A deep sea drilling tool re-entry drilling device and process
Through the cableless underwater monitoring system and reenter cone and casing system, combined with the following pipe drilling technology, the long time and winding problems of the middle and lower casing process of deep water drilling are solved, and the stability and accuracy of the drilling are improved. Reduces operation risks and costs.
Patent Information
- Application Number
- CN201910654504.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2019-07-19
- Publication Date
- 2024-11-26
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
In deep water drilling, the traditional lower casing process is long, which can easily cause unstable drilling due to mud collapse or landfill. The cable control is easy to wrap, which increases the operating risk and cost.
The cableless underwater monitoring system is used to combine the reentry cone and casing system to conduct subsea observations through visual shock-proof TV underwater platform and deck operation table. The cableless design and reducer are used to achieve drilling reentry, reduce the risk of winding, and pass Pipe drilling technology and multi-stage casing hanger support deep operation.
Improve the stability and accuracy of drilling reentry, reduce working time and cost, avoid winding problems, and enhance the efficiency and safety of drilling.
Smart Images

Figure CN110273648B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of deep-water drilling, and in particular to a deep-sea drilling tool re-entry drilling device and process. Background Art
[0002] In deepwater drilling, if it is expected that multiple drill bits will be used in the borehole, or if reentry is required for other reasons (for logging, deep drilling, downhole experiments, and the establishment of long-term observation stations, etc.), a reentry cone is usually placed on the seabed to maintain the stability of the sedimentary formation borehole. By tripping the drill bit, replacing the new drill bit, and reentering the borehole, coring or drilling to the completed depth can be achieved. In the future, reentry and deepening can be achieved in the existing casing legacy borehole, or long-term observation instruments can be arranged.
[0003] The traditional casing process is: drill a hole on the seabed, then pull the drill bit, connect the casing, install a hanger on the top of the casing, connect the casing string to the drill string through the casing running tool, and then re-enter the borehole and lower it to the predetermined position. This process takes a long time to run casing, during which time mud is mainly used to prevent the borehole from collapsing or being buried. Once the borehole collapses or is buried, the casing string cannot be lowered into the drilled wellbore, which is particularly serious in fault zones or other unstable formations.
[0004] During conventional drilling and re-entry, the VIT is in direct rigid contact with the drill pipe, which causes mutual wear and shortens its service life. Generally, it is controlled by cables, and it is easy to get entangled with the drill pipe due to the influence of internal waves during the lowering process. In severe cases, it cannot be untied underwater and needs to be pulled out of the drill, which increases the operation risk, operation time and cost. Summary of the invention
[0005] In order to solve the above technical problems, the object of the present invention is to provide a deep-sea drilling tool re-entry drilling device which can improve drilling stability, reduce operation risks, save operation time and costs, and improve the efficiency and accuracy of drilling re-entry;
[0006] Furthermore, another object of the present invention is to provide a deep-sea drilling tool re-entry drilling process that can improve drilling stability, reduce operational risks, save operational time and costs, and improve the efficiency and accuracy of drilling re-entry.
[0007] A deep-sea drilling tool re-entry drilling device of the present invention comprises a cable-free underwater monitoring system module and a re-entry cone and casing system module. The cable-free underwater monitoring system module comprises a visual shockproof television underwater platform and a deck operating table, which are used for visual observation of the seabed during the existing drilling re-entry process. The visual shockproof television underwater platform comprises an underwater control system, an underwater battery, a beacon, an underwater camera, an underwater LED light, an altimeter, a depth gauge, a fiber optic gyroscope, an obstacle avoidance sonar, a side-scan sonar, a thruster and a reducer. The deck operating table comprises an optical cable communication machine, a network hard disk recorder, an industrial computer and a monitor. The re-entry cone and casing system module is used to support multi-stage casing strings to isolate unconsolidated sediments to achieve deep operations. The re-entry cone and casing system module comprises a re-entry cone and a casing lowering tool.
[0008] The invention discloses a deep-sea drilling tool re-entry drilling device, wherein the re-entry cone is in an inverted cone shape, and the cross section of the re-entry cone gradually decreases from top to bottom, and a mud plate is arranged at the bottom end of the re-entry cone, and the mud plate is square.
[0009] The present invention discloses a deep-sea drilling tool re-entry drilling device, wherein the casing lowering tool comprises a transition pipe, a four-stage casing hanging ring, a first casing hanger, a second casing hanger, a third casing hanger, a fourth casing hanger, a first casing, a second casing, a third casing and a fourth casing, wherein the transition pipe is installed at the bottom of a mud plate, the four-stage casing hanging ring is installed on the inner wall of the transition pipe, the first casing hanger, the second casing hanger, the third casing hanger and the fourth casing hanger are installed on four groups of casing hanging rings in sequence, the first casing, the second casing, the third casing and the fourth casing are connected to the first casing hanger, the second casing hanger, the third casing hanger and the fourth casing hanger respectively, and the first casing is located inside the second casing, the second casing is located inside the third casing, and the third casing is located inside the fourth casing.
[0010] A deep-sea drilling tool re-entry drilling process of the present invention comprises a casing drilling process and a re-entry process, wherein the casing drilling process comprises the following steps:
[0011] (1) After the re-entry cone and various levels of casing are assembled on board, the drill string is lowered and the casing string is connected to the downhole drill string assembly, with the drill bit and reamer protruding a certain distance from the bottom of the casing;
[0012] (2) Start drilling with the pump, and lower the casing while drilling the hole;
[0013] (3) Use a downhole drilling tool assembly with a casing reamer, use the pilot drill bit to drill and reamer to reamer the hole, and when the hole is reamed to the casing sealing position, remove the casing and leave it in this position;
[0014] (4) After the largest-size casing is set, continue drilling until the mud plate contacts the seabed;
[0015] (5) Stop drilling, unseal the casing running tool and casing hanger, retract the casing reamer, and pull it out of the wellhead together with the drill string. Reassemble the downhole drill assembly as needed to prepare for continued drilling.
[0016] The reentry process comprises the following steps:
[0017] (a) After the drilling tool is assembled, it is lowered to the seabed by continuously connecting the drill pipes and stopped when it approaches the seabed;
[0018] (b) Using the drill string as a guide, install the cable-free underwater monitoring system and activate the braking system to keep the cable-free underwater monitoring system stationary;
[0019] (c) Turn on the decelerator again and gradually turn off the brake system. The cable-free underwater monitoring system gradually slides down by gravity. When it is about to enter the water, turn on the propeller and adjust the decelerator to automatic gear. At the same time, set the descent speed limit. Once the speed exceeds the limit, the decelerator will automatically turn on to ensure a smooth descent.
[0020] (d) stopping the movement when the cable-free underwater monitoring system slides down to the drill head;
[0021] (e) Since a positioning beacon is arranged in advance near the re-entry cone, the beacon will send out a signal during operation, and the cable-free underwater monitoring system uses the carried sonar to locate and search for objects outside the camera range, thereby determining the approximate position of the re-entry cone;
[0022] (f) After the approximate position of the re-entry cone is determined, the seabed is scanned by a black and white underwater camera under low light conditions to find the re-entry cone, and the drilling vessel locates the vessel and drill pipe through the DP system;
[0023] (g) Use a color underwater camera with pan, tilt and zoom functions to guide the drill bit to re-enter the borehole;
[0024] (h) Finally, the reducer is turned on to allow the cable-free underwater monitoring system to return to the ship.
[0025] Compared with the prior art, the present invention has the following beneficial effects:
[0026] 1. The present invention uses the pipe-following drilling technology in deep-sea drilling, lowers the reentry cone and casing into the formation while drilling, and uses a cable-free underwater monitoring system to achieve drilling reentry;
[0027] 2. The casing lowering method of the present invention greatly reduces the destructive consequences caused by the time delay between drilling the wellbore and lowering the casing, and also greatly saves the operation time and indirectly saves the operation cost;
[0028] 3. The guide sleeve of the cable-free underwater monitoring system of the present invention is equipped with 4 damping rubber wheels to prevent excessive scratching of the drill rod. The cable-free design solves the problem of entanglement in conventional cable control. The added reducer serves as a deceleration function when the system is lowered and as a propulsion function when it is returned, ensuring the smooth movement of the system. The comprehensive use of sonar, beacons, low-light cameras, and high-definition color cameras greatly improves the efficiency and accuracy of drilling re-entry. BRIEF DESCRIPTION OF THE DRAWINGS
[0029] Figure 1 It is a schematic diagram of the drilling re-entry of the present invention;
[0030] Figure 2 This is a schematic diagram of casing drilling with pipe;
[0031] Figure 3 It is a schematic diagram of the reentry cone, mud plate and wellhead device and process;
[0032] Markings in the accompanying drawings: 1. re-entry cone; 2. mud plate; 3. transition pipe; 4. fourth-stage casing hanging ring; 5. first casing hanger; 6. second casing hanger; 7. third casing hanger; 8. fourth casing hanger; 9. first casing; 10. second casing; 11. third casing; 12. fourth casing; 900. drill pipe column; 901. visual shockproof television underwater platform; 903. guide tube; 904. casing under-hole expander; 905. pilot drill bit. DETAILED DESCRIPTION
[0033] The specific implementation of the present invention is further described in detail below in conjunction with the accompanying drawings and examples. The following examples are used to illustrate the present invention, but are not intended to limit the scope of the present invention.
[0034] like Figures 1 to 3 As shown, a deep-sea drilling tool re-entry drilling device and process of the present invention includes a cable-free underwater monitoring system module and a re-entry cone and casing system module. The cable-free underwater monitoring system module includes a visual shockproof television underwater platform and a deck operating table, which are used to visualize the seabed during the existing drilling re-entry process. The visual shockproof television underwater platform 901 includes an underwater control system, underwater batteries, beacons, underwater cameras, underwater LED lights, altimeters, depth gauges, fiber optic gyroscopes, obstacle avoidance sonars, side-scan sonars, thrusters and reducers. The deck operating table includes an optical cable communication machine, a network hard disk recorder, an industrial computer and a monitor. The re-entry cone and casing system module is used to support multi-stage casing strings to isolate unconsolidated sediments to achieve deep operations. The re-entry cone and casing system module includes a re-entry cone 1 and a casing lowering tool.
[0035] The present invention discloses a deep-sea drilling tool re-entry drilling device and process, wherein the re-entry cone 1 is in an inverted cone shape, and the cross section of the re-entry cone 1 gradually decreases from top to bottom, and the minimum cross section needs to be larger than the size of the matching drill bit to ensure that various drill bits can pass smoothly. A mud plate 2 is arranged at the bottom end of the re-entry cone 1, and the mud plate 2 is square to prevent the re-entry cone from sinking too deep and being buried, while improving the bearing capacity of the wellhead and keeping the wellhead stable.
[0036] The present invention discloses a deep-sea drilling tool re-entry drilling device and process, wherein the casing lowering tool comprises a transition pipe 3, a fourth-stage casing hanging ring 4, a first casing hanger 5, a second casing hanger 6, a third casing hanger 7, a fourth casing hanger 8, a first casing 9, a second casing 10, a third casing 11 and a fourth casing 12, wherein the transition pipe 3 is installed at the bottom of the mud plate 2, the fourth-stage casing hanging ring 4 is installed on the inner wall of the transition pipe 3, the first casing hanger 5, the second casing hanger 6, the third casing hanger 7 and the fourth casing hanger 8 are installed in sequence on the fourth-stage casing hanging ring 4. On the casing hanging ring, the first casing 9, the second casing 10, the third casing 11 and the fourth casing 12 are connected to the first casing 9 hanger 5, the second casing 10 hanger 6, the third casing 11 hanger 7 and the fourth casing 12 hanger 8 respectively, and the first casing 9 is located inside the second casing 10, the second casing 10 is located inside the third casing 11, and the third casing 11 is located inside the fourth casing 12; lowering the first-level casing string into place and achieving smooth disengagement requires a casing lowering tool that is specially matched with the casing hanger at the top of the casing string. The casing lowering tool must meet two major functions: one is to fix the casing hanger and the casing string until the casing is lowered into place; the other is to smoothly disengage the casing from the casing hanger through a mechanism or action after the casing is lowered into place. The casing lowering tool is matched with casing hangers of different sizes. After the casing is disengaged from the hanger, you can choose to continue drilling downward to prepare for the next level of casing.
[0037] A deep-sea drilling tool re-entry drilling process of the present invention includes a casing drilling process and a re-entry process, wherein the casing drilling process includes the following steps:
[0038] (1) After the re-entry cone and various levels of casing are assembled on board, the drill string is lowered and the casing string is connected to the downhole drill string, wherein the drill bit and the reamer are a distance away from the bottom of the guide tube 903;
[0039] (2) Start drilling with the pump, and lower the casing while drilling the hole;
[0040] (3) Using a downhole drilling tool assembly with a casing reamer 904, drilling with a pilot drill bit 905 and reaming with the reamer, when the hole is reamed to the casing sealing position, the casing is disengaged and left at the position. This method usually uses the friction between the formation and the casing to fix the casing, so cementing is not required;
[0041] (4) After the largest-size casing is set, continue drilling until the mud plate contacts the seabed;
[0042] (5) Stop drilling, unseal the casing running tool and casing hanger, retract the casing reamer, and pull it out of the wellhead together with the drill string. Reassemble the downhole drill assembly as needed to prepare for continued drilling.
[0043] The reentry process comprises the following steps:
[0044] (a) After the drilling tool is assembled, it is lowered to the seabed by continuously connecting the drill string 900 and stops when it approaches the seabed;
[0045] (b) Using the drill string as a guide, install the cable-free underwater monitoring system and activate the braking system to keep the cable-free underwater monitoring system stationary;
[0046] (c) Turn on the decelerator again and gradually turn off the brake system. The cable-free underwater monitoring system gradually slides down by gravity. When it is about to enter the water, turn on the propeller and adjust the decelerator to automatic gear. At the same time, set the descent speed limit. Once the speed exceeds the limit, the decelerator will automatically turn on to ensure a smooth descent.
[0047] (d) stopping the movement when the cable-free underwater monitoring system slides down to the drill head;
[0048] (e) Since a positioning beacon is arranged in advance near the re-entry cone, the beacon will send out a signal during operation, and the cable-free underwater monitoring system uses the carried sonar to locate and search for objects outside the camera range, thereby determining the approximate position of the re-entry cone;
[0049] (f) After the approximate position of the re-entry cone is determined, the seabed is scanned by a black and white underwater camera under low light conditions to find the re-entry cone, and the drilling vessel locates the vessel and drill pipe through the DP system;
[0050] (g) Use a color underwater camera with pan, tilt and zoom functions to guide the drill bit to re-enter the borehole;
[0051] (h) Finally, the reducer is turned on to allow the cable-free underwater monitoring system to return to the ship.
[0052] The above is only a preferred embodiment of the present invention. It should be pointed out that for ordinary technicians in this technical field, several improvements and modifications can be made without departing from the technical principles of the present invention. These improvements and modifications should also be regarded as the scope of protection of the present invention.
Claims
1. A deep sea drilling tool re-entry drilling process, characterized in that: The process uses a deep-sea drilling tool re-entry drilling device, which includes a cable-free underwater monitoring system module and a re-entry cone and casing system module. The cable-free underwater monitoring system module includes a visual anti-vibration television underwater platform and a deck operating table, which are used to visualize the seabed during the existing drilling re-entry process. The visual anti-vibration television underwater platform includes an underwater control system, an underwater battery, a beacon, an underwater camera, an underwater LED light, an altimeter, a depth gauge, an optical fiber gyroscope, an obstacle avoidance sonar, a side-scan sonar, a thruster and a reducer. The deck operating table includes an optical cable communication machine, a network hard disk recorder, an industrial computer and a monitor. The re-entry cone and casing system module is used to support a multi-stage casing column to isolate unconsolidated sediments to achieve deep operations. The re-entry cone and casing system module includes a re-entry cone (1) and a casing lowering tool; The process includes a casing drilling process and a re-entry process, wherein the casing drilling process includes the following steps: (1) After the re-entry cone and various levels of casing are assembled on board, the drill string is lowered and the casing string is connected to the downhole drill string assembly, with the drill bit and reamer protruding a certain distance from the bottom of the casing; (2) Start drilling with the pump, and lower the casing while drilling the hole; (3) Use a downhole drilling tool assembly with a casing reamer, use the pilot drill bit to drill and reamer to reamer the hole, and when the hole is reamed to the casing sealing position, remove the casing and leave it in this position; (4) After the largest-size casing is set, continue drilling until the mud plate contacts the seabed; (5) Stop drilling, unseal the casing running tool and casing hanger, retract the casing reamer, and pull it out of the wellhead together with the drill string. Reassemble the downhole drill assembly as needed to prepare for continued drilling. The reentry process comprises the following steps: (a) After the drilling tool is assembled, it is lowered to the seabed by continuously connecting the drill pipes and stopped when it approaches the seabed; (b) Using the drill string as a guide, install the cable-free underwater monitoring system and activate the braking system to keep the cable-free underwater monitoring system stationary; (c) Turn on the decelerator again and gradually turn off the braking system. The cable-free underwater monitoring system gradually slides down by gravity. When it is about to enter the water, turn on the propeller and adjust the decelerator to automatic gear. At the same time, set a descent speed limit. Once the speed limit is exceeded, the decelerator will automatically turn on to ensure a smooth descent. (d) stopping the movement when the cable-free underwater monitoring system slides down to the drill head; (e) Since a positioning beacon is arranged in advance near the re-entry cone, the beacon will send out a signal during operation, and the cable-free underwater monitoring system uses the carried sonar to locate and search for objects outside the camera range, thereby determining the approximate position of the re-entry cone; (f) After the approximate position of the re-entry cone is determined, the seabed is scanned by a black and white underwater camera under low light conditions to find the re-entry cone, and the drilling vessel locates the vessel and drill pipe through the DP system; (g) Use a color underwater camera with pan, tilt and zoom functions to guide the drill bit to re-enter the borehole; (h) Finally, the reducer is turned on to allow the cable-free underwater monitoring system to return to the ship.
2. A deep sea drilling tool re-entry drilling process as claimed in claim 1, characterized in that: The re-entrant cone (1) is in an inverted cone shape, and the cross section of the re-entrant cone (1) gradually decreases from top to bottom. A mud plate (2) is provided at the bottom end of the re-entrant cone (1), and the mud plate (2) is square.
3. A deep sea drilling tool re-entry drilling process as claimed in claim 2, characterized in that: The casing running tool comprises a transition pipe (3), a fourth-stage casing hanging ring (4), a first casing hanger (5), a second casing hanger (6), a third casing hanger (7), a fourth casing hanger (8), a first casing (9), a second casing (10), a third casing (11) and a fourth casing (12); the transition pipe (3) is mounted at the bottom of a mud plate (2); the fourth-stage casing hanging ring (4) is mounted on the inner wall of the transition pipe (3); the first casing hanger (5), the second casing hanger (6), the third casing hanger (7) and the fourth casing hanger (8) are mounted on the inner wall of the transition pipe (3); The pipe hanger (8) is sequentially installed on four sets of casing hanging rings; the first casing (9), the second casing (10), the third casing (11) and the fourth casing (12) are respectively connected to the first casing (9) hanger (5), the second casing (10) hanger (6), the third casing (11) hanger (7) and the fourth casing (12) hanger (8); and the first casing (9) is located inside the second casing (10), the second casing (10) is located inside the third casing (11), and the third casing (11) is located inside the fourth casing (12).
Citation Information
Cited By
Drilling operation monitor with real-time feedback function
CN224017204U