Concrete module and fully-prefabricated concrete modular building structure system

By prefabricating concrete modules in the factory, including shear wall blades and beam shells, the problems of complex installation, cumbersome connections and insufficient structural strength in the existing technology are solved, and the rapid installation and high-strength structure of modular buildings are realized, which is suitable for high-intensity areas and key fortification projects.

CN222716196UActive Publication Date: 2025-04-04CHINA STATE CONSTR HAILONG TECH CO LTD +1
View PDF 0 Cites 2 Cited by

Patent Information

Application Number
CN202420922658.7
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-04-26
Publication Date
2025-04-04
Estimated Expiration
2034-04-26

AI Technical Summary

Technical Problem

The existing concrete modular building structure system has problems such as complex installation process, cumbersome connection structure and poor structural strength, which are difficult to promote and apply in high-intensity areas and projects that require key fortification.

Method used

A concrete module is adopted, including shear wall blades, partition walls, roof panels, bottom panels and beam shells, and by completing standardized prefabrication in the factory, a module that can be quickly installed is formed. There are cavities inside the shear wall leaf plate and beam shell, which are used to pour concrete to form an integrated structure and improve connection strength.

Benefits of technology

It realizes rapid installation and high structural strength of concrete modules, is suitable for high-intensity areas and construction projects that require key fortification, and improves construction speed and quality.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222716196U_ABST
    Figure CN222716196U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of building structures, in particular to a concrete module and a full-prefabricated concrete modular building structure system, which comprise shear wall leaf plates, partition walls, a top plate, a bottom plate and beam shells, the bottom plate serves as the bottom face of the concrete module, and the top plate serves as the top face of the concrete module. The shear wall leaf plates and the partition walls form the four side faces of the concrete module. The shear wall leaf plates are arranged at the corners of the concrete modules, and the partition wall is arranged between the two shear wall leaf plates. A first cavity used for pouring concrete is formed in the shear wall leaf plate; the height of the shear wall leaf plate is larger than that of the partition wall, the beam shell is arranged on the top of the partition wall, a second cavity used for pouring concrete is formed in the beam shell, and the second cavity is communicated with the first cavity so that the beam shell and the shear wall leaf plate can form a whole after the concrete is poured.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of building structures, in particular to a concrete module and a fully prefabricated concrete modular building structure system. Background Art

[0002] Traditional construction methods have many steps and complex construction processes, usually with low production efficiency, high resource consumption, and easy to cause environmental pollution. As a result, various unpredictable construction defects and safety hazards are prone to occur during the construction process, which makes it impossible to achieve the expected project progress and also affects the construction quality.

[0003] Concrete modular buildings use prefabricated concrete modules as the main components, and form a complete building through the free combination of modules. Compared with steel structure modules, concrete modular buildings have many advantages such as better thermal insulation, heat insulation, and sound insulation, and easy access to raw materials. It is one of the future development directions of modular buildings. However, the existing concrete modular building structure system has the disadvantages of complex installation process and cumbersome connection construction measures, and is usually only applicable to low-intensity areas, and it is difficult to promote and apply it in high-intensity areas and projects that require key defense.

[0004] Therefore, there is an urgent need for a concrete module and a fully prefabricated concrete modular building structure system to improve the technical problems of the existing concrete modules, such as complex installation process, cumbersome connection structure, and poor structural strength. Utility Model Content

[0005] 1. Technical issues to be resolved

[0006] In view of the above-mentioned shortcomings and deficiencies of the prior art, the utility model provides a concrete module and a fully prefabricated concrete modular building structure system, which solves the technical problems of the existing modular buildings, such as complex installation process, cumbersome connection structure and poor structural strength.

[0007] (II) Technical solution

[0008] In order to achieve the above-mentioned purpose, the main technical solutions adopted by the utility model include:

[0009] A concrete module, comprising: a shear wall blade, a partition wall, a top plate, a bottom plate and a beam shell; the bottom plate serves as the bottom surface of the concrete module, and the top plate serves as the top surface of the concrete module; the shear wall blade and the partition wall form four side surfaces of the concrete module; the shear wall blade is arranged at the corner of the concrete module, and the partition wall is arranged between two of the shear wall blades;

[0010] A first cavity for pouring concrete is provided inside the shear wall blade;

[0011] The height of the shear wall blade is higher than that of the partition wall, the beam shell is arranged on the top of the partition wall, a second cavity for pouring concrete is arranged inside the beam shell, and the second cavity is communicated with the first cavity, so that the beam shell and the shear wall blade are integrated after pouring concrete;

[0012] The top plate is fixed to the top of the shear wall blade and the beam shell, and a cast-in-place section is provided around the outer edge of the top plate so that the top of the top plate and the cast-in-place section form a whole with the shear wall blade and the beam shell after pouring concrete.

[0013] The shear wall blade comprises a first blade and a second blade that are arranged opposite to each other, and a first steel bar skeleton that is evenly arranged is provided in the first blade and the second blade.

[0014] There are also a plurality of first tie bars between the first leaf plate and the second leaf plate. The first tie bars are arranged in a horizontal direction, and both ends of the first tie bars are fixedly connected to the first steel bar skeletons in the first leaf plate and the second leaf plate, respectively, so that a first cavity for pouring concrete is formed between the first leaf plate and the second leaf plate.

[0015] The beam shell includes a first shell plate and a second shell plate that are arranged opposite to each other, and a beam shell waterproof layer fixed to the bottom ends of the first shell plate and the second shell plate. Both ends of the beam shell waterproof layer are fixedly connected to the first shell plate and the second shell plate respectively. The first shell plate and the second shell plate serve as two side surfaces of the beam shell, and the beam shell waterproof layer serves as the bottom surface of the beam shell, so that a second cavity for pouring concrete is formed between the first shell plate and the second shell plate.

[0016] A second steel skeleton and a second tie bar are provided in each of the first shell plate and the second shell plate, and the second steel skeleton and the second tie bar are arranged along the vertical direction;

[0017] Both ends of the second tie bar extend out of the first shell plate and the second shell plate, the upper end of the second tie bar is bent after binding, and the lower end of the second tie bar is inserted into the partition wall.

[0018] A steel cage is also provided between the adjacent first shell plates and the second shell plates.

[0019] Door and window openings are arranged on the partition wall.

[0020] A fully prefabricated concrete modular building structure system, comprising a plurality of said concrete modules stacked layer by layer;

[0021] A cast-in-place concrete layer is provided on the top plate of the concrete module located at the lower layer, and the bottom plate of the concrete module located at the upper layer is fixed on the cast-in-place concrete layer.

[0022] A vertical connecting dowel bar and a transverse additional rib are also provided at the connection between the shear wall blade located at the upper layer and the shear wall blade located at the lower layer. The vertical connecting dowel bar and the transverse additional rib are integrated with the concrete poured in the shear wall blade.

[0023] (III) Beneficial effects

[0024] The beneficial effects of the utility model are as follows: the utility model provides a concrete module and a fully prefabricated concrete modular building structure system, which completes the overall prefabrication of shear wall blades, partition walls, beam shells, top plates and bottom plates in the factory to form a concrete module that can be quickly installed on the construction site. Since the concrete module is standardized and produced in the factory, the quality of each concrete module can be guaranteed to be uniform, reducing the errors that may exist in manual operation.

[0025] The inside of the shear wall blades and beam shells has cavities for pouring concrete, which makes the overall weight of the concrete module lighter and facilitates the transportation and installation of the concrete module. At the same time, the cavities inside the shear wall blades and beam shells can be poured directly at the construction site. The shear wall blades and beam shells are permanent formwork for subsequent construction and pouring of concrete. The concrete modules not only have the advantages of fast and convenient installation of prefabricated components, but also can achieve various performance indicators of cast-in-place structures. They can be used in high-intensity areas and non-high-intensity areas but buildings that require key defense, and are suitable for dormitories, affordable housing, renovation of old communities, urban renewal and other projects. BRIEF DESCRIPTION OF THE DRAWINGS

[0026] Figure 1 A three-dimensional diagram of the assembled concrete modules of the fully prefabricated concrete modular building structure system of the utility model;

[0027] Figure 2 A three-dimensional diagram of the upper and lower layers of concrete modules of the fully prefabricated concrete modular building structure system of the utility model;

[0028] Figure 3 It is a horizontal cross-sectional view of the bottom floor of the fully prefabricated concrete modular building structure system of the utility model;

[0029] Figure 4 It is a top-level horizontal cross-sectional view of the fully prefabricated concrete modular building structure system of the utility model;

[0030] Figure 5 for Figure 3 Sectional view at AA in the middle;

[0031] Figure 6 for Figure 3 Cross-section at the middle BB;

[0032] Figure 7 for Figure 4 Sectional view at CC;

[0033] Figure 8 for Figure 4 Sectional view at DD in the middle;

[0034] Fig. 9 It is a partial structural schematic diagram of the beam shell and the top plate of the utility model;

[0035] Fig.10 It is a top view of the top plate of the utility model.

[0036] [Description of Reference Numerals]

[0037] 1: Concrete module; 11: Shear wall blade; 12: Partition wall; 13: Top plate; 14: Bottom plate; 15: Beam shell; 16: Waterproof sealing structure;

[0038] 111: first blade; 112: second blade; 113: steel bar skeleton; 114: first tie bar; 115: first cavity; 116: vertical connecting dowel bar; 117: transverse additional bar;

[0039] 131: the third steel skeleton; 132: cast-in-place section; 133: cast-in-place concrete layer; 134: lap reinforcement at the bottom of the slab;

[0040] 151: first shell plate; 152: second shell plate; 153: second cavity; 154: second steel skeleton; 155: second tie bar; 156: steel cage; 157: beam shell waterproof layer. DETAILED DESCRIPTION

[0041] In order to better explain the utility model and facilitate understanding, the utility model is described in detail below with reference to the accompanying drawings and through specific implementation methods. Figure 1 The orientation is used as a reference.

[0042] In order to better understand the above technical solution, exemplary embodiments of the present invention will be described in more detail with reference to the accompanying drawings. Although exemplary embodiments of the present invention are shown in the accompanying drawings, it should be understood that the present invention can be implemented in various forms and should not be limited by the embodiments described herein. On the contrary, these embodiments are provided to enable a clearer and more thorough understanding of the present invention and to fully convey the scope of the present invention to those skilled in the art.

[0043] The utility model provides a fully prefabricated concrete modular building structure system, comprising a plurality of concrete modules 1. After the concrete modules 1 are prefabricated in a factory, they are hoisted at a construction site. The plurality of concrete modules 1 are stacked layer by layer to form a concrete modular building structure system that can be quickly installed at the construction site, thereby improving the construction speed of the building structure.

[0044] The concrete module 1 includes a hollow shear wall blade 11, a partition wall 12, a top plate 13 and a bottom plate 14. The shear wall blade 11 and the partition wall 12 are fixedly connected to form four sides of the concrete module 1. The bottom plate 14 is fixedly arranged at the bottom of the shear wall blade 11 and the partition wall 12, serving as the bottom surface of the concrete module 1. The top plate 13 is fixed at the top of the shear wall blade 11 and the partition wall 12, serving as the top surface of the concrete module 1. The shear wall blade 11, the partition wall 12, the top plate 13 and the bottom plate 14 form a unit concrete module 1 that can be prefabricated in a factory.

[0045] The shear wall blade 11 is arranged at the corner of the concrete module 1, and the horizontal cross section is L-shaped or T-shaped, which can be selected according to the actual position of the shear wall blade 11. The shear wall blade 11 includes a first blade 111 and a second blade 112 arranged oppositely, and the first blade 111 and the second blade 112 are both provided with a uniformly arranged first steel frame 113. There are also a number of first tie bars 114 between the first steel skeleton 113 of the first blade plate 111 and the second blade plate 112. The first tie bars 114 are evenly distributed between the first blade plate 111 and the second blade plate 112. The first tie bars 114 are arranged along the horizontal direction, and the two ends of the first tie bars 114 are respectively fixedly connected to the first steel skeleton 113 in the first blade plate 111 and the second blade plate 112, so that a first cavity 115 for pouring concrete is formed between the first blade plate 111 and the second blade plate 112, so that the shear wall blade 11 after pouring concrete can achieve the structural strength of cast-in-place components on the basis of the advantages of fast installation speed and convenient construction of prefabricated components.

[0046] Preferably, the blades of this embodiment are cast with C60 concrete. The first steel skeleton 113 includes at least one layer of bidirectional steel bars, which are steel bars arranged in the horizontal direction and the vertical direction.

[0047] The concrete module 1 also includes a beam shell 15, which is arranged on the top of the partition wall 12. The beam shell 15 includes a first shell plate 151 and a second shell plate 152 that are arranged opposite to each other, and a beam shell waterproof layer 157 fixed to the bottom ends of the first shell plate 151 and the second shell plate 152. The two ends of the beam shell waterproof layer 157 are respectively fixedly connected to the first shell plate 151 and the second shell plate 152. The first shell plate 151 and the second shell plate 152 serve as two side surfaces of the beam shell 15, and the beam shell waterproof layer 157 serves as the bottom surface of the beam shell 15, so that a second cavity 153 for pouring concrete is formed between the first shell plate 151 and the second shell plate 152.

[0048] The first shell plate 151 and the second shell plate 152 are both provided with a second steel bar skeleton 154 and a second tie bar 155. The second steel bar skeleton 151 of this embodiment adopts a single-layer bidirectional steel bar, and the second tie bar 155 is arranged along the vertical direction, and both ends extend out of the first shell plate 151 and the second shell plate 152. The upper end of the second tie bar 155 is bent after binding, and the lower end of the second tie bar 155 is inserted into the partition wall 12. A steel cage 156 is also provided between the adjacent first shell plates 151 and the second shell plates 152, and the steel cage 156 is used to enhance the overall structural strength of the beam shell 15 after pouring concrete.

[0049] Preferably, the beam shell waterproof layer 157 of this embodiment is made of extruded board, and the moisture-proof and heat-insulating performance of the concrete module 1 is improved by arranging the beam shell waterproof layer 157 at the bottom of the beam shell 15 .

[0050] The height of the shear wall blade 11 is higher than the height of the partition wall 12. When the beam shell 15 is arranged at the top of the partition wall 12 between the two shear wall blades 11, the two ends of the beam shell 15 are respectively fixedly connected to the shear wall blades 11 at the two ends of the partition wall 12, and the second cavity 153 of the beam shell 15 is connected to the first cavity 115 of the shear wall blade 11. By arranging the beam shell 15 at the top of the partition wall 12, and the cavity inside the beam shell 15 is connected to the shear wall blade 11, the beam shell 15 and the shear wall blade 11 are poured with concrete to form a whole, thereby improving the connection strength between the shear wall blade 11, the partition wall 12 and the beam shell 15, and on the basis of having the advantages of fast installation speed of the prefabricated module, it can also have the structural strength of the cast-in-place structure.

[0051] When the beam shell 15 is arranged at the joint of two adjacent concrete modules 1, that is, the beam shell 15 is arranged at the top of two adjacent partition walls 12, that is, two adjacent partition walls 12 share one beam shell 15, the bottom of the second tie bar 155 is inserted into the lower partition wall 12. By arranging the beam shell 15 at the top of the partition wall 12 of two adjacent concrete modules 1, the structural connection strength between the adjacent partition walls is enhanced.

[0052] The top plate 13 is fixed on the top of the shear wall blade 11 and the partition wall 12. A third steel frame 131 is provided inside the top plate 13. The end of the third steel frame 131 extends to the top plate 13 as reserved steel bars for the top plate 13. The reserved steel bars are anchored to the second steel frame 151 of the beam shell 15.

[0053] The top plate 13 does not completely cover the top surface of the concrete module 1 during the prefabrication stage in the factory, that is, a cast-in-place section 132 is provided around the outer edge of the top plate 13. After the concrete module 1 is installed, the cast-in-place section 132 is cast in-place on the entire floor slab as a whole, so that the top plate 13 and the beam shell 15 can form a whole, thereby improving the connection strength of the module structure.

[0054] The steel cage 156 is also provided with lap ribs 134 at the bottom of the plate to enhance the structural connection strength between the top plate 13 and the beam shell 15 .

[0055] After the concrete module 1 is installed at the preset construction site, the first cavity 115 of the shear wall blade 11, the second cavity 153 of the beam shell 15, and the cast-in-place section 132 and the top surface of the top plate 13 are cast to form a cast-in-place concrete layer 133 on the top plate 13, so that the shear wall blade 11, the beam shell 15 and the top plate 13 are connected into a whole, thereby improving the overall performance of the concrete module 1 and enabling the concrete module 1 to achieve various performance indicators of the cast-in-place structure.

[0056] After the concrete modules 1 at the lower layer are poured, the concrete modules 1 at the upper layer are hoisted, and the bottom plates 14 of the concrete modules 1 at the upper layer are fixed on the poured top plates 13 after hoisting.

[0057] A vertical connection dowel bar 116 and a transverse additional rib 117 are also provided at the connection between the shear wall blade 11 located at the upper layer and the shear wall blade 11 located at the lower layer, and the vertical connection dowel bar 116 and the transverse additional rib 117 are used to enhance the structural connection strength between the upper and lower shear wall blades 11. The vertical connection dowel bar 116 and the transverse additional rib 117 are tied before the concrete module 1 of the lower layer is poured.

[0058] The first blade 111 is located on the outside of the second blade 112. A waterproof sealing structure 16 is also provided at the connection between the first blade 111 located on the upper layer and the first blade 111 located on the lower layer. The waterproof sealing structure 16 includes a seat slurry, a polyethylene rod and a sealant arranged in sequence from the inside to the outside to enhance the waterproof sealing performance of the connection of the concrete module 1.

[0059] The partition wall 12 is also provided with door and window openings, which can be selected according to actual needs.

[0060] The utility model provides a fully prefabricated shear wall concrete modular building structure system, which forms a prefabricated concrete module 1 by combining a shear wall blade 11, a partition wall 12, a top plate 13 and a bottom plate 14. The shear wall blade 11 and the beam shell 15 have cavities for pouring concrete inside, which makes the overall weight of the concrete module 1 lighter and facilitates the rapid installation of the concrete module 1; at the same time, the internal cavities of the shear wall blade 11 and the beam shell 15 can be directly poured at the construction site without re-setting the formwork. The shear wall blade 11 and the beam shell 15 are permanent formworks for subsequent construction and pouring concrete, so that the concrete module 1 can achieve various performance indicators of the cast-in-place structure on the basis of the advantages of fast and convenient installation of prefabricated components, and can be used in high-intensity areas and non-high-intensity areas but buildings that require key defense, and are suitable for dormitories, affordable housing, renovation of old communities, urban renewal and other projects.

[0061] In the description of the present utility model, it should be understood that the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Therefore, a feature defined as "first" or "second" may explicitly or implicitly include one or more of the features. In the description of the present utility model, the meaning of "plurality" is two or more, unless otherwise clearly and specifically defined.

[0062] In the present invention, unless otherwise clearly specified and limited, the terms "install", "connect", "connect", "fix" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium; it can be the internal connection of two elements or the interaction relationship between two elements. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0063] In the present utility model, unless otherwise clearly specified and limited, when a first feature is “on” or “below” a second feature, it may be that the first and second features are in direct contact, or the first and second features are in indirect contact through an intermediate medium. Moreover, when a first feature is “above”, “above” or “above” a second feature, it may be that the first feature is directly above or obliquely above the second feature, or it may simply mean that the first feature is higher in level than the second feature. When a first feature is “below”, “below” or “below” a second feature, it may be that the first feature is directly below or obliquely below the second feature, or it may simply mean that the first feature is lower in level than the second feature.

[0064] In the description of this specification, the description of the terms "one embodiment", "some embodiments", "embodiment", "example", "specific example" or "some examples" etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the utility model. In this specification, the schematic representations of the above terms do not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described may be combined in any one or more embodiments or examples in a suitable manner. In addition, those skilled in the art may combine and combine the different embodiments or examples described in this specification and the features of the different embodiments or examples, unless they are contradictory.

[0065] Although the embodiments of the present invention have been shown and described above, it can be understood that the above embodiments are illustrative and cannot be understood as limitations of the present invention. Ordinary technicians in the field can change, modify, replace and modify the above embodiments within the scope of the present invention.

Claims

1. A concrete module, characterized in that: include: Shear wall blades (11), partition walls (12), top plates (13), bottom plates (14) and beam shells (15); the bottom plates (14) serve as the bottom surface of the concrete module (1), and the top plates (13) serve as the top surface of the concrete module (1); the shear wall blades (11) and the partition walls (12) form four side surfaces of the concrete module (1); the shear wall blades (11) are arranged at the corners of the concrete module (1), and the partition walls (12) are arranged between two of the shear wall blades (11); A first cavity (115) for pouring concrete is provided inside the shear wall blade (11); The height of the shear wall blade (11) is higher than that of the partition wall (12); the beam shell (15) is arranged on the top of the partition wall (12); a second cavity (153) for pouring concrete is provided inside the beam shell (15); the second cavity (153) is communicated with the first cavity (115), so that the beam shell (15) and the shear wall blade (11) are integrated after pouring concrete; The top plate (13) is fixed to the top of the shear wall blade (11) and the beam shell (15), and a cast-in-place section (132) is provided around the outer edge of the top plate (13), so that the top of the top plate (13) and the cast-in-place section (132) form a whole with the shear wall blade (11) and the beam shell (15) after pouring concrete.

2. The concrete module according to claim 1, characterized in that The shear wall blade (11) comprises a first blade (111) and a second blade (112) which are arranged opposite to each other, and a first steel bar skeleton (113) which is evenly arranged is provided inside the first blade (111) and the second blade (112).

3. The concrete module according to claim 2, characterized in that There are also a plurality of first tie bars (114) between the first blade plate (111) and the second blade plate (112), wherein the first tie bars (114) are arranged along the horizontal direction, and the two ends of the first tie bars (114) are respectively fixedly connected to the first steel bar skeleton (113) in the first blade plate (111) and the second blade plate (112), so that a first cavity (115) capable of pouring concrete is formed between the first blade plate (111) and the second blade plate (112).

4. The concrete module according to claim 3, characterized in that The beam shell (15) comprises a first shell plate (151) and a second shell plate (152) which are arranged opposite to each other, and a beam shell waterproof layer (157) fixed to the bottom ends of the first shell plate (151) and the second shell plate (152); two ends of the beam shell waterproof layer (157) are respectively fixedly connected to the first shell plate (151) and the second shell plate (152); the first shell plate (151) and the second shell plate (152) serve as two side surfaces of the beam shell (15); and the beam shell waterproof layer (157) serves as the bottom surface of the beam shell (15), so that a second cavity (153) capable of pouring concrete is formed between the first shell plate (151) and the second shell plate (152).

5. The concrete module according to claim 4, characterized in that A second steel skeleton (154) and a second tie bar (155) are provided in both the first shell plate (151) and the second shell plate (152), and the second steel skeleton (154) and the second tie bar (155) are arranged along the vertical direction; Both ends of the second tie bar (155) extend outside the first shell plate (151) and the second shell plate (152), the upper end of the second tie bar (155) is bent after binding, and the lower end of the second tie bar (155) is inserted into the partition wall (12).

6. The concrete module according to claim 5, characterized in that A steel cage (156) is further provided between the adjacent first shell plates (151) and the second shell plates (152).

7. The concrete module according to claim 1, characterized in that The partition wall (12) is provided with door and window openings.

8. A fully prefabricated concrete modular building structure system, characterized in that: Comprising a plurality of concrete modules (1) according to any one of claims 1 to 7 stacked layer by layer; A cast-in-place concrete layer (133) is provided on the top plate (13) of the concrete module (1) located at the lower layer, and the bottom plate (14) of the concrete module (1) located at the upper layer is fixed on the cast-in-place concrete layer (133).

9. The fully prefabricated concrete modular building structure system according to claim 8, characterized in that: A vertical connection dowel bar (116) and a transverse additional rib (117) are further provided at the connection between the shear wall blade (11) located at the upper layer and the shear wall blade (11) located at the lower layer. The vertical connection dowel bar (116) and the transverse additional rib (117) are integrated with the concrete poured in the shear wall blade (11).

Citation Information

Cited By

  • Connecting structure for prefabricated double beams and prefabricated double walls of concrete module building and construction method

    CN120026711A

  • Connection Structure and Construction Method of Prefabricated Double Beams and Prefabricated Double Walls in Concrete Module Buildings

    CN120026711B