A pedestal suitable for post-tensioned prefabricated box beam and a method for preparing the box beam
By designing a detachable pedestal structure, using inclined surfaces and isolation plates to decompose the force of gravity, the collision between the anchor end and the pedestal is avoided, the problem of shear damage of the anchor end in post-tensioned precast box beams is solved, and the box girder is ensured stability and normality of prestressing.
Patent Information
- Application Number
- CN201911084118.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2019-11-07
- Publication Date
- 2024-10-01
- Estimated Expiration
- 2039-11-07
AI Technical Summary
During the construction process of post-tensioned precast box beams, the pedestal caused the anchor end to collide with the beam body, causing shear damage and affecting the stability of the beam body.
A pedestal structure including a main pedestal and an end pedestal is designed, which can be detachably fixed through the connector of the inner pedestal and the outer pedestal. Inclined surfaces and isolation plates are used to decompose the gravity effect, avoid the conversion of thrust force into vertical pressure, and ensure the sealing of the anchor end. When tensioning the prestressed steel tendons, they are in a suspended state to avoid collision with the pedestal.
It effectively avoids shear damage at the anchor end, ensures the stability of the box girder and the normal application of the prestressed steel tendons, and extends the service life of the box girder.
Smart Images

Figure CN110843124B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of bridge construction, and in particular to a pedestal suitable for post-tensioned prefabricated box girders and a method for preparing the box girders. Background Art
[0002] Box girders of reinforced concrete structures are divided into prefabricated box girders and cast-in-place box girders. Box girders prefabricated in an independent site can be erected with a bridge erection machine after the lower part of the project is completed, which can speed up the project progress and save construction time; cast-in-place box girders are mostly used for large continuous bridges.
[0003] Prefabricated construction of bridges can reduce construction period and save production costs, so prefabricated box girders are increasingly widely used in engineering construction. Prefabricated box girders are generally used in bridges. Prefabricated box girders are prefabricated bending members that are pre-tensioned by prestressing steel bars through pre-tensioning or post-tensioning methods, and then transported to the construction site for installation. In the process of preparing box girders, the pedestal is an important component of the prefabricated box girder. Because the anchor end of the beam body is relatively weak, due to the pedestal, the box girder body often has an arch phenomenon during the later tensioning of the prestressed steel strands. When the box girder body has an arch phenomenon, the anchor ends at both ends of the box girder body will be squeezed downward, and the downward squeezed anchor ends will collide with the pedestal, which can easily cause shear damage to the anchor ends (stress concentration ends), thereby affecting the stability of the entire beam body. Summary of the invention
[0004] In view of the above problems, the present invention is proposed to provide a pedestal suitable for post-tensioned prefabricated box girders and a method for preparing box girders that overcome the above problems or at least partially solve the above problems.
[0005] In a first aspect, the present application provides a pedestal suitable for post-tensioned prefabricated box girders.
[0006] The pedestal comprises: a main pedestal and end pedestals arranged at both ends of the main pedestal, wherein the main pedestal and the end pedestals are both placed on a concrete base;
[0007] The end pedestal includes an inner end pedestal and an outer end pedestal, and the inner end pedestal and the outer end pedestal are detachably fixedly connected by a connecting piece; the outer end pedestal is provided with a downwardly inclined lower surface on the surface opposite to the inner end pedestal, and the inner end pedestal is provided with an upper inclined surface matching the lower inclined surface on the surface opposite to the outer end pedestal, and an isolation plate is provided between the lower inclined surface and the upper inclined surface to prevent the two from contacting, and the friction coefficient between the lower inclined surface and the isolation plate, or the friction coefficient between the upper inclined surface and the isolation plate is smaller than the friction coefficient between the lower inclined surface and the upper inclined surface.
[0008] When prefabricating a box girder, first place the bottom formwork of the box girder on the pedestal, and tie the reinforcement of the beam body so that the junction of the box girder's anchor end and the beam body is aligned with the upper joint of the outer and inner pedestals. Then install the side formwork and the inner formwork, and then pour the concrete. After the concrete solidifies, remove the formwork for curing. Before tensioning the prestressed steel strands, remove the connector between the inner and outer pedestals. At this time, the gravity at the anchor end acts on the outer pedestal. The gravity G at the anchor end can be decomposed into a downward thrust F along the inclined plane between the outer and inner pedestals and a downward pressure N in the vertical direction. Due to the presence of the isolation plate between the inclined planes, the thrust F is much larger. The frictional resistance caused by the vertical pressure, that is, the frictional resistance caused by the vertical pressure can be ignored. Under the action of the thrust F along the inclined plane, the outer end pedestal and the inner end pedestal will slide relative to each other along the inclined plane, and the outer end pedestal and the concrete base will also slide relative to each other. At this time, the top of the outer end pedestal and the bottom of the box girder anchor end are in a separated state, and the box girder anchor end is in a suspended state; then the prestressed steel strands are tensioned. Since the tensioning of the prestressed steel strands will cause the box girder body to arch upward, the box girder anchor end is in a suspended state and will not collide or squeeze with the pedestal and will not be subjected to shear force. The relatively weak anchor end of the entire beam will not be sheared.
[0009] Preferably, the isolation plate is a tetrafluoroethylene plate.
[0010] As an improvement of the present invention, a pad is provided between the outer end pedestal and the concrete base, and the friction coefficient between the pad and the outer end pedestal, or the friction coefficient between the pad and the concrete base is smaller than the friction coefficient between the outer end pedestal and the concrete base.
[0011] Preferably, the backing plate is a tetrafluoroethylene plate.
[0012] As an improvement of the present invention, the inner end seat and the outer end seat both include a connecting portion with a through hole, and the connecting member is a bolt and nut connecting the connecting portions of the inner end seat and the outer end seat that are in relative positions.
[0013] As an improvement of the present invention, the main pedestal is placed on the main concrete base, the inner end pedestal is placed on the inner concrete base, the outer end pedestal is placed on the outer concrete base, and the main concrete base includes a plurality of sub-main concrete bases, which are evenly spaced and distributed.
[0014] In a second aspect, the present application provides a method for preparing a box girder.
[0015] The preparation method comprises the following steps:
[0016] Install the pedestal described above, and fix the inner end pedestal and the outer end pedestal of the pedestal through a connecting piece;
[0017] Install the box beam template on the pedestal so that the junction between the anchor end of the box beam and the beam body is aligned with the upper joint of the outer end pedestal and the inner end pedestal;
[0018] Pour concrete into the box girder formwork;
[0019] After the concrete solidifies, the formwork is removed and curing is carried out;
[0020] After removing the connectors that fixedly connect the inner end pedestal and the outer end pedestal, the prestressed steel strands of the box girder body are tensioned;
[0021] Grouting and anchor sealing are completed to complete the box girder preparation.
[0022] Preferably, the prestressed steel strands of the box girder body are tensioned after the strength and elastic modulus of the concrete both reach 85% of the design values and the age of the concrete is not less than 7 days.
[0023] Preferably, the box beam template is installed on the pedestal so that the junction between the anchor end of the box beam and the beam body is aligned with the upper joint of the outer end pedestal and the inner end pedestal, including:
[0024] Install the bottom formwork of the box beam on the pedestal;
[0025] The beam reinforcement is tied so that the junction between the anchor end of the box beam and the beam body is aligned with the upper joint of the outer end pedestal and the inner end pedestal;
[0026] Install the side formwork and inner formwork of the box girder on the pedestal.
[0027] The present invention has the following beneficial effects:
[0028] In the present invention, the inner end pedestal and the outer end pedestal are detachably fixedly connected via a connecting piece, and before tensioning the prestressed steel bundles of the box girder body, the connecting piece that fixedly connects the inner end pedestal and the outer end pedestal is removed. Since tensioning the prestressed steel bundles will cause the box girder body to arch upward, the box girder anchor end is in a suspended state and does not collide or squeeze with the pedestal and is not subjected to shear force, thereby ensuring that the relatively weak anchor end of the entire beam body will not be shear damaged. BRIEF DESCRIPTION OF THE DRAWINGS
[0029] The included drawings are used to provide a further understanding of the embodiments of the present application, which constitute a part of the specification, are used to illustrate the implementation methods of the present application, and together with the text description, explain the principles of the present application. Obviously, the drawings described below are only some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work. In the drawings:
[0030] Figure 1 It is a schematic diagram of a pedestal applicable to a post-tensioned prefabricated box girder of the present invention;
[0031] Figure 2 for Figure 1 Partial enlargement.
[0032] In the figure: 10, main pedestal; 20, inner end pedestal; 21, upper inclined surface; 30, outer end pedestal; 31, lower inclined surface; 40, isolation plate; 50, connecting piece; 60, pad; 71, beam body; 72, anchor end; 81, main concrete base; 82, inner concrete base; 83, outer concrete base. DETAILED DESCRIPTION
[0033] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0034] It should be noted that if there are directional indications (such as up, down, left, right, front, back, etc.) in the embodiments of the present invention, the directional indications are only used to explain the relative position relationship, movement, etc. between the components under a certain specific posture (as shown in the accompanying drawings). If the specific posture changes, the directional indication will also change accordingly. In addition, the technical solutions between the various embodiments can be combined with each other, but they must be based on the ability of ordinary technicians in this field to implement them. When the combination of technical solutions is contradictory or cannot be implemented, it should be considered that such a combination of technical solutions does not exist and is not within the protection scope required by the present invention.
[0035] Example
[0036] See also Figure 1 and Figure 2 A pedestal suitable for post-tensioned prefabricated box beams includes: a main pedestal 10 and end pedestals arranged at both ends of the main pedestal 10, and the main pedestal 10 and the end pedestals are both placed on a concrete base.
[0037] The end stand comprises an inner end stand 20 and an outer end stand 30 , and the inner end stand 20 and the outer end stand 30 are detachably fixedly connected via a connecting piece 50 .
[0038] Moreover, the outer end pedestal 30 is provided with a downwardly inclined lower surface 31 on the surface opposite to the inner end pedestal 20, and the inner end pedestal 20 is provided with an upper inclined surface 21 matching the lower inclined surface 31 on the surface opposite to the outer end pedestal 30, and an isolation plate 40 is provided between the lower inclined surface 31 and the upper inclined surface 21 to prevent the two from contacting each other, and the friction coefficient between the lower inclined surface 31 and the isolation plate 40, or the friction coefficient between the upper inclined surface 31 and the isolation plate 40 is smaller than the friction coefficient between the lower inclined surface 31 and the upper inclined surface 21.
[0039] When prefabricating a box girder, first place the bottom formwork of the box girder on the pedestal, tie the beam body reinforcement so that the junction of the anchor end 72 and the beam body 71 is aligned with the upper joint of the outer end pedestal 30 and the inner end pedestal 20, then install the side formwork and the inner formwork, and then pour the concrete. After the concrete solidifies, remove the formwork for curing, and remove the connecting parts between the inner end pedestal and the outer end pedestal before tensioning the prestressed steel strands. At this time, the gravity of the anchor end acts on the outer end pedestal, and the gravity G of the anchor end can be decomposed into a downward thrust F along the inclined surface and a downward pressure N in the vertical direction along the matching inclined surface between the outer end pedestal and the inner end pedestal. Due to the existence of the isolation plate between the matching inclined surfaces, the thrust F The frictional resistance is much greater than the frictional resistance caused by the vertical pressure, that is, the frictional resistance caused by the vertical pressure can be ignored. Under the action of the thrust F along the inclined plane, the outer end pedestal and the inner end pedestal will slide relative to each other along the inclined plane, and the outer end pedestal and the concrete base will also slide relative to each other. At this time, the top of the outer end pedestal and the bottom of the box girder anchor end are in a separated state, and the box girder anchor end is in a suspended state; then the prestressed steel strands are tensioned. Since the tensioning of the prestressed steel strands will cause the box girder body to arch upward, the box girder anchor end is in a suspended state and will not collide or squeeze with the pedestal and will not be subjected to shear force. The relatively weak anchor end of the entire beam will not be sheared.
[0040] In this embodiment, the isolation plate 40 is a tetrafluoroethylene plate. The tetrafluoroethylene plate separates the lower inclined surface from the upper inclined surface on the one hand, and on the other hand, the tetrafluoroethylene plate is hard and will not be deformed by the inner and outer pedestals. The friction coefficient between the tetrafluoroethylene plate and the isolation plate is small, which can effectively reduce friction and make the outer and inner pedestals slide relatively smoothly along the inclined surface.
[0041] In this embodiment, a pad 60 is provided between the outer end pedestal 30 and the concrete base, and the friction coefficient between the pad 60 and the outer end pedestal 30, or the friction coefficient between the pad 60 and the concrete base is smaller than the friction coefficient between the outer end pedestal 30 and the concrete base. The friction coefficient between the pad and the outer end pedestal is smaller, which can effectively reduce the friction between the outer end pedestal and the concrete base, thereby making the relative sliding between the outer end pedestal and the concrete base smoother. Among them, the pad 60 is a tetrafluoroethylene plate, which is hard and will not be deformed by the squeezing of the outer end pedestal and the concrete base, and the friction coefficient between the tetrafluoroethylene plate and the outer end pedestal is smaller, which can effectively reduce friction and further reduce the friction between the outer end pedestal and the concrete base.
[0042] In this embodiment, the inner pedestal 20 and the outer pedestal 30 both include a connecting portion with a through hole, and the connecting member 50 is a bolt and nut connecting the connecting portions of the inner pedestal and the outer pedestal at relative positions. Specifically, the connecting portion is a first nut welded to the edge of the steel plate of the inner pedestal 20 and the outer pedestal 30, the screw hole of the first nut is the through hole, and the two first nuts at relative positions in the inner pedestal 20 and the outer pedestal 30 are fixedly connected by the bolt and nut, i.e., the connecting member 50. In an alternative embodiment, the connecting portion is an embedded steel plate of the inner pedestal 20 and the outer pedestal 30, the protruding portion of the steel plate is provided with a through hole, and the embedded steel plates at relative positions in the inner pedestal 20 and the outer pedestal 30 are fixedly connected by the bolt and nut, i.e., the connecting member 50.
[0043] In addition, the main pedestal 10 is placed on the main concrete base 81, the inner end pedestal 20 is placed on the inner concrete base 82, and the outer end pedestal 30 is placed on the outer concrete base 83, and the main concrete base 81 includes a plurality of sub-main concrete bases, which are evenly spaced and distributed. The main pedestal, the inner end pedestal and the outer end pedestal are respectively placed on independent concrete bases, which is conducive to convenient operation, easy loading and unloading of connectors or bolts and nuts, and can reduce production costs.
[0044] A method for preparing a box beam based on the pedestal described above.
[0045] The preparation method comprises the following steps:
[0046] S1. Install the pedestal described above, and fix the inner end pedestal and the outer end pedestal of the pedestal through a connecting member;
[0047] S2. Install the box beam template on the pedestal so that the junction between the anchor end of the box beam and the beam body is aligned with the upper joint of the outer end pedestal and the inner end pedestal;
[0048] S3. pouring concrete into the box beam formwork;
[0049] S4. After the concrete solidifies, remove the formwork and carry out curing;
[0050] S5. After removing the connectors that fixedly connect the inner end pedestal and the outer end pedestal, tension the prestressed steel strands of the box girder body;
[0051] S6. Grouting and anchor sealing to complete the box girder preparation.
[0052] In the preparation method of the present invention, the connecting piece between the inner end pedestal and the outer end pedestal is disassembled before the prestressed steel strand is tensioned. At this time, the gravity at the anchor end acts on the outer end pedestal, and the gravity G at the anchor end can be decomposed into a downward thrust F along the inclined surface and a downward pressure N in the vertical direction along the matching inclined surface between the outer end pedestal and the inner end pedestal. Due to the existence of the isolation plate between the matching inclined surfaces, the thrust F is much greater than the frictional resistance generated by the vertical pressure, that is, the frictional resistance generated by the vertical pressure can be ignored, and the thrust along the inclined surface is negligible. Under the action of F, the outer end pedestal and the inner end pedestal will slide relative to each other along the inclined surface, and the outer end pedestal and the concrete base will also slide relative to each other. At this time, the top of the outer end pedestal and the bottom of the box girder anchor end are in a separated state, and the box girder anchor end is in a suspended state; then the prestressed steel strands are tensioned. Since the tensioning of the prestressed steel strands will cause the box girder body to arch upward, the box girder anchor end is in a suspended state and will not collide or be squeezed with the pedestal and will not be subjected to shear force. Therefore, the relatively weak anchor end of the entire beam body will not be sheared.
[0053] In this embodiment, after the strength and elastic modulus of the concrete reach 85% of the design value and the concrete age is not less than 7 days, the prestressed steel strands of the box girder body are tensioned. Since tensioning the prestressed steel strands will cause the box girder body to arch upward, tensioning is performed after the strength and elastic modulus of the concrete of the box girder body reach the safety threshold, so as to ensure that the box girder body will not be damaged.
[0054] In this embodiment, the box beam template is installed on the pedestal so that the junction between the anchor end of the box beam and the beam body is aligned with the upper joint of the outer end pedestal and the inner end pedestal, including:
[0055] Install the bottom formwork of the box beam on the pedestal;
[0056] The beam reinforcement is tied so that the junction between the anchor end of the box beam and the beam body is aligned with the upper joint of the outer end pedestal and the inner end pedestal;
[0057] Install the side formwork and inner formwork of the box girder on the pedestal.
[0058] The above-mentioned embodiments only express some implementation methods of the present invention, and the description thereof is relatively specific and detailed, but it cannot be understood as limiting the scope of the patent of the present invention. It should be pointed out that, for ordinary technicians in this field, several modifications and improvements can be made without departing from the concept of the present invention, which all belong to the protection scope of the present invention. Therefore, the protection scope of the patent of the present invention shall be based on the attached claims.
Claims
1. A pedestal suitable for post-tensioned prefabricated box beams, characterized in that: include: A main pedestal and end pedestals arranged at both ends of the main pedestal, wherein the main pedestal and the end pedestals are both placed on a concrete base; The end pedestal includes an inner end pedestal and an outer end pedestal, and the inner end pedestal and the outer end pedestal are detachably fixedly connected by a connecting piece; the outer end pedestal is provided with a downwardly inclined lower surface on the surface opposite to the inner end pedestal, and the inner end pedestal is provided with an upper inclined surface matching the lower inclined surface on the surface opposite to the outer end pedestal, and an isolation plate is provided between the lower inclined surface and the upper inclined surface to prevent the two from contacting, and the friction coefficient between the lower inclined surface and the isolation plate, or the friction coefficient between the upper inclined surface and the isolation plate is smaller than the friction coefficient between the lower inclined surface and the upper inclined surface.
2. The pedestal for post-tensioned prefabricated box beam according to claim 1, characterized in that: The isolation plate is a tetrafluoroethylene plate.
3. The pedestal for post-tensioned prefabricated box beam according to claim 1, characterized in that: A pad is provided between the outer end pedestal and the concrete base, and the friction coefficient between the pad and the outer end pedestal, or between the pad and the concrete base is smaller than the friction coefficient between the outer end pedestal and the concrete base.
4. The pedestal for post-tensioned prefabricated box beam according to claim 3, characterized in that: The backing plate is a tetrafluoroethylene plate.
5. The pedestal for post-tensioned prefabricated box beam according to claim 1, characterized in that: The inner end pedestal and the outer end pedestal both include a connecting portion with a through hole, and the connecting member is a bolt and nut connecting the connecting portions of the inner end pedestal and the outer end pedestal that are in relative positions.
6. The pedestal for post-tensioned prefabricated box beam according to claim 1, characterized in that: The main pedestal is placed on the main concrete base, the inner end pedestal is placed on the inner concrete base, the outer end pedestal is placed on the outer concrete base, and the main concrete base includes a plurality of sub-main concrete bases, which are evenly spaced and distributed.
7. A method for preparing a box beam, characterized in that: The following steps are involved: Installing a pedestal as claimed in any one of claims 1 to 6, and fixing the inner end pedestal and the outer end pedestal of the pedestal together by a connecting piece; Install the box beam template on the pedestal so that the junction between the anchor end of the box beam and the beam body is aligned with the upper joint of the outer end pedestal and the inner end pedestal; Pour concrete into the box girder formwork; After the concrete solidifies, the formwork is removed and curing is carried out; After removing the connectors that fixedly connect the inner end pedestal and the outer end pedestal, the prestressed steel strands of the box girder body are tensioned; Grouting and anchor sealing are completed to complete the box girder preparation.
8. The box beam preparation method according to claim 7, characterized in that: After the strength and elastic modulus of the concrete reach 85% of the design values and the age of the concrete is not less than 7 days, the prestressed steel strands of the box girder body are tensioned.
9. The box beam manufacturing method according to claim 7, characterized in that: The box beam template is installed on the pedestal so that the junction between the anchor end of the box beam and the beam body is aligned with the upper joint of the outer end pedestal and the inner end pedestal, including: Install the bottom formwork of the box beam on the pedestal; The beam reinforcement is tied so that the junction between the anchor end of the box beam and the beam body is aligned with the upper joint of the outer end pedestal and the inner end pedestal; Install the side formwork and inner formwork of the box girder on the pedestal.