ground beam trench
A technology of ground beams and trenches, applied in water conservancy projects, artificial islands, underwater structures, etc., can solve the problems of cable or pipeline soaking, affecting cables and pipelines, etc., and achieve the effect of saving project cost and quantity
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Publication Date
- 2016-08-24
Smart Images
Figure 1 Figure 2
Abstract
Description
technical field
[0001] The invention belongs to the technical field of thermal power generation, in particular to a ground beam type trench. Background technique
[0002] Cable trenches and pipe trenches are an important part of thermal power plants and one of the common trenches inside power plants.
[0003] Existing cable trenches and pipe trenches are composed of trench walls, trench bottoms and trench cover plates. The material is reinforced concrete. Temporary trenches can be laid with bricks. There are embedded parts inside the trenches to fix cable supports or pipes. . Both the cable trench and the pipe trench are independent trenches, which are mainly used to solve the drainage problem of the trench. The conventional practice is to raise the trench surface by 100 mm above the bottom surface to prevent rainwater from entering the trench; and, in the trench In addition, a drainage pipe is connected to the nearby drainage system to ensure that there will be no water a...
Examples
Embodiment Construction
[0025] Embodiments of the present invention are described in detail below:
[0026] Such as figure 1 , figure 2 As shown, a ground beam trench 100 includes a trench wall 110, a trench cover 120, a trench bottom 130 and embedded parts 140, the trench bottom 130 is set at the bottom of the trench, and the trench walls 110 are set on both sides of the trench bottom 130, And the ditch bottom 130 is connected to the bottom of the ditch wall 110; the ditch cover 120 is arranged on the upper part of the ditch wall 110, and the embedded part 140 is arranged on the inner wall of the ditch wall 110; the ditch bottom 130 is provided with a drainage hole 132, and the corresponding A gravel layer 150 is provided at the bottom of the ditch bottom 130 .
[0027] The ditch bottom 130 is arranged on the foundation, the ditch wall 110 is arranged on both sides of the ditch bottom 130, and the ditch bottom 130 is connected to the bottom of the ditch wall 110, and the ditch cover 120 is arrang...