By integrating lifting and moving systems as well as shading and cooling devices into the construction platform for the foundation pit, the problems of platform flexibility and high-temperature protection were solved, thereby improving construction efficiency and safety.
Patent Information
- Application Number
- CN202520130325.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-01-20
- Publication Date
- 2026-01-02
- Estimated Expiration
- 2035-01-20
AI Technical Summary
The existing construction operation platform for foundation pits requires frequent erection or dismantling of scaffolding to adapt to changes in the construction location, and lacks sunshade structures in hot weather, resulting in a high risk of heatstroke for construction workers.
The operating platform is raised and lowered and moved using components such as a fixed frame, guide rails, pulleys, motors, dual-axis motors, transmission rods, winding shafts, and steel ropes. It is equipped with sunshades, fans, solar panels, and battery panels to provide shading and cooling functions.
The platform allows for flexible movement, avoiding the need for repeated scaffolding erection, reducing the temperature of construction workers, and lowering the risk of heatstroke.
Smart Images

Figure CN223753672U_ABST
Abstract
Description
TECHNICAL FIELD
[0001] The utility model relates to the technical field of foundation pit construction operation platform, concretely to a foundation pit construction operation platform. BACKGROUND
[0002] The foundation pit is the soil pit that is excavated according to the foundation design position, base elevation and foundation plane size, and the foundation pit construction operation platform is the working platform for worker operation, equipment placement, material stacking and the like in the foundation pit construction process, which provides a safe and stable operation environment for construction personnel, and also helps to improve construction efficiency.
[0003] At present, the foundation pit construction operation platform in the prior art is usually driven by a walking motor along a construction track through a transverse walking roller to move the L-shaped framework transversely, but in the use process, the existing construction platform needs to be arranged by the erection of a scaffold, and with the change of the construction position, the scaffold needs to be erected or removed. Not only waste manpower and material resources, affect the construction period, and the construction is not very convenient, therefore, there is the problem of change of construction position and erection or removal of scaffold, and in high temperature weather, since the existing operation platform generally does not set up a corresponding sunshade structure, the construction personnel are prone to heat stroke under long-time sunlight, which endangers the health of the construction personnel, therefore, there is the problem of heat stroke of the construction personnel under long-time sunlight. UTILITY MODEL CONTENT
[0004] In view of the deficiencies of the prior art, the utility model provides a foundation pit construction operation platform, which solves the problems in the background art.
[0005] To achieve the above object, the utility model is realized by the following technical scheme: including foundation pit side wall, the top of foundation pit side wall is installed with fixed frame, the inboard of fixed frame is installed with guide rail, the top of guide rail is movably connected with first pulley;
[0006] The first pulley is movably connected to the inner wall of the moving frame, the top of the moving frame is fixedly connected with a double-shaft motor, the output shaft of the double-shaft motor is fixedly connected with a transmission rod, one end of the transmission rod is fixedly connected with a winding shaft, the outer side of the winding shaft is installed with a steel wire, one end of the steel wire is fixedly connected with an operation platform, the top of the moving frame is fixedly connected with a limiting frame;
[0007] The top of the operation platform is fixedly connected with a supporting rod, the top of the supporting rod is fixedly connected with a sunshade board, the inner wall of the sunshade board is fixedly connected with a fan, the inner wall of the operation platform is fixedly connected with a protective net.
[0008] Optionally, the top of the sunshade board is fixedly connected with a solar panel, and the inner wall of the sunshade board is fixedly connected with a battery panel.
[0009] Optionally, the outer side of the moving frame is provided with a first motor, the output shaft of the first motor is fixedly connected with a second pulley, the inner wall of the moving frame is movably connected with the second pulley, and the bottom of the second pulley is movably connected with a guide rail.
[0010] Optionally, the inner wall of the limiting frame is movably connected with a first lubricating column, the inner wall of the steel rope is movably connected with a second lubricating column, the second lubricating column is cylindrical, the shape of the second lubricating column is the same as that of the first lubricating column, and the outer side of the first lubricating column and the second lubricating column is slidably connected with the steel rope.
[0011] Optionally, one side of the limiting frame is provided with a groove, the groove is square, and the width of the two ends of the operation platform is less than the width of the middle part of the operation platform.
[0012] Optionally, the number of the transmission rods is two, the transmission rods are arranged at the two ends of the double-shaft motor, and the number of the winding shafts is the same as that of the transmission rods.
[0013] The base pit construction operation platform has the following beneficial effects:
[0014] The base pit construction operation platform is provided with a fixing frame, a guide rail, a first pulley, a moving frame, a first motor, a double-shaft motor, a transmission rod, a winding shaft, a steel rope, a first lubricating column, a second lubricating column and a limiting frame, the double-shaft motor drives the winding shaft through the transmission rod, the winding shaft winds and unwinds the steel rope, the operation platform is lifted, the first motor drives the second pulley, the equipment is moved, the change of the construction position is avoided, and the scaffold needs to be built or removed.
[0015] The base pit construction operation platform is provided with an operation platform, a supporting rod, a solar panel, a battery panel, a fan, a protective net and a sunshade, the sunshade shields the sunlight, the fan blows wind on the construction personnel, the temperature near the construction personnel is reduced, and the construction personnel is prevented from suffering from heatstroke under long-time sunlight irradiation. BRIEF DESCRIPTION OF DRAWINGS
[0016] Figure 1 It is a structure schematic view of the vertical shaft side of the utility model;
[0017] Figure 2 It is a structure schematic view of the front view of the utility model;
[0018] Figure 3 It is a guide rail structure schematic view of the utility model;
[0019] Figure 4The cross-section structure schematic view of the limiting frame is shown in the utility model;
[0020] Figure 5 The utility model discloses Figure 4 The enlarged structure schematic view of middle A is shown in the utility model;
[0021] Figure 6 The cross-section structure schematic view of the sunshade is shown in the utility model;
[0022] Figure 7 The utility model discloses Figure 6 The enlarged structure schematic view of middle B is shown in the utility model.
[0023] In the drawing: 1, foundation pit side wall;2, fixed frame;3, guide rail;4, first pulley;5, moving frame;6, first motor;7, double-shaft motor;8, transmission rod;9, winding shaft;10, steel rope;11, first lubricating column;12, second lubricating column;13, limiting frame;14, operation platform;15, support rod;16, solar panel;17, battery panel;18, fan;19, protective net;20, sunshade;21, second pulley. Specific implementation
[0024] The technical solutions in the embodiments of the utility model will be clearly and completely described below with reference to the drawings in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all the embodiments. Embodiment
[0025] Please refer to Figures 1 to 7 The utility model provides a technical scheme: a foundation pit construction operation platform, including foundation pit side wall 1, the top of foundation pit side wall 1 is installed with fixed frame 2, the inside of fixed frame 2 is installed with guide rail 3, the top of guide rail 3 is movably connected with first pulley 4;
[0026] The first pulley 4 is movably connected to the inner wall of the moving frame 5, the outer side of the moving frame 5 is provided with the first motor 6, the output shaft of the first motor 6 is fixedly connected with the second pulley 21, the second pulley 21 is movably connected to the inner wall of the moving frame 5, the bottom of the second pulley 21 is movably connected with the guide rail 3, the top of the moving frame 5 is fixedly connected with the double-shaft motor 7, the output shaft of the double-shaft motor 7 is fixedly connected with the transmission rod 8, the number of the transmission rod 8 is two, the transmission rod 8 is distributed at both ends of the double-shaft motor 7, the number of the winding shaft 9 is the same as that of the transmission rod 8, one end of the transmission rod 8 is fixedly connected with the winding shaft 9, the outer side of the winding shaft 9 is provided with the steel wire 10, one end of the steel wire 10 is fixedly connected with the operation platform 14, the top of the moving frame 5 is fixedly connected with the limiting frame 13, the inner wall of the limiting frame 13 is movably connected with the first lubricating column 11, the inner wall of the steel wire 10 is movably connected with the second lubricating column 12, the shape of the second lubricating column 12 is cylindrical, the shape of the second lubricating column 12 is the same as that of the first lubricating column 11, one side of the limiting frame 13 is provided with a slot, the shape of the slot is square, the width of both ends of the operation platform 14 is smaller than that of the middle part of the operation platform 14, the width of both ends of the operation platform 14 is the same as that of the slot, through the setting of the fixed frame 2, the guide rail 3, the first pulley 4, the moving frame 5, the first motor 6, the double-shaft motor 7, the transmission rod 8, the winding shaft 9, the steel wire 10, the first lubricating column 11, the second lubricating column 12 and the limiting frame 13, the operation platform has the functions that the double-shaft motor 7 drives the winding shaft 9 through the transmission rod 8, the winding shaft 9 winds and unwinds the steel wire 10, the operation platform 14 is lifted and lowered, the equipment is moved through the first motor 6 driving the second pulley 21, and the change of the construction position is avoided, and the scaffold needs to be built or removed.
[0027] In use, the double-shaft motor 7 drives the transmission rod 8, the transmission rod 8 drives the winding shaft 9, the winding shaft 9 controls the lifting and lowering of the operation platform 14 through the winding and unwinding of the steel wire 10, the limiting frame 13 can limit the operation platform 14, prevent the operation platform 14 from shaking during the lifting and left-right movement, adjust the height of the operation platform 14, the first motor 6 drives the second pulley 21, the second pulley 21 and the first pulley 4 move along the guide rail 3, the limiting frame 13 is fixed on the moving frame 5, the operation platform 14 moves synchronously with the moving frame 5, the operation platform 14 can move left and right, secondly, the fixed frame 2 is provided with a groove to limit the moving frame 5, keep the moving frame 5 balanced, and the first lubricating column 11 and the second lubricating column 12 in the limiting frame 13 can reduce the friction between the steel wire 10 and the limiting frame 13, prolong the service life of the steel wire 10. EMBODIMENT
[0028] Please refer to Figures 1 to 7The utility model provides a technical scheme: a foundation pit construction operation platform, including foundation pit side wall 1, the top of foundation pit side wall 1 is installed with fixed frame 2, the inboard of fixed frame 2 is installed with guide rail 3, the top of guide rail 3 is connected with first pulley 4,
[0029] The top of operation platform 14 is fixedly connected with support rod 15, the top of support rod 15 is fixedly connected with sun shield 20, the top of sun shield 20 is fixedly connected with solar panel 16, the inner wall of sun shield 20 is fixedly connected with battery panel 17, the inner wall of sun shield 20 is fixedly connected with fan 18, the inner wall of operation platform 14 is fixedly connected with protective net 19, are set up through operation platform 14, support rod 15, solar panel 16, battery panel 17, fan 18, protective net 19, sun shield 20, and a foundation pit construction operation platform has the advantages that the sun shield 20 is shielded to sunlight, then the fan 18 is blown to construction personnel, reduces the temperature near construction personnel, avoids that construction personnel is prone to heat stroke under long-time sunlight irradiation.
[0030] When using, the support rod 15 is arranged on the operation platform 14 to achieve the sun-shading effect, then the fan 18 is started, the battery panel 17 provides power for the fan 18, the fan 18 works to blow the construction personnel, reduces the temperature near the construction personnel, avoids the heat stroke of the construction personnel, and the solar panel 16 on the support rod 15 converts the sunlight into electric energy to supplement the electric quantity of the battery panel 17, thereby saving the electric energy.
[0031] The above is only the preferred specific embodiment of the utility model, but the protection scope of the utility model is not limited to this, any skilled person in the art in the technical range disclosed by the utility model, according to the technical scheme and utility model concept of the utility model, carries out equivalent replacement or change, should be covered in the protection scope of the utility model.
Claims
1. A foundation pit construction operation platform comprising a foundation pit side wall (1), characterized in that: The top of the foundation pit side wall (1) is provided with a fixing frame (2), the inner side of the fixing frame (2) is provided with a guide rail (3), and the top of the guide rail (3) is movably connected with a first pulley (4). The first pulley (4) is movably connected with the inner wall of a moving frame (5), the top of the moving frame (5) is fixedly connected with a double-shaft motor (7), the output shaft of the double-shaft motor (7) is fixedly connected with a transmission rod (8), one end of the transmission rod (8) is fixedly connected with a winding shaft (9), the outer side of the winding shaft (9) is provided with a steel wire (10), one end of the steel wire (10) is fixedly connected with an operation platform (14), and the top of the moving frame (5) is fixedly connected with a limiting frame (13). The top of the operation platform (14) is fixedly connected with a supporting rod (15), the top of the supporting rod (15) is fixedly connected with a sunshade (20), the inner wall of the sunshade (20) is fixedly connected with a fan (18), and the inner wall of the operation platform (14) is fixedly connected with a protective net (19).
2. The excavation construction operation platform according to claim 1, characterized in that: The top of the sunshade (20) is fixedly connected with a solar panel (16), and the inner wall of the sunshade (20) is fixedly connected with a battery panel (17).
3. The excavation construction operation platform according to claim 1, characterized in that: The outer side of the moving frame (5) is provided with a first motor (6), the output shaft of the first motor (6) is fixedly connected with a second pulley (21), the second pulley (21) is movably connected with the inner wall of the moving frame (5), and the bottom of the second pulley (21) is movably connected with a guide rail (3).
4. The operation platform for foundation pit construction of claim 1, wherein: The inner wall of the limiting frame (13) is movably connected with a first lubricating column (11), the inner wall of the steel wire (10) is movably connected with a second lubricating column (12), the shape of the second lubricating column (12) is cylindrical, and the shape of the second lubricating column (12) is the same as that of the first lubricating column (11).
5. The operation platform for foundation pit construction of claim 1, wherein: One side of the limiting frame (13) is provided with a groove, the shape of the groove is square, the width of both ends of the operation platform (14) is smaller than that of the middle part of the operation platform (14), and the width of both ends of the operation platform (14) is the same as that of the groove.
6. The operation platform for foundation pit construction of claim 1, wherein: The number of the transmission rod (8) is two, the transmission rod (8) is distributed at both ends of the double-shaft motor (7), and the number of the winding shaft (9) is the same as that of the transmission rod (8).