Assembled building structure concrete vertical component butt joint structure and method

By adding flare nuts at the lower end of the steel sleeve, the problem of difficulty in accurate docking by construction workers is solved, the installation efficiency of prefabricated concrete structures is improved, and the docking process is simplified, instead of concrete gaskets, achieving more efficient vertical Connect the steel bars to the steel sleeve.

CN109025071BActive Publication Date: 2024-11-15ARCHITECTURAL DESIGN RES INST OF GUANGDONG PROVINCE
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN201810892478.8
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2018-08-07
Publication Date
2024-11-15
Estimated Expiration
2038-08-07

AI Technical Summary

Technical Problem

In prefabricated concrete building structures, when the steel sleeve is connected to the reserved vertical steel bars below, it is difficult for construction personnel to accurately judge the position of the steel sleeve, and the inner diameter of the steel sleeve is very different from the diameter of the steel sleeve, which leads to difficulty in docking and needs to be set up separately. Concrete gaskets to ensure the height of the seat slurry.

Method used

The flare nut is added at the lower end of the steel sleeve. The flare nut has a gradually expanded opening with a diameter gradually increasing from the top to the bottom, which is used to quickly and accurately find the position of the steel sleeve and serve as a gasket instead of concrete gaskets to improve the Docking efficiency.

Benefits of technology

It improves the butt efficiency of the steel sleeve and vertical steel bars, simplifies the installation process, reduces installation time, and replaces traditional concrete gaskets to ensure the flatness of the structure and the height of the seat slurry.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN109025071B_ABST
    Figure CN109025071B_ABST
Patent Text Reader

Abstract

The present invention discloses a butt joint structure and method for a prefabricated building structure concrete vertical member, wherein the butt joint structure comprises a steel sleeve, a lower vertical steel bar and a flared nut, wherein the steel sleeve is prefabricated in an upper concrete structural member, the steel sleeve has a grouting port, grouting is performed through the grouting port, the lower vertical steel bar is prefabricated in the lower concrete structural member and extends upward, and is inserted into the steel sleeve after passing through a cast-in-place reinforced concrete floor slab and a seat grout, the flared nut is connected to the lower end of the steel sleeve, and is convenient for a construction unit to accurately find the specific position of the steel sleeve, the flared nut has a gradually expanding flared opening with a gradually increasing diameter from top to bottom, and the diameter of the lower end opening of the flared opening is larger than the inner diameter of the steel sleeve, so as to facilitate the rapid butt joint of the lower vertical steel bar into the steel sleeve, and improve the butt joint efficiency of the steel sleeve and the lower vertical steel bar. The present invention also discloses a butt joint method.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of assembled concrete structures, in particular to an assembled building structure concrete vertical component butt joint structure and method. Background Art

[0002] In prefabricated concrete building structures, vertical steel bar connection is one of the key technologies. Among the existing technologies for vertical steel bar connection, steel bar sleeve grouting connection is the simplest, most convenient and effective. However, this connection technology has relatively large defects during the installation process:

[0003] 1. The steel sleeve is embedded in the prefabricated concrete vertical structural member. When the steel sleeve is connected and installed with the vertical steel bars reserved in the prefabricated concrete structural member below, the construction workers cannot accurately determine the specific position of the steel sleeve and need to use tools such as mirrors to assist in determining the position of the steel sleeve.

[0004] 2. Since the thickness of the steel bar protective layer of the prefabricated concrete vertical structural components is thinner than that of the cast-in-place concrete vertical structural components, the diameter of the steel sleeve is limited. The inner diameter of the steel sleeve is about 10 mm larger than the diameter of the connecting steel bar, making it difficult to connect the steel sleeve with the reserved vertical steel bars below.

[0005] 3. A 20mm base mortar needs to be laid between the upper prefabricated concrete structural components and the cast-in-place reinforced concrete floor slab, so a separate concrete gasket needs to be set to ensure the 20mm base mortar height. Summary of the invention

[0006] One of the purposes of the present invention is to provide a docking structure for concrete vertical components of an assembled building structure. The docking structure adds a bell-mouth nut at the lower end of the steel sleeve, so that construction workers can quickly and accurately find the specific position of the steel sleeve for docking with the lower vertical steel bars, thereby improving the installation efficiency of the concrete structural components.

[0007] This object of the present invention is achieved through the following technical scheme: a butt joint structure of concrete vertical members of an assembled building structure, the building structure comprises an upper concrete structural member, a lower concrete structural member, a cast-in-place reinforced concrete floor slab located on the lower concrete structural member, and a seat grout laid on the cast-in-place reinforced concrete floor slab, the butt joint structure comprises a steel sleeve and lower vertical steel bars, the steel sleeve is prefabricated in the upper concrete structural member, the steel sleeve has a grouting port, grouting is performed through the grouting port, the lower vertical steel bars are prefabricated in the lower concrete structural member and extend upward, and are inserted into the steel sleeve after passing through the cast-in-place reinforced concrete floor slab and the seat grout, and the characteristics are as follows: Yu: The docking structure also includes a bell-mouth nut, which is connected to the lower end of the steel sleeve, so that the construction unit can accurately find the specific position of the steel sleeve. The bell-mouth nut has a gradually expanding bell opening with a diameter gradually increasing from top to bottom. The diameter of the lower end opening of the bell opening is larger than the inner diameter of the steel sleeve, so that it is convenient for the lower vertical steel bars to quickly dock into the steel sleeve, thereby improving the docking efficiency of the steel sleeve and the lower vertical steel bars, thereby completing the rapid installation of the upper concrete structural components and the lower concrete structural components, and improving the installation efficiency of the concrete structural components. The bell-mouth nut is also used as a gasket for the upper concrete structural components placed on the cast-in-place reinforced concrete floor slab.

[0008] The docking structure of the present invention is provided with a bell-mouth nut below the steel sleeve, and the bell-mouth nut protrudes from the lower end of the upper concrete structural member. Construction personnel can quickly and accurately find the specific position of the steel sleeve so as to dock it with the lower vertical steel bars; the inner diameter of the bell-mouth nut mouth is larger than the inner diameter of the steel sleeve, so the docking efficiency of the steel sleeve and the lower vertical steel bars can be greatly improved. After the docking is completed, the bell-mouth nut can also be used as a steel gasket for the upper concrete structural member to be placed on the cast-in-place reinforced concrete floor slab, replacing the concrete gasket.

[0009] In the present invention, the bell-mouth nut comprises a nut connecting portion and a bell-mouth opening portion, the nut connecting portion and the bell-mouth opening portion have interpenetrating center holes, wherein the center hole of the nut connecting portion is a cylindrical hole, the center hole of the bell-mouth opening portion is a truncated cone hole with a variable cross-section, the center hole of the bell-mouth opening portion is the bell opening of the bell-mouth nut, the aperture of the center hole of the nut connecting portion is the same as the aperture of the upper end opening of the bell opening, the nut connecting portion has an external thread, the steel sleeve has an internal thread matched with the external thread, and the bell-mouth nut is connected to the steel sleeve by a thread.

[0010] Since the bell-mouth nut acts as a gasket, it is necessary to ensure the flatness of the upper concrete structure member by adjusting the bell-mouth nut. In order to facilitate the operation of the wrench, four 15mmX10mm (heightXwidth) rectangles are cut around the bell-mouth nut.

[0011] In the present invention, the material of the bell-mouth nut is steel.

[0012] In the present invention, the height of the nut connection part is 10 mm and the wall thickness is 2 mm.

[0013] In the present invention, the height of the trumpet opening is 20 mm, which is the same as the height of the seat slurry. The wall thickness at the uppermost end of the trumpet opening is the thickest, which is 10 mm. The inner diameter of the opening at the uppermost end is the smallest, which is 4 mm smaller than the inner diameter of the steel sleeve. The wall thickness at the lowermost end of the trumpet opening is the thinnest, which is 1 mm. The inner diameter of the opening at the lowermost end is the largest, which is 14 mm larger than the inner diameter of the steel sleeve.

[0014] The second object of the present invention is to provide a docking method using the above docking structure, which is convenient to construct and has strong operability.

[0015] This object of the present invention is achieved by the following technical solution: The docking method of the above docking structure is characterized in that the method comprises the following steps:

[0016] (1) The flared nut on the upper concrete structural member is pre-connected to the lower end of the steel sleeve;

[0017] (2) The steel sleeve reserved in the upper concrete structural member is butted against the lower vertical steel bar through the bell mouth of the bell nut;

[0018] (3) The upper concrete structural components are lowered onto the pre-laid base mortar to quickly complete the docking and installation of the prefabricated concrete vertical structural components;

[0019] (4) The height of the bell-mouth nut can be adjusted by a wrench, and then the flatness of the upper concrete structure component can be adjusted to meet the design requirements. BRIEF DESCRIPTION OF THE DRAWINGS

[0020] The present invention is further described in detail below with reference to the accompanying drawings and specific embodiments.

[0021] Figure 1 It is a diagram of the use state of the docking structure of the present invention;

[0022] Figure 2 for Figure 1 A-A section view;

[0023] Figure 3 for Figure 2 B-B section of

[0024] Figure 4 It is a parts diagram of the bell-mouth nut in the docking structure of the present invention.

[0025] In the figure: 1-lower vertical reinforcement, 2-lower concrete structural member, 3-cast-in-place reinforced concrete floor slab, 4-seat grout, 5-trumpet nut, 51-nut connecting part, 52-trumpet opening, 6-upper concrete structural member, 7-grouting material, 8-grouting port, 9-steel sleeve. DETAILED DESCRIPTION

[0026] like Figures 1 to 4 The shown prefabricated building structure concrete vertical component docking structure, the building structure includes an upper concrete structural member 6, a lower concrete structural member 2, a cast-in-place reinforced concrete floor 3 located on the lower concrete structural member 2, and a seat mortar 4 laid on the cast-in-place reinforced concrete floor 3, and the docking structure includes a steel sleeve 9, a lower vertical steel bar 1 and a bell-mouth nut 5.

[0027] The steel sleeve 9 is prefabricated in the upper concrete structural member 6. The wall thickness of the steel sleeve 9 is 4 mm. The steel sleeve 9 has a grouting port 8. Grouting is performed through the grouting port 8 so that the grouting material 7 enters the steel sleeve 9. The lower vertical steel bar 1 is prefabricated in the lower concrete structural member 2 and extends upward, and is inserted into the steel sleeve 9 after passing through the cast-in-place reinforced concrete floor 3 and the seat grout 4. The material of the bell-mouth nut 5 is steel. The bell-mouth nut 5 is connected to the lower end of the steel sleeve 9, which is convenient for the construction unit to accurately find the specific position of the steel sleeve 9. The nut 5 has a gradually expanding trumpet opening with a gradually increasing diameter from top to bottom. The diameter of the lower end opening of the trumpet opening is larger than the inner diameter of the steel sleeve 9, so that the lower vertical steel bar 1 can be quickly docked into the steel sleeve 9, which improves the docking efficiency of the steel sleeve 9 and the lower vertical steel bar 1, thereby completing the rapid installation of the upper concrete structure member 6 and the lower concrete structure member 2, and improving the installation efficiency of the concrete structure member. The trumpet nut 5 also serves as a gasket for the upper concrete structure member 6 to be placed on the cast-in-place reinforced concrete floor 3. Since the trumpet nut 5 acts as a gasket, it is necessary to ensure the flatness of the upper concrete structure member 6 by adjusting the trumpet nut 5. In order to facilitate the operation of the wrench, four 15mmX10mm (heightXwidth) rectangles are cut out around the trumpet nut 5.

[0028] In this embodiment, the bell-mouth nut 5 includes a nut connecting portion 51 and a bell opening portion 52, and the nut connecting portion 51 and the bell opening portion 52 have a central hole that intersects with each other, wherein the central hole of the nut connecting portion 51 is a cylindrical hole, and the central hole of the bell opening portion 52 is a truncated cone hole with a variable cross-section, and the central hole of the bell opening portion 52 is the bell opening of the bell-mouth nut 5, and the aperture of the central hole of the nut connecting portion 51 is the same as the aperture of the upper end opening of the bell opening, the nut connecting portion 51 has an external thread, and the steel sleeve 9 has an internal thread that matches the external thread, and the bell-mouth nut 5 is connected to the steel sleeve 9 through a thread.

[0029] The height of the nut connection part 51 is 10mm and the wall thickness is 2mm; the height of the trumpet opening part 52 is 20mm, which is the same as the height of the seat slurry 4, thereby ensuring the accuracy of the height of the seat slurry 4. The trumpet nut 5 is used as a gasket for the upper concrete structural member 6 placed on the cast-in-place reinforced concrete floor 3, replacing the traditional concrete gasket. The height of the trumpet opening part 52 is required to be consistent with the height of the seat slurry 4. The wall thickness of the uppermost end of the trumpet opening part 52 is the thickest, which is 10mm, and the inner diameter of the opening at the uppermost end is the smallest, which is 4mm smaller than the inner diameter of the steel sleeve 9. The wall thickness of the lowermost end of the trumpet opening part 52 is the thinnest, which is 1mm, and the inner diameter of the opening at the lowermost end is the largest, which is 14mm larger than the inner diameter of the steel sleeve 9.

[0030] In the docking structure of the present invention, the bell-mouth nut 5 on the upper concrete structural member 6 is pre-connected to the lower end of the steel sleeve 9 through a thread, and the steel sleeve 9 reserved in the upper concrete structural member 6 is docked with the lower vertical steel bar 1 through the bell-mouth nut 5. After the docking is completed, the upper concrete structural member 6 is lowered onto the pre-laid seat slurry 4, and the installation of the prefabricated concrete vertical structural member is quickly completed, which greatly improves the installation efficiency of the vertical prefabricated concrete structural member. The prior art takes about 20 minutes to install a piece of prefabricated shear wall, and the installation using the docking structure of the present invention takes about 5 minutes, which greatly improves the docking installation efficiency of the lower vertical steel bar 1 and the steel sleeve 9.

[0031] The docking method of the above docking structure comprises the following steps:

[0032] (1) The bell nut 5 on the upper concrete structural member 6 is pre-connected to the lower end of the steel sleeve 9;

[0033] (2) The steel sleeve 9 reserved in the upper concrete structural member 6 is butted against the lower vertical steel bar 1 through the bell mouth of the bell nut 5;

[0034] (3) The upper concrete structural member 6 is lowered onto the pre-laid seat mortar 4 to quickly complete the docking installation of the assembled concrete vertical structural member.

[0035] (4) The height of the bell-mouth nut 5 can be adjusted by a wrench, and then the flatness of the upper concrete structural member 6 can be adjusted to meet the design requirements.

[0036] The above-mentioned docking method pre-installs a bell-mouth nut 5 at the lower end of the steel sleeve 9 of the upper concrete structural member 6. The bell-mouth nut 5 protrudes 20 mm from the lower end of the upper concrete structural member 6. During the docking installation, it is convenient for construction personnel to quickly and accurately find the specific position of the steel sleeve 9. The inner diameter of the mouth of the bell-mouth nut 5 is 14 mm larger than the inner diameter of the steel sleeve 9, which greatly improves the docking installation efficiency of the lower vertical steel bar 1 and the steel sleeve 9. The bell-mouth nut can replace the concrete gasket to ensure that the seat slurry height meets the design requirements, which is worthy of vigorous and extensive promotion.

[0037] The above embodiments of the present invention are not intended to limit the protection scope of the present invention, and the implementation modes of the present invention are not limited thereto. All other modifications, replacements or changes made to the above structures of the present invention based on the above contents of the present invention, in accordance with common technical knowledge and customary means in the art, without departing from the above basic technical ideas of the present invention, should fall within the protection scope of the present invention.

Claims

1. A butt joint structure of concrete vertical members of an assembled building structure, the building structure comprising an upper concrete structural member, a lower concrete structural member, a cast-in-place reinforced concrete floor slab located on the lower concrete structural member, and a seat grouting material laid on the cast-in-place reinforced concrete floor slab, the butt joint structure comprising a steel sleeve and lower vertical steel bars, the steel sleeve being prefabricated in the upper concrete structural member, the steel sleeve having a grouting port, grouting through the grouting port, the lower vertical steel bars being prefabricated in the lower concrete structural member and extending upward, and being inserted into the steel sleeve after passing through the cast-in-place reinforced concrete floor slab and the seat grouting material, characterized in that: The docking structure also includes a bell-mouth nut, which is connected to the lower end of the steel sleeve, so that the construction unit can accurately find the specific position of the steel sleeve. The bell-mouth nut has a gradually expanding bell opening with a diameter gradually increasing from top to bottom. The diameter of the lower end opening of the bell opening is larger than the inner diameter of the steel sleeve, so that the lower vertical steel bars can be quickly docked into the steel sleeve, which improves the docking efficiency of the steel sleeve and the lower vertical steel bars, thereby completing the rapid installation of the upper concrete structural components and the lower concrete structural components, and improving the installation efficiency of the concrete structural components. The bell-mouth nut is also used as a gasket for the upper concrete structural component placed on the cast-in-place reinforced concrete floor slab.

2. The butt joint structure of concrete vertical components of an assembled building structure according to claim 1, characterized in that: The bell-mouth nut includes a nut connecting part and a bell opening part, and the nut connecting part and the bell opening part have a central hole that intersects with each other, wherein the central hole of the nut connecting part is a cylindrical hole, and the central hole of the bell opening part is a truncated cone hole with a variable cross-section, and the central hole of the bell opening part is the bell opening of the bell-mouth nut, and the aperture of the central hole of the nut connecting part is the same as the aperture of the upper end opening of the bell opening, the nut connecting part has an external thread, and the steel sleeve has an internal thread that matches the external thread, and the bell-mouth nut is connected to the steel sleeve by a thread.

3. The butt joint structure of concrete vertical components of prefabricated building structures according to claim 2 is characterized in that: The material of the bell-mouth nut is steel.

4. The butt joint structure of concrete vertical components of an assembled building structure according to claim 2, characterized in that: The height of the nut connection part is 10 mm and the wall thickness is 2 mm.

5. The butt joint structure of concrete vertical components of an assembled building structure according to claim 2, characterized in that: The height of the trumpet opening is 20 mm, the same as the height of the seat slurry. The thickest wall thickness at the uppermost end of the trumpet opening is 10 mm, and the inner diameter of the opening at the uppermost end is the smallest, which is 4 mm smaller than the inner diameter of the steel sleeve. The thinnest wall thickness at the lowermost end of the trumpet opening is 1 mm, and the inner diameter of the opening at the lowermost end is the largest, which is 14 mm larger than the inner diameter of the steel sleeve.

6. The method for docking a docking structure according to any one of claims 1 to 5, characterized in that: The method comprises the following steps: (1) The flared nut on the upper concrete structural member is pre-connected to the lower end of the steel sleeve; (2) The steel sleeve reserved in the upper concrete structural member is butted against the lower vertical steel bar through the bell mouth of the bell nut; (3) The upper concrete structural components are lowered onto the pre-laid base mortar to quickly complete the docking and installation of the prefabricated concrete vertical structural components; (4) The height of the bell-mouth nut can be adjusted by a wrench, and then the flatness of the upper concrete structure component can be adjusted to meet the design requirements.