A new integrated tool installation structure

By integrating the hob and fastening structure into the tool, the problems of complex installation of traditional tool and safety risks of manual operation are solved, and efficient and safe tool installation for robot arm operation is achieved.

CN110130911BActive Publication Date: 2025-04-22CHINA RAILWAY ENGINEERING EQUIPMENT GROUP CO LTD
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
CN201910510988.9
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2019-06-13
Publication Date
2025-04-22
Estimated Expiration
2039-06-13

AI Technical Summary

Technical Problem

The installation method of traditional shield cutter wheel hobs has a large number of parts and is complex in installation, which is not suitable for robot operation, and there are safety risks for manual tool change.

Method used

Design a new integrated tool installation structure, which forms a tool system that is easy to install by integrating the hob and related fastening structures into the tool, and is suitable for robotic arm operation.

Benefits of technology

It realizes rapid and safe installation and disassembly of tools, reduces the risk of manual operation, improves tool change efficiency, and is suitable for efficient and safe machine replacement operation mode.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN110130911B_ABST
    Figure CN110130911B_ABST
Patent Text Reader

Abstract

The present invention proposes a novel integrated tool installation structure, including a tool box, wherein a tool integration system is arranged in the tool box, and the tool integration system includes a tool assembly, a mounting assembly and a clamping assembly, wherein the tool assembly is connected to a stud, and a mounting assembly is sleeved on the stud, and the mounting assembly cooperates with the tool assembly, and the mounting assembly cooperates with a mounting portion in the tool box, and a gap is formed between the relative mounting portions, and the stud passes through the gap and is threadedly connected to the clamping assembly, and the clamping assembly cooperates with the mounting portion. The advantages of the present invention are: changing the traditional hob installation structure, integrating the hob and the related fastening structure onto the tool, forming a tool system that is easy to install, suitable for the operation of a robot arm, and fundamentally eliminating the risk of manual tool change.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of mechanical processing and manufacturing, and in particular to a novel integrated tool installation structure. Background Art

[0002] In the field of underground engineering, the application of shield construction is becoming more and more extensive. At present, many large-scale infrastructure projects such as water diversion projects, highway and railway tunnels have been rapidly planned and constructed in various regions at home and abroad, and the demand for large-diameter slurry shields is increasing. The installation method of the traditional shield cutter disc hob generally includes the hob cutter body, cutter box, fasteners, bolts, nuts, etc., with a relatively large number of parts, and the disassembly and assembly actions are relatively complicated. At present, the tool detection and tool changing work in the construction process of the full-section tunnel boring machine mainly relies on manual operation. Manual tool changing operations under construction environments such as deep burial and high water pressure have great safety risks, and are prone to major safety accidents such as casualties. In addition, the tool changing efficiency is low. It is imperative to realize tool detection and tool changing operations in an efficient and safe "machine-for-man" operation mode. Therefore, in order to facilitate the robot tool changing operation, we need to develop a tool holder installation method that is easy to operate and suitable for robot arm operation. Summary of the invention

[0003] The present invention proposes a novel integrated tool installation structure, which solves the problems that traditional tools have many parts, are complicated to install, and are not convenient for robot operation.

[0004] The technical solution of the present invention is implemented as follows: a new integrated tool installation structure includes a tool box, a tool integration system is arranged in the tool box, the tool integration system includes a tool assembly, a mounting assembly and a clamping assembly, the tool assembly is connected to a stud, a mounting assembly is sleeved on the stud, the mounting assembly cooperates with the tool assembly, the mounting assembly cooperates with a mounting portion in the tool box, a gap is formed between the relative mounting portions, the stud passes through the gap and is threadedly connected to the clamping assembly, and the clamping assembly cooperates with the mounting portion.

[0005] The tool assembly comprises a hob in the middle and end blocks at both ends. The end blocks are connected with studs and matched with mounting assemblies.

[0006] The tool assembly and the stud are integrated.

[0007] The lower part of the end block is provided with a trapezoidal groove, and the upper part of the mounting assembly is provided with a trapezoidal protrusion.

[0008] The installation assembly includes a tensioning block I and a sleeve both mounted on the stud, the tensioning block I cooperates with the tool assembly, the tensioning block I cooperates with the installation portion, the tensioning block I is connected to one end of the sleeve, and the other end of the sleeve passing through the gap is provided with a clamping portion I.

[0009] The lower part of the tool assembly is provided with a trapezoidal groove, and the upper part of the tensioning block I is provided with a trapezoidal protrusion.

[0010] Both ends of the lower portion of the tension block 1 are provided with oblique end surfaces, and the upper portion of the mounting portion is provided with an oblique end surface.

[0011] The installation assembly also includes a tensioning block II, which is sleeved on the stud, cooperates with the installation part, cooperates with the clamping assembly, and a slot is provided in the tensioning block II. The clamping part I is sleeved in the slot, and the clamping part I cooperates with the slot.

[0012] The lower part of the tension block II is provided with a clamping part II, and the clamping part II cooperates with the clamping assembly.

[0013] Both ends of the upper portion of the tension block II are provided with oblique end surfaces, and the lower portion of the mounting portion is provided with an oblique end surface.

[0014] The clamping assembly comprises a nut.

[0015] The advantages of the present invention are as follows: the traditional hob installation structure is changed, the hob and related fastening structures are integrated into the tool, forming a tool system that is easy to install and suitable for operation by a robot arm, and fundamentally eliminating the risk of manual tool change. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0017] Figure 1 It is a schematic diagram of the structure of the present invention.

[0018] Figure 2 It is a schematic diagram of the integrated tool structure of the present invention.

[0019] Figure 3 It is a structural schematic diagram of the disassembly and assembly process of the present invention.

[0020] Figure 4 This is a schematic diagram of the disassembly and assembly structure of the present invention.

[0021] Figure 5 FIG. 1 is a diagram of disassembly and assembly step I of the present invention.

[0022] Figure 6 This is a diagram of disassembly and assembly step II of the present invention.

[0023] Figure 7 This is a diagram of disassembly and assembly step III of the present invention.

[0024] Figure 8 This is a diagram of disassembly and assembly step IV of the present invention.

[0025] In the figure: 1-hob, 2-end block, 3-stud, 4-tension block I, 5-sleeve, 6-tension block II, 7-slot, 8-nut, 9-tool box, 10-installation part, 11-A surface, 12-B surface. DETAILED DESCRIPTION

[0026] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0027] Example 1

[0028] like Figure 1 and 2 As shown, a novel integrated tool installation structure includes a tool box 9, a mounting portion 10 is provided in the tool box 9, a gap is formed between the mounting portions 10, and the upper and lower portions of the mounting portions 10 are provided with oblique end surfaces. A tool integration system is provided in the tool box 9, and the tool integration system includes a tool assembly, a mounting assembly, and a clamping assembly. Before installation, the three assemblies need to be combined and connected into an integrated tool integration system, and the entire tool integration system needs to be inserted into the tool box for installation.

[0029] The tool assembly includes a hob 1 in the middle and end blocks 2 at both ends. The hob 1 is rotatably arranged between the end blocks 2. The end blocks 2 are connected to studs 3. The hob 1, end blocks 2 and studs 3 form an integrated structure. A trapezoidal groove is provided at the bottom of the end block 2.

[0030] An installation component is sleeved on the stud 3, and the installation component includes a tensioning block I4 and a sleeve 5 both of which are sleeved on the stud 3. The upper part of the tensioning block I4 is provided with a trapezoidal protrusion that cooperates with the trapezoidal groove, and the two ends of the lower part of the tensioning block I4 are provided with inclined end surfaces that cooperate with the upper part of the installation part. The tensioning block I4 is connected to one end of the sleeve 5, and the other end of the sleeve 5 passing through the gap is provided with a clamping part I.

[0031] The installation assembly also includes a tensioning block II6, and the clamping assembly includes a nut 8. The stud 3 passes through the gap and is threadedly connected to the nut 8. The tensioning block II6 is sleeved on the stud 3. The two ends of the upper part of the tensioning block II6 are provided with inclined end surfaces that cooperate with the lower part of the installation part. The lower part of the tensioning block II6 is provided with a hexagonal clamping part II, and the clamping part II cooperates with the nut 8. A clamping groove 7 is provided in the tensioning block II6, and the clamping part I is sleeved in the clamping groove 7. The cross-sections of the clamping part I and the clamping groove 7 are both hexagonal shapes that are clamped and matched with each other.

[0032] like Figure 3 and 4 As shown, the installation structure of the present invention is back-mounted. During the tool installation process, the A surface of the tension block I and the B surface of the tool box are perpendicular. After the installation is completed, the A surface and the B surface are parallel.

[0033] like Figures 5 to 8 As shown, the specific installation steps of the present invention are as follows: Step I, the tool integration system is gradually installed from the back of the tool box according to the existing state, at this time, the A surface of the tension block I is perpendicular to the B surface of the tool box, and the tension block I passes through the gap and is installed within the predetermined range; Step II, at this time, the tension block II is rotated 90 degrees by using the clamping part II, and the tension block I is affected by the clamping part I and the clamping groove, and rotates together with the tension block II; Step III, rotate until the A surface of the tension block I is parallel to the B surface of the tool box; Step IV, tighten the screw by rotating the nut, so that the end block is wedged with the tension block I, the tension block I and the mounting part are wedged, and the tension block II and the mounting part are wedged, completing the entire assembly process. The tool removal process can be reversed.

[0034] Example 2

[0035] On the basis of Example 1, the tension block II is cancelled, and a nut larger than the gap is adopted. The tension block I is turned directly through the clamping part I, and the nut is pressed on the mounting part to realize the pulling installation of the tool.

[0036] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims

1. A novel integrated tool installation structure, comprising a tool box (9), characterized in that: The tool box (9) is provided with a tool integration system, the tool integration system comprising a tool assembly, a mounting assembly and a clamping assembly, the tool assembly being connected to the stud (3), the stud (3) being provided with a mounting assembly, the mounting assembly cooperating with the tool assembly, the mounting assembly cooperating with a mounting portion (10) in the tool box (9), a gap being formed between the opposing mounting portions (10), the stud (3) passing through the gap being threadedly connected with the clamping assembly, the clamping assembly cooperating with the mounting portion (10); The mounting assembly comprises a tensioning block I (4) and a sleeve (5) both of which are sleeved on the stud (3); the tensioning block I (4) cooperates with the tool assembly, the tensioning block I (4) cooperates with the mounting portion (10), the tensioning block I (4) is connected to one end of the sleeve (5), and the other end of the sleeve (5) passing through the gap is provided with a clamping portion I; The two ends of the lower portion of the tension block I (4) are provided with oblique end surfaces, and the upper portion of the mounting portion (10) is provided with an oblique end surface; The installation assembly further comprises a tensioning block II (6), the tensioning block II (6) being sleeved on the stud (3), the tensioning block II (6) cooperating with the installation portion (10), the tensioning block II (6) cooperating with the clamping assembly, a clamping slot (7) being provided in the tensioning block II (6), the clamping portion I being sleeved in the clamping slot (7), the clamping portion I being clamped and cooperating with the clamping slot (7), and the cross sections of the clamping portion I and the clamping slot (7) being hexagonal and mutually clamped and cooperating; The two ends of the upper part of the tension block II (6) are provided with oblique end surfaces, and the lower part of the mounting part is provided with an oblique end surface; the lower part of the tension block II (6) is provided with a clamping part II, and the clamping part II cooperates with the clamping assembly; The tool integration system is gradually installed from the back of the tool box (9), the tension block I (4) passes through the gap between the mounting parts (10) and is installed within a predetermined range, the tension block II is rotated 90 degrees using the clamping part II, and the tension block I is affected by the clamping part I and the clamping slot, and rotates together with the tension block II until the A surface of the tension block I is parallel to the B surface of the tool box; thus, a tool system that is easy to install is formed, which is suitable for operation of a robot arm and fundamentally eliminates the risk of manual tool change.

2. The new integrated tool installation structure according to claim 1 is characterized in that: The tool assembly comprises a hob (1) in the middle and end blocks (2) at both ends, the end blocks (2) are connected to the studs (3), and the end blocks (2) cooperate with the mounting assembly.

3. The new integrated tool installation structure according to claim 2 is characterized in that: The tool assembly and the stud (3) are integrated.

4. The new integrated tool installation structure according to claim 2 is characterized in that: The lower part of the end block (2) is provided with a trapezoidal groove, and the upper part of the mounting assembly is provided with a trapezoidal protrusion.

5. The new integrated tool installation structure according to claim 1 is characterized in that: The lower part of the tool assembly is provided with a trapezoidal groove, and the upper part of the tensioning block I (4) is provided with a trapezoidal protrusion.

Citation Information

Patent Citations

  • Tearing cutter assembly and replacement method of tearing cutter of tearing cutter assembly

    CN108590685A

  • Novel integrated cutter mounting structure

    CN210068161U

  • Method for replacing a tunnel boring machine roller cutter, handling device and roller cutter suited to such a method

    US20130045055A1