Online repair system and repair method after pipeline component seal failure
The leakage material is collected and pressure-raised through the bag sealing diaphragm and outlet pipe system, which solves the leakage problem caused by high-pressure pipeline seal failure, achieves online zero-leakage repair, avoids equipment shutdown and parts replacement, and ensures safe production and environmental protection.
Patent Information
- Application Number
- CN202010245671.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2020-03-31
- Publication Date
- 2024-10-25
- Estimated Expiration
- 2040-03-31
AI Technical Summary
When the seal of a high-pressure pipeline fails, existing technology cannot realize online repair, resulting in material leakage, resulting in waste, fire, explosion hazards, pollution and health hazards, and the equipment needs to be shut down for maintenance before substantial repair can be carried out.
The bag-type sealing diaphragm is fixed with a tie or tape, and the leaked material is collected through the upper and lower outlet pipes, and the explosion-proof air compressor and pump are used to raise the pressure to a state higher than that of the high-pressure pipeline, achieving zero leakage repair and avoiding disassembly. equipment and replacement parts.
It achieves zero leakage repair without downtime, disassembly, or replacement of parts when the equipment is running, avoiding explosions and fires, improving the production environment, reducing costs, and is suitable for a variety of sealing points.
Smart Images

Figure CN111306395B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to a seal of a high-pressure pipeline and a high-pressure pipeline connection assembly, and in particular to an online repair system and method after the seal of a pipeline assembly fails. Background Art
[0002] Most of the materials transported by pipelines in refineries and chemical plants have the following characteristics: gas-liquid miscibility, high temperature, high pressure, flammable and explosive, toxic, highly corrosive, etc. The overall pipeline is composed of countless pipelines connected end to end, and the pipelines are connected by connecting components. Therefore, the number of connecting components on the entire pipeline is quite large, and the structure and size of the connecting components are also different. Different connecting components are used according to different locations. Figure 1 to Figure 4 As shown, different connection components are used, including a manual valve connection component A, an electric valve connection component B, a threaded connection component C, a flange connection component D, etc.
[0003] like Figure 1 to Figure 4 As shown, at each connection, a sealing point 2 is formed between the high pressure pipeline 1 and the connection components A / B / C / D, and different sealing methods are selected at the sealing point 2 according to different connection components A / B / C / D. For the manual valve connection component A and the electric valve connection component B, the sealing point 2 is sealed by the packing as a seal; for the threaded connection component C, the sealing point 2 is sealed by the thread as a seal; for the flange connection component D, the sealing point 2 is sealed by the gasket as a seal.
[0004] There are quite a lot of sealing points on the entire high-pressure pipeline 1. Since the equipment in refineries and chemical plants must always operate continuously and cannot be cooled, depressurized, or shut down at any time, and the materials cannot be emptied at will, when some sealing points leak, the materials cannot be emptied for repair. For example, when the equipment is running, the manual valve connection assembly A, electric valve connection assembly B, threaded connection assembly C, and flange connection assembly D at the connection between pipelines cannot be replaced; nor can the gaskets, threaded seals, and packings be replaced. The only way is to simply tighten the screws with a wrench and compress the packing, and no substantial repair can be achieved. Generally, the equipment and pipeline components of refineries and chemical plants are shut down for maintenance once every two years. Once a sealing point 2 leaks, they can only watch the leaked material 9 leak, and they have been allowed to leak without doing anything until the next shutdown and maintenance cycle arrives, when substantial repairs such as replacing accessories can be taken.
[0005] Therefore, the prior art necessarily has the following disadvantages:
[0006] 1. Cause huge waste of materials;
[0007] 2. All materials are flammable, and leakage will increase the risk of fire and explosion;
[0008] 3. The leaked materials will pollute the atmosphere, water and soil;
[0009] 4. The materials contain toxic and harmful substances that may cause cancer and harm health;
[0010] 5. The materials are accompanied by a pungent smell, unpleasant smell, and disturbing to others. Summary of the invention
[0011] The technical problem to be solved by the present invention is to provide an online repair system and a repair method for pipeline components after sealing failure, which do not require work stoppage for repair and achieve zero leakage repair effect.
[0012] The technical solution adopted by the present invention is: an online repair system after the sealing failure of a pipeline assembly, comprising a plurality of high-pressure pipelines connected end to end to form a material conveying pipeline, each two adjacent high-pressure pipelines are connected to each other through a connecting assembly, thereby forming a sealed connection structure, the connecting assembly is a manual valve connecting assembly or an electric valve connecting assembly or a threaded connecting assembly or a flange connecting assembly, each of the sealed connection structures is sealed by a bag-type sealing diaphragm, the edges of each of the bag-type sealing diaphragms are sealed and fixed to the high-pressure pipelines at both ends of the connecting assembly by cable ties or tapes, the connecting assembly is located inside the bag-type sealing diaphragm, and the bag-type sealing diaphragm The upper part of the bag-type sealing diaphragm is integrally formed with an upper outlet pipe connected to the interior for outlet leaked material gas, and the lower part of the bag-type sealing diaphragm is integrally formed with a lower outlet pipe connected to the interior for outlet leaked material liquid, wherein the outlet port of the upper outlet pipe is connected to an upper collecting pipe through an upper one-way valve, the output port of the lower outlet pipe is connected to a lower collecting pipe through a lower one-way valve, the output ports of the upper collecting pipe and the lower collecting pipe are both connected to the collecting end of a leaked material collecting device, and the output end of the leaked material collecting device is connected to the high-pressure pipeline closest to the output end of the leaked material collecting device through a material pressurizing device, so as to return the collected leaked material to the high-pressure pipeline.
[0013] A repair method for an online repair system after a pipeline component seal fails, characterized in that the leaked material at normal pressure leaking from a sealed connection structure between two high-pressure pipelines is controlled in a closed space and isolated from the atmosphere by a bag-type sealing diaphragm, the edges of the bag-type sealing diaphragm are sealed with the outer surface of the high-pressure pipeline in the sealed connection structure and the valve stem by cable ties and tapes, the leaked material is sent to a gas material collection bag and a liquid material collection box by an upper outlet pipe and a lower outlet pipe on the bag-type sealing diaphragm, and the material in the bag-type sealing diaphragm is kept at normal pressure at all times; then the pressure of the gas material in the gas material collection bag is increased by an explosion-proof air compressor to a pressure higher than the material pressure in the high-pressure pipeline and then directly sent back to the high-pressure pipeline, and at the same time, the pressure of the liquid material in the liquid material collection box is increased by an explosion-proof pump to a pressure higher than the material pressure in the high-pressure pipeline and then directly sent back to the high-pressure pipeline, and this cycle is repeated to maintain zero leakage until the next shutdown and maintenance cycle arrives for substantial repair.
[0014] The online repair system and method for pipeline assembly seal failure of the present invention have the following advantages:
[0015] 1. Repairing the leak does not affect the operation of the equipment and does not require shutdown.
[0016] 2. During maintenance, equipment and pipelines can be operated under warm and pressurized conditions.
[0017] 3. No need to dismantle equipment and pipelines during maintenance
[0018] 4. No need to replace equipment parts during maintenance
[0019] 5. The repair effect achieves zero leakage
[0020] 6. Avoid explosion and fire to achieve safe production
[0021] 7. Energy saving, emission reduction, green and environmental protection
[0022] 8. Eliminate odors and disease causes, improve production environment, and increase health index.
[0023] 9. Adapt to various sealing points and have a wide range of applications
[0024] 10. Easy to operate and low cost. BRIEF DESCRIPTION OF THE DRAWINGS
[0025] Figure 1 It is a structural schematic diagram of a manual valve connection assembly in the prior art;
[0026] Figure 2 It is a structural schematic diagram of the electric valve connection assembly of the prior art;
[0027] Figure 3It is a structural schematic diagram of a prior art threaded connection assembly;
[0028] Figure 4 It is a structural schematic diagram of a flange connection assembly in the prior art;
[0029] Figure 5 It is a schematic diagram of the overall structure of an online repair system and a repair method after a pipeline assembly seal failure according to the present invention;
[0030] Figure 6 It is a schematic diagram of the development of the bag-type sealing diaphragm used for the electric valve, thread and flange connection assembly in the present invention;
[0031] Figure 7 It is a schematic diagram of the deployment of the bag-type sealing diaphragm used in the manual valve connection assembly of the present invention;
[0032] Figure 8 It is a schematic diagram of the unfolding of the bag-type sealing diaphragm zipper used for the electric valve, thread and flange connection assembly of the present invention;
[0033] Fig. 9 It is a schematic diagram of the closing and opening of the bag-type sealing diaphragm zipper used for the manual valve connection assembly in the present invention.
[0034] In the picture
[0035] 1: High pressure pipeline 2: Sealing point
[0036] 3: Lower check valve 4: Valve stem
[0037] 5: Cable tie or tape 6: Bag seal diaphragm
[0038] 7: Upper outlet pipe 8: Lower outlet pipe
[0039] 9: Leaking material 10: Upper one-way valve
[0040] 11: Upper collection tube 12: Lower collection tube
[0041] 13: Gas material collection capsule 14: Liquid material
[0042] 15: Liquid material collection box 16: Explosion-proof air compressor
[0043] 17: Explosion-proof pump 18: Gas discharge pipe
[0044] 19: High-pressure air pipe 20: Material introduction check valve
[0045] 21: Sealed zipper 22: Casing
[0046] 23: Upper connection hole 24: Lower connection hole
[0047] 25: Edge 26: Liquid discharge pipe
[0048] 27: High pressure liquid pipe 28: Sheet membrane
[0049] 29: Connecting hole DETAILED DESCRIPTION
[0050] The online repair system and method for repairing pipeline components after seal failure of the present invention are described in detail below in conjunction with the embodiments and drawings.
[0051] like Figure 5 As shown, the online repair system after the pipeline assembly seal failure of the present invention comprises a plurality of high-pressure pipelines 1 connected end to end to form a material conveying pipeline, each two adjacent high-pressure pipelines 1 are connected to each other through a connecting assembly to form a sealed connection structure, the connecting assembly is a manual valve connecting assembly A or an electric valve connecting assembly B or a threaded connecting assembly C or a flange connecting assembly D, each of the sealed connection structures is sealed by a bag-type sealing diaphragm 6, and the edge 25 of each bag-type sealing diaphragm 6 is sealed and fixed to the outer surface of the high-pressure pipeline 1 at both ends of the connecting assembly by a cable tie or an adhesive tape 5, the connecting assembly is located inside the bag-type sealing diaphragm 6, the upper part of the bag-type sealing diaphragm 6 is integrally formed with an upper outlet pipe 7 connected to the interior for outlet leaked material gas, the lower part of the bag-type sealing diaphragm 6 is integrally formed with a lower outlet pipe 8 connected to the interior for outlet leaked material liquid, and the bag-type sealing diaphragm (6) is integrally formed with one or more upper outlet pipes (7) and one or more lower outlet pipes (8). Among them, the outlet port of the upper outlet pipe 7 is connected to an upper collecting pipe 11 through an upper one-way valve 10, and the output port of the lower outlet pipe 8 is connected to a lower collecting pipe 12 through a lower one-way valve 3. The output ports of the upper collecting pipe 11 and the lower collecting pipe 12 are both connected to the collecting end of a leaked material collecting device, and the output end of the leaked material collecting device is connected to the high-pressure pipeline 1 closest to the output end of the leaked material collecting device through a material pressurizing device, so as to send the collected leaked material back to the high-pressure pipeline 1.
[0052] When the connecting assembly is a manual valve connecting assembly A, the bag-type sealing diaphragm 6 is integrally formed with a sleeve 22 protruding outward and used to be sleeved on the valve stem 4 at the valve stem 4 of the corresponding manual valve. The sleeve 22 is sealed and fixed on the valve stem 4 by a cable tie or tape 5.
[0053] The leaked material collecting device includes: a gas material collecting bag 13 and a liquid material collecting box 15. The output port of the upper collecting tube 11 is connected to the collecting port of the gas material collecting bag 13, which is used to discharge the gas material in the leaked material into the gas material collecting bag 13. The output port of the lower collecting tube 12 is connected to the collecting port of the liquid material collecting box 15, which is used to discharge the liquid material 14 in the leaked material into the liquid material collecting box 15. A connecting pipe 23 connected to the liquid material collecting box 15 is formed at the bottom of the gas material collecting bag 13, which is used to discharge the liquid material 14 entering with the gas material into the liquid material collecting box 15. The gas discharge pipe 18 of the gas material collecting bag 13 and the liquid discharge pipe 26 of the liquid material collecting box 15 are respectively connected to the material suction port of the material pressurizing equipment.
[0054] The material pressurizing equipment includes: an explosion-proof air compressor 16 and an explosion-proof pump 17, wherein the suction port of the explosion-proof air compressor 16 is connected to the outlet end of the gas discharge pipe 18 of the gas material collecting bag 13 in the leaked material collecting device, and the suction port of the explosion-proof pump 17 is connected to the outlet end of the liquid discharge pipe 26 of the liquid material collecting box 15 in the leaked material collecting device. The discharge port of the explosion-proof air compressor 16 is connected to the high-pressure pipeline 1 closest to the output end of the leaked material collecting device through the high-pressure air pipe 19, and the discharge port of the pump 17 is connected to the high-pressure pipeline 1 closest to the output end of the leaked material collecting device through the high-pressure liquid pipe 27.
[0055] Two connecting holes 29 are formed on the high-pressure pipeline 1 closest to the output end of the leaked material collection device and located outside the bag-type sealing diaphragm 6. The two connecting holes 29 are connected to the inside of the high-pressure pipeline 1 and are respectively connected to the output port of the high-pressure gas pipe 19 and the output port of the high-pressure liquid pipe 27. Each of the connecting holes 29 is provided with a material introduction check valve 20.
[0056] like Figure 6 , Figure 8 As shown, the bag-type sealing diaphragm 6 includes a sheet-like membrane body 28, and the two side edges of the sheet-like membrane body 28 are connected to form a cylindrical structure by a corrosion-resistant sealing zipper 21 with a sealing tape formed integrally on the two side edges. An upper connecting hole 23 for connecting the upper outlet pipe 7 is formed on one side of the cylindrical structure, and a lower connecting hole 24 for connecting the lower outlet pipe 8 is formed on the other side of the cylindrical structure. The upper outlet pipe 7 and the lower outlet pipe 8 are respectively connected to the upper connecting hole 23 and the lower connecting hole 24 integrally formed with the sheet-like membrane body 28 and correspondingly.
[0057] like Figure 7 , Fig. 9As shown, when the connection assembly is a manual valve connection assembly A, a sleeve 22 protruding outward and used for sleeved on the valve stem 4 is integrally formed on the sheet-like membrane 28 at the valve stem 4 corresponding to the manual valve.
[0058] Although the materials in the equipment in the refinery and chemical plant are in a state of high temperature and high pressure, once leaked into the atmosphere, the pressure of the leaked material 9 instantly becomes normal pressure, and the temperature also decreases accordingly. The online repair system after the pipeline assembly seal failure of the present invention is to control the normal pressure leaked material 9 leaked from the sealing connection structure between the two high-pressure pipelines 1, whether in liquid or gaseous state, in a closed space and isolated from the atmosphere through the bag-type sealing diaphragm 6, because the edge 25 of the bag-type sealing diaphragm 6 is reliably sealed with the outer surface of the high-pressure pipeline 1 and the valve stem 4 by cable ties and tapes 5, and the leaked leaked material 9 is continuously sent to the gas material collection bag 13 and the liquid material collection box 15 by several upper outlet pipes 7 and lower outlet pipes 8 on the bag-type sealing diaphragm 6. The amount of leaked leaked material 9 is sent away as much as possible, so that the material in the bag-type sealing diaphragm 6 can be kept at normal pressure at all times (because the bag-type sealing diaphragm 6 is in a soft state, the internal and external pressures are balanced). Because the sheet-like membrane body 28 has an integrally formed sealing zipper and a plurality of upper and lower outlet pipes 7 and 8, it is very convenient to install the bag-type sealing diaphragm 6 on the outer surface of the high-pressure pipeline 1. Then, the pressure of the gas material is increased by the explosion-proof air compressor 16 to a pressure higher than the material pressure in the high-pressure pipeline 1 and then directly sent back to the high-pressure pipeline 1. At the same time, the pressure of the liquid material 14 is increased by the explosion-proof pump 17 to a pressure higher than the material pressure in the high-pressure pipeline 1 and then directly sent back to the high-pressure pipeline 1. This cycle is repeated to maintain zero leakage until the next shutdown and maintenance cycle arrives for substantial repair.
[0059] No matter how many sealing points there are, as long as the sealed materials are the same material of the same chemical device, the online repair system after the pipeline assembly seal failure of the present invention can be used to directly inject the collected materials back into the same high-pressure pipeline 1, which is both economical and convenient.
[0060] The upper outlet pipe 7 and the lower outlet pipe 8 can also be used to introduce a circulating liquid that is incompatible with the material to quickly carry the material out to improve the processing efficiency. The upper outlet pipe 7 and the lower outlet pipe 8 can also be used to introduce clean liquid or gas to flush the inside of the bag diaphragm system to keep the inside of the bag system unobstructed, intact and efficient.
[0061] The repair method of the online repair system after the pipeline assembly seal failure of the present invention is as follows: leaked material 9 at normal pressure leaked from the sealed connection structure between two high-pressure pipelines 1 is controlled in a closed space and isolated from the atmosphere by a bag-type sealing diaphragm 6, the edge 25 of the bag-type sealing diaphragm 6 is sealed with the outer surface of the high-pressure pipeline 1 and the valve stem 4 in the sealed connection structure by a cable tie and an adhesive tape 5, and the leaked material 9 is sent to a gas material collection bag 13 and a liquid material collection box 15 by an upper outlet pipe 7 and a lower outlet pipe 8 on the bag-type sealing diaphragm 6, and the material in the bag-type sealing diaphragm 6 is always kept at normal pressure; then the pressure of the gas material in the gas material collection bag 13 is increased by an explosion-proof air compressor 16 to a pressure higher than the material pressure in the high-pressure pipeline 1 and then directly sent back to the high-pressure pipeline 1, and at the same time, the pressure of the liquid material 14 in the liquid material collection box 15 is increased by an explosion-proof pump 17 to a pressure higher than the material pressure in the high-pressure pipeline 1 and then directly sent back to the high-pressure pipeline 1, and this cycle is repeated to maintain zero leakage until the next shutdown and maintenance cycle arrives for substantial repair.
Claims
1. An online repair system after a pipeline assembly seal failure, comprising a plurality of high-pressure pipelines (1) connected end to end to form a material conveying pipeline, wherein each two adjacent high-pressure pipelines (1) are connected to each other via a connecting assembly to form a sealed connection structure, wherein the connecting assembly is a manual valve connecting assembly (A) or an electric valve connecting assembly (B) or a threaded connecting assembly (C) or a flange connecting assembly (D), characterized in that: Each of the sealed connection structures is sealed by a bag-type sealing diaphragm (6), and the edge (25) of each of the bag-type sealing diaphragms (6) is sealed and fixed to the high-pressure pipelines (1) at both ends of the connection assembly by means of a cable tie or an adhesive tape (5). The connection assembly is located inside the bag-type sealing diaphragm (6), and the upper portion of the bag-type sealing diaphragm (6) is integrally formed with an upper outlet pipe (7) connected to the interior and used for outlet leaked material gas, and the lower portion of the bag-type sealing diaphragm (6) is integrally formed with a lower outlet pipe (8) connected to the interior and used for outlet leaked material liquid. ), wherein the outlet port of the upper outlet pipe (7) is connected to an upper collecting pipe (11) via an upper one-way valve (10), the output port of the lower outlet pipe (8) is connected to a lower collecting pipe (12) via a lower one-way valve (3), the output ports of the upper collecting pipe (11) and the lower collecting pipe (12) are both connected to the collecting end of a leaked material collecting device, and the output end of the leaked material collecting device is connected to the high-pressure pipeline (1) closest to the output end of the leaked material collecting device via a material pressurizing device, so as to return the collected leaked material to the high-pressure pipeline (1); The leaked material collecting device comprises: a gas material collecting bag (13) and a liquid material collecting box (15); the output port of the upper collecting pipe (11) is connected to the collecting port of the gas material collecting bag (13) for discharging gaseous material in the leaked material into the gas material collecting bag (13); the output port of the lower collecting pipe (12) is connected to the collecting port of the liquid material collecting box (15) for discharging liquid material (14) in the leaked material into the liquid material collecting box (15); a connecting pipe (23) connected to the liquid material collecting box (15) is formed at the bottom of the gas material collecting bag (13) for discharging liquid material (14) entering with the gas material into the liquid material collecting box (15); the gas discharge pipe (18) of the gas material collecting bag (13) and the liquid discharge pipe (26) of the liquid material collecting box (15) are respectively connected to the material suction port of the material pressurizing device; The material pressurizing device comprises: an explosion-proof air compressor (16) and an explosion-proof pump (17), wherein the suction port of the explosion-proof air compressor (16) is connected to the outlet end of the gas discharge pipe (18) of the gas material collection bag (13) in the leaked material collection device, and the suction port of the explosion-proof pump (17) is connected to the outlet end of the liquid discharge pipe (26) of the liquid material collection box (15) in the leaked material collection device. The discharge port of the explosion-proof air compressor (16) is connected to the high-pressure pipeline (1) closest to the output end of the leaked material collection device through a high-pressure gas pipe (19), and the discharge port of the explosion-proof pump (17) is connected to the high-pressure pipeline (1) closest to the output end of the leaked material collection device through a high-pressure liquid pipe (27).
2. The online repair system after pipeline component seal failure according to claim 1 is characterized in that: When the connection assembly is a manual valve connection assembly (A), the bag-type sealing diaphragm (6) is integrally formed with a sleeve (22) protruding outwards and used for sleeved on the valve stem (4) at the valve stem (4) corresponding to the manual valve, and the sleeve (22) is sealed and fixed on the valve stem (4) by a cable tie or an adhesive tape (5).
3. The online repair system after pipeline component seal failure according to claim 1 is characterized in that: One or more upper outlet pipes (7) and one or more lower outlet pipes (8) are integrally formed on the bag-type sealing diaphragm (6).
4. The online repair system after pipeline component seal failure according to claim 1 is characterized in that: Two connecting holes (29) are formed on the high-pressure pipeline (1) closest to the output end of the leaked material collection device and located outside the bag-type sealing diaphragm (6), which are connected to the inside of the high-pressure pipeline (1) and are respectively connected to the output port of the high-pressure gas pipe (19) and the output port of the high-pressure liquid pipe (27).
5. The online repair system after seal failure of pipeline components according to claim 4 is characterized in that: Each of the communication holes (29) is provided with a material introduction one-way valve (20).
6. The online repair system after pipeline component seal failure according to claim 1 is characterized in that: The bag-type sealing diaphragm (6) comprises a sheet-like membrane body (28), the two side edges of the sheet-like membrane body (28) being connected to form a cylindrical structure by means of a corrosion-resistant sealing zipper (21) with a sealing tape formed integrally on the two side edges, an upper connecting hole (23) for connecting the upper outlet pipe (7) being formed on one side of the cylindrical structure, and a lower connecting hole (24) for connecting the lower outlet pipe (8) being formed on the other side of the cylindrical structure, the upper outlet pipe (7) and the lower outlet pipe (8) being respectively connected to the upper connecting hole (23) and the lower connecting hole (24) in a manner integrally formed with the sheet-like membrane body (28).
7. The online repair system after seal failure of pipeline components according to claim 6, characterized in that: When the connection assembly is a manual valve connection assembly (A), a sleeve (22) protruding outwards and used for sleeved on the valve stem (4) is integrally formed on the sheet-like membrane (28) at the valve stem (4) corresponding to the manual valve.
8. A method for repairing an online repair system after seal failure of a pipeline assembly according to claim 1, characterized in that: The leaked material (9) at normal pressure leaking from the sealed connection structure between the two high-pressure pipelines (1) is controlled in a closed space and isolated from the atmosphere by a bag-type sealing diaphragm (6). The edge (25) of the bag-type sealing diaphragm (6) is sealed with a cable tie and an adhesive tape (5) to the outer surface of the high-pressure pipeline (1) in the sealed connection structure and the valve stem (4). The upper outlet pipe (7) and the lower outlet pipe (8) on the bag-type sealing diaphragm (6) are used to send the leaked material (9) to the gas material collection bag (13) and the liquid material collection box (15), and the leaked material (9) is kept at all times. The material in the bag-type sealing diaphragm (6) is at normal pressure. Then, the pressure of the gas material in the gas material collection bag (13) is increased by an explosion-proof air compressor (16) to a pressure higher than the pressure of the material in the high-pressure pipeline (1) and then directly sent back to the high-pressure pipeline (1). At the same time, the pressure of the liquid material (14) in the liquid material collection box (15) is increased by an explosion-proof pump (17) to a pressure higher than the pressure of the material in the high-pressure pipeline (1) and then directly sent back to the high-pressure pipeline (1). This cycle is repeated to maintain zero leakage until the next shutdown and maintenance cycle arrives for substantial repair.