Project progress deviation dynamic early warning method facing whole process consultation
By adopting strategies for assessing propulsion synchronization fluctuations and pre-controlling resource consumption levels in shield tunnel construction, the problem of lack of coordination in multi-face propulsion was solved, achieving balanced resource supply and overall efficiency improvement in tunnel construction.
Patent Information
- Application Number
- CN202610058042.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-01-16
- Publication Date
- 2026-05-01
AI Technical Summary
Existing technologies have failed to effectively quantify and reflect the collaborative relationship between multiple working faces in shield tunnel construction, resulting in an imbalance in the pace of working face advancement, uneven resource allocation, reduced overall advancement efficiency, and an inability to predict and control progress in advance.
By using a multi-face collaborative evaluation mechanism based on the propulsion synchronization fluctuation rate and a hierarchical pre-control strategy for resource consumption, the construction management system is used to obtain tunnel area information, detect the ring number propulsion rate and cutterhead replacement frequency, calculate the engineering propulsion index and shield wear coefficient, evaluate the propulsion synchronization fluctuation rate, collect the grouting material consumption and the arrival interval of muck transport vehicles, identify the vehicle accumulation status and stratum hardness, predict resource consumption trends and generate resource consumption levels, determine the synchronization imbalance in the area and select pre-control measures.
It enables adaptive control of the working face rhythm, proactively mitigates resource shortages and blockage risks, ensures a balanced supply of grouting and transportation resources, and improves the overall tunnel advancement efficiency.
Smart Images

Figure CN121960970A_ABST
Abstract
Description
A dynamic early warning method for project schedule deviations oriented towards full-process consulting Technical Field
[0001] This invention relates to the field of engineering early warning technology, and more specifically, to a dynamic early warning method for engineering progress deviations that is oriented towards full-process consulting. Background Technology
[0002] Shield tunneling is usually carried out in a "ring-by-ring" manner. However, in complex scenarios such as densely populated urban areas, long tunnel sections, and connecting passage intersections, multiple working faces often exist in the same area (region) at the same time, such as the tunnel entrance working face, the main tunnel working face, and the connecting passage working face. In order to ensure the overall construction cycle and resource coordination efficiency, a certain degree of synchronization in the advancement of each working face is required.
[0003] The existing technology has the following shortcomings:
[0004] Currently, existing technologies mostly rely on planning deviations of a single working face for early warning. However, due to factors such as geological differences, cutterhead wear, and resource scheduling fluctuations, they neglect the collaborative relationship between multiple working faces within a region. They lack synchronicity indicators and dynamic evaluation mechanisms that can quantify the consistency of progress, leading to an imbalance in the working face's progress rhythm, uneven resource allocation, a decline in the overall progress efficiency of the region, and an inability to predict and control progress in advance. Therefore, a dynamic early warning method for engineering progress deviations based on full-process consulting is proposed.
[0005] The information disclosed in the background section is only intended to enhance the understanding of the background of this disclosure, and therefore may include information that does not constitute prior art known to those skilled in the art. Summary of the Invention
[0006] To overcome the aforementioned deficiencies of the prior art, embodiments of the present invention provide a dynamic early warning method for engineering progress deviations oriented towards full-process consultation. This method addresses the problems mentioned in the background art by employing a multi-workface collaborative evaluation mechanism based on propulsion synchronization volatility and a hierarchical pre-control strategy for resource consumption.
[0007] To achieve the above objectives, the present invention provides the following technical solution: a dynamic early warning method for engineering progress deviations oriented towards full-process consulting, comprising the following steps:
[0008] Step S1: During the tunnel boring machine (TBM) construction, access the construction management system to obtain the zoning information of the tunnel area to be tested, retrieve the working face classification data of each zoning area based on the zoning information, and detect the ring number advance rate and cutter change frequency of each working face.
[0009] Step S2: Calculate the engineering advancement index of the working face based on the ring number advancement rate, generate the shield wear coefficient of the working face using the cutterhead replacement frequency, evaluate the advancement synchronization fluctuation rate of the area in combination with the engineering advancement index, and determine whether to enter the resource analysis mechanism based on the advancement synchronization fluctuation rate.
[0010] Step S3: Collect the grouting material consumption of each working face within the resource analysis mechanism, count the arrival interval of the muck transport vehicles and analyze the vehicle accumulation status. When the vehicle accumulation status is abnormal, detect the hardness of the stratum in the working face environment.
[0011] Step S4: Based on the grouting material consumption, predict the resource consumption trend of the working face, combine the formation hardness to correct the resource consumption trend and generate a resource consumption level, and determine whether the area to which the resource consumption level belongs is synchronously unbalanced and select different pre-control measures.
[0012] In a preferred embodiment, in step S1, when the tunnel boring machine is advancing, the construction management system is accessed to obtain the zoning information of the area to be measured in the tunnel, and the zoning information includes the zoning number of each zoning area.
[0013] Import the area number into the engineering data index table to retrieve the work surface classification data of each area, including the number of each work surface;
[0014] The preset statistical period is used to obtain the number of tunneling rings of the working face within the preset statistical period through the ring number advancement log. The number of tunneling rings refers to the number of tunneling rings completed by the working face.
[0015] The ratio of the number of tunneling rings to the preset statistical period is used as the ring advance rate;
[0016] The number of cutter replacement operations for each working face is obtained from the maintenance log of the tunnel boring machine. The ratio of the number of cutter replacement operations to the preset statistical period is used as the cutter replacement frequency.
[0017] In a preferred embodiment, in step S2, within the same area, the advancement rate of each ring number is standardized using the Min-Max standardization method to obtain the ring number advancement rate factor.
[0018] Calculate the engineering advancement index of the working face based on the ring number advancement rate factor: ,in, The first in the area Ring number propulsion rate factor of each working face The first in the area The project progress index for each work area It is a natural constant. The preset gain coefficient, To preset the balance factor, The first in the area The ring number propulsion rate factor of each working face.
[0019] In a preferred embodiment, in step S2, the tool change frequency is standardized using the Min–Max standardization method to obtain the tool change frequency factor.
[0020] Calculation of shield wear coefficient at the working face based on cutter replacement frequency factor: ,in, The first in the area Tool change frequency factor for each working face To preset the wear coefficient, The first in the area The shield wear coefficient of each working face;
[0021] The shield wear coefficient, combined with the engineering propulsion index, is used to calculate the propulsion synchronization fluctuation rate of the corresponding area. ,in, The first in the area The shield wear coefficient of each working face This represents the average of the progress indices for various projects within the area. This represents the total number of working faces within the area. The value can be from 1 to N. The first in the area The project progress index for each work area To synchronize the fluctuation rate of the region's progress.
[0022] In a preferred embodiment, in step S2, the propulsion synchronization volatility is compared with a preset propulsion synchronization threshold to determine whether to enter the resource analysis mechanism:
[0023] If the synchronization volatility exceeds the preset synchronization threshold, the resource analysis mechanism will be activated.
[0024] Conversely, if the condition is not met, the resource analysis mechanism will not be initiated.
[0025] In a preferred embodiment, in step S3, data is accessed for the grouting pump stations corresponding to each working face within the resource analysis mechanism to obtain the grouting material consumption per unit time for each working face.
[0026] The flow rate of the grout is continuously measured per unit time by the flow meter of the grouting pump, and the cumulative grouting volume is generated based on the product of the output flow rate and the grouting duration. The cumulative grouting volume is the amount of grouting material consumed at the working face.
[0027] The arrival records of construction waste transport vehicles responsible for the task of discharging and transporting construction waste within the area are statistically analyzed, and the time difference between the arrival of two adjacent construction waste transport vehicles at the working face is taken as the arrival interval of construction waste transport vehicles.
[0028] In a preferred embodiment, in step S3, within a preset statistical window, the reciprocal of the arrival interval of each muck transport vehicle is calculated, and the arithmetic mean of all reciprocals is calculated as the vehicle accumulation index.
[0029] When the vehicle accumulation index is less than or equal to the preset vehicle status threshold, the vehicle accumulation status is determined to be normal; when the vehicle accumulation index is greater than the preset vehicle status threshold, the vehicle accumulation status is determined to be abnormal.
[0030] When the vehicles are piled up abnormally, the soil hardness is obtained by continuously collecting the pressure of the soil in front of the cutterhead through the earth pressure sensor at the front of the tunnel boring machine.
[0031] In a preferred embodiment, in step S4, a continuous time series analysis is performed on the grouting material consumption of each working face within a preset statistical window based on the grouting material consumption, that is, the resource consumption trend of the working face is generated by the cumulative weighted average method.
[0032] The resource consumption trend is corrected using formation hardness; the correction calculation formula is as follows:
[0033] ;
[0034] in, As resource consumption trends, This is the revised resource consumption trend. For the hardness of the formation, The preset reference formation hardness;
[0035] Based on the revised resource consumption trend, the resource consumption levels of each working face are divided into low-load and high-load levels.
[0036] In a preferred embodiment, in step S4, the proportion of work surfaces with high resource consumption level within the area is statistically analyzed to obtain the area imbalance assessment index.
[0037] The regional imbalance assessment index is compared with the preset synchronous imbalance threshold. When the regional imbalance assessment index is greater than the synchronous imbalance threshold, it is determined that there is synchronous imbalance in the region.
[0038] Conversely, when the imbalance assessment index of a region is less than or equal to the preset synchronization imbalance threshold, the region is determined to remain in a synchronized state.
[0039] When there is a synchronous imbalance in the area, different pre-control measures are implemented for work surfaces with different resource consumption levels.
[0040] The technical effects and advantages of this invention are as follows:
[0041] This invention obtains tunnel section zoning information by accessing the construction management system during shield tunneling, retrieves classification data for each section's working face, and detects the ring number advancement rate and cutterhead replacement frequency. Based on this, it calculates the engineering advancement index and shield wear coefficient, and then assesses the section's advancement synchronization fluctuation rate. Based on this fluctuation rate, it determines whether to enter the resource analysis mechanism. In this mechanism, it collects the grouting material consumption of each working face, counts the arrival intervals of excavated soil transport vehicles, and identifies vehicle accumulation status. When accumulation is abnormal, it detects the stratum hardness and predicts resource consumption trends based on grouting consumption. After correction based on stratum hardness, it generates a resource consumption level. Based on this level, it determines whether the section is synchronously unbalanced and selects corresponding pre-control measures. This achieves adaptive control of the working face rhythm, proactively mitigating the risks of resource shortages and blockages caused by asynchronous advancement, ensuring a balanced supply of grouting and transportation resources, and improving the overall tunnel advancement efficiency. Attached Figure Description
[0042] Figure 1 is a flowchart illustrating the implementation of a dynamic early warning method for engineering progress deviations based on full-process consulting according to the present invention.
[0043] Figure 2 is a schematic diagram of the steps of a dynamic early warning method for engineering progress deviations oriented towards full-process consulting according to the present invention. Detailed Implementation
[0044] The technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention.
[0045] This invention obtains tunnel section zoning information by accessing the construction management system during shield tunneling, retrieves classification data for each section's working face, and detects the ring number advancement rate and cutterhead replacement frequency. Based on this, it calculates the engineering advancement index and shield wear coefficient, and then assesses the section's advancement synchronization fluctuation rate. Based on this fluctuation rate, it determines whether to enter the resource analysis mechanism. In the mechanism, it collects the grouting material consumption of each working face, counts the arrival interval of muck transport vehicles, and identifies the vehicle accumulation status. When the accumulation is abnormal, it detects the stratum hardness and predicts the resource consumption trend based on grouting consumption. After combining the stratum hardness correction, it generates a resource consumption level. Based on this level, it determines whether the section is synchronously unbalanced and selects corresponding pre-control measures to achieve adaptive control of the working face rhythm, resolves the risk of resource shortage and blockage caused by asynchronous advancement in advance, and ensures a balanced supply of grouting and transportation resources.
[0046] Example 1, as shown in Figures 1 and 2, illustrates a dynamic early warning method for engineering schedule deviations in a full-process consulting framework, comprising the following steps:
[0047] Step S1: During the tunnel boring machine (TBM) construction, access the construction management system to obtain the zoning information of the tunnel area to be tested, retrieve the working face classification data of each zoning area based on the zoning information, and detect the ring number advance rate and cutter change frequency of each working face.
[0048] Step S2: Calculate the engineering advancement index of the working face based on the ring number advancement rate, generate the shield wear coefficient of the working face based on the cutterhead replacement frequency, evaluate the advancement synchronization fluctuation rate of the area in combination with the engineering advancement index, and determine whether to enter the resource analysis mechanism based on the advancement synchronization fluctuation rate.
[0049] Step S3: Collect the grouting material consumption of each working face within the resource analysis mechanism, count the arrival interval of the muck transport vehicles and analyze the vehicle accumulation status. When the vehicle accumulation status is abnormal, detect the hardness of the stratum in the working face environment.
[0050] Step S4: Based on the grouting material consumption, predict the resource consumption trend of the working face, combine the formation hardness to correct the resource consumption trend and generate a resource consumption level, and determine whether the area to which the resource consumption level belongs is synchronously unbalanced and select different pre-control measures.
[0051] The specific implementation is as follows:
[0052] In step S1, shield tunneling is a tunnel construction method that uses a shield machine to continuously excavate, support, and form tunnels in underground soil layers. During the shield machine's advancement, there are multiple working faces in each tunnel area at the same time. It is possible that the advancement of one working face is lagging behind, while another working face is advancing too fast, resulting in an imbalance in resource scheduling and thus affecting the overall construction rhythm. During the shield advancement process, the area division and the corresponding working face situation are first identified, and the basic advancement information of each working face is obtained.
[0053] During the implementation of tunnel boring machine (TBM) construction, the construction management system is accessed to obtain the zoning information of the tunnel area to be measured. The zoning information is the spatial division and management unit configuration information established for the overall construction scope of the tunnel, including the zoning number of each zoning area.
[0054] Import the area number into the engineering data index table to retrieve the working face classification data of each area. The working face classification data refers to the structured data that identifies, classifies and numbers the working faces of tunneling operations in each area, including the number of each working face.
[0055] A zone is used to divide the tunnel space into areas for unified management of construction resources and progress targets within the area; a working face is the specific construction point within a zone that actually undertakes tunneling operations; a zone can contain multiple working faces of different types.
[0056] The preset statistical period is used to obtain the number of tunneling rings of the working face within the preset statistical period through the ring number advancement log. The number of tunneling rings refers to the number of tunneling rings actually completed by the working face.
[0057] The tunneling ring number refers to the sequence number of the tunnel lining structure formed by the tunnel boring machine during the shield tunneling process. Each time a section of tunnel is completed and a ring of segments is installed, a new ring number is added.
[0058] The ratio of the number of tunneling rings to the preset statistical period is used as the ring advance rate;
[0059] The number of cutter replacement operations for each working face is obtained from the maintenance log of the tunnel boring machine. The ratio of the number of cutter replacement operations to the preset statistical period is used as the cutter replacement frequency.
[0060] The cutterhead replacement operation count refers to the cumulative number of times the tunnel boring machine performs a cutterhead replacement operation.
[0061] It should be noted that the construction management system is an engineering information platform used to store and manage data related to the tunnel construction process; the engineering data index table is an index structure used to retrieve data on the working face of a region based on the region number; the preset statistical period can be set according to the granularity of construction scheduling, the tunnel boring machine's advance speed, and data sampling requirements; the ring number advance log records the advance ring number and tunneling mileage of the tunnel boring machine at different time nodes; and the tunnel boring machine equipment maintenance log records equipment operation logs such as cutter replacement, maintenance, and changes in equipment status.
[0062] By acquiring information on zone divisions and classification data of working faces, a zone-level construction structure model is established in the early stages of the project. By collecting data on the advance rate of ring numbers and the frequency of cutter changes, quantifiable basic characteristics are provided for the advancement efficiency and equipment load of each working face. This ensures that subsequent synchronization analysis has data integrity and consistency, thereby effectively avoiding deviations in construction organization judgments caused by information fragmentation.
[0063] In step S2, within the same area, the advancement rate of each ring number is standardized using the Min–Max standardization method to obtain the ring number advancement rate factor: ,in, This represents the minimum advancing rate of the ring road within the area. This represents the maximum speed of the ring road within the area. The first in the area The propulsion rate of each ring number, The first in the area The ring number propulsion rate factor of each working face;
[0064] Calculate the engineering advancement index of the working face based on the ring number advancement rate factor: ,in, The first in the area The project progress index for each work area It is a natural constant. The preset gain coefficient, Preset balance factor;
[0065] It should be explained that the preset gain coefficient can be set according to the project's sensitivity requirements to the difference in ring number advancement rate factor; the preset balance factor can be set according to the ring number advancement rate factor corresponding to the advancement needs of the area.
[0066] The engineering progress index reflects the actual progress efficiency of the working face within a preset statistical period and its relative progress level within the area. The larger the engineering progress index, the faster the ring number of the working face increases, and its progress pace is among the top in the area. The smaller the engineering progress index, the lower the actual progress capacity of the working face, and its progress pace is relatively lagging.
[0067] The tool change frequency factor is obtained by standardizing each tool change frequency using the Min–Max standardization method.
[0068] Calculation of shield wear coefficient at the working face based on cutter replacement frequency factor: ,in, The first in the area Tool change frequency factor for each working face To preset the wear coefficient, The first in the area The shield wear coefficient of each working face;
[0069] The shield wear coefficient is used to identify the degree of limitation in the advancement of the working face. The larger the shield wear coefficient, the more frequent the cutter replacement operation is within the preset statistical period, the stronger the abrasiveness of the strata or the faster the cutter wear rate. The shield machine will experience greater advancement resistance and its advancement efficiency will be more easily affected.
[0070] The shield wear coefficient, combined with the engineering advancement index, is used to assess the advancement synchronization fluctuation rate of the corresponding area. ,in, The first in the area The shield wear coefficient of each working face This represents the average of the progress indices for various projects within the area. This represents the total number of working faces within the area. The value can be from 1 to N. The first in the area The project progress index for each work area To synchronize the volatility of the region's development;
[0071] The synchronization volatility reflects the consistency of the progress rhythm of each work face within the area, and is used to measure whether different work faces maintain coordinated progress within the same construction cycle. The larger the synchronization volatility, the more obvious the deviation between the engineering progress index of each work face and the average progress level of the area, the greater the difference in progress rhythm, and the risk that the overall construction organization of the area may face a decline in synchronization.
[0072] The propulsion synchronization volatility is compared with a preset propulsion synchronization threshold to determine whether to initiate the resource analysis mechanism.
[0073] If the synchronization volatility exceeds the preset synchronization threshold, the resource analysis mechanism will be activated.
[0074] Conversely, if the condition is not met, the resource analysis mechanism will not be initiated.
[0075] It should be explained that the Min-Max standardization method is a scaling method that uses the minimum and maximum values of parameters in the sample set to construct a linear interval, mapping the original data to a dimensionless range; the preset wear coefficient can be set according to the wear resistance level of the shield cutter, the average cycle of cutter replacement operations, and the statistical results of equipment operating load in the project; the preset propulsion synchronization threshold can be set according to the previous propulsion rhythm data of similar tunnel projects and the number of working faces in the area.
[0076] This step combines the engineering progress index with the shield wear coefficient, which can assess the coordination of progress across multiple working faces. This helps to schedule resources, adjust the pace, or control risks in advance, thereby improving the overall progress efficiency and construction stability of the area.
[0077] In step S3, after determining that the area has entered the resource analysis mechanism, the resource chain status of each working face in the area is collected and analyzed to identify the coupling imbalance between resource supply and progress rhythm. This includes obtaining the grouting material consumption, statistically analyzing the arrival interval of muck transport vehicles, analyzing the vehicle accumulation status, and detecting the hardness of the stratum. The data sources, parameter meanings, and analysis purposes of each part are as follows.
[0078] Data is accessed for the grouting pump stations corresponding to each working face within the resource analysis mechanism to obtain the grouting material consumption per unit time for each working face. The output flow rate of the grout per unit time is continuously measured by the flow meter of the grouting pump, and the cumulative grouting volume is generated based on the product of the output flow rate and the grouting duration. The cumulative grouting volume is used as the grouting material consumption of the working face to reflect the immediate needs of the working face advancement activities for stratum stability and backfilling requirements.
[0079] Secondly, the arrival records of construction waste transport vehicles responsible for waste disposal within the area are statistically analyzed to calculate the arrival interval of these vehicles. This interval is derived from the vehicle check-in data of the construction waste transportation dispatch system. When a construction waste transport vehicle arrives at the work site, the onboard construction waste transportation dispatch system automatically checks in and records the arrival time. The arrival interval represents the time difference between the arrival of two adjacent construction waste transport vehicles at the work site, reflecting the continuity and smoothness of the construction waste transportation chain within the area. When the arrival interval is significantly shortened, it indicates an increase in the work site advancement speed or an increase in the amount of construction waste generated. Conversely, when the arrival interval is extended, it indicates a decrease in the capacity for transporting construction waste or an obstruction in the waste disposal route.
[0080] It should be noted that the construction waste transportation dispatch system is a dedicated information system for managing the transportation of construction waste during tunnel construction. It uses onboard terminals installed on construction waste transport vehicles as data acquisition units. These terminals automatically record the time information of key milestones such as vehicle arrival at the work site, completion of loading, and departure from the work site, and transmit this time information back to the dispatch platform. Through unified management of vehicle location, operational status, and arrival time, the construction waste transportation dispatch system enables the dispatch, tracking, and statistics of the construction waste transportation chain within the area. The vehicle check-in data generated by the system constitutes the sole source of information on the arrival intervals of construction waste transport vehicles and provides fundamental data support for the analysis of construction waste transportation capacity and the assessment of the synchronicity of regional progress.
[0081] Subsequently, after obtaining the arrival intervals of the muck transport vehicles, the vehicle accumulation status within the working face was analyzed. Specifically, within a preset statistical window, the reciprocal of each muck transport vehicle arrival interval was calculated, and the arithmetic mean of all reciprocals was taken as the vehicle accumulation index. The vehicle accumulation index is used to characterize the instantaneous density of vehicles within the working face. The larger the value, the more frequently the muck transport vehicles arrive, the denser the vehicles within the working face, and the higher the accumulation risk; the smaller the value, the lower the vehicle arrival frequency, and the smoother the transportation chain within the working face.
[0082] To achieve automatic identification of congestion in the transportation of construction waste at the working face, a vehicle status threshold is set based on a vehicle accumulation index to classify the status. Specifically, when the vehicle accumulation index is less than or equal to the vehicle status threshold, the vehicle accumulation status is determined to be normal, indicating that the arrival frequency of construction waste transport vehicles is within an acceptable range and the transportation chain at the working face remains smooth. When the vehicle accumulation index is greater than the vehicle status threshold, the vehicle accumulation status is determined to be abnormal, indicating that the arrival of construction waste transport vehicles at the working face is too dense, and there are phenomena such as queuing, congestion, or increased loading waiting time.
[0083] It should be noted that in the early stages or pre-construction phase of tunnel boring machine (TBM) construction, historical statistical analysis is conducted on the continuous arrival data of muck transport vehicles within the target working face. The mean value and fluctuation range of the vehicle accumulation index under normal construction progress conditions are calculated. Combined with the maximum queue length and maximum waiting time allowed by construction scheduling, the vehicle accumulation index is added to the mean value as the vehicle status threshold. This will not be elaborated upon here.
[0084] When abnormal vehicle accumulation occurs, the hardness of the soil in the working face is tested to identify whether the accumulation is caused by fluctuations in propulsion resistance due to changes in the soil. Soil hardness is determined by an earth pressure sensor located at the front of the tunnel boring machine (TBM). This sensor continuously collects data on the pressure exerted on the soil in front of the cutterhead during TBM tunneling. Specifically, before the soil is cut by the cutterhead, the earth pressure sensor senses the positive resistance of the soil to the TBM's excavation face. By recording changes in this positive resistance, a pressure curve reflecting the soil's resistance to cutting is formed. The average pressure value extracted from this curve is defined as the soil hardness, which characterizes the resistance of the soil in front of the working face to cutterhead cutting under current tunneling conditions. A higher value indicates denser or harder soil, resulting in increased tunneling resistance; a lower value indicates looser or more easily cut soil, resulting in decreased tunneling resistance.
[0085] It should be noted that an earth pressure sensor is a specialized measuring device installed near the cutterhead or tunnel face of a tunnel boring machine (TBM) to sense the pressure exerted by the soil on the TBM in real time. It converts the positive resistance of the soil on the cutterhead or tunnel face into a digital signal through mechanical elements and continuously records the changes in the pressure exerted by the soil on the TBM.
[0086] In step S4, based on the grouting material consumption, a continuous time series analysis is performed on the grouting material consumption of each working face within a preset statistical window. The rate of change of grouting material consumption per unit time is calculated, i.e., the resource consumption trend of the working face is generated by the cumulative weighted average method. The calculation formula is as follows:
[0087] ;
[0088] in, As resource consumption trends, Let be the amount of grouting material consumed at time t. Let t be the time weight of time t, and n be the total number of times within the statistical window.
[0089] It should be noted that the time weight is used to reflect the degree of influence of grouting material consumption on resource consumption trends in different time periods. The method of setting it is to allocate gradually increasing weight coefficients in chronological order within the statistical window, so that the statistical results can better reflect the current progress status, while avoiding unnecessary influence of early data on trend judgment.
[0090] Resource consumption trend is used to characterize the growth or decline trend of resource consumption per unit time in the future. The larger the value, the higher the resource consumption intensity.
[0091] Subsequently, the resource consumption trend was corrected using ground hardness to reflect the impact of soil hardness changes on propulsion resistance and material requirements. The corrected calculation formula is as follows:
[0092] ;
[0093] in, This is the revised resource consumption trend. For the hardness of the formation, For reference formation hardness.
[0094] It should be noted that the reference stratum hardness is used to measure whether the current stratum hardness variation is within the normal range. It is set based on the pre-construction geological survey report, test excavation records, and data collected by earth pressure sensors during the initial stable tunneling phase of the tunnel boring machine (TBM). The stable range of stratum hardness is calculated, and the average value of this stable range is taken as the reference stratum hardness. When the stratum hardness is higher than the reference stratum hardness, it means the soil is harder and the TBM tunneling resistance is greater. To maintain the stability of the excavation face and control stratum settlement, it is necessary to increase the grouting pressure or grouting volume, leading to an increased resource consumption trend. Therefore, the corrected resource consumption trend will be correspondingly increased. Conversely, when the stratum hardness is lower, the tunneling resistance is smaller, and the dependence on grouting materials is reduced; therefore, the resource consumption trend is corrected downwards.
[0095] Based on the revised resource consumption trend, resource consumption levels for each work surface are divided into low-load and high-load levels. Specifically, the resource consumption trend is compared with preset resource consumption thresholds:
[0096] When the resource consumption trend is less than or equal to the preset resource consumption threshold, the resource consumption level of the corresponding work surface will be determined as the low load level.
[0097] When the resource consumption trend exceeds the preset resource consumption threshold, the resource consumption level of the corresponding work surface will be determined as the high load level.
[0098] The resource consumption level is used to characterize the pressure on the working face to consume grouting materials during the future construction cycle.
[0099] It should be noted that the resource consumption threshold is used to distinguish between high-load and low-load levels of resource consumption trends. The method for setting it is to collect resource consumption trend values of typical working faces under normal advance conditions during the initial stage of shield tunneling or trial operation, statistically analyze its long-term average and fluctuation range, and then add the resource supply fluctuation margin allowed by the construction organization to the average value as the resource consumption threshold, thereby ensuring that the resource consumption threshold has the representativeness and stability to reflect the conventional construction load.
[0100] The proportion of workfaces with high resource consumption levels within the designated area is statistically analyzed to obtain the area's imbalance assessment index. The specific calculation formula is as follows:
[0101] ;
[0102] in, As an assessment index for regional imbalance, The number of workfaces at the high-load resource consumption level. This represents the total number of working faces within the area.
[0103] The regional imbalance assessment index is used to quantify the degree of balance in resource consumption pressure among various work surfaces within a region. By calculating the proportion of high-load work surfaces in the region, it reflects the synchronicity of the overall progress activities in the region at the resource level. The higher the value, the more high-load work surfaces there are in the region, the more resource supply pressure is concentrated in a local area, and the risk that the overall progress of the region is constrained by high-load work surfaces. Conversely, the lower the regional imbalance assessment index, the more balanced the distribution of resource consumption pressure in the region, and the better the synchronicity of the overall progress.
[0104] The imbalance assessment index of a region is compared with the preset synchronous imbalance threshold. When the imbalance assessment index of a region is greater than the synchronous imbalance threshold, it is determined that there is synchronous imbalance in the region, indicating that there are significant differences in resource consumption pressure among the various work surfaces within the region, and the resource supply chain cannot simultaneously meet the advancement needs of each work surface. Conversely, when the imbalance assessment index of a region is less than or equal to the synchronous imbalance threshold, it is determined that the region remains in a synchronous state.
[0105] Among them, the synchronous imbalance threshold is used to determine whether there is a synchronous imbalance in the progress rhythm of the area. The method of setting it is based on the material supply capacity, slag transportation capacity and equipment support capacity that can be dispatched simultaneously in the area. During the trial operation phase, the proportion of high-load level working faces in the area under normal progress conditions is counted, and the sum of the mean of the proportion and twice the standard deviation is used as the synchronous imbalance threshold.
[0106] When there is a synchronous imbalance in the area, differentiated pre-control measures are implemented for working faces with different resource consumption levels: for high-load working faces, measures such as reducing the advance speed, increasing the supply capacity of grouting materials, optimizing the scheduling frequency of muck transport vehicles, adjusting the load of grouting pump stations, or adding auxiliary grouting lines are taken to alleviate their resource pressure.
[0107] For low-load working faces, the resource demand is made more consistent with the overall advance rhythm of the area by maintaining the original advance intensity, appropriately increasing the advance rate, or reducing the material supply frequency, thereby achieving a rebalancing of the advance load within the area.
[0108] The above process achieves overall coordination of the advancement pace and resource consumption of each working face within the area, ensuring the synchronicity of the tunnel boring machine construction process.
[0109] The dynamic early warning method for project progress deviations in this invention can be widely applied to the entire process consulting scenarios of various engineering projects, such as digital economy industrial parks, educational facilities, and green buildings. It is particularly suitable for projects with multi-functional areas under simultaneous construction and cross-regional collaborative work, accurately responding to the core needs for progress control, resource optimization, and risk prevention clearly defined in the feasibility study. Addressing common pain points in project construction, such as imbalanced progress across multiple regions, uncoordinated material supply and transportation scheduling, and mismatch between resource consumption and construction progress, this method quantifies the fluctuation rate of progress synchronization and the level of resource consumption to predict and resolve construction bottlenecks in advance. This helps projects achieve efficient and intensive progress within the preset construction period, highly aligning with the core requirements of various engineering projects for progress assurance and risk control.
[0110] Finally, it should be noted that in this paper, relational terms such as first and second are used only to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations.
[0111] Furthermore, the terms "comprising," "including," or any other variations thereof are intended to cover non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements includes not only those elements but also other elements not expressly listed, or elements inherent to such a process, method, article, or apparatus. Without further limitation, an element defined by the phrase "comprising one..." does not exclude the presence of other identical elements in the process, method, article, or apparatus that includes said element.
[0112] In this document, the singular forms “a,” “an,” and “the” may also include the plural forms unless the context clearly indicates otherwise. It should also be understood that terms such as “comprising / including” or “having” specify the presence of the stated features, integrals, steps, operations, components, parts, or combinations thereof, but do not preclude the possibility of the presence or addition of one or more other features, integrals, steps, operations, components, parts, or combinations thereof. Meanwhile, the term “and / or” as used in this specification includes any and all combinations of the associated listed items.
[0113] The various embodiments in this specification are described in a progressive manner. Each embodiment focuses on the differences from other embodiments. The various embodiments can be combined as needed, and the same or similar parts can be referred to each other.
[0114] The above description of the disclosed embodiments will enable those skilled in the art to make or use various modifications to these embodiments. It will be readily apparent to those skilled in the art that the general principles defined herein may be implemented in other embodiments without departing from the spirit or scope of this application. Therefore, this application is not to be limited to the embodiments shown herein, but is to be accorded the widest scope consistent with the principles and novel features disclosed herein.
Claims
1. A dynamic early warning method for engineering schedule deviations oriented towards full-process consulting, characterized in that: Including the following Steps: Step S1: When the shield tunneling is being carried out, access the construction management system to obtain the zoning information of the area to be tested in the tunnel. Based on the zoning information, retrieve the working face classification data of each area and detect the ring number advance rate and cutter change frequency of each working face. Step S2: Calculate the engineering advancement index of the working face based on the ring number advancement rate, generate the shield wear coefficient of the working face using the cutterhead replacement frequency, and assess the advancement synchronization fluctuation rate of the corresponding area based on the engineering advancement index. Determine whether to enter the resource analysis mechanism based on the advancement synchronization fluctuation rate. Step S3: Collect the grouting material consumption of each working face within the resource analysis mechanism, count the arrival interval of muck transport vehicles and analyze the vehicle accumulation status. When the vehicle accumulation status is abnormal, detect the ground hardness of the environment where the working face is located. Step S4: Predict the resource consumption trend of the working face based on the grouting material consumption, correct the resource consumption trend based on the ground hardness and generate a resource consumption level. Determine whether the corresponding area is synchronously unbalanced based on the resource consumption level and select different pre-control measures.
2. The method for dynamic early warning of engineering progress deviations based on full-process consulting as described in claim 1, characterized in that: In step S1, during the tunnel boring machine (TBM) construction, the construction management system is accessed to obtain the zoning information of the tunnel area to be measured. The zoning information includes the zoning number of each zoning area. The zoning number is imported into the engineering data index table to retrieve the working face classification data of each zoning area, including the number of each working face. A preset statistical period is established, and the number of tunneling rings within the preset statistical period is obtained through the ring number advancement log. The number of tunneling rings refers to the number of tunneling rings completed by the working face. The ratio of the number of tunneling rings to the preset statistical period is used as the ring number advancement rate. The number of cutterhead replacement operations for each working face is obtained through the TBM equipment maintenance log. The ratio of the number of cutterhead replacement operations to the preset statistical period is used as the cutterhead replacement frequency.
3. The method for dynamic early warning of engineering progress deviations based on full-process consulting as described in claim 1, characterized in that: In step S2, within the same area, the advancement rate of each ring number is standardized using the Min-Max standardization method to obtain the ring number advancement rate factor; based on the ring number advancement rate factor, the engineering advancement index of the working face is calculated: ,in, The first in the area The project progress index for each work area It is a natural constant. The preset gain coefficient, To preset the balance factor, The first in the area The ring number propulsion rate factor of each working face.
4. The method for dynamic early warning of engineering progress deviations based on full-process consulting as described in claim 3, characterized in that: In step S2, the Min–Max normalization method is used to standardize each cutter change frequency to obtain the cutter change frequency factor; based on the cutter change frequency factor, the shield wear coefficient of the working face is calculated: ,in, The first in the area Tool change frequency factor for each working face To preset the wear coefficient, The first in the area The shield wear coefficient of each working face; the shield wear coefficient combined with the engineering propulsion index to calculate the propulsion synchronization fluctuation rate of the corresponding area: ,in, The first in the area The shield wear coefficient of each working face This represents the average of the progress indices for various projects within the area. This represents the total number of working faces within the area. The value can be from 1 to N. The first in the area The project progress index for each work area To synchronize the fluctuation rate of the region's progress.
5. The method for dynamic early warning of engineering progress deviations based on full-process consulting as described in claim 1, characterized in that: In step S2, the propulsion synchronization volatility is compared with a preset propulsion synchronization threshold to determine whether to enter the resource analysis mechanism: if the propulsion synchronization volatility is greater than the preset propulsion synchronization threshold, it is determined that the resource analysis mechanism will be entered; otherwise, it is determined that the resource analysis mechanism will not be entered.
6. The method for dynamic early warning of engineering progress deviations oriented towards full-process consulting as described in claim 1, characterized in that: In step S3, data is accessed for the grouting pump stations corresponding to each working face within the resource analysis mechanism to obtain the grouting material consumption per unit time for each working face; the output flow rate of the grout per unit time is continuously measured by the flow meter of the grouting pump, and the cumulative grouting volume is generated based on the product of the output flow rate and the grouting duration, which is used as the grouting material consumption of the working face; the arrival records of the muck transport vehicles undertaking the task of muck removal within the area are statistically analyzed, and the time difference between the arrival of two adjacent muck transport vehicles at the working face is used as the muck transport vehicle arrival interval.
7. A dynamic early warning method for engineering progress deviations based on full-process consulting, as described in claim 6, is characterized in that: In step S3, within a preset statistical window, the reciprocal of the arrival interval of each muck transport vehicle is calculated, and the arithmetic mean of all reciprocals is calculated as the vehicle accumulation index. When the vehicle accumulation index is less than or equal to the preset vehicle status threshold, the vehicle accumulation status is determined to be normal; when the vehicle accumulation index is greater than the preset vehicle status threshold, the vehicle accumulation status is determined to be abnormal. When the vehicles are piled up abnormally, the soil hardness is obtained by continuously collecting the pressure of the soil in front of the cutterhead through the earth pressure sensor at the front of the tunnel boring machine.
8. A dynamic early warning method for engineering progress deviations based on full-process consulting, as described in claim 6, is characterized in that: In step S4, a continuous time series analysis is performed on the grouting material consumption of each working face within a preset statistical window based on the grouting material consumption, i.e., the resource consumption trend of the working face is generated by the cumulative weighted average method; the resource consumption trend is corrected using the formation hardness, and the correction calculation formula is as follows: ;in, Due to resource consumption trends, This is the revised resource consumption trend. For the hardness of the formation, The preset reference formation hardness is used; based on the corrected resource consumption trend, the resource consumption levels of each working face are divided into low-load levels and high-load levels.
9. A dynamic early warning method for engineering progress deviations based on full-process consulting, as described in claim 8, characterized in that: In step S4, the proportion of workfaces with high resource consumption levels within the area is statistically analyzed to obtain the area imbalance assessment index. The area imbalance assessment index is compared with a preset synchronous imbalance threshold. When the area imbalance assessment index is greater than the synchronous imbalance threshold, it is determined that the area has synchronous imbalance. Conversely, when the area imbalance assessment index is less than or equal to the preset synchronous imbalance threshold, it is determined that the area remains synchronous. When there is synchronous imbalance in the area, different pre-control measures are implemented for workfaces with different resource consumption levels.