A comparative analysis method of line loss in the same period based on theoretical line loss calculation
Through the simultaneous line loss comparison analysis method based on theoretical line loss calculation, the complex problem of simultaneous line loss abnormality analysis is solved, and the effect of quickly positioning the cause of abnormality and improving the correctness of calculation results is achieved, which improves the efficiency of simultaneous line loss calculation.
Patent Information
- Application Number
- CN201910527034.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2019-06-18
- Publication Date
- 2024-11-01
- Estimated Expiration
- 2039-06-18
AI Technical Summary
The existing technology is difficult to quickly locate the causes of abnormal line loss in the same period, which leads to the calculation results of linear loss in the same period being large, unreasonable or negative, and the abnormality analysis is complex, affecting work efficiency.
The comparison and analysis method of concurrent line loss based on theoretical line loss calculation is adopted. By derive and process the system data of the same period, analyzing the required model and operation data of theoretical calculations, the gate is automatically generated and compared and analyzed, and the gate name keyword is matched by regular expressions. Automatic correspondence, supplemented by manual adjustment, display data tables and charts to quickly verify abnormalities.
Effectively assist the line loss personnel in the same period to quickly locate the causes of abnormalities, improve the accuracy and compliance rate of calculation results, simplify the abnormality analysis process, and improve work efficiency.
Smart Images

Figure CN110442625B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to a method for analyzing abnormality of synchronous line losses, and in particular to a method for comparing and analyzing synchronous line losses based on theoretical line loss calculation. Background Art
[0002] The current calculation items for synchronous line loss include partition, voltage division, mother level, transmission line, distribution line and substation. The calculation process is to first extract the grid architecture and equipment model, then manually set the gateway model configuration relationship of the synchronous line loss calculation project, then obtain the operation data, and finally calculate the synchronous line loss according to the gateway model. There are many abnormal factors for synchronous line loss, mainly as follows: 1) Incomplete model ledger: The basic ledger of the synchronous line loss model is missing, resulting in incomplete equipment; 2) Gateway model configuration error: The gateway configuration of the synchronous line loss is missing records, the gateway direction is wrong, etc.; 3) Calculation relationship error: The addition and subtraction relationship of the gateway forward and reverse power data is configured incorrectly; 4) Operation data error: The gateway power data leads to operation data errors due to transmission, interference, meter replacement, multiplier error, etc.; 5) There is no corresponding cross-reference relationship: The corresponding cross-reference relationship with the metering point of the source system is missing, resulting in the inability to collect data.
[0003] There are many calculation items for the line loss calculation in the same period. Each calculation item needs to be configured with a relatively complex transfer-in and transfer-out gateway model. It is also necessary to make a good correspondence between each metering point and the source system, and the operating data of the metering point must be guaranteed to be correct. If the data of a metering point is abnormal, or the transfer-in and transfer-out gateway model configuration of the line loss calculation in the same period is wrong, then it will cause the line loss of the line loss calculation item corresponding to the gateway configuration model to be abnormal, and it will also be related to the line loss abnormalities of other line loss calculation items in the same period, which will eventually lead to abnormal line losses such as excessive, unreasonable, and negative losses in the calculation results of the line loss in the same period.
[0004] Due to the strong correlation between the various calculation items of synchronous line loss, the metering points in the gateway configuration model of a calculation item are often also related to the gateway model configuration of other synchronous line loss calculation items. For example, the correctness of the gateway model configuration of a transmission line also affects the synchronous line loss rate of the mother level where the transmission line is located; the metering point on the side of a main transformer is not only the metering point of the gateway model configuration of the mother level, but also the metering point of the gateway model configuration of the voltage divider or zone. Therefore, in the current synchronous line loss calculation with strong correlation, the diagnosis and analysis of the causes of abnormal synchronous line loss and troubleshooting are relatively complicated.
[0005] Currently, there is no relevant technology that can directly locate the cause of abnormal synchronous line loss diagnosis and analysis. It is still necessary to manually conduct investigation and analysis on gateway model configuration, data collection, calculation relationship, etc.
[0006] For example, if the mother-to-mother balance of line loss is abnormal, it is necessary to first check the configuration of the mother-to-mother balance gateway model to see if there are any missing metering points, whether the direction of the amount of electricity transferred in and out of the metering points is correct, whether there are cross-references between the metering points, whether the collected data is correct, whether the line loss rate of the transmission line associated with the mother-to-mother balance metering point is normal, etc. All related factors should be checked one by one. There are too many troubleshooting links and strong correlations, which has indeed caused great obstacles to the analysis of the causes of abnormal line loss in the same period. Summary of the invention
[0007] In order to overcome the deficiencies in the above-mentioned background technology and improve the work efficiency of the abnormal analysis of the synchronous line loss, the present invention provides a synchronous line loss comparative analysis technology based on theoretical line loss calculation, which can ensure the correctness of the theoretical line loss calculation results while taking the theoretical line loss results and the model configuration relationship of the theoretical line loss and the gateway metering point data as benchmarks to perform difference comparison analysis with the synchronous line loss, so as to quickly verify the abnormalities of the synchronous line loss.
[0008] A method for comparing and analyzing line losses during the same period based on theoretical line loss calculation, characterized in that it comprises the following steps:
[0009] S1. Data export and processing of the synchronous system: export line loss related data from the synchronous system. After the data export is completed, import the data into the system through the system upload function. The data of the synchronous system is parsed and stored in the database through the developed Excel data file parsing plug-in.
[0010] S2. Analysis and processing of model data required for theoretical calculation: Download CIM files through FTP and parse the files to obtain model data required for theoretical calculation, parse topology information to build calculation models and generate equipment metering points, and save calculation models and metering points;
[0011] S3. Analysis and processing of operation data required for theoretical calculation: Use the ETL component in the system to download the DT file through FTP and parse the DT file to obtain the operation data of the equipment;
[0012] S4, automatically generate a checkpoint, generate a process based on the calculation relationship, classify and analyze various electric quantities according to the corresponding voltage levels, generate a calculation relationship for voltage division, and perform theoretical calculations;
[0013] S5. The theoretical line loss threshold corresponds to the system threshold of the same period, and a comparative analysis is performed;
[0014] S6. Result display: Display data tables and charts on web pages through a report engine developed based on Javascript and HTML5 front-end technology;
[0015] The S1 comprises the following steps:
[0016] S101. Export the main network equipment data from the synchronous system, including the transmission line, busbar, voltage divider, switch and other equipment information and the distribution network equipment information including distribution line, distribution transformer, substation, and substation users. The exported data format is Excel file, including the equipment number, name, substation to which it belongs, and voltage level;
[0017] S102. Export the equipment metering point information in the form of an Excel file, including metering point number, source system, metering point name, PT, CT, magnification, and equipment type;
[0018] S103, deriving the calculation results of transmission line loss, voltage division loss, distribution line loss, and substation loss.
[0019] The S2 comprises the following steps:
[0020] S201, download the CIM model file, and parse the file through the parsing program in the ETL component to obtain the equipment information of the substation, busbar, main transformer, generator, load, transmission line, distribution line, distribution transformer, substation user, and switch;
[0021] S202: parse the CIM file to obtain information to build a calculation model, generate equipment metering points, and save the calculation model and metering points.
[0022] The DT file is parsed in S3 to obtain the active power, reactive power, switch status, main transformer gear information of the main network equipment metering point and the daily active and reactive power information of the distribution network equipment.
[0023] The automatically generated gateways in S4 are: the standard eight gateway types of the State Grid, which have built-in cross-border transmission gateways, inter-regional transmission gateways, inter-provincial transmission gateways, provincial power supply gateways, municipal power supply gateways, wholesale gateways, power generation gateways and billing user gateways, are further subdivided into fourteen electricity categories, and main transformer gateways and other gateways are expanded.
[0024] : In S4, a process is generated based on the calculation relationship,
[0025] S401, analyzing the gateway attributes of the loads in the power grid equipment and incorporating them into the gateways of the corresponding voltage levels according to the voltage levels;
[0026] S402, analyzing the gateway attributes of the PQ node generator in the power grid equipment, and incorporating them into the gateway of the corresponding voltage level according to the voltage level;
[0027] S403, analyzing the voltage level of the main transformer winding, and incorporating the voltage level into the gate of the corresponding voltage level of the main transformer according to the voltage level;
[0028] S404. Analyze the distribution lines and include the metering point of the first section of the distribution lines into the 10kV public line head end gate. Analyze the public and private transformer attributes of the distribution transformer and include the distribution transformer into the 10kV public transformer area and 10kV private transformer area gates respectively.
[0029] S405, determining the direction of each checkpoint in accordance with the principle that the incoming bus is negative and the outgoing bus is positive;
[0030] S406. According to the corresponding voltage levels, various electrical quantities are classified and analyzed to generate a calculation relationship for voltage division.
[0031] In S406, the corresponding voltage level is the voltage level enabled by the unit.
[0032] The correspondence between the theoretical line loss gate in S5 and the gate of the same period system consists of two parts. The gate correspondence plug-in uses regular expression comparison technology to automatically match through name keywords. For the gates that cannot be matched or the automatic matching is incorrect, they are manually matched or adjusted.
[0033] The beneficial effects of the present invention are as follows: through the invention, research and application of a synchronous line loss comparative analysis technology based on theoretical line loss calculation, it is possible to assist synchronous line loss personnel in verifying synchronous line loss power collection data, quickly locate abnormal causes of synchronous line losses, assist line loss personnel in performing synchronous line loss related configurations and on-site cause investigation, effectively improve the correctness of synchronous line loss calculation results, and improve the compliance rate of synchronous line losses. BRIEF DESCRIPTION OF THE DRAWINGS
[0034] Figure 1 To compare and analyze the overall process;
[0035] Figure 2 It is the data processing process of the same system;
[0036] Figure 3 It is the data processing process of theoretical calculation model;
[0037] Figure 4 Run data processing for theoretical calculations;
[0038] Figure 5 Generate a flow chart for the voltage division calculation relationship;
[0039] Figure 6 This is a schematic diagram of the relationship level of 330kV voltage division calculation;
[0040] Figure 7 Rendering diagram for report engine data; DETAILED DESCRIPTION
[0041] In order to better understand the essential content of the present invention, the following description is given:
[0042] 1: Import and process system data at the same time
[0043] Export the main network equipment data from the synchronous system, including transmission lines, busbars, voltage dividers, switches and other equipment information, and distribution network equipment information including distribution lines, distribution transformers, substations, and substation users. The exported data format is an Excel file, including equipment number, name, substation, voltage level, and the data grid is shown in the table below.
[0044]
[0045]
[0046] Then export the equipment metering point information. The exported data format is an Excel file, including metering point number, source system, metering point name, PT, CT, ratio, equipment type, and the data format is as follows: Figure 6 Export the daily electricity quantity detailed data of the metering point in the format of Excel file, including metering point number, date, forward electricity quantity and reverse electricity quantity. The data grid is shown in the table below.
[0047]
[0048] Finally, the calculation results of transmission line loss, voltage division loss, distribution line loss, and substation loss are derived.
[0049] After the data is exported, the data is imported into the system through the system upload function. The data of the same system is parsed and stored in the database through the developed Excel data file parsing plug-in.
[0050] 2. Analysis and processing of model data required for theoretical calculation
[0051] The model data required for theoretical calculations are obtained by downloading CIM files through FTP and parsing the files, such as Figure 3 As shown, first download the CIM model file, and obtain the substation, bus, main transformer, generator, load, transmission line, distribution line, distribution transformer, substation user, switch and other equipment information by parsing the CIM model file in the ETL component, and then parse the topology information to build a calculation model and generate equipment metering points to save the calculation model and metering points.
[0052] 3. Analysis and processing of operating data required for theoretical calculation
[0053] Use the ETL component in the system to download the DT file via FTP and parse the DT file to obtain the active and reactive power, switch status, main transformer gear information of the main network equipment and the daily active and reactive power information of the distribution network equipment.
[0054] 4. Gateway Management
[0055] The system has built-in 8 types of standard gateways for State Grid, including cross-border transmission gateway, cross-regional transmission gateway, cross-provincial transmission gateway, provincial power supply gateway, municipal power supply gateway, wholesale gateway, power generation gateway and billing user gateway. Figure 5 The calculation relationship generation process is further refined into 14 power categories based on these 8 major checkpoints, and the main transformer checkpoint and other checkpoints are expanded. As shown in the following table,
[0056]
[0057] 4: Calculation relationship generation
[0058] in accordance with Figure 5 The calculation relationship generation process analyzes the gateway attributes of the load in the power grid equipment and incorporates them into the gateways of the corresponding voltage levels according to 1000kV, 750kV, 330kV, 220kV, 110kV, 66kV, 35kV, and 10kV.
[0059] By analyzing the gateway properties of the PQ node generators in the power grid equipment, they are included in the gateways of the corresponding voltage levels according to the voltage levels of 1000kV, 750kV, 330kV, 220kV, 110kV, 66kV, 35kV, 10kV, and 400V.
[0060] By analyzing the voltage levels of the main transformer windings, the corresponding voltage levels of the main transformer are included according to 1000kV, 750kV, 330kV, 220kV, 110kV, 66kV, 35kV, and 10kV.
[0061] Analyze the distribution lines and include the metering point at the head end of the distribution lines into the 10kV public line head end gate. Analyze the public and private transformer attributes of the distribution transformer and include the distribution transformer into the 10kV public transformer area and 10kV private transformer area gates respectively.
[0062] Then, according to the principle of reverse direction for input busbar and positive direction for output busbar, the input direction of each gate is determined respectively. For example, the load is reversed as input and forward as output. The generator needs to be specially processed with forward direction as input and reverse direction as output, so as to generate and save the calculation relationship of power classification. The main transformer winding is classified into the forward and reverse power classification of the corresponding voltage level according to the forward and reverse directions.
[0063] Then, according to the corresponding voltage level (according to the voltage level enabled by the unit), various electrical quantities are classified and analyzed to generate the calculation relationship of the voltage division.
[0064] Taking the 330kV voltage division of the central dispatch as an example, the logic of generating the voltage division calculation relationship is explained. The voltage levels enabled by the central dispatch are 750kV, 330kV, 220kV, 110kV, 66kV, 35kV, and 10kV. The calculation relationship generation plug-in first collects the electricity classification of this voltage level, 330kV inter-regional transmission gateway, 330kV inter-provincial transmission gateway, 330kV wholesale gateway, 330kV billing user gateway, and 330kV power generation gateway. Then collect the main transformer gateway, 750kV main transformer medium voltage 330kV side, 330kV main transformer medium voltage 110kV side, 330kV main transformer medium voltage 220kV side, 330kV main transformer low voltage 35kV side, and 330kV main transformer low voltage 10kV side. Because the standard of the State Grid is to calculate the voltage division including transformer loss, the 330kV main transformer should be calculated from the medium and low voltage sides. If you need to calculate the voltage division without transformer loss, you can manually adjust the calculation relationship of the voltage division, delete the medium and low voltage sides of the 330kV main transformer here, and add the high voltage side of the 330kV main transformer. Finally, the 330kV voltage division calculation relationship is generated according to the type of on-grid and off-grid as shown in the following table:
[0065]
[0066]
[0067] The generated 330kV transfer-in and transfer-out calculation relationship is as follows: Figure 6 shown.
[0068] Five: Theoretical calculation
[0069] The transmission network calculation plug-in is used to calculate the voltage distribution and transmission line loss calculation results of the transmission network at a 15-minute granularity.
[0070] The calculation results of 96 time points are summarized through the summary function to calculate the voltage division and transmission line loss calculation results for one day.
[0071] The distribution network calculation plug-in and the substation calculation plug-in are used to calculate the calculation results of the distribution line and substation for one day respectively.
[0072] 6. Model and checkpoint correspondence
[0073] The theoretical line loss model comes from the SCADA system. The model corresponding plug-in can correspond to the unified code of PO interconnection and the model of synchronous line loss. For devices that do not have a unique code for PO interconnection, the regular expression comparison technology is used to perform fuzzy matching on the device name keywords for automatic matching. For devices that cannot be matched or are incorrectly matched automatically, they are manually matched or adjusted.
[0074] The correspondence between the theoretical line loss gate and the system gate of the same period consists of two parts. The gate correspondence plug-in uses regular expression comparison technology to automatically match the name keywords such as the number in the name and the same keyword in the name. For the gates that cannot be matched or the automatic matching is incorrect, they are manually matched or adjusted.
[0075] Comparative Analysis
[0076] Take the voltage comparison analysis as an example to illustrate. The voltage comparison of the theoretical line loss calculation and the voltage comparison of the line loss calculation in the same period are shown in the following table:
[0077]
[0078] Compare the partial pressure calculated by theoretical line loss with the partial pressure calculated by the line loss of the same period. Detailed data comparison:
[0079]
[0080] VII. Results display
[0081] The results are displayed on the web page through a report engine developed based on Javascript and HTML5 front-end technology to display data tables and charts. Figure 7 As shown in the figure, the server-side report engine component first queries the active report data, and then encapsulates the report data into a result set in JSON format. The result set is sent to the browser through AJAX asynchronous transmission. The browser-side report engine component parses the JSON data set and further processes it to display the report data in the data table of the report component built by Javascript. The chart rendering component built by Javascript renders the data into various chart forms such as bar charts, line charts, and pie charts, which are embedded in the page and displayed to the user.
[0082] It will be apparent to those skilled in the art that the invention is not limited to the details of the exemplary embodiments described above and that the invention can be implemented in other specific forms without departing from the spirit or essential features of the invention. Therefore, the embodiments should be considered exemplary and non-limiting in all respects, and the scope of the invention is defined by the appended claims rather than the foregoing description, and it is intended that all variations falling within the meaning and scope of the equivalent elements of the claims be included in the invention. Any reference numeral in a claim should not be considered as limiting the claim to which it relates.
[0083] In addition, it should be understood that although the present specification is described according to implementation modes, not every implementation mode contains only one independent technical solution. This description of the specification is only for the sake of clarity. Those skilled in the art should regard the specification as a whole. The technical solutions in each embodiment may also be appropriately combined to form other implementation modes that can be understood by those skilled in the art.
Claims
1. A comparative analysis method of line loss in the same period based on theoretical line loss calculation, Features: The following steps are involved: S1. Data export and processing of the synchronous system: export line loss related data from the synchronous system. After the data export is completed, import the data into the system through the system upload function. The data of the synchronous system is parsed and stored in the database through the developed Excel data file parsing plug-in. S2. Analysis and processing of model data required for theoretical calculation: Download CIM files through FTP and parse the files to obtain model data required for theoretical calculation, parse topology information to build calculation models and generate equipment metering points, and save calculation models and metering points; S3. Analysis and processing of operation data required for theoretical calculation: Use the ETL component in the system to download the DT file through FTP and parse the DT file to obtain the operation data of the equipment; S4, automatically generate a checkpoint, generate a process based on the calculation relationship, classify and analyze various electric quantities according to the corresponding voltage levels, generate a calculation relationship for voltage division, and perform theoretical calculations; S5. The theoretical line loss threshold corresponds to the system threshold of the same period, and a comparative analysis is performed; S6. Result display: Display data tables and charts on web pages through a report engine developed based on Javascript and HTML5 front-end technology; The automatic generation of the gateways in S4 is as follows: the eight standard gateway types of the State Grid, which have built-in cross-border transmission gateways, inter-regional transmission gateways, inter-provincial transmission gateways, provincial power supply gateways, municipal power supply gateways, wholesale gateways, power generation gateways and billing user gateways, are further subdivided into fourteen power categories, and the main transformer gateway and other gateways are expanded; the process is generated according to the calculation relationship in S4; S401, analyzing the gateway attributes of the loads in the power grid equipment and incorporating them into the gateways of the corresponding voltage levels according to the voltage levels; S402, analyzing the gateway attributes of the PQ node generator in the power grid equipment, and incorporating them into the gateway of the corresponding voltage level according to the voltage level; S403, analyzing the voltage level of the main transformer winding, and incorporating the voltage level into the gate of the corresponding voltage level of the main transformer according to the voltage level; S404. Analyze the distribution lines and include the metering point of the first section of the distribution lines into the 10kV public line head end gate. Analyze the public and private transformer attributes of the distribution transformer and include the distribution transformer into the 10kV public transformer area and 10kV private transformer area gates respectively. S405, determining the direction of each checkpoint in accordance with the principle that the incoming bus is negative and the outgoing bus is positive; S406, classifying and analyzing various electric quantities according to corresponding voltage levels to generate a calculation relationship for voltage division; In S406, the corresponding voltage level is the voltage level enabled by the unit.
2. According to the method for comparing and analyzing line losses in the same period based on theoretical line loss calculation according to claim 1, Features: The S1 comprises the following steps: S101. Export the main network equipment data from the synchronous system, including the transmission line, busbar, voltage divider, switch and other equipment information and the distribution network equipment information including distribution line, distribution transformer, substation, and substation users. The exported data format is Excel file, including the equipment number, name, substation to which it belongs, and voltage level; S102. Export the equipment metering point information in the form of an Excel file, including metering point number, source system, metering point name, PT, CT, magnification, and equipment type; S103, deriving calculation results of transmission line loss, voltage division loss, distribution line loss, and substation loss.
3. According to the method for comparing and analyzing line losses in the same period based on theoretical line loss calculation according to claim 1, Features: The S2 comprises the following steps: S201, download the CIM model file, and parse the file through the parsing program in the ETL component to obtain the equipment information of the substation, busbar, main transformer, generator, load, transmission line, distribution line, distribution transformer, substation user, and switch; S202: parse the CIM file to obtain information to build a calculation model, generate equipment metering points, and save the calculation model and metering points.
4. According to claim 1, a method for comparing and analyzing line losses in the same period based on theoretical line loss calculation, Features: The DT file is parsed in S3 to obtain the active power, reactive power, switch status, main transformer gear information of the main network equipment metering point and the daily active and reactive power information of the distribution network equipment.
5. According to the method for comparing and analyzing line losses in the same period based on theoretical line loss calculation according to claim 1, Features: The correspondence between the theoretical line loss gate in S5 and the gate of the same period system consists of two parts. The gate correspondence plug-in uses regular expression comparison technology to automatically match through name keywords. For the gates that cannot be matched or the automatic matching is incorrect, they are manually matched or adjusted.