a designated person conducts a safety inspection of the excavation area. After excavation is completed, scaffolders promptly install protective railings around the foundation pit and set up a safe pedestrian access path.

[0032] Y2. Based on the tower crane design load parameters, construct a slab-type reinforced concrete foundation. The top elevation of the foundation should be consistent with the bottom elevation of the adjacent water tank and a post-cast area should be reserved. Specifically, the tower crane foundation has a plan dimension of 8200mm×8200mm and a height of 1650mm. The top elevation of the foundation is ±0. The reinforcement is arranged according to the foundation drawings. Grade III threaded steel is selected according to the actual site conditions. The tower crane foundation reinforcement uses Φ25 steel bars, with double layers and bidirectional arrangement in the upper and lower rows. Φ12 tie bars are set between the upper and lower layers of reinforcement. The tie bars are arranged in parallel to control the upper and lower protective layers. The thickness of the reinforcement protective layer of the foundation is 75mm.

[0033] Y3. A drainage system should be installed around the concrete foundation soil layer to ensure that water can be effectively drained and to prevent the foundation from being soaked in water, which would affect its bearing capacity and stability. Y4. Two flat iron bars are led out from the main grounding of the building to the foundation surface, and protruded 200mm to 300mm from the concrete surface. The grounding resistance is required to be ≤4Ω to ensure that when the tower crane is struck by lightning or the equipment leaks electricity, the huge dangerous current can be quickly and safely conducted to the ground, thereby ensuring the safety of equipment, buildings and personnel. Y5. Embed support legs or sections in the foundation steel mesh, and set a pad or iron stool under the embedded support leg to ensure that its installation flatness error is less than 1 / 1000 of the cross-section of the standard section. The exposed size of the anchor foot of the embedded support leg is 150mm to 200mm.

[0034] In this embodiment, by setting shims or iron stools, the height and position of the embedded outriggers can be effectively adjusted, ensuring that the installation surface is flat with an error of <1 / 1000, meeting high-precision installation requirements. Strict control of flatness also helps in the accurate positioning of subsequent tower crane bases, steel structures, and other components, avoiding structural deformation or stress concentration caused by uneven foundations. The exposed dimension of the embedded outrigger anchor foot is 150mm, ensuring sufficient anchorage length so that the anchor can firmly bond to the concrete foundation, enhancing overall connection strength. Sufficient anchorage length helps resist various forces generated during construction and use, such as shear, tension, and torque, thereby improving the stability of the tower crane structure.

[0035] Specifically, the fixing of the pre-embedded outriggers includes: ① The pre-embedded support legs can be connected to the pre-embedded connecting frame or a 2.0m standard section to form an installation reference; ② Use axle pins to fix the pre-embedded connecting frame or 2.0m standard section to the pre-embedded support leg, and install pins and cotter pins on the axle pins to lock them in place; ③ The installation reference of the pre-embedded support legs should be symmetrical with the center of the concrete foundation; ④ When inserting the pre-embedded outriggers into the foundation pit, ensure proper grounding of the tower crane.

[0036] Y6. Pour concrete and cure it until the concrete strength reaches 1.2MPa before conducting foundation acceptance.

[0037] Specifically, the tower crane foundation concrete is poured using self-mixed concrete. Before concrete construction, debris inside the formwork should be cleaned. For the foundation construction with a large volume of concrete, the concrete is poured using a natural flow method to form a sloping concrete layer, with each layer being 30cm to 40cm thick. A Φ50 immersion vibrator is used for concrete vibration, inserted quickly and withdrawn slowly. Between two layers of concrete, the vibrator should be inserted approximately 50mm into the next layer to eliminate the joint. Vibration points are evenly spaced, and the distance moved each time should not exceed 1.5 times the vibrator's radius of action R, i.e., approximately 50cm. The vibration time is 20s to 30s. Forty minutes before the initial setting time of the concrete, a second vibration is required to ensure the concrete's density and improve its strength and crack resistance.

[0038] Before the tower crane is installed, the installation personnel must be inspected, and the machinery and materials must be accepted. The inspection by installation personnel includes: First, before equipment installation, the project's engineering management department verifies the identity and credentials of all installation and dismantling personnel. Second, the project's engineering management department verifies the validity of the personnel certificates provided by the subcontractors. Third, the project's engineering management department verifies the qualifications and equipment documentation of the subcontractors.

[0039] The acceptance inspection of mechanical equipment and materials includes: First, whether the components, accessories, and connectors are fully and completely installed, correctly positioned, and free from structural deformation, weld defects, fatigue cracks, and the weight and position of the counterweights conform to the instruction manual requirements. Second, whether the wire ropes and pulleys meet the requirements; the wire ropes are neatly wound on the drum and well lubricated. The wire rope specifications are correct, broken wires and wear do not reach the scrap standard, the wire rope fixing and splicing conform to national and industry standards, all pulleys rotate flexibly and reliably without jamming, the hook wear does not reach the scrap standard, the safety device is reliable, all mechanisms rotate smoothly without abnormal noise, all lubrication points are well lubricated with the correct lubricating oil grade, the brakes operate flexibly and reliably, and the couplings are well connected without abnormalities. Third, inspect and adjust all safety limit devices, ensuring that each mechanism operates correctly, smoothly, and without abnormal noise, and that braking is sensitive and reliable; the combined error of the lifting limiter and torque limiter should be ≤ ±5% of the rated value; check the integrity and reliability of the jacking beam anti-derailment device, the wire rope anti-derailment device on the hook, the wire rope anti-derailment devices on the pulleys and drum, and the sensitivity and reliability of the trolley rope breakage protection device. Fourth, inspect and adjust the condition of the slings, including broken wires, wear, corrosion, lubrication, deformation, and the tightness of the strands in the heavy-duty collar connection. Fifth, inspect and accept the tower crane foundation construction, requiring the concrete strength to reach at least 75%, and provide acceptance documents for the concealed works at the concrete embedded parts, including the original material certificate for the reinforcing steel and the reinforcing steel binding construction acceptance form.

[0040] Tower crane installation: S1. Install one basic section and one standard section; S2. Install the climbing frame and lifting system; S3. Install special sections, slewing assemblies, and boom root sections; S4. Assemble the lifting boom and counterweight on the ground, and then hoist the counterweight, part of the counterweight, the lifting boom and the remaining counterweight in sequence. S5. Install warning lights and an anemometer, and thread steel wire ropes through them; S6. Connect the power supply and conduct no-load test run and functional test; S7. Tower crane jacking and phased installation of attachment devices.

[0041] Furthermore, step S1 specifically includes: S11. Lift the base section above the pre-embedded support leg, align the pin hole of the base section with the hole of the pre-embedded support leg, and insert the Φ65 pin, vertical pin and cotter pin. S12. Lift the standard section above the base section, align the pin hole of the standard section with the hole of the base section, and insert the Φ55 pin, vertical pin and cotter pin; like Figure 1As shown, in this embodiment, different diameter pins are used for different installation positions. This ensures that the strength and stability of the connection matches the actual stress conditions, avoiding loosening of the connection or structural damage due to improper selection of the pin diameter. Furthermore, timely installation of the vertical pin and cotter pin after inserting the pin effectively prevents the pin from falling off during operation, ensuring the safety of the tower crane installation process.

[0042] Furthermore, step S2 specifically includes: S21. Install the climbing frame platform, ladder, lead-in structure and jacking cylinder in sequence, and carry out overall hoisting after ensuring that the connection is firm. During hoisting, hang the lifting gear on the climbing frame, tighten the wire rope and hoist it. The position of the jacking cylinder is on the same side as the tower steps. Then slowly put the climbing frame on the outside of the tower. S22. Place the climbing claws on the climbing frame onto the steps on the upper part of the base section. Adjust the position of the climbing frame to ensure that the clearance between the climbing guide wheels and the standard section is basically consistent on all sides. Appropriate clearance and good fit reduce mechanical friction and wear, extending the service life of the climbing frame. After installing the lifting cylinder, hoist the hydraulic pump station to one corner of the climbing frame platform, connect the oil pipes, and check the operation of the hydraulic system. Ensure that the rotation direction of the pump motor fan blades is consistent with the arrow marking on the casing to avoid burning out the pump. If there is an error, reconnect the motor wiring.

[0043] Furthermore, step S3 specifically includes: S31. Install the special section: Lift the special section equipped with the guide beam for installation. First, align the main chord connection hole on the special section with the fishplate connection hole on the lower foundation section, and insert pins, vertical pins, and cotter pins for fixation. Then, use the hydraulic system to lift the climbing frame, so that the lug connection hole on the special section aligns with the connection lug at the upper end of the climbing frame, and then insert pins and cotter pins for fixation. S32. Install the slewing assembly: First, hoist the upper and lower supports onto a flat surface to prepare for the ground assembly of the slewing assembly. Simultaneously, check that the pre-tightening torque of the bolts on the slewing bearing reaches 1350 N·m, and that the pre-tightening torque of the locknuts is slightly greater than 1350 N·m to ensure a secure and reliable connection. Then, after the slewing assembly is assembled, hoist it above the special section, ensuring that the direction of the lower support ladder is consistent with the direction of the special section ladder. Then, slowly lower the slewing assembly and secure it using eight pins. To prevent the pins from falling off, install a vertical pin between two pins, with the lower end of the vertical pin inserted into a hoist pin for fixation, ensuring a safe and stable connection. S33. Install the boom root section: When hoisting the boom root section, use four steel wire ropes to pass through the lifting lugs on the boom root section, and finally suspend them together on the hook. During the hoisting process, ensure the balance of the hoisting to ensure that the boom root section is lifted safely and stably. Then, connect the boom root section to the upper support through four pins, insert the short shaft, and lock the short shaft with round clamps to ensure a firm and reliable connection.

[0044] Furthermore, step S4 specifically includes: S41. Lifting the counterweight boom: Lift the assembled counterweight boom, align it with the connecting lugs on the boom root section, and insert pins, cotter pins, and R-pins to secure it. Then, slowly lower the counterweight boom. Place the counterweight boom to the preset position, connect the short tie rod installed on the boom root section with the long tie rod on the counterweight boom, and insert pins and cotter pins to secure it. Slowly lower the counterweight boom until the tie rods are taut, keeping the counterweight boom horizontal.

[0045] S42. Lifting counterweight: Install two 3.25t counterweights, each of which is mounted on the counterweight boom via two counterweight pins; when lifting the first 3.25t counterweight, the counterweight should be placed on the counterweight boom and positioned close to the tower body, and the counterweights should be lifted in sequence.

[0046] S43, Lifting boom; S44. Remaining counterweights for hoisting: The remaining counterweights shall be placed in the tower crane counterweight position using a 50t truck crane, according to the usage requirements. The counterweights shall be placed neatly and orderly.

[0047] Step S43 specifically includes: S431. Assemble the crane boom to the specified boom length according to construction requirements; S432. Place the second section of the boom on a flat surface. The luffing mechanism can be installed after the second section of the boom has been placed. S433. Install the third section of the boom. To facilitate the connection between the boom sections, tilt the boom section slightly and lift it up. Move the boom section slowly so that its upper chord connecting lug plate is correctly connected to the upper chord lug plate of the connected boom section. Use pins, locking pins and connecting lug plates. Slowly lower the boom and use positioning pins to align the lower chord of the connected boom section. Then connect the lower chord with bolts, washers, nuts and pins. S434. When installing the lower chord bolts, first connect the lower chord bolts to the positioning plates at the ends of the two boom sections, so that the bolt heads protrude from the positioning plates at the ends of the two boom sections. The bolt heads of the lower chord connecting the boom sections should be aligned with the boom head direction. Then, use washers, nuts, and cotter pins to connect the lower chord of the boom sections and ensure that the cotter pins are fully open. S435. According to the boom length, install each boom section in sequence on the ground. The upper chord of the boom is connected and fixed with pins, vertical pins and pins. The lower chord of the boom is connected and fixed with bolts, washers and nuts. The bolt head direction is consistent with the boom head direction. Insert cotter pins and fully open the cotter pins. S436. Each section of the boom has a safety rope hook. First, thread the safety rope into the safety rope hook on the boom. At the same time, lock the wire rope with at least three wire rope clamps in the safety ring at the boom head and the first section of the boom. S437. When lifting the boom assembly, first attach a rope at the center of gravity and perform a trial lift to check for balance. If imbalance is found, adjust the position of the rope as appropriate and record the final lifting point position for reference when dismantling the tower crane later. Then lift the boom assembly to the installation height.

[0048] In this embodiment, the installation of the climbing frame and jacking system provides the necessary support and operating platform for subsequent jacking operations. As a key component in tower crane jacking, the installation quality of the climbing frame directly affects the safety and stability of the jacking process. During installation, it is essential to ensure a secure and reliable connection between the climbing frame and the tower body, and that all components are installed accurately to prevent the counterweight from shifting or falling off during tower crane operation, thereby guaranteeing the stability and safety of the tower crane's operation.

[0049] Furthermore, step S5 specifically includes: S51. When the hinge point height at the base of the boom is greater than 50m, an anemometer can be installed on the top of the tower crane to ensure that it issues a stop-work alarm when the wind speed exceeds the working limit; when the tower crane is used at a height greater than 30m, obstruction lights can be installed, and the light distance of the obstruction lights is greater than 150m. In this embodiment, to ensure the safety of tower crane operations at height, the following safety devices must be installed according to the installation height: When the height of the boom root hinge point is greater than 50 meters, an anemometer should be installed on the top of the tower crane where it is not obstructed, to ensure that it can issue a stop-work alarm when the wind speed exceeds the working limit; at the same time, when the tower crane is used at a height of more than 30 meters, obstruction lights powered by safe voltage must be installed, and their arrangement should be able to clearly outline the working contour and emit continuous, flashing or rotating red light visible at least 150 meters away, so as to serve as a warning, effectively prevent collision accidents, and ensure the safety of nighttime operations.

[0050] In step S5, the winding of the wire rope includes: Luffing wire rope: First, lead the wire rope from the luffing mechanism drum, pass it sequentially through the pulley at the base of the boom, and then use pins and cotter pins to secure the wedge joint at the end of the wire rope to the designated anchor point on the luffing trolley. Next, lead the wire rope to the front end of the boom, pass it through the boom end pulley, and pull it back to the luffing drum. Start winding the rope from below the drum upwards in an orderly fashion, ensuring at least three safety turns remain on the drum after winding. Finally, secure the end of the wire rope to the side of the drum with bolts and pressure plates. The other end of the wire rope must pass through the guide ring of the anti-breakage device, be introduced into the tensioning drum from below, and wound at least three turns. After passing through the fixing hole on the drum, secure it with wedge sleeves and wedge blocks. Finally, tension the wire rope to the required preload by turning the handle.

[0051] Hoisting Wire Rope: First, the wire rope emerges from the top of the hoisting mechanism drum, passes through the lifting capacity limiter on the base section of the counterweight boom, then through the pulley at the base of the boom, and then extends and connects to the trolley. Next, the hoisting wire rope is wound around the trolley. After exiting the trolley, the hoisting wire rope enters the anti-twist device at the boom head for connection. A wedge is used to lock the wire rope within the wedge sleeve, and a rope clamp is installed at the end of the wire rope for fixation. Then, the wedge sleeve is installed onto the wire rope anti-twist device using a pin and cotter pin. After installation, it should be checked that the anti-twist device can rotate freely. To prevent the wire rope from unraveling, the ends of the wire rope can be reinforced with thin iron wire.

[0052] Furthermore, step S6 specifically includes: S61. When the wind speed is ≤3m / s and the tower is unloaded, the verticality of the tower is measured with a theodolite and the error of the verticality is ≤4 / 1000. Specifically, after the tower crane is fully installed, when the wind speed is ≤3m / s and under no-load conditions, the verticality of the tower body should be measured with a theodolite. The verticality error should be ≤4 / 1000 to ensure the stability and safety of the tower crane during subsequent use, avoiding uneven structural stress or abnormal operation due to excessive verticality deviation. If the measurement result exceeds the allowable error range, the verticality of the tower body should be adjusted in time until there is basically no error. Then, connect the power supply of all circuits according to the circuit diagram requirements, test run each mechanism, and check whether the operation of each mechanism is correct. At the same time, check whether the wire ropes are in normal working condition and whether there is friction with the structural components. All abnormal conditions should be eliminated. Before the tower crane is tested, it is necessary to check whether the hoisting mechanism, luffing mechanism, slewing mechanism and hydraulic jacking system are operating normally, check whether the pump and cylinder oil volume in the jacking system is sufficient, and check whether all oil nozzles, oil cups, oil pipes and oil lines are unobstructed. After the trial run, and after checking that each mechanism, tower body mechanism and safety device are qualified, it can be officially put into operation. Three no-load tests were conducted. Only after everything was confirmed to be normal could the crane be put into trial operation. The trolley handle was activated, and the no-load trolley moved back and forth along the track several times. There was no obvious wheel slippage, and starting and braking were normal. The hoisting mechanism was activated, and the hook was raised and lowered several times without load. The limit switches were sensitive and accurate. The hook rotated several times in both directions without load, and the rotation was smooth without obvious shaking. The trolley was moved to a distance of 30m to 35m from the center of the tower crane. Starting and braking should not cause wheel slippage, and the operation was smooth, with the limit switches acting sensitively.

[0053] The tower crane functional tests include: No-load test: The tower crane's operation under no-load conditions, including hoisting, luffing, slewing, and running, will be tested. The following checks will be performed: First, the accuracy and flexibility of the operating system, control system, and interlocking devices. Second, the accuracy and reliability of each travel limit switch. Finally, whether there is oil leakage between non-moving parts in each mechanism, leakage at moving parts, and the smoothness of each mechanism's movement, including any climbing, vibration / impact, overheating, or abnormal noise.

[0054] Rated load test: The test shall be conducted under rated load conditions and shall include all actions. During the entire operation, each action shall be subjected to no less than three normal braking actions and each working condition shall be tested no less than three times. The measured values ​​of each parameter shall be the arithmetic average of the three tests.

[0055] 110% Rated Load Dynamic Load Test: The test is conducted under 110% rated load dynamic load conditions, and the test should include all actions. Each working condition should be tested no less than three times, and the measured values ​​of each parameter should be the arithmetic average of the three tests. Each action should be allowed to come to a complete stop before the next start-up. After unloading, there should be no loosening or damage to any components of the mechanism and structure.

[0056] 125% Rated Load Static Load Test: The test is conducted under a static load condition of 125% of the rated load. When lifting the rated load, the test load should be maintained at a distance of 100mm to 200mm from the ground. After maintaining this condition for ten minutes, measurements are taken at the same location and compared. During the test, the boom is positioned at two different angles relative to the tower body, namely 0° and 45°. During the test, there must be no visible cracks, permanent deformation or damage, loose connections, or other potential hazards that could affect the tower crane's performance or safety. The tower crane can only be put into use after the functional tests are completed, all indicators meet the requirements, and it has passed the acceptance inspection by all parties.

[0057] Furthermore, step S7 specifically includes: S71. The initial independent height of the tower crane installation is determined by the tower crane model. It is finally lifted to the installation height as the cooling tower is constructed. A total of four attachments are set. The height between the first attachment and the ground is greater than the distance between the second attachment and the other attachments. Specifically, the tower crane model is QTZ250. The initial independent installation height of the tower crane is 60m. It is eventually raised to the final installation height of 165m during the cooling tower construction. Four attachment points are installed, with the first attachment point at a height of 40m, and subsequent attachments every 30m. The larger height of the first attachment point from the ground effectively distributes the lateral forces and bending moments of the tower crane's upper structure, reducing stress concentration at the bottom of the tower crane. The smaller spacing between subsequent attachment points helps to evenly transfer and disperse the lateral loads of the tower crane, improving overall stability. Each attachment point must be installed after the concrete strength of the tower wall reaches 100% at the corresponding height, ensuring that the structure at the attachment point has sufficient load-bearing capacity and stability. This prevents attachment failure or structural damage due to insufficient concrete strength, effectively preventing excessive deformation or damage to the attachment points during the tower crane's lifting process and ensuring construction safety.

[0058] S72. The attachment device is connected to the main chord of the tower body through the attachment frame, and is connected to the connecting base embedded in the cooling tower wall through the attachment rod. The height difference between the attachment frame and the connecting base is allowed to be ≤200mm, which can effectively adapt to the verticality deviation during the construction of the cooling tower wall and ensure the connection reliability and stability of the attachment device. S73. When installing the attachment device, a theodolite can be used to check the verticality of the tower body axis. The lateral verticality deviation of the tower body axis above the uppermost attachment is 4 / 1000, and the verticality deviation of the tower body axis below the uppermost attachment is 2 / 1000.

[0059] In this embodiment, by accurately measuring the verticality of the tower's centerline, it is possible to ensure that the tower crane maintains a good vertical state during installation and use, avoiding abnormal stress and safety hazards caused by tilting. The verticality deviation of the part below the top attachment is 2 / 1000, because this part is close to the ground and is the foundation and main load-bearing part of the tower crane, and its verticality directly affects the overall stability. The part above the top attachment is allowed a slightly larger deviation of 4 / 1000. Considering the measurement difficulty and structural elastic deformation caused by the increase in height, the deviation limit is reasonably relaxed to balance construction difficulty and safety.

[0060] Tower crane dismantling: X1. Check the lifting system and rotate the boom back to the opening side of the climbing frame; Specifically, check whether each component of the lifting system is intact and free from leaks or oil seepage, and whether the lifting cylinder moves smoothly and in the correct position; check the oil level gauge of the lifting tank to see if the oil level is between 1 / 3 and 2 / 3 of the mark when the cylinder is fully retracted. If the oil level decreases, add oil in time; operate the lifting control handle to perform a test lifting action. When the pressure of the lifting system reaches the pressure set by the overflow valve, hold it for 10 seconds. If the pressure remains unchanged, the lifting system can be used for lifting and adding sections.

[0061] X2. Lower the standard section to the initial disassembly height; X3. Remove most of the counterweights, leaving only a small amount of counterweights; X4. Install a boom crane on the load-bearing trolley, including fixed lugs, boom main body, boom crane lugs, boom, auxiliary support rod, boom rope and anti-failure boom rope; X5. Use a derrick to disassemble the boom section from the top section to the third section of the boom in sequence. X6. After dismantling the derrick, dismantle the attachment devices one by one and continue to lower the standard sections. Before each dismantling of the attachments, the tower body must be lowered to the corresponding height. X7. Disassemble the remaining second section of the boom, counterweight, balance boom, boom root section, slewing assembly, special sections, climbing frame, and remaining standard and foundation sections.

[0062] like Figure 2 As shown in this embodiment, during tower crane dismantling, due to space constraints preventing lowering the crane sections, it is necessary to dismantle the jib tip section to the third section of the jib. By setting up a derrick crane and installing it on a load-bearing trolley, the problem of traditional dismantling methods being difficult to implement under limited space conditions is effectively solved. This improves the safety of the dismantling operation, significantly increases construction efficiency, shortens the construction period, and reduces construction and labor costs. Furthermore, detailed and reasonable planning of each stage of tower crane dismantling helps construction personnel operate according to the plan, reducing errors and omissions, improving work efficiency, ensuring the stability of the entire tower crane structure, and guaranteeing the smooth progress of the construction site.

[0063] Furthermore, step X2 specifically includes: X21. Rotate the boom back to the lead-in direction, i.e. the side of the climbing frame with the opening, so that the slewing brake is in the braking state, and the load trolley stops in the leveling position, which is consistent with the leveling position of the load trolley when the tower is lifted and the section is added. X22. Remove the connecting pin between the top standard section and the special section of the tower body, lift it slightly upwards, and place the guide wheel under the standard section in the specified direction, ensuring safety and reliability. Then remove the connecting bolts between the top standard section and the next standard section. X23. Extend the lifting cylinder, place the lifting beam in the arc groove of the third step from the top, insert the anti-detachment pin, lift the upper structure slightly, align the pin holes of the special section and the climbing frame connecting ear plate, drive in the pin shaft, and install the cotter pin. X24. Remove the connecting pin between the top standard section and the special section of the tower body, lift it slightly upwards, ensuring safety and reliability. Then remove the connecting pin between the top standard section and the next standard section, and install guide wheels at the four corners; X25. Continue lifting until the top standard section separates from the bottom standard section. Push the standard section out of the guide beam and support it firmly. Do not use excessive force when pushing it out, so as to avoid the standard section rushing out of the guide beam and overturning, causing an accident. X26. Open the movable climbing claw, retract the hydraulic cylinder, and let the movable climbing claw pass the pair of steps closest to it. Then, reset and flatten it, and continue to descend until the movable climbing claw supports the next pair of steps and supports the upper structure. Then, remove the anti-detachment pin and retract the hydraulic cylinder until the lifting beam moves away from the steps. X27. Extend the hydraulic cylinder, place the lifting beam on the next pair of steps, insert the anti-detachment pin, lift slightly until the climbing claw can avoid the steps it originally supported when it flips, then stop, spread the climbing claw, retract the hydraulic cylinder until the next standard section contacts the special section. If the connecting sleeve pin hole is misaligned, it can be adjusted into place with the random climbing frame adjustment tool. It is strictly forbidden to adjust or rotate the load trolley. X28. The special section is securely fastened to the standard section of the tower body with a high-strength pin, and the standard section is lifted to the ground with a trolley hook. X29. Repeat the above steps to disassemble the 5 standard sections one by one. At this point, the tower height is 150m.

[0064] In this embodiment, the positions of the load-bearing trolley and the slewing brake are first determined to ensure that the tower crane structure is under control during jacking. After disassembling the connecting pins and bolts, the tower body is gradually jacked up using the jacking cylinders and jacking beams, and anti-detachment pins are inserted for fixation to prevent structural loosening and overturning, ensuring the overall rigidity and stability of the tower body. The flexible operation of the movable climbing claws allows the climbing frame to smoothly climb to the next step, ensuring continuous and stable jacking operations. By disassembling five standard sections in stages, the tower height is reduced to 150 meters, facilitating transportation, maintenance, and construction adjustments.

[0065] Furthermore, step X3 specifically includes: X31. Secure the load trolley to the base of the crane boom and use the tower crane maintenance boom to remove the counterweight. X32. Following the reverse order of installation, remove each counterweight in turn, leaving only the 3.25t×2 counterweight block.

[0066] In this embodiment, during the counterweight disassembly process, the load trolley is first fixed to the base of the crane boom to prevent it from moving during disassembly and ensure construction safety. The counterweight is then disassembled using the tower crane's maintenance boom, leveraging its lifting capacity to conveniently and safely remove the counterweight piece by piece. Operating in the reverse order of counterweight installation ensures the tower crane's balance during disassembly, preventing tilting or instability due to improper sequence.

[0067] Furthermore, the X4 step specifically includes: X41. The fixed lugs of the boom crane are installed on the four corners of the load trolley; X42. Move the load trolley to the first section of the boom and weld at least four boom lugs onto the load trolley. X43. First, fix the load-bearing trolley with steel wire or hemp rope, then weld the connecting lugs of the auxiliary support rod and the connecting lugs of the main arm onto the trolley. The welding is performed using CO2 gas shielded welding, the weld grade is level three, and the weld leg height is ≥12mm. X44. After the derrick is assembled on the ground, use a roof crane to lift the entire derrick and install it onto the boom of the tower crane. After the X45, derrick, and auxiliary struts are assembled at the upper crossbeam, they are lifted to the installation height using a roof crane and connected to the ear plate on the load-bearing trolley via a Φ42 pin.

[0068] In this embodiment, by using CO2 gas shielded welding, the firmness and reliability of the connection between the derrick crane and the load trolley can be ensured. High-quality welding is the fundamental guarantee for the safe operation of the derrick crane, effectively preventing the risk of connection failure, thereby greatly enhancing the structural safety and stability of the derrick crane installation.

[0069] Furthermore, the X5 step specifically includes: X51. Disassembling the boom tip section and the ninth section of the boom: X52. Disassemble the eighth section of the boom, and then disassemble the seventh to third sections of the boom in the same way as disassembling the eighth section of the boom. X53. After the third section of the crane boom is disassembled, the derrick crane will be disassembled.

[0070] Furthermore, the X51 steps specifically include: After the X511, auxiliary support rod and derrick are installed, the load trolley is temporarily fixed and the derrick is lifted and pushed to the eighth section of the crane boom. X512. After moving the load trolley to the installation position, use a cloth belt and a 2t hoist to fix it at the four rollers of the load trolley and at the lower chord of the lifting arm. Then, first use the cloth belt to pass through the lower chord of the lifting arm from under the load trolley and wrap it around twice. Fix the 2t hoist to the upper chord of the lifting arm, with one end of the hoist connected to the cloth belt. Pull the chain hoist to fix the load trolley at the lower chord of the lifting arm. X513. Use a 4t to 5t hoist as the boom rope, hang the hoist on the upper chord of the crane boom, and connect the other end of the hoist to the boom rod; the connection should be treated to prevent slippage and detachment, and ensure stable force distribution.

[0071] X514. After the boom rope is installed, add another failure prevention boom rope to improve operational safety. X515. Adjusting the lifting angle of the boom: First, tighten the two arm ropes to relieve the auxiliary support rod from stress. Then, loosen the auxiliary support rod and slowly release the two arm rope hoist chains to adjust the lifting angle of the boom. X516. Install wire rope guide pulleys on the counterweight boom and the upper chord of the lifting boom. The guide pulleys are fixed to the upper chord with clamps and bolts. The tower crane hoisting wire rope first passes through the guide pulley at the upper chord of the counterweight boom, then passes through the guide pulley at the upper chord of the lifting boom, then passes between the two derricks, and then passes around the pulley at the lifting end of the derrick. Finally, it passes out between the two derricks to complete the arrangement of the wire rope. Finally, install the hook. X517. First, disassemble the connecting pin between the lower chord of the ninth section and the eighth section of the boom, then disassemble the connecting pin of the upper chord, and slightly loosen the hoisting wire rope; next, slowly release the hemp rope connecting the ninth section and the upper chord of the eighth section of the boom, so that the upper chord connection gradually separates. After the upper chord connection is completely separated, slowly release the hemp rope again; when the ninth section of the boom and the boom tip reach a balanced state, gradually lower the hoisting wire rope and control the derrick to lower the disassembled boom section to the ground.

[0072] In this embodiment, by providing temporary wire or hemp rope and two methods for securing the load-bearing trolley during operation—using a cloth strap and a 2t hoist—the precise position and stability of the load-bearing trolley during the installation of the boom crane and the dismantling of the boom section are ensured. This effectively prevents accidental displacement of the trolley during stress or operation, thus guaranteeing the accuracy and safety of the boom crane operation. Secondly, by adding a fail-safe boom rope, meaning that if the 5t hoist, acting as the boom rope, fails unexpectedly, the fail-safe boom rope can intervene in time to prevent the boom crane from becoming unstable or falling, thereby significantly improving the safety of the core dismantling operation and reducing potential accident risks. Furthermore, the method of adjusting the boom angle avoids impact and instability during the angle adjustment process, allowing the boom crane to accurately align with the boom section to be dismantled, thereby improving the efficiency and safety of the core dismantling operation.

[0073] Furthermore, the X52 steps specifically include: X521. Disassemble the connecting part of the auxiliary support rod, pull the pole up with two pull arm ropes to tilt it at an angle of 70° to 80°, and then install the auxiliary support rod. X522. Slowly loosen the two arm ropes to allow the auxiliary support rod to bear the force, then remove the two arm ropes. When the derrick is lifting, the lifting wire rope should be tightened slowly at the same time. X523. After removing the two pull arm ropes, slowly loosen the cloth belt that fixes the trolley, release the 2t hoist chain, and after the cloth belt is loosened, remove it completely. All removed hoists, cloth belts, pull arm ropes, etc. should be placed inside the trolley maintenance platform. After disassembling X524, the cloth belt and the 2t hoist, start from the end of the eighth section of the boom and remove all the wire rope guide pulleys on the eighth section of the boom. At this time, the lifting wire rope is completely loosened. The operator places two hemp ropes on the main legs at both ends of the boom. When pulling the hemp ropes, the load trolley slides towards the seventh section of the boom. After the X525 trolley arrives at its position, install it on the seventh section of the boom, following the installation method for the derrick crane. After the derrick crane is installed, disassemble the eighth section of the boom, following the disassembly method for the ninth and tip sections. Then, disassemble the seventh to third sections of the boom, following the steps for disassembling the eighth section.

[0074] In this embodiment, the boom is pulled up by two arm ropes to tilt at an angle of 70°–80°, ensuring that the auxiliary support rod is in the correct position and angle during installation, facilitating subsequent dismantling operations. Slowly releasing the arm ropes and applying force to the auxiliary support rod smoothly transfers the load during dismantling to the rod, preventing sudden stress that could cause structural damage or safety accidents. Disassembling the arm ropes, conveyor belt, and 2t hoist, and placing them within the trolley maintenance platform, ensures a clean and orderly construction site, prevents component loss or damage, and facilitates subsequent maintenance and management.

[0075] Furthermore, the X6 step specifically includes: X61. Remove the fourth attachment; X62. After dismantling the attachment device, the tower crane lowers 10 standard sections by itself, at which point the tower height is 111m. X63. Remove the third attachment in the same manner as removing the fourth attachment; X64. After removing the attachments, the tower crane lowers the tower by 10 standard sections, at which point the tower height is 81m. X65. Remove the second attachment in the same manner as removing the fourth attachment; X66. After removing the attachments, the tower crane lowers the tower by 10 standard sections, at which point the tower height is 51m. X67. Remove the first attachment in the same way as removing the fourth attachment; X68. After removing the attachments, the tower crane lowers 11 standard sections by itself, at which point the tower height is 18m.

[0076] In this embodiment, after each attachment is dismantled, a certain number of standard sections are lowered by the tower crane itself to gradually reduce the height of the tower, which facilitates the subsequent dismantling work. This phased dismantling method not only improves the dismantling efficiency, but also ensures the safety and stability of the entire dismantling process.

[0077] Furthermore, the X7 steps specifically include: X71. Before disassembling the second section of the crane boom, first disassemble the load trolley; X72. Use a truck crane to lift the remaining counterweights one by one and place them on the ground; X73. When the hoisting wire rope and the counterweight boom are taut, first remove the connecting pin between the tie rod and the root section of the boom, then slowly lift the boom so that the counterweight boom and the root section of the boom are tilted to the specified angle, and finally remove the connecting pin between the counterweight boom and the boom. X74. When the wire rope of the boom root section is taut, remove the pin, bushing, pin and locking pin connecting the boom root section and the upper support, and then slowly lift the boom root section and place it on the support surface with pads or wooden partition boards. X75. According to the lifting point position during installation, use a crane to lift the slewing assembly, then disassemble the connecting pin and vertical pin between the lower slewing support and the special section, and finally lift the slewing assembly to the ground. X76. Before disassembly, check whether there are cable connections between the special section and adjacent components. Then, use a crane to lift the special section, remove the connecting pin between the special section and the tower body, and lower the special section to the ground with slings. X77. Use a crane to lift the climbing frame, remove the pin between the lifting beam and the lifting cylinder, retract the lifting cylinder to let it hang down naturally, and then slowly lift the climbing frame along the tower body and place it on the ground. X78. Disassemble the standard section and the foundation section in sequence to complete the entire disassembly work.

[0078] In this embodiment, by disassembling each remaining structure in a detailed and reasonable sequence, construction personnel can operate according to plan, reduce errors and omissions, improve work efficiency, ensure the stability of the entire tower crane structure, and guarantee the smooth progress of construction on site.

[0079] After the tower crane is dismantled, it needs to be inspected by engineering technicians and professional maintenance personnel. The main load-bearing structural components should be inspected for metal fatigue, weld cracks, structural deformation, etc. The tower crane parts should be checked for damage or dents. After the inspection is completed, the defects and hidden dangers should be repaired before rust prevention and painting.

[0080] The present application has been described in detail above. Specific examples have been used to illustrate the principles and implementation methods of the present application. The descriptions of the embodiments above are only for the purpose of helping to understand the present application and its core ideas. It should be noted that those skilled in the art can make several improvements and modifications to the present application without departing from the principles of the present application, and these improvements and modifications also fall within the protection scope of the claims of the present application.

Claims

1. A construction method for a tower crane, characterized by the following steps: include: Tower crane foundation construction; Tower crane installation: S1. Install one foundation section and one standard section; S2. Install the climbing frame and jacking system; S3. Install the special section, slewing assembly, and boom root section; S4. Assemble the boom and counterweight on the ground, and sequentially hoist the counterweight, part of the counterweight, boom, and remaining counterweight; S5. Install warning lights and anemometer, and thread the wire rope; S6. Connect the power supply and conduct no-load test run and functional tests; S7. Jack up the tower crane and install the attachment devices in stages; Tower crane dismantling: X1. Inspect the jacking system and rotate the jib to the opening side of the climbing frame; X2. Lower the standard section to the initial dismantling height; X3. Remove most of the counterweight, leaving a small amount; X4. Install the derrick crane on the load trolley, including the fixed lugs, derrick main body, derrick crane lugs, derrick, auxiliary struts, tie rod ropes, and anti-failure tie rod ropes; X5. Use the derrick crane to dismantle the jib section from the tip section to the third section of the jib in sequence; X6. After dismantling the derrick crane, dismantle the attachment devices one by one and continue to lower the standard section. Before each attachment removal, the tower body must be lowered to the corresponding height; X7. Dismantle the remaining second section of the jib, counterweight, counterweight boom, boom root section, slewing assembly, special sections, climbing frame, and the remaining standard and foundation sections.

2. The construction method of the tower crane according to claim 1, characterized in that: The steps involved in tower crane foundation construction include: Y1. Excavate the tower crane foundation according to the determined coordinates. Combine the excavation of the cooling tower with the excavation of the earthwork. Use a slope ratio of 1:0.75 for the excavation. Set up warning lines in the construction area during the excavation. Y2. Based on the tower crane design load parameters, construct a slab-type reinforced concrete foundation. The top elevation of the foundation should be consistent with the bottom elevation of the adjacent water tank and a post-cast area should be reserved. Y3. A drainage system should be installed around the concrete foundation soil layer; Y4. Two flat iron bars are led out from the main grounding of the building to the foundation surface, and protruded 200mm to 300mm from the concrete surface. The grounding resistance is required to be ≤4Ω. Y5. Embed fixed legs or sections in the foundation steel mesh, and set a pad or iron stool under the embedded legs to ensure that the installation flatness error is less than 1 / 1000 of the cross-section of the standard section. The exposed size of the anchor foot of the embedded leg is 150mm to 200mm. Y6. Pour concrete and cure it until the concrete strength reaches 1.2MPa before conducting foundation acceptance.

3. The construction method of the tower crane according to claim 1, characterized in that: The S1 step specifically also includes: S11. Lift the base section above the pre-embedded support leg, align the pin hole of the base section with the hole of the pre-embedded support leg, and insert the pin, vertical pin and cotter pin. S12. Lift the standard section above the base section, align the pin hole of the standard section with the hole of the base section, and insert the pin, vertical pin and cotter pin; The S2 step specifically also includes: S21. Install the climbing frame platform, ladder, lead-in structure and jacking cylinder in sequence, and carry out overall hoisting after ensuring that the connection is firm. During hoisting, hang the lifting gear on the climbing frame, tighten the wire rope and hoist it. The position of the jacking cylinder is on the same side as the tower steps. Then slowly put the climbing frame on the outside of the tower. S22. Place the climbing claws on the climbing frame onto the steps on the upper part of the base section, and adjust the position of the climbing frame so that the gaps on each side between the climbing guide wheel and the standard section are basically consistent.

4. The construction method of the tower crane according to claim 1, characterized in that: The S5 step specifically includes: S51. When the hinge point height at the base of the boom is greater than 50m, an anemometer can be installed on the top of the tower crane. When the tower crane is used at a height greater than 30m, obstruction lights can be installed, and the distance between the obstruction lights and the beams must be greater than 150m.

5. The construction method of the tower crane according to claim 1, characterized in that: The S6 step specifically includes: S61. When the wind speed is ≤3m / s and the tower is unloaded, the verticality of the tower is measured with a theodolite and the error of the verticality is ≤4 / 1000.

6. The construction method of the tower crane according to claim 1, characterized in that: The S7 step specifically includes: S71. The initial independent height of the tower crane installation is determined by the tower crane model. It is finally lifted to the installation height as the cooling tower is constructed. A total of four attachments are set. The height between the first attachment and the ground is greater than the distance between the second attachment and the other attachments. S72. The attachment device is connected to the main chord of the tower body through the attachment frame, and is connected to the connecting base embedded in the cooling tower wall through the attachment rod. The height difference between the attachment frame and the connecting base is allowed to be ≤200mm. S73. When installing the attachment device, a theodolite can be used to check the verticality of the tower body axis. The lateral verticality deviation of the tower body axis above the uppermost attachment is 4 / 1000, and the verticality deviation of the tower body axis below the uppermost attachment is 2 / 1000.

7. The construction method of the tower crane according to claim 1, characterized in that: The X4 step specifically includes: X41. The fixed lugs of the boom crane are installed on the four corners of the load trolley; X42. Move the load trolley to the first section of the boom and weld at least four boom lugs onto the load trolley. X43. First, fix the load-bearing trolley with steel wire or hemp rope. Then, weld the connecting lugs of the auxiliary support rod and the connecting lugs of the main body of the derrick onto the trolley. The weld grade is level three, and the weld leg height is ≥12mm.

8. The construction method of the tower crane according to claim 7, characterized in that: The X5 step specifically includes: X51. Disassemble the boom tip section and the ninth section of the boom; X52. Disassemble the eighth section of the boom, and then disassemble the seventh to third sections of the boom in the same way as disassembling the eighth section of the boom. X53. After the third section of the crane boom has been disassembled, the derrick crane will be disassembled. Specifically, step X52 further includes: X521. Disassemble the connecting part of the auxiliary support rod, pull up the pole with the two pull arm ropes to make its tilt angle 70°~80°, and then install the auxiliary support rod.

9. The construction method of the tower crane according to claim 8, characterized in that: The X51 step specifically includes: After the X511, auxiliary support rod and derrick are installed, the load trolley is temporarily fixed and the derrick is lifted and pushed to the eighth section of the crane boom. X512. After moving the load trolley to the installation position, use cloth straps and a 2t hoist to fix it at the four rollers of the load trolley and the lower chord of the lifting arm. X513. Use a 4t to 5t hoist as the boom rope, hang the hoist on the upper chord of the crane boom, and connect the other end of the hoist to the boom rod. X514. After the boom rope is installed, add another boom rope to prevent failure. X515. Adjust the angle of the boom lift; X516. Install wire rope guide pulleys on the upper chord of the counterweight boom and lifting boom; X517. First, remove the connecting pin between the lower chord of the ninth section of the boom and the eighth section of the boom, then remove the connecting pin of the upper chord; control the derrick to lower the disassembled boom section to the ground.

10. The construction method of the tower crane according to claim 9, characterized in that: The X7 step specifically includes: X71. Before disassembling the second section of the crane boom, first disassemble the load trolley; X72. Use a truck crane to lift the remaining counterweights one by one and place them on the ground; X73. When the hoisting wire rope and the counterweight boom are taut, first remove the connecting pin between the tie rod and the root section of the boom, then slowly lift the boom so that the counterweight boom and the root section of the boom are tilted to the specified angle, and finally remove the connecting pin between the counterweight boom and the boom. X74. When the wire rope of the boom root section is taut, remove the pin, bushing, pin and locking pin connecting the boom root section and the upper support, and then slowly lift the boom root section and place it on the support surface with pads or wooden partition boards. X75. According to the lifting point position during installation, use a crane to lift the slewing assembly, then disassemble the connecting pin and vertical pin between the lower slewing support and the special section, and finally lift the slewing assembly to the ground. X76. Before disassembly, check whether there are cable connections between the special section and adjacent components. Then, use a crane to lift the special section, remove the connecting pin between the special section and the tower body, and lower the special section to the ground with slings. X77. Use a crane to lift the climbing frame, remove the pin between the lifting beam and the lifting cylinder, retract the lifting cylinder to let it hang down naturally, and then slowly lift the climbing frame along the tower body and place it on the ground. X78. Disassemble the standard section and the foundation section in sequence to complete the entire disassembly work.

Citation Information

Patent Citations

  • Wind speed detection device and tower crane

    CN103274320A

  • Construction process for mounting and dismounting tower crane

    CN117776008A

  • Tower crane mounting and dismounting method

    CN118619129A

  • Installation and device of dismantling jib loading boom

    CN205527435U

  • Dismounting device for cargo boom and balance arm of tower crane

    CN212712478U