A rapid construction structure and method for secondary lining of a dark-excavated tunnel with multiple variable cross-sections
Through the formwork movable bracket and partition wall structure, combined with the special steel formwork, the high cost and long construction period problems caused by the variable section of the tunnel construction are solved, the rapid and economical construction of the tunnel's secondary lining is realized, and the construction safety and efficiency are improved. .
Patent Information
- Application Number
- CN202010221101.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2020-03-26
- Publication Date
- 2024-10-25
- Estimated Expiration
- 2040-03-26
AI Technical Summary
In tunnel construction, especially subway tunnels, due to the variable cross-section dimensions, traditional construction methods are costly, long-term, and difficult to construct, making it difficult to quickly and economically complete the secondary lining construction of variable-section underground tunnels.
The template mobile bracket and partition wall structure are used, including arch frames, temporary invert brackets, longitudinal and transverse partition walls, and the brackets are moved as a whole through electric or hand chain hoists, combined with pre-bent sections of I18 I-beam and I14 I-beam steel. Formwork enables rapid erection and dismantling, adapting to the construction of secondary linings of tunnels with different cross-section sizes.
It reduces construction costs, improves work efficiency, enhances construction safety and support stability, reduces the risk of temporary support removal, and enables rapid secondary lining construction of tunnels with variable cross-sections.
Smart Images

Figure CN111271092B_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of tunnel engineering, and in particular relates to a method and structure for rapid construction of secondary linings of multiple variable-section dark-excavated tunnels in a double-side wall pilot tunnel method. Background Art
[0002] Due to the functional setting requirements in tunnel construction, the cross-sectional dimensions of tunnels vary, especially in subway tunnels, which are often hundreds of meters long and have several to dozens of cross-sectional dimensions. The YDK11+197.880-YDK11+401.200 section of the Hongqing Station-Zixiasan Road Station section of Xi'an Metro Line 9 TGSG-5 section is constructed using the shallow buried tunneling method. This section of tunneling tunnel adopts a horseshoe-shaped section with a total length of 203m. The cross-sectional forms include five sections, A, B, C, D, and E, and AB transition sections (a total of 6 types). The tunneling section A is constructed using the CRD method, and the tunneling sections B, C, D, and E are all constructed using the double sidewall pilot tunnel method. The transition section process is the transition from the CRD method to the double sidewall pilot tunnel method. There are two traditional construction methods for the secondary lining construction of such short-length tunnels with many cross-section types. The most commonly used method is to use multiple lining trolleys corresponding to the cross-sections, and the other method is to use the loose formwork assembly method of the full-frame support for casting. In the first method, multiple trolleys will greatly increase the construction cost, and when the tunnel entrance is a small cross-section and the tunnel is a large cross-section, the assembly and disassembly of the trolleys must be carried out inside the tunnel, which increases the construction difficulty and construction period; while the second method has the problem that the workload of setting up and dismantling the full-frame support is large, and the assembly of small loose formwork has high construction requirements and is difficult.
[0003] Therefore, there is an urgent need for a rapid construction method and structure for the secondary lining of a variety of variable-section dark-excavated tunnels that can cope with short tunnel lengths, a variety of cross-section types, tight construction schedules, and low cost investment. Summary of the invention
[0004] The purpose of the present invention is to provide a method and structure for rapid construction of a second lining of a double-side wall pilot tunnel with multiple variable cross-sections, which can cope with a short tunnel length, a variety of cross-section types, a tight construction period, and a low cost investment. The content of the present invention is as follows:
[0005] A rapid construction structure for the secondary lining of a multiple variable-section dark-excavated tunnel, comprising a template movable bracket and a partition wall, wherein the number of the template movable brackets is at least two, and the template movable brackets are used to support and fix the secondary lining template; the template movable bracket comprises an arch frame and a temporary invert bracket; the arch frame comprises an arch bracket, a column, a crossbeam and an arch wall arch frame, wherein one end of the arch bracket is fixedly connected to the secondary lining template, and the other end is fixedly connected to the column; the other end of the column is fixedly connected to the top end of the crossbeam; the bottom end of the crossbeam is fixedly connected to the top end of the temporary invert bracket; one end of the arch wall arch frame is fixedly connected to the secondary lining template, and the other end is fixedly connected to the temporary invert bracket; the arch bracket is fixedly connected to the arch wall bracket; each A connecting beam is arranged between the cross beams of the template movable bracket; the partition wall comprises a longitudinal partition wall and a transverse partition wall. When the template movable bracket is assembled, the longitudinal partition wall corresponding to the height of the arch frame is removed; a track is arranged on the removed longitudinal partition wall, and the track comprises a support frame and a sliding wheel. The support frame is fixedly connected to the removed longitudinal partition wall, and the sliding wheel is fixedly connected to the support frame; the sliding wheel is slidably matched with the connecting beam, and is used for pulling the arch frame as a whole to the next section of the second lining by an electric hoist or a hand hoist according to the weight of the arch frame after the second lining is poured; the columns and cross beams are arranged with different specifications and sizes, and are used for selection and use according to the requirements of the variable-section tunnel second lining template and the size of the arch frame.
[0006] Furthermore, the temporary inverted arch support includes a temporary inverted arch lower support and a temporary inverted arch upper support, the temporary inverted arch lower support and the temporary inverted arch upper support include vertical poles, longitudinal horizontal poles, longitudinal sweeping poles and transverse sweeping poles, the bottom of the vertical poles are provided with fixed seats for fixing the vertical poles to the inverted arch; the longitudinal sweeping poles are fixed to the vertical poles at a position not more than 200 mm from the bottom of the fixed seat by right-angle fasteners; the transverse sweeping poles are fixed to the vertical poles close to the bottom of the longitudinal sweeping poles by right-angle fasteners; the top of the vertical poles are provided with top supports for fixedly connecting the crossbeams to the vertical poles; the arch wall arch frame is fixedly connected to the horizontal poles.
[0007] Furthermore, the support at the temporary inverted arch adopts a coupler-type scaffolding, and the vertical poles are arranged at a spacing of 900×750mm and a step distance of 900mm, which is used to support the arch frame; vertical scissors braces are continuously arranged from bottom to top on the outside and inside of the support at the temporary inverted arch, in the longitudinal and transverse directions, every 5 spans and not less than 3m, and the bottom ends of the scissors brace rods should be pressed against the ground; the angle between the diagonal rods of the scissors braces and the ground is between 45° and 60°, and the diagonal rods are buckled with the vertical poles at each span; horizontal scissors braces should be arranged on the intersection plane of the top of the vertical scissors braces, and horizontal scissors braces should be arranged on the setting layer of the sweeping rods, and the angle between the horizontal scissors braces and the longitudinal or transverse support at the temporary inverted arch should be between 45° and 60°.
[0008] Furthermore, the longitudinal horizontal rods are extended by connecting with butt fasteners, and the joints of two adjacent longitudinal horizontal rods should not be arranged in the same synchronization or span; the horizontal offset distance of two adjacent joints of asynchronous or different spans should not be less than 500mm; the distance from the center of each joint to the nearest main node should not be greater than 1 / 3 of the longitudinal distance; the distance between the joint position and the vertical pole should not be greater than 300mm; the longitudinal horizontal rods are overlapped, wherein the overlap length is not less than 1000mm, and the overlap is fixed with 3 rotating fasteners, and the distance from the edge of the rotating fastener cover plate to the rod end of the overlap rod is not less than 100mm.
[0009] Furthermore, the arch support and arch wall support are pre-bent into sections using I18 I-beams by a surface cold-bending machine and assembled into frames in the hole; the columns and beams are made of I14 I-beams, which are arranged horizontally according to the horizontal spacing and top support positions of the scaffolding, and the longitudinal spacing is arranged according to the longitudinal spacing of the scaffolding of 750mm.
[0010] A method for rapid construction of a secondary lining of a multiple variable-section dark-excavation tunnel comprises the following steps:
[0011] S10, invert construction, after the tunnel excavation of the dark excavation section of the storage line is completed and the initial support is stable, the invert construction is carried out;
[0012] S20, erection of full-hall scaffolding under the temporary invert and removal of the temporary invert at the arch wall;
[0013] S30, erection of full-hall scaffolding above the temporary invert and removal of the temporary invert at the arch top;
[0014] S40, erecting a formwork movable support, wherein the formwork movable support includes an arch support and a temporary invert support; installing the secondary lining formwork;
[0015] S50, pouring of secondary lining concrete;
[0016] S60, removing the secondary lining formwork;
[0017] S70, the arch frame moves forward;
[0018] S80: The secondary lining construction is completed and the temporary support is removed.
[0019] Furthermore, the invert construction comprises the following steps:
[0020] S11. According to the monitoring situation, remove the temporary middle partition concrete at the invert arch of the first section and the second lining section;
[0021] S12, remove temporary supports for partitions and lay waterproof boards and protective layers for inverts;
[0022] S13, after the waterproof construction of the inverted arch below the removed support is completed, the remaining supports are removed, and the removed supports are restored at intervals, and then the waterproof construction below the later removed supports is carried out;
[0023] S14. Ensure the integrity of the arch waterproofing while ensuring construction safety; tie the arch reinforcement according to the design requirements, install the formwork, pour the arch concrete, reserve joints between the reinforcement and the waterproofing board at the arch wall, and pour the arch backfill concrete after the arch concrete strength meets the requirements.
[0024] Further, the erection of the full-height scaffolding below the temporary inverted arch and the removal of the temporary inverted arch at the arch wall in step S20 and the erection of the full-height scaffolding above the temporary inverted arch and the removal of the temporary inverted arch at the arch top in step S30 should meet the following requirements:
[0025] S21. After the construction of the inverted arch is completed, a temporary scaffolding is set up at the bottom of the inverted arch, wherein the bracket adopts a fastener scaffolding, the spacing of the vertical poles is 900×750mm, and the step distance is 900mm;
[0026] S22. A fixed base is provided at the bottom of each vertical pole, and the scaffolding must be provided with longitudinal poles and transverse poles; the longitudinal sweeping pole should be fixed to the vertical pole at a distance of no more than 200 mm from the bottom of the steel pipe by a right-angle fastener, and the transverse sweeping pole should be fixed to the vertical pole immediately below the longitudinal sweeping pole by a right-angle fastener;
[0027] S23. When the longitudinal horizontal bars are extended, butt fasteners should be used for connection; the joints of two adjacent longitudinal horizontal bars should not be set in the same synchronization or span; the horizontal offset distance between two adjacent joints of different synchronization or different spans should not be less than 500mm; the distance from the center of each joint to the nearest main node should not be greater than 1 / 3 of the longitudinal distance; the distance between the joint position and the vertical pole should not be greater than 300mm; if the longitudinal horizontal bars are overlapped, the overlap length should not be less than 1000mm, and the overlap should be fixed with 3 rotating fasteners, and the distance from the edge of the rotating fastener cover plate to the rod end of the overlapped rod should not be less than 100mm;
[0028] S24. The formwork support belongs to the full-floor reinforced scaffolding. Vertical scissors braces are continuously set from bottom to top on the outside and inside of the support in the longitudinal and transverse directions every 5 spans and not less than 3m. The bottom end of the scissors brace rod should be pressed against the ground; the angle between the diagonal rod of the scissors brace and the ground is between 45° and 60°, and the diagonal rod is buckled with the vertical rod in each span; horizontal scissors braces should be set on the intersection plane of the top of the vertical scissors braces, and horizontal scissors braces should be set on the setting layer of the sweeping rod. The angle between the horizontal scissors brace and the support in the longitudinal or transverse direction should be between 45° and 60°;
[0029] S25. After the lower scaffolding of the temporary inverted arch is erected, according to the monitoring situation, the temporary inverted arch with a width of 1.6m is dismantled in sections longitudinally, and the supporting I-beam is cut;
[0030] S26. Set up a temporary upper scaffolding for the inverted arch. The support structure requirements are the same as those for the temporary lower scaffolding for the inverted arch. After the erection is completed, according to the monitoring situation, the temporary middle partition wall with a height of 2.4m shall be dismantled in sections longitudinally and the supporting I-beams shall be cut.
[0031] Furthermore, in step S40, the template movable bracket is set up, and the installation of the secondary lining template includes the following steps and requirements:
[0032] S41, after the erection of the temporary inverted arch lower part and the temporary inverted arch upper part scaffolding is completed, the temporary supports within the second lining range of the arch top and the arch wall are removed, the overall waterproof board of the arch wall is laid, and the arch wall steel bars are tied;
[0033] S42, erecting the second lining arch frame when moving, the arch frame is pre-bent into sections by using I18 I-beam cold bending machine on the ground, and assembled into frames in the hole; the longitudinal beam is made of I14 I-beam, and is arranged horizontally according to the horizontal spacing of 900mm and the top support position of the scaffold, and the longitudinal spacing is arranged according to the longitudinal spacing of 750mm of the scaffold; during installation, first use the vertical pole to fix the arch support, and then use the horizontal pole to tighten and fix the arch wall arch frame; the arch frames are connected by pins, and single and double pin ear plates are set at intervals at the ends of the arch frames; the arch ring and the vertical chord are connected by welding connecting plates, and the vertical chord is connected to the lower horizontal rod with high-strength bolts. The main beam longitudinal beam is set at the lower part of the horizontal chord. The longitudinal beam is 100×100mm, the longitudinal support point spacing is 750mm, and the horizontal spacing is 900mm. The longitudinal beam forms a support system with the frame pipe through the top support;
[0034] S43, the arch wall adopts Q235 steel formwork, the steel formwork specifications are 1500×300mm, 1500×200mm, 1500×100mm, and the formwork is assembled; when assembling the steel formwork, the adjacent formwork ribs are connected with U-shaped clips, and the spacing shall not be greater than 200mm. The U-shaped clips are installed alternately in front and back; the longitudinal joints of the steel formwork are connected with "L"-shaped pins;
[0035] S44. The plugging formwork is made of wooden formwork, wooden board or quick-closing gateway formwork. The formwork is formed by using square timber or steel pipes to support it. Steel bars are welded to the longitudinal distribution reinforcement and fixed inside. The top is supported by diagonal braces made of square timber, steel pipes or wooden boards for firm reinforcement. The angle of the diagonal braces should not be greater than 45 degrees. After closing the formwork, the gaps are sealed with cotton yarn.
[0036] Furthermore, the requirement for removing the secondary lining formwork is that the secondary lining concrete strength ensures that the surface and edges of the structural components are not damaged due to the removal of the formwork, and the strength reaches above 8MPa.
[0037] Beneficial effects of the present invention:
[0038] 1) Safety: In the construction of the secondary lining by the large-section double-side wall pilot pit method, the traditional trolley method requires the removal of all temporary supports. The present invention uses a mobile bracket to remove the temporary supports in stages and parts, reducing the risk of deformation of the initial support in the air for a long time after the temporary support is removed. Compared with the traditional method, the steel arch frame, beam and column support system used in the mobile bracket provided by the present invention has a higher stability, and the safety during the casting process is improved.
[0039] 2) Economy: Compared with the trolley construction method, this method has a great economic advantage. The five sections and one transition section of the dark excavated tunnel of the storage line of the present invention require at least four lining trolleys. The cost of each lining trolley is about 450,000 yuan, totaling 1.8 million yuan. Even if one trolley + panel replacement is used, it will cost at least 900,000 to 1 million yuan. The total cost of the support system of the present invention is only about 250,000 yuan.
[0040] 3) Comparison of work efficiency: During the template installation process, the installation of the trolley takes more than 15 days, and each subsequent template installation takes 1 day; while the installation of the template and the support system for the loose formwork assembly takes about 10 days each time; in the construction method of the present invention, the first installation of the movable bracket and the template takes 7 days, and each subsequent installation takes 3 days, which has the best work efficiency.
[0041] 4) Technical operability: Compared with the trolley construction, the mobile bracket provided by the present invention is more convenient to install the template and support system in the hole. The forward movement can be pulled by a hand winch as a whole, which is simple and effective. However, during the trolley installation, mechanical coordination is required due to the heavy weight and large volume of the components. In the narrow space inside the hole, mechanical operation and installation are difficult. Compared with the loose mold assembly method, the mobile bracket of the present invention has the advantages of convenient modular erection of the bracket system and convenient template installation and positioning. BRIEF DESCRIPTION OF THE DRAWINGS
[0042] Figure 1 Flow chart of rapid construction method of secondary lining for various variable cross-section dark excavation tunnels
[0043] Figure 2 Schematic diagram of the structural section of the rapid construction structure of the secondary lining of a variety of variable-section dark-excavated tunnels
[0044] Figure 3 Schematic diagram of longitudinal arrangement of the secondary lining rapid construction structure of various variable cross-section dark excavation tunnels
[0045] Figure 4 Effect drawing of mobile support system for secondary lining construction
[0046] Figure 5 Temporary support of invert removed
[0047] Figure 6 Invert arch replacement construction
[0048] Figure 7 Partition removal and support replacement
[0049] Figure 8 The waterproofing of the invert is completed
[0050] Fig. 9 The reinforcement binding of the inverted arch is completed
[0051] Fig.10 Longitudinal demolition of 1.6m wide temporary invert
[0052] Fig.11 Longitudinal demolition of the 2.4m high temporary partition wall
[0053] Fig.12 Mobile bracket template installation
[0054] Fig.13 Detailed structural drawing of formwork support system
[0055] Fig.14 Plug template construction
[0056] Among them, 1-arch frame; 11-arch support; 12-column; 13-cross beam; 14-arch wall support; 2-temporary invert support; 21-cross bar; 22-vertical bar; 23-diagonal bar; 3-secondary lining; 4-secondary lining formwork; 5-primary support; 6-inverter, 7-longitudinal partition wall; 8-track; 81-sliding wheel; 82-support frame; 9-connecting beam. DETAILED DESCRIPTION
[0057] Example 1
[0058] This embodiment is applicable to the field of dark excavation tunnel construction using the double side wall pilot tunnel method or the CRD method.
[0059] A rapid construction structure for the secondary lining of a dark-excavated tunnel with multiple variable cross-sections, including a template moving bracket and a partition wall, wherein the number of the template moving brackets is at least two, and the template moving brackets are used to support and fix the secondary lining template 4; the template moving bracket includes an arch frame 1 and a temporary invert bracket 2; the arch frame 1 includes an arch support 11, a column 12, a crossbeam 13 and an arch wall arch frame 14, one end of the arch 1 support is fixedly connected to the secondary lining template 4, and the other end is fixedly connected to the column 12; the other end of the column 12 is fixedly connected to the top of the crossbeam 13; the bottom end of the crossbeam 13 is fixedly connected to the top of the temporary invert bracket 2; one end of the arch wall arch frame 14 is fixedly connected to the secondary lining template 4, and the other end is fixedly connected to the temporary invert bracket 11; the arch support 11 is fixedly connected to the arch wall support 14, and the fixed connection form can be a mechanical connection form such as hinged, bolted or welded, preferably hinged; the crossbeam 13 of each template moving bracket A connecting beam 9 is arranged between them; the partition wall comprises a longitudinal partition wall 7 and a transverse partition wall. When the template moving bracket is assembled, the longitudinal partition wall 7 adapted to the height of the arch frame 1 is removed; a track 8 is arranged on the removed longitudinal partition wall 7, and the track 8 comprises a support frame 81 and a sliding wheel 82. The support frame 81 is fixedly connected to the removed longitudinal partition wall 7, and the sliding wheel 82 is fixedly connected to the support frame 81. In this embodiment, the support frame 81 is fixedly connected to the longitudinal partition wall 7 using channel steel, and the fixing form is bolt connection. The sliding wheel 82 is a round steel pipe welded to the top of the support frame 81; the sliding wheel 82 is slidably matched with the connecting beam 9, and is used for pulling the arch frame 1 as a whole to the next section of the second lining by an electric hoist or a hand hoist according to the weight of the arch frame after the second lining 3 is poured; the columns 12 and the cross beams 13 are provided with different specifications and sizes, and are used for selection and use according to the size requirements of the second lining template 4 and the arch frame 1 for variable-section tunnel excavation.
[0060] In this embodiment, the second lining formwork adopts a standard steel formwork with a size of 300mm (width) × 1500mm (length) × 55mm (total thickness) and a plate thickness of δ = 2.75mm. The formworks are connected by U-shaped buckles and bolts, and the formwork and the arch frame are fixed by pin locking or wire tying.
[0061] In this embodiment, each arch frame 1 is assembled by 7 arch rings, 1 cross beam 13, and 4 columns 12. The 7 arch rings of the arch part are hingedly connected by pins to form the arch frame 1. The arch support 11 is composed of 3 arch rings at the top, and is bolted to the cross beam 13 and the column 12 to form a whole. The other 4 arch rings form an arch wall support 14.
[0062] The bracket at the temporary inverted arch includes a temporary lower bracket and a temporary upper bracket of the inverted arch. The temporary lower bracket and the temporary upper bracket of the inverted arch include a vertical pole, a longitudinal horizontal pole, a longitudinal sweeping pole and a transverse sweeping pole. A fixing seat is provided at the bottom of the vertical pole 22 for fixing the vertical pole 22 to the inverted arch; the longitudinal sweeping pole is fixed to the vertical pole at a position not greater than 200 mm from the bottom of the fixing seat by a right-angle fastener; the transverse sweeping pole is fixed to the vertical pole close to the bottom of the longitudinal sweeping pole by a right-angle fastener; a top support is provided at the top of the vertical pole 22 for fixing the crossbeam 13 to the vertical pole 22; the arch wall arch frame 14 is fixedly connected to both ends of the horizontal pole 21. The bracket at the temporary inverted arch adopts a coupler-type scaffolding with a diameter of 48.3mm and a wall thickness of 3.6mm. The spacing of the vertical poles is 900×750mm and the step distance is 900mm, which is used to support the arch frame; vertical scissors braces are continuously set from bottom to top on the outside and inside of the bracket at the temporary inverted arch every 5 spans and not less than 3m in the longitudinal and transverse directions, and the bottom end of the scissors brace rod should be pressed against the ground; the angle between the diagonal rod 23 of the scissors brace and the ground is between 45° and 60°, and the diagonal rod 23 is buckled with the vertical pole 22 at each span; horizontal scissors braces should be set at the intersection plane of the top of the vertical scissors braces, and horizontal scissors braces should be set at the setting layer of the sweeping rod. The angle between the horizontal scissors brace and the longitudinal or transverse bracket at the temporary inverted arch should be between 45° and 60°.
[0063] The longitudinal horizontal rods are extended by butt fasteners. The joints of two adjacent longitudinal horizontal rods should not be set in the same synchronization or span; the horizontal offset distance between two adjacent joints of asynchronous or different spans should not be less than 500mm; the distance from the center of each joint to the nearest main node should not be greater than 1 / 3 of the longitudinal distance; the distance between the joint position and the vertical pole should not be greater than 300mm; the longitudinal horizontal rods are overlapped, with an overlap length of not less than 1000mm, and the overlap is fixed with 3 rotating fasteners, and the distance from the edge of the rotating fastener cover plate to the rod end of the overlap rod should be not less than 100mm.
[0064] The material selection of the arch frame 11 needs to be combined with the cross-sectional dimensions of the tunnel secondary lining and the construction conditions for structural design. In this embodiment, the arch support 11 and the arch wall support 14 are pre-bent into sections using I18 I-beams on the ground by a cold bending machine and assembled into frames in the tunnel; the columns 12 and the crossbeams 13 are made of I14 I-beams, which are arranged horizontally according to the horizontal spacing and top support position of the scaffolding, and the longitudinal spacing is arranged according to the longitudinal spacing of the scaffolding of 750mm. Among them, the longitudinal support point spacing of the column 12 is 750mm, and the lateral spacing is 900mm.
[0065] In this embodiment, the full-floor scaffolding adopts a support system composed of a bottom support + a steel pipe with a specification of Φ48.3×3.6 + a fastener + a top support, and the vertical poles 22 are arranged at a spacing of 900×750mm and a step distance of 900mm.
[0066] In this embodiment, construction is allowed only after the primary support 5 is stable, and the concrete of the secondary lining 3 is poured between the secondary lining formwork 4 and the primary support 5 .
[0067] The method of using this embodiment is as follows: when the upper support of the temporary arch is in the formwork moving support, according to the size of the arch frame 1 and the secondary lining formwork 4, the top of the longitudinal partition wall matched with it is removed, which is 2.4m in this embodiment, and the track 8 is installed on the removed longitudinal partition wall 7. The sliding wheel 82 of the track 8 is smeared with lubricating oil and slidably matched with the connecting beam 9. When the casting of the secondary lining 3 is completed, an electric hoist or a hand hoist is used to pull the arch frame 1 as a whole to slide through the slide rail 8 to the next section of the secondary lining 3.
[0068] A method for rapid construction of a secondary lining of a multiple variable-section dark-excavation tunnel comprises the following steps:
[0069] S10, invert construction: after the tunnel excavation of the storage line is completed and the initial support is stable, the invert construction is carried out;
[0070] The construction of the invert includes the following steps:
[0071] S11. According to the monitoring situation, the 2.2m high temporary middle partition concrete at the invert of the first section of the second lining section was broken;
[0072] S12, remove temporary supports for partitions and lay waterproof boards and protective layers for inverts;
[0073] S13, after the waterproofing construction of the inverted arch below the removed support is completed, the remaining supports are removed, and the removed supports are restored at intervals, and then the waterproofing construction below the later removed supports is carried out;
[0074] S14. Ensure the integrity of the arch waterproofing while ensuring construction safety; tie the arch reinforcement according to the design requirements, install the formwork, pour the arch concrete, reserve joints between the reinforcement and the waterproofing board at the arch wall, and pour the arch backfill concrete after the arch concrete strength meets the requirements.
[0075] S20, erection of full-hall scaffolding under the temporary invert and removal of the temporary invert at the arch wall;
[0076] S30, erection of full-hall scaffolding above the temporary invert and removal of the temporary invert at the arch top;
[0077] The erection of the full-height scaffolding below the temporary inverted arch and the removal of the temporary inverted arch at the arch wall in step S20 and the erection of the full-height scaffolding above the temporary inverted arch and the removal of the temporary inverted arch at the arch top in step S30 should meet the following requirements:
[0078] S21. After the construction of the inverted arch is completed, a temporary scaffolding is set up at the bottom of the inverted arch. The bracket adopts a fastener scaffolding with a diameter of 48.3mm and a wall thickness of 3.6mm. The spacing of the vertical poles is 900×750mm and the step distance is 900mm.
[0079] S22. A fixed base is provided at the bottom of each vertical pole, and the scaffolding must be provided with longitudinal poles and transverse poles; the longitudinal sweeping pole should be fixed to the vertical pole at a distance of no more than 200mm from the bottom of the steel pipe by right-angle fasteners, and the transverse sweeping pole should be fixed to the vertical pole immediately below the longitudinal sweeping pole by right-angle fasteners;
[0080] S23. When the longitudinal horizontal bars are extended, butt fasteners should be used for connection; the joints of two adjacent longitudinal horizontal bars should not be set in the same synchronization or span; the horizontal offset distance between two adjacent joints of different synchronization or different spans should not be less than 500mm; the distance from the center of each joint to the nearest main node should not be greater than 1 / 3 of the longitudinal distance; the distance between the joint position and the vertical pole should not be greater than 300mm; if the longitudinal horizontal bars are overlapped, the overlap length should not be less than 1000mm, and the overlap should be fixed with 3 rotating fasteners, and the distance from the edge of the rotating fastener cover plate to the rod end of the overlapped rod should not be less than 100mm;
[0081] S24. The formwork support belongs to the full-floor reinforced scaffolding. Vertical scissors braces are continuously set from bottom to top on the outside and inside of the formwork support in the longitudinal and transverse directions every 5 spans and not less than 3m. The bottom end of the scissors brace rod should be pressed against the ground; the angle between the diagonal rod of the scissors brace and the ground is between 45° and 60°, and the diagonal rod is buckled with the vertical rod in each span; horizontal scissors braces should be set at the intersection plane of the top of the vertical scissors braces, and horizontal scissors braces should be set at the setting layer of the sweeping rod. The angle between the horizontal scissors brace and the support in the longitudinal or transverse direction should be between 45° and 60°;
[0082] S25. After the lower scaffolding of the temporary invert is erected, according to the monitoring situation, the temporary invert with a width of 1.6m is dismantled in sections longitudinally and the supporting I-beams are cut;
[0083] S26. Set up the temporary upper scaffolding for the inverted arch. The support structure requirements are the same as those for the temporary lower scaffolding for the inverted arch. After the erection is completed, according to the monitoring situation, the temporary middle partition wall with a height of 2.4m shall be dismantled in sections longitudinally and the supporting I-beams shall be cut.
[0084] S40, erecting the mobile formwork support, the mobile formwork support includes the arch frame and the temporary invert arch support; installing the secondary lining formwork; erecting the mobile arch frame, the installation of the mobile support formwork includes the following steps and requirements:
[0085] S41, after the erection of the temporary inverted arch lower part and the temporary inverted arch upper part scaffolding is completed, the temporary supports within the second lining range of the arch top and the arch wall are removed, the overall waterproof board of the arch wall is laid, and the arch wall steel bars are tied;
[0086] S42, when erecting the second lining arch frame, the arch frame is pre-bent into sections by a cold bending machine on the ground using I18 I-beams, and assembled into frames in the hole; the longitudinal beam is made of I14 I-beams, and the horizontal spacing is arranged according to the horizontal spacing of the scaffolding 900mm and the top support position, and the longitudinal spacing is arranged according to the longitudinal spacing of the scaffolding 750mm; when installing, first use the vertical poles to fix the arch frame, and then use the horizontal poles to tighten and fix the arch wall arch frame; the outer arch ring of the bracket is connected with pins, and single and double pin ear plates are set at intervals at the ends of the arch frame; the arch ring and the vertical chord are connected by welding connecting plates, and the vertical chord and the lower horizontal rod are connected with high-strength bolts. The main beam longitudinal beam is set at the lower part of the horizontal chord. The longitudinal beam is 100×100mm, with a longitudinal support point spacing of 750mm and a horizontal spacing of 900mm. The longitudinal beam forms a support system with the frame pipe through the top support;
[0087] S43. The arch wall formwork adopts Q235 steel formwork, and the steel formwork specifications are 1500×300mm, 1500×200mm, and 1500×100mm in length and width. The surface of the arch wall formwork shall not be uneven, and the flatness and specifications must meet the requirements of the construction specifications. When assembling the steel formwork, the adjacent formwork ribs are connected with U-shaped clips, and the spacing shall not be greater than 200mm. The U-shaped clips are installed alternately in front and back; the longitudinal joints of the steel formwork are connected with "L"-shaped pins;
[0088] S44. The plugging formwork is made of wooden formwork, wooden board or quick-closing gateway formwork. The formwork is formed by backing it with square wood or steel pipe. It is welded on the longitudinal distribution reinforcement with Φ18 steel bars and fixed inside. It is firmly reinforced with diagonal braces made of square wood, steel pipe or wooden board. The angle of the diagonal brace should not be greater than 45 degrees. After closing the formwork, the gap is sealed with cotton yarn.
[0089] S50, pouring of secondary lining concrete;
[0090] S51. Concrete pouring should be carried out continuously. When it is necessary to pause, the pause time should be shortened, and the second layer of concrete should be poured before the initial setting of the previous layer of concrete. If it exceeds the time limit, construction joints should be left according to relevant waterproofing requirements, and the pouring method of "one slope, thin layer pouring, gradual advancement, and one-time completion" should be adopted to reduce the exposed surface of concrete, and the pouring intensity should be increased to shorten the pouring time. Measures such as preventing the formation of pouring cold joints and improving the crack resistance and impermeability of structural concrete.
[0091] S52. Reserve 300mm×300mm pouring and vibrating holes on the side wall formwork, and pour evenly layer by layer through the pouring holes. When the pouring surface is about to reach the lower edge of the pouring hole, clean the pouring hole cover and the residual concrete on the pouring side of the surrounding formwork, close the pouring hole, and ensure that the pouring hole is tightly and smoothly closed.
[0092] S53. The pouring of side wall concrete must be carried out in layers and symmetrically, with a symmetrical pouring height of no more than 0.5m. The pouring speed should be controlled at 0.5m / h to make the formwork symmetrical and evenly stressed, avoid deformation and displacement of the formwork, and ensure the accuracy of the structural dimensions. A hose must be installed at the front end of the concrete delivery pipeline to ensure that the concrete is directly delivered to the pouring surface and the concrete fall height does not exceed 2.0m to prevent stone accumulation and affect the quality of concrete. Use an extra-long tamping rod to tamp the lower concrete of the lining wall.
[0093] S54. During pouring, pay attention to strengthening the tamping at the joints. If there is water on the top surface of the concrete, it should be drained before continuing pouring.
[0094] S60. Removal of the secondary lining formwork. The requirements for removal of the secondary lining formwork are as follows: the strength of the secondary lining concrete shall ensure that the surface and edges of the structural components are not damaged due to the removal of the formwork, and the strength shall reach 8MPa or above.
[0095] S70, move the arch forward; install rails above the temporary support, and after each section of the secondary lining is poured, use an electric hoist or hand hoist to pull the arch as a whole to the next section for pouring the next section of concrete;
[0096] S80, Secondary lining construction completed, temporary supports removed. After the secondary lining arch wall construction of the entire storage line is completed, the support system will be removed in sequence, and the remaining temporary supports will be removed uniformly.
[0097] In other embodiments, the scaffolding at the variable section is set: the bracket at the variable section of the structure is set at a spacing of 900×750mm and a step distance of 900mm. According to the spacing of the scaffolding in the general construction section, when the distance between the scaffolding uprights at the variable section and the end mold is greater than 300mm, an inclined rod is added at the plug to strengthen the end mold force system. Pre-embedded reinforcement is made and set at the bottom of the inclined rod, and 100×100mm triangular square wood is placed on the pre-embedded reinforcement. The end of the scaffolding is fixed on the backfill concrete of the inverted arch to ensure the stability of the support force.
[0098] In other embodiments, the arch frame and formwork are set when the cross-section changes: when the mobile formwork system is performing secondary lining construction with different cross-sections, if the sizes of the two cross-sections are quite different, when the support system is moved from the previous section to the next section, the method of replacing the vertical bars and horizontal bars of the support with appropriate sizes is adopted to ensure that the formwork size meets the requirements; if the cross-section difference is small, a special-shaped wooden formwork is directly set at the corresponding position on the arch ring to fine-tune the cross-section size of the formwork.
[0099] The above description is only a preferred embodiment of the present invention and does not limit the technical scope of the present invention. Therefore, any slight modifications, equivalent changes and modifications made to the above embodiments based on the technical essence of the present invention still fall within the scope of the technical solution of the present invention.
Claims
1. A rapid construction structure for secondary lining of multiple variable-section dark-excavated tunnels, characterized in that: It includes a template movable bracket and a partition wall, the number of the template movable bracket is at least 2, which is used to support and fix the second lining template; the template movable bracket includes an arch frame and a temporary inverted arch bracket; the arch frame includes an arch bracket, a column, a crossbeam and an arch wall arch frame, one end of the arch bracket is fixedly connected to the second lining template, and the other end is fixedly connected to the column; the other end of the column is fixedly connected to the top of the crossbeam; the bottom end of the crossbeam is fixedly connected to the top of the temporary inverted arch bracket; one end of the arch wall arch frame is fixedly connected to the second lining template, and the other end is fixedly connected to the temporary inverted arch bracket; the arch bracket is fixedly connected to the arch wall arch frame; a connecting beam is arranged between the crossbeams of each template movable bracket; the partition wall It includes longitudinal partition walls and transverse partition walls. When the template moving bracket is assembled, the longitudinal partition wall adapted to the height of the arch frame is removed; a track is arranged on the removed longitudinal partition wall, and the track includes a support frame and a sliding wheel. The support frame is fixedly connected to the removed longitudinal partition wall, and the sliding wheel is fixedly connected to the support frame; the sliding wheel is slidably matched with the connecting beam, and is used to pull the arch frame as a whole to the next section of the second lining by an electric hoist or a hand hoist according to the weight of the arch frame after the second lining is poured; the columns and beams are provided with different specifications and sizes, and are used to select and use according to the requirements of the second lining template for variable-section tunnel excavation and the size of the arch frame; the second lining template adopts a 300mm×1500mm×55mm steel template; The temporary inverted arch support includes a temporary inverted arch lower support and a temporary inverted arch upper support, the temporary inverted arch lower support and the temporary inverted arch upper support include a vertical pole, a longitudinal horizontal pole, a longitudinal sweeping pole and a transverse sweeping pole, the vertical pole bottom is provided with a fixing seat for fixing the vertical pole to the inverted arch; the longitudinal sweeping pole is fixed to the vertical pole at a position not greater than 200mm from the bottom of the fixing seat by a right-angle fastener; the transverse sweeping pole is fixed to the vertical pole immediately below the longitudinal sweeping pole by a right-angle fastener; the vertical pole top is provided with a top support for fixing the crossbeam to the vertical pole; the arch wall arch frame is fixedly connected to the horizontal pole; The support for the temporary inverted arch adopts a coupler-type scaffolding, with a vertical pole spacing of 900×750mm and a step distance of 900mm, which is used to support the arch frame; vertical scissors braces are continuously arranged from bottom to top on the outside and inside of the support for the temporary inverted arch, in the longitudinal and transverse directions every 5 spans and not less than 3m, and the bottom ends of the scissors brace rods should be pressed against the ground; the angle between the diagonal rods of the scissors braces and the ground is between 45° and 60°, and the diagonal rods are buckled with the vertical poles in each span; horizontal scissors braces should be arranged on the plane of the intersection of the tops of the vertical scissors braces, and horizontal scissors braces should be arranged on the setting layer of the sweeping rods, and the angle between the horizontal scissors braces and the longitudinal or transverse support of the temporary inverted arch should be between 45° and 60°.
2. The secondary lining rapid construction structure according to claim 1 is characterized in that: The longitudinal horizontal rods are extended by connecting with butt fasteners, and the joints of two adjacent longitudinal horizontal rods should not be arranged in the same synchronization or span; the horizontal offset distance of two adjacent joints of asynchronous or different spans should not be less than 500mm; the distance from the center of each joint to the nearest main node should not be greater than 1 / 3 of the longitudinal distance; the distance between the joint position and the vertical pole should not be greater than 300mm; the longitudinal horizontal rods are overlapped, and the overlap length is not less than 1000mm. The overlap is fixed with 3 rotating fasteners, and the distance from the edge of the rotating fastener cover plate to the rod end of the overlap rod is not less than 100mm.
3. The secondary lining rapid construction structure according to claim 2 is characterized in that: The arch support and arch wall support are pre-bent into sections using I18 I-beams using a surface cold-bending machine and assembled into frames in the hole; the columns and beams are made of I14 I-beams, which are arranged horizontally according to the horizontal spacing of the scaffolding and the top support position, and the longitudinal spacing is arranged according to the longitudinal spacing of the scaffolding of 750mm.
4. A method for rapid construction of secondary lining of multiple variable cross-section dark excavation tunnels, characterized in that: A second lining rapid construction method using the second lining rapid construction structure according to any one of claims 1 to 3, the second lining rapid construction method comprising the following steps: S10, invert construction, after the tunnel excavation of the dark excavation section of the storage line is completed and the initial support is stable, the invert construction is carried out; S20, erection of full-hall scaffolding under the temporary invert and removal of the temporary invert at the arch wall; S30, erection of full-hall scaffolding above the temporary invert and removal of the temporary invert at the arch top; S40, erecting a formwork movable support, wherein the formwork movable support includes an arch support and a temporary invert support; installing the secondary lining formwork; S50, pouring of secondary lining concrete; S60, removing the secondary lining formwork; S70, the arch frame moves forward; S80: The secondary lining construction is completed and the temporary support is removed.
5. The rapid construction method for secondary lining according to claim 4 is characterized in that: The invert construction comprises the following steps: S11. According to the monitoring situation, remove the temporary middle partition concrete at the invert arch of the first section and the second lining section; S12, remove temporary supports for partitions and lay waterproof boards and protective layers for inverts; S13, after the waterproof construction of the inverted arch below the removed support is completed, the remaining supports are removed, and the removed supports are restored at intervals, and then the waterproof construction below the later removed supports is carried out; S14. Ensure the integrity of the arch waterproofing while ensuring construction safety; tie the arch reinforcement according to the design requirements, install the formwork, pour the arch concrete, reserve joints between the reinforcement and the waterproofing board at the arch wall, and pour the arch backfill concrete after the arch concrete strength meets the requirements.
6. The rapid construction method for secondary lining according to claim 5 is characterized in that: The erection of the full-height scaffolding below the temporary inverted arch and the removal of the temporary inverted arch at the arch wall in step S20 and the erection of the full-height scaffolding above the temporary inverted arch and the removal of the temporary inverted arch at the arch top in step S30 should meet the following requirements: S21. After the construction of the inverted arch is completed, a temporary scaffolding is set up at the bottom of the inverted arch, wherein the bracket adopts a fastener scaffolding, the spacing of the vertical poles is 900×750mm, and the step distance is 900mm; S22. A fixed base is provided at the bottom of each vertical pole, and the scaffolding must be provided with longitudinal poles and transverse poles; the longitudinal sweeping pole should be fixed to the vertical pole at a distance of no more than 200 mm from the bottom of the steel pipe by a right-angle fastener, and the transverse sweeping pole should be fixed to the vertical pole immediately below the longitudinal sweeping pole by a right-angle fastener; S23. When the longitudinal horizontal bars are extended, butt fasteners should be used for connection; the joints of two adjacent longitudinal horizontal bars should not be set in the same synchronization or span; the horizontal offset distance between two adjacent joints of different synchronization or different spans should not be less than 500mm; the distance from the center of each joint to the nearest main node should not be greater than 1 / 3 of the longitudinal distance; the distance between the joint position and the vertical pole should not be greater than 300mm; if the longitudinal horizontal bars are overlapped, the overlap length should not be less than 1000mm, and the overlap should be fixed with 3 rotating fasteners, and the distance from the edge of the rotating fastener cover plate to the rod end of the overlapped rod should not be less than 100mm; S24. The formwork support belongs to the full-floor reinforced scaffolding. Vertical scissors braces are continuously set from bottom to top on the outside and inside of the support in the longitudinal and transverse directions every 5 spans and not less than 3m. The bottom end of the scissors brace rod should be pressed against the ground; the angle between the diagonal rod of the scissors brace and the ground is between 45° and 60°, and the diagonal rod is buckled with the vertical rod in each span; horizontal scissors braces should be set on the intersection plane of the top of the vertical scissors braces, and horizontal scissors braces should be set on the setting layer of the sweeping rod. The angle between the horizontal scissors brace and the support in the longitudinal or transverse direction should be between 45° and 60°; S25. After the lower scaffolding of the temporary inverted arch is erected, according to the monitoring situation, the temporary inverted arch with a width of 1.6m is dismantled in sections longitudinally, and the supporting I-beam is cut; S26. Set up a temporary upper scaffolding for the inverted arch. The support structure requirements are the same as those for the temporary lower scaffolding for the inverted arch. After the erection is completed, according to the monitoring situation, the temporary middle partition wall with a height of 2.4m shall be dismantled in sections longitudinally and the supporting I-beams shall be cut.
7. The rapid construction method for secondary lining according to claim 6 is characterized in that: In step S40, the template moving bracket is set up, and the installation of the secondary lining template includes the following steps and requirements: S41, after the erection of the temporary inverted arch lower part and the temporary inverted arch upper part scaffolding is completed, the temporary supports within the second lining range of the arch top and the arch wall are removed, the overall waterproof board of the arch wall is laid, and the arch wall steel bars are tied; S42, erect the second lining arch frame when moving, the arch frame is pre-bent into sections by using I18 I-beam cold bending machine on the ground, and assembled into frames in the hole; the longitudinal beam is made of I14 I-beam, and the horizontal spacing is arranged according to the horizontal spacing of 900mm and the top support position of the scaffolding, and the longitudinal spacing is arranged according to the longitudinal spacing of 750mm of the scaffolding; when installing, first use the vertical pole to fix the arch support, and then use the horizontal pole to tighten and fix the arch wall arch frame; The arch frames are connected by pins, and single and double pin ear plates are set at intervals at the ends of the arch frames; the arch ring and the vertical chord are connected by welding connecting plates, and the vertical chord and the lower horizontal rod are connected by high-strength bolts. The main beam longitudinal beam is set at the bottom of the horizontal chord. The longitudinal beam is 100×100mm, with a longitudinal support point spacing of 750mm and a transverse spacing of 900mm. The longitudinal beam forms a support system with the frame pipe through the top support; S43. The arch wall adopts Q235 steel formwork, and the steel formwork specifications are 1500×300mm, 1500×200mm, and 1500×100mm in length and width. When assembling the steel formwork, the adjacent formwork ribs are connected with U-shaped clips, and the spacing shall not be greater than 200mm. The U-shaped clips are installed alternately in front and back. The longitudinal joints of the steel formwork are connected with "L"-shaped pins; S44. The plugging formwork is made of wooden formwork, wooden board or quick-closing gateway formwork. The formwork is formed by using square timber or steel pipes to support it. Steel bars are welded to the longitudinal distribution reinforcement and fixed inside. The top is supported by diagonal braces made of square timber, steel pipes or wooden boards for firm reinforcement. The angle of the diagonal braces should not be greater than 45 degrees. After closing the formwork, the gaps are sealed with cotton yarn.
8. The rapid construction method for secondary lining according to claim 4 is characterized in that: The requirements for removing the secondary lining formwork are: the secondary lining concrete strength ensures that the surface and edges of the structural components are not damaged due to the removal of the formwork, and the strength reaches above 8MPa.