A multi-level scheduling method based on overall optimization

Through a multi-level scheduling method based on overall optimization, the national and provincial scheduling information is summarized, and the overall optimization calculation and adjustment plan is provided, the problems of low scheduling efficiency and difficult resource allocation are solved, and the scheduling coordination and resource optimization effects are improved.

CN109978322BActive Publication Date: 2024-11-12CHINA ELECTRIC POWER RESEARCH INSTITUTE CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN201910044679.7
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2019-01-17
Publication Date
2024-11-12
Estimated Expiration
2039-01-17

AI Technical Summary

Technical Problem

Among the existing power system scheduling methods, the preparation efficiency of the three-level scheduling plan in China is low, the coordination period is long, the interaction between levels is frequent, the process is complex, and it is difficult to optimize resource allocation, especially in the case of ultra-high voltage power grids and large-scale clean energy access. Traditional scheduling models are difficult to improve the degree of collaboration and resource coordination efficiency.

Method used

A multi-level scheduling method based on overall optimization is adopted, through basic data preparation, constraints and target summary, overall optimization calculation and adjustment plan provision, the unified analysis and coordination of national and provincial scheduling plans are achieved, and the scheduling coordination capabilities and resource optimization effects are improved.

Benefits of technology

Through overall optimization calculation and adjustment plan, the coordination capabilities and resource coordination and optimization effects between the three-level schedulings in the country and provinces have been improved, the dispatch cycle and personnel work intensity have been reduced, and the efficiency of power grid resource allocation has been improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN109978322B_ABST
    Figure CN109978322B_ABST
Patent Text Reader

Abstract

A multi-level scheduling method based on overall optimization combines the business processing characteristics of national, local and provincial scheduling plans. By calling the overall optimization function that considers the national, local and provincial scheduling plan information and constraints, it can realize the judgment and analysis of whether there are conflicts in constraints between national and provincial plans, and give corresponding adjustment plans, thereby improving the ability of coordinated scheduling among national, local and provincial multi-level scheduling and enhancing the overall optimization effect of three-level scheduling resources.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of power system operation dispatching, and in particular relates to a dispatching method of a national dispatching, a sub-dispatching and a provincial dispatching multi-level dispatching organization based on overall optimization. Background Art

[0002] At present, my country has established a national, sub-district and provincial dispatching plan workflow, and realized the coordinated preparation of multi-level dispatching plans. However, the rapid development of UHV has made the AC and DC coupling of the power grid, the coupling of the sending and receiving ends, and the high and low voltage coupling closer, which has posed new challenges to the existing dispatching plan business model of sub-provincial balance and weak coupling of dispatching at all levels. The current national sub-provincial dispatching plan business adopts a serial work mode of upper and lower levels. After the national dispatching plan is completed, it is sent to the sub-dispatching plan, which serves as the boundary of the sub-dispatching plan for its own preparation. If there are constraints that cannot be adjusted by itself, it will be fed back to the national dispatching plan for modification and iteration. After the sub-dispatching plan is completed, it is sent to the provincial dispatching plan, which serves as the boundary of the provincial dispatching plan for its own preparation. If there are constraints that cannot be adjusted by itself, it will be fed back to the sub-dispatching plan for modification and iteration. In this way, the reciprocating coordination cycle between the national, sub-provincial and multi-level is long, the interaction between the levels is too frequent, and the process complexity, data transmission pressure, and personnel work intensity are constantly increasing. At the same time, the sending-end power grid plan and the receiving-end power grid plan are highly coupled through national and provincial plans. The power grid constraints at the sending and receiving ends are prone to form a "seesaw" phenomenon, which makes the national and provincial plans highly coupled. The traditional planning method that considers regional and provincial balance makes it difficult to improve the degree of national and provincial cooperation. The efficiency of the three-level dispatching plan preparation and the degree of overall optimization need to be improved.

[0003] In addition, the widespread access to large-scale clean energy, the rapid development of ultra-high voltage power grids, and the continuous advancement of the construction of large-scale operation systems have posed challenges to the operation and dispatching of power systems. The requirements for safe and stable operation of large power grids and optimal resource allocation are becoming increasingly urgent. The current power generation plan is usually based on provincial plans for local balance, and the business models of the national dispatch and various sub-dispatches are different. With the rapid development of cross-regional configuration capabilities, the national sub-dispatches play an outstanding role in the balance of power and electricity in the entire network. At present, the serial planning and coordination cycle between national and provincial dispatch is long, the interaction between levels is too frequent, the process complexity, data transmission pressure, and personnel work intensity are constantly increasing, making it difficult to give full play to the optimal allocation capabilities of large power grid resources, and the efficiency of dispatch plan preparation and the degree of overall optimization need to be improved. Summary of the invention

[0004] In this regard, the present invention designs a multi-level scheduling method based on overall optimization, including:

[0005] Step 1: Basic data preparation: including national survey preparation, regional survey preparation and provincial survey preparation;

[0006] Step 2: National, sub-district and provincial governments determine their own constraints, targets and boundary conditions respectively: national, sub-district and provincial governments aggregate constraints, targets and boundary conditions into a unified analysis platform, thus providing panoramic analysis conditions for national, sub-district and provincial dispatch plan information of large power grids;

[0007] Step 3: Based on the information summarized by the national and provincial dispatch plans, the overall optimization calculation of the national and provincial power generation plans is performed to obtain the interconnection line and unit plans that meet the objective function and various constraints;

[0008] Step 4, check the adjustment after overall optimization: check whether the objective function value calculated in step 3 is zero. If it is zero, it indicates that the national and provincial declared unit plan does not need to be adjusted and the national and provincial declared plan can be executed. If it is not zero, the national and provincial declared units are adjusted according to the constraints, and the adjusted national and provincial declared plans meet the execution requirements.

[0009] Step 5, result display and return: return the national and provincial declared plans to the national, sub-district and provincial dispatching agencies for dispatching and execution.

[0010] The present invention combines the business processing characteristics of national, branch and provincial dispatching plans, and proposes a dispatching method for national, branch and provincial dispatching agencies based on overall optimization. The national, branch and provincial dispatching agencies simultaneously carry out dispatching plan business work and compile their own dispatching plan information, so that the dispatching plan information and constraints of each branch and provincial dispatching agency are gathered to the national dispatching agency for overall analysis; by calling the overall optimization function that considers the national, branch and provincial dispatching plan information and constraints, it is possible to judge and analyze whether there are conflicts in constraints in the national and provincial plans, and give corresponding adjustment plans, thereby improving the ability of coordinated dispatching among the national, branch and provincial dispatching agencies, and enhancing the overall optimization effect of the three-level dispatching resources. BRIEF DESCRIPTION OF THE DRAWINGS

[0011] Figure 1 Flow chart of the method of the present invention DETAILED DESCRIPTION

[0012] In order to better understand the present invention, the system of the present invention is further explained below with reference to the description of the embodiments in combination with the accompanying drawings.

[0013] In order to fully understand the present invention, many specific details are mentioned in the following detailed description. However, it should be understood by those skilled in the art that the present invention can be implemented without these specific details. In the embodiments, well-known methods, processes, components are not described in detail to avoid making the embodiments unnecessarily cumbersome.

[0014] See also Figure 1 As shown, the present invention provides a multi-level scheduling method based on overall optimization, comprising:

[0015] Step 1: Basic data preparation: including national survey preparation, regional survey preparation and provincial survey preparation;

[0016] Step 2: National, sub-district and provincial governments determine their own constraints, targets and boundary conditions respectively: national, sub-district and provincial governments aggregate constraints, targets and boundary conditions into a unified analysis platform, thus providing panoramic analysis conditions for national, sub-district and provincial dispatch plan information of large power grids;

[0017] Step 3: Based on the information summarized by the national and provincial dispatch plans, the overall optimization calculation of the national and provincial power generation plans is performed to obtain the interconnection line and unit plans that meet the objective function and various constraints;

[0018] Step 4, check the adjustment after overall optimization: check whether the objective function value calculated in step 3 is zero. If it is zero, it indicates that the national and provincial declared unit plan does not need to be adjusted and the national and provincial declared plan can be executed. If it is not zero, the national and provincial declared units are adjusted according to the constraints, and the adjusted national and provincial declared plans meet the execution requirements.

[0019] Step 5, result display and return: return the national and provincial declared plans to the national, sub-district and provincial dispatching agencies for dispatching and execution.

[0020] Preferably, the basic data includes power grid model, equipment parameters, unit operation parameters, maintenance plan, power plan, various types of constraint information, etc.

[0021] Preferably, the step 1, basic data preparation, specifically includes:

[0022] Step 1-1, National Dispatching Preparation: The basic data involved include medium- and long-term DC cross-regional transaction power plan, DC channel power transmission capacity, DC channel power outage maintenance plan, direct dispatch unit operation constraints, and direct dispatch unit maintenance plan.

[0023] Step 1-2, preparation for dispatching: The basic data preparation involved includes operating constraints of direct dispatching units, maintenance plans of direct dispatching units, cross-provincial section limits, direct main grid power outage maintenance plans, and medium- and long-term electricity plans for inter-provincial interconnection lines.

[0024] Steps 1-3, provincial dispatch preparation: The basic data preparation involved includes basic unit parameters, unit maintenance plan, unit operation constraints, power progress balance range, large-user direct supply transactions, power balance constraints, power grid safety constraints, power grid outage maintenance plan, and clean energy power generation forecast.

[0025] Preferably, the step 3, based on the information summarized by the national and provincial dispatching plans, performs overall optimization calculation of the national and provincial power generation plans to obtain the tie line and unit plans that meet the objective function and various constraints, specifically including:

[0026] Step 3-1, set the objective function:

[0027] The goal is to minimize the adjustment of national and provincial declaration plans.

[0028] Minimize:

[0029] Among them, Minimize means minimum, N G is the number of generator sets, N T is the number of time periods, i is the unit number, t is the time period number, P i (t) is the active power output of unit i during period t, B i (P i (t),t) is the cost of the i-th generator in the t-th period,

[0030] B i (P i (t),t)=K i (t)|(P i (t)u i (t)-P i,0 (t)u i (t))| (2)

[0031] Among them, P i,0 (t) is the submitted output of unit i in period t, u i (t) is the start and stop status of unit i in period t, K i (t) is the output adjustment penalty function of unit i in time period t;

[0032] Step 3-2, set constraints;

[0033] Step 3-3, perform overall optimization calculation of national and provincial power generation plans based on the objective function and constraints, and obtain interconnection line and unit plans that meet the objective function and various constraints.

[0034] Preferably, the step 3-2, setting constraints, specifically includes:

[0035] Step 3-2-1, set national, regional and provincial power balance constraints:

[0036]

[0037] Among them, N G is the number of units, P load (t) is the system load forecast for period t;

[0038] Step 3-2-2, set up national, sub-district and provincial standby constraints:

[0039]

[0040]

[0041] in, and They are the positive and negative standby requirements of the country, the sub-district and the province respectively. is the lower limit of the output of unit i in time period t, is the upper limit of the output of unit i in period t;

[0042] Step 3-2-3, set national, sub-provincial and unit output constraints:

[0043]

[0044] Step 3-2-4, set the national, sub- and provincial unit climbing constraints:

[0045] P i (t)-P i (t-1)≤P i up (t),u i (t)=1&u i (t-1)=1 (7)

[0046] P i (t-1)-P i (t)≤P i down (t),u i (t)=1&u i (t-1)=1 (8)

[0047] Among them, P i up (t) and P i down (t) is the upper and lower limits of the ramp rate of unit i in time period t;

[0048] Step 3-2-5, set the minimum operating time and minimum downtime constraints for national, sub- and provincial units:

[0049]

[0050]

[0051] in, and are the minimum operating time and minimum downtime of national, sub- and provincial units i in time period t, respectively;

[0052] Step 3-2-6, set network security constraints:

[0053]

[0054] Among them, P line (t) is the power flow value of the transmission line in period t, and They are the minimum and maximum limits of branch or section power flow respectively.

[0055] The present invention combines the business processing characteristics of national, branch and provincial dispatching plans, and proposes a dispatching method for national, branch and provincial dispatching agencies based on overall optimization. The national, branch and provincial dispatching agencies simultaneously carry out dispatching plan business work and compile their own dispatching plan information, so that the dispatching plan information and constraints of each branch and provincial dispatching agency are gathered to the national dispatching agency for overall analysis; by calling the overall optimization function that considers the national, branch and provincial dispatching plan information and constraints, it is possible to judge and analyze whether there are conflicts in constraints in the national and provincial plans, and give corresponding adjustment plans, thereby improving the ability of coordinated dispatching among the national, branch and provincial dispatching agencies, and enhancing the overall optimization effect of the three-level dispatching resources.

[0056] Only preferred embodiments of the present invention are described herein, but are not intended to limit the scope, applicability and configuration of the present invention. On the contrary, the detailed description of the embodiments enables those skilled in the art to implement. It should be understood that some details may be appropriately changed and modified without departing from the spirit and scope of the present invention as defined in the appended claims.

Claims

1. A multi-level scheduling method based on overall optimization, characterized in that: include: Step 1: Basic data preparation: including national survey preparation, regional survey preparation and provincial survey preparation; Step 2: National, sub-district and provincial governments determine their own constraints, targets and boundary conditions respectively: national, sub-district and provincial governments aggregate constraints, targets and boundary conditions into a unified analysis platform, thus providing panoramic analysis conditions for national, sub-district and provincial dispatch plan information of large power grids; Step 3: Based on the information summarized by the national and provincial dispatch plans, the overall optimization calculation of the national and provincial power generation plans is performed to obtain the interconnection line and unit plans that meet the objective function and various constraints; Step 4, check the adjustment after overall optimization: check whether the objective function value calculated in step 3 is zero. If it is zero, it indicates that the national and provincial declared unit plan does not need to be adjusted and the national and provincial declared plan can be executed. If it is not zero, the national and provincial declared units are adjusted according to the constraints, and the adjusted national and provincial declared plans meet the execution requirements. Step 5, result display and return: return the national and provincial application plans to the national, provincial and sub-provincial dispatching agencies for dispatch execution; The step 3 is to perform overall optimization calculation of the national and provincial power generation plans based on the information summarized in the national and provincial dispatch plans, and obtain the tie line and unit plans that meet the objective function and various constraints, specifically including: Step 3-1, set the objective function: The goal is to minimize the adjustment of national and provincial declaration plans. Among them, Minimize means minimum, N G is the number of generator sets, N T is the time period number, i is the unit number, t is the time period number, P i (t) is the active power output of unit i during period t, B i (P i (t),t) is the cost of the i-th generator in the t-th period, The said B i (P i (t), t) = K i (t)|(P i (t)u i (t)-P i,0 (t)u i (t))| (2) Among them, P i,0 (t) is the submitted output of unit i in period t, u i (t) is the start and stop status of unit i in period t, K i (t) is the output adjustment penalty function of unit i in time period t; Step 3-2, set constraints; Step 3-3, perform overall optimization calculation of national and provincial power generation plans based on the objective function and constraints, and obtain interconnection line and unit plans that meet the objective function and various constraints.

2. The method according to claim 1, wherein: The basic data includes power grid model, equipment parameters, unit operating parameters, maintenance plan, power plan and various constraint information.

3. The method according to claim 1, wherein: The step 1, basic data preparation, specifically includes: Step 1-1, National Dispatching Preparation: The basic data involved include medium- and long-term DC cross-regional trading power plan, DC channel transmission capacity, DC channel power outage maintenance plan, direct dispatch unit operation constraints, and direct dispatch unit maintenance plan; Step 1-2, preparation for dispatching: The basic data involved include operation constraints of direct dispatching units, maintenance plans of direct dispatching units, cross-provincial section limits, power outage maintenance plans of direct main grids, and medium- and long-term power plans of inter-provincial interconnection lines; Steps 1-3, provincial dispatch preparation: The basic data preparation involved includes basic unit parameters, unit maintenance plan, unit operation constraints, power progress balance range, large-user direct supply transactions, power balance constraints, power grid safety constraints, power grid outage maintenance plan, and clean energy power generation forecast.

4. The method according to claim 1, wherein: The step 3-2, setting constraints, specifically includes: Step 3-2-1, set national, regional and provincial power balance constraints: Among them, N G is the number of units, P load (t) is the system load forecast for period t; Step 3-2-2, set up national, sub-district and provincial standby constraints: in, and are the positive and negative reserve requirements of the country, sub-district and province respectively, P i (t) is the lower limit of the output of unit i in time period t, is the upper limit of the output of unit i in period t; Step 3-2-3, set national, sub-provincial and unit output constraints: Step 3-2-4, set the national, sub- and provincial unit climbing constraints: in, and are the upper and lower limits of the ramp rate of unit i in time period t; Step 3-2-5, set the minimum operating time and minimum downtime constraints for national, sub- and provincial units: in, and are the minimum operating time and minimum downtime of national, sub- and provincial units i in time period t, respectively; Step 3-2-6, set network security constraints: Among them, P line (t) is the power flow value of the transmission line in period t, and They are the minimum and maximum limits of branch or section power flow respectively.