The design of adjustable rods and top truss structure solves the problems of complex installation and inconvenient adjustment of traditional hanging fences, achieving the effects of simplified installation, improved safety and expanded application range.

CN224678544UActive Publication Date: 2026-08-25CHINA RAILWAY SIXTH GRP TIANJIN RAILWAY CONSTR +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202522076665.7
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-09-26
Publication Date
2026-08-25
Estimated Expiration
2035-09-26

AI Technical Summary

Technical Problem

Traditional suspended railings are complex to install, requiring a complex system including an electrically controlled hoist, wire ropes, and safety locks. This results in low construction efficiency, high safety risks, and difficulty in adjusting the platform height, thus limiting their applicability.

Method used

The platform employs adjustable hangers and a top truss structure, using a combination of I-beams and channel steel to adjust the platform height, simplifying the installation process, eliminating the need for electrical controls, and improving stability and safety.

Benefits of technology

It simplifies construction operations, improves construction efficiency and safety, expands the scope of application, reduces construction time and the risks of complex systems, and is suitable for various pier sizes.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN224678544U_ABST
    Figure CN224678544U_ABST
Patent Text Reader

Abstract

The utility model discloses an adjustable hanging fence safe operation platform, including operation platform, adjustable derrick and top truss, operation platform includes platform steel sheet and platform fence, and the bottom of platform fence is connected with the edge position of platform steel sheet, adjustable derrick includes channel steel, I -beam and adjusting bolt, and I -beam is movably arranged in channel steel, channel steel and I -beam are connected through adjusting bolt that sets up in adjusting screw hole respectively and is set up adjusting screw hole respectively, and the bottom of adjustable derrick is connected with platform fence, and top truss is connected with the top of adjustable derrick, and it does not need the complex system of electrical control elevator, steel wire rope, safety lock and the like, and it is beneficial to the stress concentration of hanging fence safe operation platform in multidirectional direction to be conducted to pier body side and pier top, thereby avoiding the complex counterweight problem of traditional hanging basket and the risk of unbalanced overturning, and improving safety and stability.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model relates to the field of building technology, and in particular to an adjustable hanging fence safety operation platform. Background Technology

[0002] The high-speed railway suspended fence is an auxiliary structure of the pier, with two main purposes: 1. Safety protection, preventing workers from falling while working on top of the pier and ensuring their safety; 2. Facilitating construction, providing a relatively safe and stable operating space for workers during operations such as bridge maintenance and equipment installation. However, because the suspended fence is located at the top of the pier, there are significant risks associated with working at height during construction.

[0003] In traditional construction, suspended scaffolding installation is carried out using cranes, elevators, or pier-top suspended scaffolding. Using cranes and elevators requires specific site conditions and necessitates frequent changes in work position and frequent deployment and removal of cranes and elevators, resulting in low construction efficiency. When using pier-top suspended scaffolding, the overall system is complex, and the requirements for the balance and vertical force of the tooling are extremely high, leading to significant construction safety risks and poor applicability. Utility Model Content

[0004] The purpose of this utility model is to provide an adjustable suspended fence safety work platform, solving the following problems existing in the current pier-top suspended fence: it requires a complex system such as an electrically controlled hoist, wire rope, and safety lock, leading to complex counterweights and the risk of imbalance and overturning; it is inconvenient for construction and operation; installation is cumbersome and construction time is long; the platform height is not easy to adjust, and the scope of application is limited; it can improve safety, facilitate construction and operation, and is easy to install, saving construction time; and it is easy to adjust the platform height, expanding the scope of application.

[0005] To achieve the above objectives, the present invention adopts the following technical solution:

[0006] This utility model provides an adjustable suspended safety work platform, including a work platform, an adjustable suspension rod, and a top truss. The work platform includes a platform steel plate and a platform fence, with the bottom of the platform fence connected to the edge of the platform steel plate. The adjustable suspension rod includes a channel steel, an I-beam, and an adjusting bolt, with the I-beam movably disposed within the channel steel. Adjusting screw holes are respectively provided on the channel steel and the I-beam, and they are connected by adjusting bolts disposed within these holes. The bottom of the adjustable suspension rod is connected to the platform fence, and the top truss is connected to the top of the adjustable suspension rod.

[0007] This utility model discloses an adjustable suspended safety work platform. The platform steel plate supports construction workers for their work, while the platform railing provides protection. I-beams move vertically within the channel steel to extend and retract the adjustable boom, thereby adjusting the platform height to suit the pier dimensions. Adjustable bolts secure the I-beams within the channel steel, fixing the length of the adjustable boom and thus the platform's height. A top truss contacts the pier to bear the platform's weight and provide support.

[0008] Preferably, the channel steels are configured as a pair, and the openings of the two channel steels are arranged opposite to each other; the two side flanges of the I-beam are respectively arranged inside the pair of channel steels.

[0009] Preferably, the working platform is configured as a rectangular ring structure; the adjustable rods are configured as at least one pair, each pair of adjustable rods is symmetrically arranged, and the top of each pair of adjustable rods is connected to both ends of a top truss.

[0010] Preferably, the platform steel plate includes two C-shaped steel plates bent at right angles, and the platform fence includes two C-shaped fences bent at right angles; the bottoms of the two C-shaped fences are respectively connected to the edges of the two C-shaped steel plates to form two C-shaped platforms;

[0011] The openings of the two C-shaped platforms are arranged opposite each other and connected to form a rectangular ring structure of the work platform; each C-shaped platform is connected to at least one pair of adjustable booms, and the bottom of each pair of adjustable booms is connected to the side edges of the openings of the C-shaped platforms respectively.

[0012] Preferably, each of the C-shaped platforms is connected to two pairs of adjustable booms, and the four pairs of adjustable booms are arranged symmetrically from the inside to the outside; the open ends of the two C-shaped platforms are connected by a combination of connecting angle steel and connecting bolts.

[0013] Preferably, the channel steel includes a lower channel steel and an upper channel steel, the adjusting screw hole includes a lower adjusting screw hole and an upper adjusting screw hole, and the adjusting bolt includes a lower adjusting bolt and an upper adjusting bolt;

[0014] The lower and upper parts of the I-beam are respectively movably disposed within the lower channel steel and the upper channel steel; the lower parts of the lower channel steel and the I-beam are respectively provided with lower adjusting screw holes and connected by lower adjusting bolts provided in the lower adjusting screw holes; the upper parts of the upper channel steel and the I-beam are respectively provided with lower adjusting screw holes and connected by upper adjusting bolts provided in the upper adjusting screw holes.

[0015] The bottom of the lower channel steel is connected to the bottom of the platform fence, and the top of the upper channel steel is connected to the top truss.

[0016] Preferably, the lower channel steel and the C-shaped steel plate are connected by diagonal bracing angle steel, and the two diagonal bracing angle steels on the same side of the opening of each C-shaped steel plate are inclined outward from top to bottom.

[0017] Preferably, the bottom of the lower channel steel is connected to the C-shaped steel plate.

[0018] Preferably, a toe board is provided at the bottom of the platform fence; and a supporting channel steel is provided at the bottom of the top truss.

[0019] Preferably, the upper surface of the platform steel plate is provided with anti-slip patterns, and the platform fence is composed of at least two horizontal flat steel bars and at least two vertical fence angle steels connected perpendicularly to form a fence structure; the top truss is set as an isosceles triangle.

[0020] The adjustable suspended safety work platform provided by this utility model has the following beneficial effects:

[0021] 1. The adjustable suspended platform safety work platform provided by this utility model can solve the problem of existing pier-top suspended baskets that require complex systems such as electrically controlled hoists, wire ropes, and safety locks, which lead to complex counterweights and the risk of imbalance and overturning. It eliminates the need for complex systems such as electrically controlled hoists, wire ropes, and safety locks, and facilitates the concentrated transmission of forces from multiple directions to the sides and top of the pier, thereby avoiding the complex counterweight problem and the risk of imbalance and overturning of traditional suspended baskets, and improving safety and stability.

[0022] 2. The adjustable suspended fence safety work platform provided by this utility model can solve the problem of inconvenience in construction and operation of existing suspended cages on pier tops; it avoids the problem of using special equipment for construction for a long time, and can accommodate multiple construction workers to walk and work on the work platform at the same time, which facilitates construction and greatly improves the safety and efficiency of construction.

[0023] 3. The adjustable suspended fence safety operation platform provided by this utility model can solve the problems of complicated installation and long construction time of existing suspended fences on pier tops; its installation is simple and saves construction time.

[0024] 4. The adjustable suspended fence safety work platform provided by this utility model can solve the problems of the existing pier-top suspended fences, which are inconvenient to adjust the height of the platform and have a limited scope of application. The adjustable suspension rod, which is composed of I-beams, channel steel and adjusting bolts, can easily adjust the height of the platform according to the size of the pier column, expand the scope of application and improve applicability.

[0025] 5. The adjustable hanging fence safety work platform provided by this utility model can be set as a rectangular ring to surround the outside of the pier, which is conducive to wrapping the pier body and forming a ring-shaped passage to facilitate construction personnel to reach each installation point. The hanging fence installation work of one pier only requires moving the hanging fence safety work platform once, thus improving efficiency.

[0026] 6. The adjustable suspended fence safety work platform provided by this utility model has a rectangular ring-shaped work platform that can be designed in a split manner, which facilitates the hoisting of the C-shaped platforms with split structures on both sides, and makes it easy to combine and connect the two C-shaped platforms to form an integrated suspended fence safety work platform, which is conducive to meeting the diverse needs of pier suspended fence operations on construction sites; and it is also conducive to the use of adjustable lifting rods to further expand the range to be applicable to various pier suspended fence operations; the two C-shaped platforms can be connected by connecting angle steel and connecting bolts, which helps to ensure the overall balance and stability of the work platform.

[0027] 7. The adjustable hanging fence safety work platform provided by this utility model can be connected with a diagonal bracing angle steel between the lower part of the adjusting rod and the C-shaped platform, so as to concentrate the force of the hanging fence safety work platform in multiple directions to the side and top of the pier, which helps to improve the balance and stability. Attached Figure Description

[0028] Figure 1 This is a front view of an adjustable hanging fence safety work platform provided in an embodiment of this utility model.

[0029] Figure 2 This is a side view of an adjustable hanging fence safety work platform provided in an embodiment of this utility model.

[0030] Figure 3 This is a front view of the work platform of the adjustable hanging fence safety work platform provided in one embodiment of the present utility model.

[0031] Figure 4 This is a front view of the adjustable boom of the adjustable hanging fence safety work platform provided in one embodiment of this utility model.

[0032] Figure 5 This is a front view of a C-shaped platform with a one-sided split structure for safe operation of an adjustable hanging fence, provided in an embodiment of this utility model.

[0033] Figure 6 This is a top view of a C-shaped platform with a split structure on one side of an adjustable hanging fence safety work platform provided in an embodiment of the present invention.

[0034] Figure reference numerals:

[0035] 1. Working platform; 110. Platform steel plate; 111. C-shaped steel plate; 112. Diagonal bracing angle steel; 113. Connecting angle steel; 114. Connecting bolts; 115. C-shaped fence; 116. Connecting rib plate; 120. Platform fence; 121. Flat steel rod; 122. Fence angle steel; 123. Toe board; 2. Adjustable hanging rod; 210. Channel steel; 211. Lower channel steel; 212. Upper channel steel; 220. I-beam; 230. Adjusting bolts; 231. Lower adjusting bolts; 232. Upper adjusting bolts; 3. Top truss; 310. Supporting channel steel. Detailed Implementation

[0036] The present invention will be further described in detail below with reference to the accompanying drawings and specific embodiments.

[0037] Example

[0038] Please refer to the reference. Figures 1 to 4 This embodiment provides an adjustable suspended fence safety work platform, including a work platform 1, an adjustable suspension rod 2, and a top truss 3; the work platform 1 includes a platform steel plate 110 and a platform fence 120, the bottom of the platform fence 120 being connected to the edge of the platform steel plate 110; the adjustable suspension rod 2 includes a channel steel 210, an I-beam 220, and an adjusting bolt 230, the I-beam 220 being movably disposed within the channel steel 210; the channel steel 210 and the I-beam 220 are respectively provided with adjusting screw holes, and are connected by adjusting bolts 230 disposed within the adjusting screw holes; the bottom of the adjustable suspension rod 2 is connected to the platform fence 120; the top truss 3 is connected to the top of the adjustable suspension rod 2.

[0039] In this embodiment, the adjustable suspended safety work platform features an I-beam 220 movably mounted within the channel steel 210. The height of the adjustable boom 2 can be adjusted by moving the I-beam 220 up and down, allowing for vertical adjustment of the work platform 1 to match the height of the pier. Tightening the adjusting bolts 230 secures the boom 2 and the work platform 1. The top truss 3 is integrated with the adjustable boom 2 and the work platform 1. When the work platform 1 is positioned on top of the pier, the top truss 3 contacts the pier, supporting the weight of the work platform 1 and ensuring its stability at the preset height on the pier. This design facilitates movement and work on the platform steel plate 110, while the platform railing 120 provides protection for the workers.

[0040] Among them, the up and down directions refer to... Figures 1 to 5 The up and down directions in the middle.

[0041] Please refer to the reference. Figure 1 , Figure 4 and Figure 5Specifically, the channel steel 210 is set as a pair, and the openings of the two channel steel 210 are arranged opposite each other; the two side flanges of the I-beam 220 are respectively set in the pair of channel steel 210.

[0042] By symmetrically arranging the channel steels 210 in pairs, the I-beams 220 can be stably and movably and adjustablely installed within the pair of channel steels 210 with their openings facing each other.

[0043] Among them, left and right directions respectively refer to Figure 1 , Figure 4 and Figure 5 left and right direction in center.

[0044] Please refer to the reference. Figures 1 to 3 Specifically, the work platform 1 is configured as a rectangular ring structure; the adjustable rods 2 are configured as at least one pair, each pair of adjustable rods 2 is symmetrically arranged, and the top of each pair of adjustable rods 2 is connected to both ends of a top truss 3.

[0045] The rectangular ring-shaped work platform 1 can form a ring-shaped passage around the outside of the pier, which facilitates the movement of construction personnel on the work platform 1 to various installation points; so that the installation of the hanging fence of a pier only requires moving the hanging fence safety work platform once.

[0046] The adjustable rods 2 are arranged in pairs and symmetrically, which facilitates the connection of the top of each pair of adjustable rods 2 to the front and rear ends of a top truss 3, and the connection of the bottom of each pair of adjustable rods 2 to the working platform 1, thereby ensuring the overall balance and stability of the suspended fence safety working platform.

[0047] Among them, each pair of adjustable rods 2 is arranged symmetrically front and back, with the front and back directions respectively pointing to Figure 2 The right and left directions in the middle.

[0048] Please refer to the reference. Figure 1 , Figure 3 , Figure 5 and Figure 6 Specifically, the platform steel plate 110 includes two right-angle bent C-shaped steel plates 111, and the platform fence 120 includes two right-angle bent C-shaped fences 115; the bottom of the two C-shaped fences 115 are respectively connected to the edge of the two C-shaped steel plates 111 to form two C-shaped platforms.

[0049] Please refer to the reference. Figure 2 and Figure 3 The openings of two C-shaped platforms are arranged opposite each other and connected to form a rectangular ring structure working platform 1; each C-shaped platform is connected to at least one pair of adjustable rods 2, and the bottom of each pair of adjustable rods 2 is connected to the side edges of the openings of the C-shaped platform respectively.

[0050] By arranging two C-shaped platforms side by side with their openings facing each other and connecting the openings of the two C-shaped platforms to form a split-structure work platform 1, the length of the work platform 1 can be easily adjusted. For example, the overall length of the work platform 1 can be adjusted by adjusting the distance between the two C-shaped platforms and connecting the two C-shaped platforms with a connector of appropriate length.

[0051] The work platform 1 is formed by combining and connecting two separate C-shaped platforms, making it easier to install. Installation can be achieved through the following steps:

[0052] Step S1: Adjust the height of the adjustable boom 2 according to the height of the pier column, and fix the height of the adjustable boom 2 and the height position of the working platform 1 by adjusting bolt 230;

[0053] Step S2: Use lifting machinery to hoist the two split C-shaped platforms to the top of the pier, so that the top truss 3 of both C-shaped platforms are in contact with the top of the pier, so that the top truss 3 bears the weight of the working platform 1 and supports the working platform 1.

[0054] Step S3: After hoisting the two separate C-shaped platforms to the top of the pier, the construction personnel can be sent to the top of the pier by a lift. Then, the two separate C-shaped platforms are connected to form the overall structure of the work platform 1, ensuring the stability and firmness of the work platform 1.

[0055] Since the C-type platform is connected to at least one pair of symmetrically arranged adjustable rods 2 on the sides of the opening, the C-type platform is connected to at least one top truss 3 through the at least one pair of symmetrically arranged adjustable rods 2. This allows each C-type platform to be supported on the top of the pier through its respective top truss 3, thereby improving the overall stability of the combined suspended fence safety operation platform.

[0056] Please refer to the reference. Figure 1 , Figures 4 to 6 Specifically, each C-shaped platform is connected to two pairs of adjustable rods 2, and the four pairs of adjustable rods 2 are arranged symmetrically from the inside to the outside; the open ends of the two C-shaped platforms are connected by a combination of connecting angle steel 113 and connecting bolts 114.

[0057] On the work platform 1, which consists of two C-shaped platforms, four adjustable booms 2 are arranged from left to right on the same side of the opening of the C-shaped platform. The two adjustable booms 2 on the inner side are arranged symmetrically, and the two adjustable booms 2 on the outer side are also arranged symmetrically.

[0058] Each C-shaped platform is connected to two top trusses 3 via two pairs of adjustable booms 2. When installing the work platform 1, with two support beams placed on top of the pier, in step S2, the two top trusses 3 of each of the two C-shaped platforms can be placed on either side of the two support beams. Furthermore, of the four pairs of adjustable booms 2 and four top trusses 3 of the work platform 1 as a whole, the inner two pairs of adjustable booms 2 and two top trusses 3 are symmetrically arranged, and the outer two pairs of adjustable booms 2 and two top trusses 3 are also symmetrically arranged, thus further ensuring that each C-shaped platform is supported in a balanced and stable manner. In step S3, the open ends of the two separate C-shaped platforms can be connected to each other using two connecting angle steels 113 and connecting bolts 114, thereby forming an integrated suspended fence safety work platform.

[0059] Please refer to the reference. Figure 1 , Figure 2 and Figure 4 , Figure 5 Specifically, the channel steel 210 includes a lower channel steel 211 and an upper channel steel 212, the adjusting screw hole includes a lower adjusting screw hole and an upper adjusting screw hole, and the adjusting bolt 230 includes a lower adjusting bolt 231 and an upper adjusting bolt 232.

[0060] The lower and upper parts of the I-beam 220 are respectively movably disposed within the lower channel steel 211 and the upper channel steel 212; the lower channel steel 211 and the lower part of the I-beam 220 are respectively provided with lower adjusting screw holes and are connected by lower adjusting bolts 231 provided in the lower adjusting screw holes; the upper channel steel 212 and the upper part of the I-beam 220 are respectively provided with lower adjusting screw holes and are connected by upper adjusting bolts 232 provided in the upper adjusting screw holes.

[0061] The bottom of the lower channel steel 211 is connected to the bottom of the platform fence 120, and the top of the upper channel steel 212 is connected to the top truss 3.

[0062] The adjustable hanging fence safety work platform of this embodiment uses an adjustable hanging rod 2 with an upper and lower adjustable structure formed by matching the lower channel steel 211 and the upper channel steel 212 to the lower and upper parts of the I-beam 220, respectively. This expands the height adjustment range of the adjustable hanging rod 2 and the work platform 1, making it more suitable for piers of various sizes and structural forms. The bottom of the lower channel steel 211 can be welded to the bottom of the platform fence 120.

[0063] Please refer to the reference. Figure 1 and Figure 5 An inclined bracing angle steel 112 can be connected between the lower part of the adjusting rod 2 and the working platform 1 to facilitate the concentrated transmission of the forces on the suspended fence safety working platform in multiple directions to the side and top of the pier, thereby improving balance and stability.

[0064] Specifically, the lower channel steel 211 and the C-shaped steel plate 111 are connected by diagonal bracing angle steel 112, and the two diagonal bracing angle steels 112 on the same side of the opening of each C-shaped steel plate 111 are inclined outward from top to bottom.

[0065] By welding an outward-sloping angle steel 112 to the lower channel steel 211 of the two pairs of adjustable rods 2 of each C-shaped platform, the two angle steels 112 of each C-shaped platform are arranged in a figure-eight shape; thereby improving the connection between the lower part of the adjustable rod 2 and the C-shaped platform, which helps to ensure the overall stability of the suspended fence safety operation platform.

[0066] Specifically, the bottom of the lower channel steel 211 is connected to the C-shaped steel plate 111, thereby improving the connection strength between the adjustable rod 2 and the C-shaped platform.

[0067] Please refer to the reference. Figures 1 to 3 , Figure 5 Specifically, a toe board 123 is installed at the bottom of the platform fence 120; a supporting channel steel 310 is installed at the bottom of the top truss 3.

[0068] The toe board 123 connected to the bottom of the platform fence 120 can prevent construction workers from accidentally slipping off the work platform 1, thus improving safety. The supporting channel steel 310 is welded to the bottom of the top truss 3, which can serve as a support between the top truss 3 and the pier column.

[0069] Specifically, such as Figure 6 As shown, the upper surface of the platform steel plate 110 is provided with anti-slip patterns;

[0070] Please refer to the reference. Figures 1 to 3 , Figure 5 The platform fence 120 is composed of at least two transverse flat steel bars 121 and at least two longitudinal fence angle steel bars 122 connected perpendicularly to form a fence structure.

[0071] like Figure 2 As shown, the top truss 3 is set as an isosceles triangle.

[0072] like Figure 6 As shown, the platform steel plate 110 can be made of patterned steel plate using existing technology. That is, the C-shaped steel plate 111 can be made of patterned steel plate.

[0073] Flat steel rods 121 and fence angle steel 122 are welded horizontally and vertically to form a grid-like platform fence 120, which can improve the sturdiness and protection of the platform fence 120.

[0074] The isosceles triangle at the top truss 3 enhances its robustness and stability.

[0075] The adjustable suspended fence safety work platform of this embodiment can also be specifically, such as... Figure 6As shown, triangular connecting ribs 116 are connected to the two bending points of the C-shaped steel plate 111 to reinforce the C-shaped steel plate 111. The connecting ribs 116 are welded to the C-shaped steel plate 111, and the two are located in the same horizontal plane. The connecting ribs 116 can also be made of checkered steel plate.

[0076] Please refer to the reference. Figure 1 , Figure 3 , Figure 5 and Figure 6 The two C-shaped platforms are connected by connecting angle steel 113 and connecting bolts 114 at their respective open ends to form a rectangular ring structure of the working platform 1.

[0077] Please refer to the reference. Figure 1 and Figure 5 Each C-shaped platform is connected to at least one pair of adjustable booms 2, with the two adjustable booms 2 in each pair symmetrically arranged on both sides of the opening of the C-shaped platform.

[0078] Each C-shaped platform can be connected to two pairs of adjustable rods 2, so each C-shaped platform has two adjustable rods 2 connected to each side of the opening. The two diagonal bracing angle steels 112 on the same side of the opening of each C-shaped platform form an asymmetrical figure-eight structure. The angle between the diagonal bracing angle steel 112 closer to the opening and the C-shaped steel plate 111 is greater than the angle between the other diagonal bracing angle steel 112 and the C-shaped steel plate 111.

[0079] When two C-shaped platforms are connected to form a rectangular ring structure working platform 1, among the four diagonal bracing angle steels 112 on the same side of the openings of the two C-shaped platforms, the two inner diagonal bracing angle steels 112 form a symmetrical V-shaped structure, and the two outer diagonal bracing angle steels 112 form a symmetrical figure-eight structure.

[0080] The diagonal bracing angle steel 112 and the side of the C-shaped fence 115 on the same side are located in the same vertical plane.

[0081] Please refer to the reference. Figures 1 to 3 , Figure 5 The flat steel rod 121 is set as a rectangular steel rod. The toe plate 123 is set as a vertical rectangular plate, and can be set as a C-shaped plate with a right angle bend. The toe plate 123 can be welded to the bottom of the C-shaped fence 115.

[0082] Please refer to the reference. Figure 1 , Figure 2 , Figure 4 and Figure 5Both the lower channel steel 211 and the upper channel steel 212 are set as right-angled channel steels. Each adjustable rod 2 may include a pair of symmetrically arranged lower channel steels 211 and a pair of symmetrically arranged upper channel steels 212, and the lower and upper parts of the I-beam 220 are respectively movably set in the pair of lower channel steels 211 and the pair of upper channel steels 212.

[0083] Please refer to the reference. Figure 1 and Figure 5 In each C-shaped platform, the top ends of the two outermost angle steels 112 on the same side of the opening are welded to the two outermost lower channel steels 211. Furthermore, the bottom ends of the four angle steels 112 of each C-shaped platform are welded to the four corners of the C-shaped platform.

[0084] Please refer to the reference. Figure 1 , Figure 2 , Figure 4 and Figure 5 Five pairs of lower adjusting screw holes are respectively opened on both sides of the lower channel steel 211 and the lower two side flanges of the I-beam 220, and lower adjusting bolts 231 are respectively installed in the lower adjusting screw holes of both. Five pairs of upper adjusting screw holes are respectively opened on both sides of the upper channel steel 212 and the upper two side flanges of the I-beam 220, and upper adjusting bolts 232 are respectively installed in the upper adjusting screw holes of both.

[0085] Five pairs of lower and upper adjusting screw holes are evenly arranged from top to bottom.

[0086] Please refer to the reference. Figure 1 and Figure 2 The top truss 3 is formed by welding multiple square tubes to create an isosceles triangle. The top of the upper channel steel 212 of each pair of adjustable rods 2 is welded to both ends of the base of a top truss 3. That is, each pair of adjustable rods 2 and the connected top truss 3 are located in the same vertical plane.

[0087] like Figure 2 As shown, a support channel steel 310 is welded to the middle of the bottom edge of the top truss 3.

[0088] The above embodiments are merely illustrative examples and are not intended to limit the implementation. Those skilled in the art will recognize that other variations or modifications can be made based on the above description. It is neither necessary nor possible to exhaustively list all possible implementations. However, obvious variations or modifications derived therefrom are still within the protection scope of this invention.

[0089] It should be noted that, unless otherwise specified, the embodiments and features described in these embodiments of the present invention can be combined with each other.

[0090] In the description of this utility model, it should be understood that the terms "center," "longitudinal," "lateral," "upper," "lower," "front," "rear," "left," "right," "vertical," "horizontal," "top," "bottom," "inner," and "outer," etc., indicating the orientation or positional relationship, are based on the orientation or positional relationship shown in the accompanying drawings and are only for the convenience of describing this utility model and simplifying the description, and do not indicate or imply that the device or element referred to has a specific orientation, or is constructed and operated in a specific orientation, and therefore should not be construed as a limitation of this utility model. Furthermore, the terms "first," "second," etc., are used for descriptive purposes only and should not be construed as indicating or implying relative importance or implicitly specifying the number of indicated technical features. Thus, features defined with "first," "second," etc., may explicitly or implicitly include one or more of that feature. In the description of this utility model, unless otherwise stated, "a plurality of" means two or more.

[0091] In the description of this utility model, it should be noted that, unless otherwise explicitly specified and limited, the terms "installation," "connection," and "joining" should be interpreted broadly. For example, they can refer to a fixed connection, a detachable connection, or an integral connection; they can refer to a mechanical connection or an electrical connection; they can refer to a direct connection or an indirect connection through an intermediate medium; and they can refer to the internal connection of two components. Those skilled in the art can understand the specific meaning of the above terms in this utility model based on the specific circumstances.

Claims

1. An adjustable suspended safety work platform, characterized in that, include: The working platform includes a platform steel plate and a platform fence, wherein the bottom of the platform fence is connected to the edge of the platform steel plate; An adjustable boom includes a channel steel, an I-beam, and an adjusting bolt. The I-beam is movably disposed within the channel steel. The channel steel and the I-beam are respectively provided with adjusting screw holes and are connected by adjusting bolts disposed within the adjusting screw holes. The bottom of the adjustable boom is connected to the platform railing. The top truss is connected to the top of the adjustable hanger.

2. The adjustable hanging fence safety work platform according to claim 1, characterized in that, The channel steels are configured as a pair, and the openings of the two channel steels are arranged opposite each other; the two side flanges of the I-beam are respectively set inside the pair of channel steels.

3. The adjustable hanging fence safety work platform according to claim 1, characterized in that, The working platform is configured as a rectangular ring structure; the adjustable rods are configured as at least one pair, each pair of adjustable rods is symmetrically arranged, and the top of each pair of adjustable rods is connected to both ends of one of the top trusses.

4. The adjustable hanging fence safety work platform according to claim 3, characterized in that, The platform steel plate includes two C-shaped steel plates bent at right angles, and the platform fence includes two C-shaped fences bent at right angles; the bottom of the two C-shaped fences are respectively connected to the edge of the two C-shaped steel plates to form two C-shaped platforms; The openings of the two C-shaped platforms are arranged opposite each other and connected to form a rectangular ring structure of the work platform; each C-shaped platform is connected to at least one pair of adjustable booms, and the bottom of each pair of adjustable booms is connected to the side edges of the openings of the C-shaped platforms respectively.

5. The adjustable hanging fence safety work platform according to claim 4, characterized in that, Each of the C-shaped platforms is connected to two pairs of adjustable booms, and the four pairs of adjustable booms are arranged symmetrically from the inside to the outside; the open ends of the two C-shaped platforms are connected by a combination of connecting angle steel and connecting bolts.

6. The adjustable hanging fence safety work platform according to claim 5, characterized in that, The channel steel includes a lower channel steel and an upper channel steel, the adjusting screw hole includes a lower adjusting screw hole and an upper adjusting screw hole, and the adjusting bolt includes a lower adjusting bolt and an upper adjusting bolt; The lower and upper parts of the I-beam are respectively movably disposed within the lower channel steel and the upper channel steel; the lower parts of the lower channel steel and the I-beam are respectively provided with lower adjusting screw holes and connected by lower adjusting bolts provided in the lower adjusting screw holes; the upper parts of the upper channel steel and the I-beam are respectively provided with lower adjusting screw holes and connected by upper adjusting bolts provided in the upper adjusting screw holes. The bottom of the lower channel steel is connected to the bottom of the platform fence, and the top of the upper channel steel is connected to the top truss.

7. The adjustable suspended fence safety work platform according to claim 6, characterized in that, The lower channel steel and the C-shaped steel plate are connected by diagonal bracing angle steels, and the two diagonal bracing angle steels on the same side of the opening of each C-shaped steel plate are inclined outward from top to bottom.

8. The adjustable suspended fence safety work platform according to claim 6, characterized in that, The bottom of the lower channel steel is connected to the C-shaped steel plate.

9. The adjustable hanging fence safety work platform according to claim 5, characterized in that, The platform fence is equipped with a toe board at the bottom; the top truss is equipped with a supporting channel steel at the bottom.

10. The adjustable hanging fence safety work platform according to any one of claims 1-9, characterized in that, The upper surface of the platform steel plate is provided with anti-slip patterns, and the platform fence is composed of at least two horizontal flat steel bars and at least two vertical fence angle steel bars connected perpendicularly to form a fence structure; the top truss is set as an isosceles triangle.