A monitoring system and method for a cantilever external protection frame
By installing BIM information sheets and a central processor monitoring system at key parts of the cantilevered external protection frame, real-time data collection and management have solved the potential safety hazards of the cantilevered external protection frame in the construction of high-rise buildings and achieved a timely implementation of the construction process. Improved control and security.
Patent Information
- Application Number
- CN202010395065.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2020-05-12
- Publication Date
- 2024-10-18
- Estimated Expiration
- 2040-05-12
AI Technical Summary
In the construction of high-rise and super-high-rise buildings, cantilevered external protective frames are prone to potential safety hazards such as azimuth deviations, unstable connections, and component failures during the construction process. Real-time and effective safety monitoring is required to prevent engineering accidents.
A monitoring system including multiple BIM information pieces, central processors, display devices and alarm devices is used to collect data in real time through position sensors, stress sensors and strain sensors attached to key parts of the cantilevered external protective frame, and through wireless communication with The central processor is connected to establish a BIM data model, display and manage construction status in real time, and issue alarms in a timely manner.
It realizes the monitoring of the real-time position and stress and strain of the cantilevered external protection frame, timely and accurate control and management of the construction process, reduces safety hazards, avoids the problem of information omission and re-collection, and improves construction safety.
Smart Images

Figure CN111535570B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of building construction, and in particular to a monitoring system and method for a cantilever external protective frame. Background Art
[0002] With the development of society, the original integral lifting scaffolding can no longer meet the complex architectural shapes and structures required by high-rise and super-high-rise buildings, so a new type of cantilever external protective frame system has emerged. Figure 1 As shown, this protection frame system includes a frame body 1, a cantilever 2 fixedly connected to the frame body 1, and an adjustable fastening clamp 3, wherein the fastening clamp 3 is used to fix the cantilever 2 to the beam-column system of the building, wherein the beam-column system is composed of a structural column 4 and a structural steel beam 5. This protection frame system is hoisted and climbed by a tower crane to carry out construction operations. However, due to the complex structure of high-rise and super-high-rise buildings, there are many uncertain factors during the construction process, and the connection between the fastening clamp 3 and the building structure is prone to safety risks. The protection frame system is prone to safety hazards such as orientation deviation, unstable connection, and component failure during the construction process, and real-time and effective safety monitoring is required to prevent the occurrence of engineering accidents.
[0003] Therefore, how to provide a safe and effective monitoring system and method for a cantilever external protection frame is a technical problem that needs to be solved urgently by those skilled in the art. Summary of the invention
[0004] The present invention provides a monitoring system and method for a cantilever external protection frame to solve the above technical problems.
[0005] In order to solve the above technical problems, the present invention provides a monitoring system for a cantilever external protection frame, comprising: a detection device, comprising a plurality of BIM information sheets, wherein the plurality of BIM information sheets are correspondingly pasted on key parts of the cantilever external protection frame;
[0006] A central processing unit is connected to the plurality of BIM information pieces by signal, and the central processing unit is used to establish a BIM data model and debug the BIM data model using information collected by the BIM information pieces;
[0007] a display device, connected to the CPU signal and used to display the processing result of the CPU; and
[0008] The alarm device is connected to the central processing unit signal and is used to issue an alarm when the processing result of the central processing unit exceeds a preset value.
[0009] Preferably, the BIM information sheet includes at least a position sensor, a stress sensor and a strain sensor.
[0010] Preferably, the key parts of the cantilever external protection frame at least include the cantilever beam and the fastening clamp.
[0011] Preferably, a wireless transmitter is installed on the BIM information sheet, and a corresponding wireless receiver is installed on the central processing unit.
[0012] The present invention also provides a monitoring method for a cantilever external protection frame, comprising the following steps:
[0013] Step 11: Install multiple BIM information sheets at key locations of the cantilever external protection frame;
[0014] Step 12: The central processing unit receives and processes the data transmitted by the BIM information sheet, and determines whether the actual installation position of the cantilever external protective frame is within the tolerance range of the predetermined installation position. If it exceeds the tolerance range, an alarm is issued, and the on-site construction personnel adjust the actual installation position of the cantilever external protective frame, and return to step 11; if it does not exceed the tolerance range, proceed to the next step;
[0015] Step 13: The central processor detects whether the stress and strain of the cantilever external protection frame is within the tolerance range. If it is beyond the tolerance range, an alarm is issued to guide the on-site staff to check the safety problem. After the check is completed, return to step 11; if it is within the tolerance range, proceed to the next step;
[0016] Step 14: Continue construction until it is completed.
[0017] Preferably, the method for obtaining the predetermined installation position of the cantilever external protection frame and its corresponding tolerance range, as well as the stress-strain condition and its corresponding tolerance range comprises:
[0018] Step 21: Establish the BIM data model of the building structure;
[0019] Step 22: using a plurality of BIM information sheets attached to key parts of the cantilever external protective frame to collect BIM data model information and load information of the cantilever external protective frame, and inputting the BIM data model information and load information into the BIM data model of the building structure;
[0020] Step 23: judging whether there is an internal collision at the predetermined installation position of the cantilever external protection frame according to the BIM data model information of the cantilever external protection frame, and if there is an internal collision, returning to step 22 to adjust the BIM data model information of the cantilever external protection frame; if there is no internal collision, proceeding to the next step;
[0021] Step 24: Calculate whether the stress and strain of the cantilever external protection frame exceeds the safety range according to the load information of the cantilever external protection frame. If yes, return to step 22 to adjust the BIM data model information of the cantilever external protection frame; if no, proceed to the next step;
[0022] Step 25: Output the predetermined installation position of the cantilever external protection frame and its corresponding tolerance range, as well as the stress-strain condition and its corresponding tolerance range.
[0023] Preferably, the BIM information sheet includes at least a position sensor, a stress sensor and a strain sensor.
[0024] Preferably, the key parts of the cantilever external protection frame at least include the cantilever beam and the fastening clamp.
[0025] Preferably, the BIM information sheet communicates with the central processor via a wireless device.
[0026] Compared with the prior art, the monitoring system and method of the cantilever external protection frame provided by the present invention has the following advantages:
[0027] 1. The present invention can display the installation position of the protection frame and the stress and strain conditions of the key parts in real time by pasting BIM information sheets on the key parts of the cantilever external protection frame. By comparing with the BIM data model established in the early stage, the construction status of the protection frame can be controlled and managed in a timely and accurate manner;
[0028] 2. BIM information sheets can be replaced in time when problems occur, and the data before replacement is saved to the central processor through real-time transmission, which can avoid information omission and re-collection problems;
[0029] 3. BIM information sheets can collect information such as location, stress and strain in real time and use wireless transmission technology to transmit data without manual operation, which is timely, convenient and fast. BRIEF DESCRIPTION OF THE DRAWINGS
[0030] Figure 1 It is a structural schematic diagram of the cantilever external protection frame system;
[0031] Figure 2 It is a structural schematic diagram of a monitoring system of a cantilever external protection frame in a specific embodiment of the present invention;
[0032] Figure 3 It is a schematic flow chart of a monitoring method of a cantilever external protection frame in a specific embodiment of the present invention;
[0033] Figure 4The figure is a flow chart of establishing and debugging a BIM data model in a specific implementation manner of the present invention.
[0034] In the figure: 1-frame, 2-cantilever, 3-fastening clamp, 4-structural column, 5-structural steel beam; 10-BIM information sheet, 20-central processing unit, 30-display device, 40-alarm device. DETAILED DESCRIPTION
[0035] In order to describe the technical solution of the above invention in more detail, specific embodiments are listed below to demonstrate the technical effect; it should be emphasized that these embodiments are used to illustrate the present invention but are not limited to the scope of the present invention.
[0036] The monitoring system of the cantilever external protection frame provided by the present invention is as follows: Figure 2 As shown, it includes: a detection device, the detection device includes multiple BIM (Building Information Modeling) information sheets 10, the BIM information sheets at least include position sensors, stress sensors and strain sensors, etc., the multiple BIM information sheets 10 are correspondingly pasted on key parts of the cantilever external protective frame, the key parts include at least the cantilever beam and the fastening clamp 3, the BIM information sheet 10 can be used to detect the position and stress and strain of the cantilever 2, the position and stress and strain of the fastening clamp 3 and other information in real time.
[0037] The central processor 20 is connected to the plurality of BIM information sheets 10 by signal. In this embodiment, a wireless transmitter is installed on the BIM information sheet 10, and a corresponding wireless receiver is installed on the central processor 20. The BIM information sheet 10 communicates with the central processor 20 via a wireless device. The central processor 20 is used to establish a BIM data model and debug the BIM data model using the information collected by the BIM information sheet.
[0038] A display device 30 is connected to the central processor 20 for displaying the processing result of the central processor 20; and an alarm device 40 is connected to the central processor 20 for issuing an alarm when the processing result of the central processor 20 exceeds a preset value.
[0039] The present invention pastes the BIM information sheet 10 on the key parts of the cantilever external protection frame. During the construction process, the BIM information sheet 10 can collect stress, strain and other information in real time and transmit it to the central processor 20. The central processor 20 displays the operation status of the protection frame through the display device 30, and alarms through the alarm device 40 when the stress and strain are abnormal or exceed the reasonable range, so as to timely and accurately control and manage the construction status of the protection frame. The BIM information sheet 10 can collect information in real time and use wireless transmission technology to transmit data without manual operation, which is timely, convenient and fast. The BIM information sheet 10 is easy to replace. It only needs to save the previous data transmission to the central processor to avoid the problem of missing information and re-collection.
[0040] The present invention also provides a monitoring method for a cantilever external protection frame, please refer to Figure 3 Combined with Figure 2 , including the following steps:
[0041] Step 11: Install multiple BIM information sheets 10 at key positions of the cantilever external protection frame, wherein the BIM information sheets 10 include at least a position sensor, a stress sensor, and a strain sensor, etc. The key positions include at least the cantilever beam and the fastening fixture 3, and the multiple BIM information sheets 10 are used to measure the position, stress, strain and other information of the key positions respectively;
[0042] Step 12: The central processor 20 receives and processes the data transmitted by the BIM information sheet 10. Specifically, the BIM information sheet 10 communicates with the central processor 20 via wireless devices, without manual operation, in a timely, convenient and fast manner. The central processor 20 determines whether the actual installation position of the cantilever external protective frame is within the tolerance range of the predetermined installation position. If it exceeds the tolerance range, an alarm is issued, and the on-site construction personnel adjust the actual installation position of the cantilever external protective frame and return to step 11; if it does not exceed the tolerance range, proceed to the next step;
[0043] Step 13: The central processor 10 detects whether the stress and strain of the cantilever external protection frame is within the tolerance range. If it is beyond the tolerance range, an alarm is issued to guide the on-site staff to check the safety problem. After the check is completed, the process returns to step 11; if it is within the tolerance range, the process proceeds to the next step;
[0044] Step 14: Continue construction until it is completed.
[0045] Preferably, please focus on Figure 4 , a method for establishing and debugging a BIM data model, that is, a method for obtaining a predetermined installation position of the cantilever external protection frame and its corresponding tolerance range, as well as a stress-strain condition and its corresponding tolerance range, includes:
[0046] Step 21: Establish a BIM data model of the building structure, input information such as the building structure, protective frame, and engineering load, determine the connection position between the building structure and the protective frame, and the stress and strain of key parts of the protective frame. During the building design process, the connection position of the protective frame with the building structure in actual construction, the installation of the fastening fixture 3 and other construction information can be determined in advance, and guidance can be provided for subsequent construction during the design stage to prevent accidents such as collisions in advance.
[0047] Step 22: using a plurality of BIM information sheets 10 attached to key parts of the cantilever external protective frame to collect BIM data model information and load information of the cantilever external protective frame, inputting the BIM data model information and load information into the BIM data model of the building structure, and determining the stress and strain conditions of key parts during the construction process;
[0048] Step 23: judging whether there is an internal collision at the predetermined installation position of the cantilever external protection frame according to the BIM data model information of the cantilever external protection frame, and if there is an internal collision, returning to step 22 to adjust the BIM data model information of the cantilever external protection frame; if there is no internal collision, proceeding to the next step;
[0049] Step 24: Calculate whether the stress and strain of the cantilever external protective frame exceeds the safety range according to the load information of the cantilever external protective frame. If yes, return to step 22 to adjust the BIM data model information of the cantilever external protective frame, such as adjusting the number and position of the fastening clamps 3; if no, proceed to the next step;
[0050] Step 25: Output the predetermined installation position of the cantilever external protection frame and its corresponding tolerance range, as well as the stress-strain condition and its corresponding tolerance range.
[0051] The present invention can connect the data, processes and resources of different stages of the construction project life cycle by establishing a complete information model, which can be widely used by all parties involved in the construction project. By establishing an integrated management environment for construction projects through the BIM data model, the efficiency of the construction project in the entire process can be significantly improved, and the risks can be greatly reduced.
[0052] In summary, the monitoring system and method of the cantilever external protective frame provided by the present invention comprises a detection device, including a plurality of BIM information sheets 10, wherein the plurality of BIM information sheets 10 are correspondingly pasted on key parts of the cantilever external protective frame; a central processing unit 20, which is connected to the plurality of BIM information sheets 10 by signal, and the central processing unit 20 is used to establish a BIM data model and debug the BIM data model using the information collected by the BIM information sheets 10; a display device 30, which is connected to the central processing unit 20 by signal, and is used to display the processing result of the central processing unit 20; and an alarm device 40, which is connected to the central processing unit 20 by signal, and is used to sound an alarm when the processing result of the central processing unit 20 exceeds a preset value. The present invention can display the position of the protective frame and the stress and strain conditions of the key parts in real time by pasting the BIM information sheets 10 on the key parts of the cantilever external protective frame, and can timely and accurately control and manage the construction status of the protective frame by comparing with the BIM data model established in the early stage.
[0053] Obviously, those skilled in the art can make various changes and modifications to the invention without departing from the spirit and scope of the invention. Thus, if these modifications and variations of the invention fall within the scope of the claims of the invention and their equivalents, the invention is also intended to include these modifications and variations.
Claims
1. A monitoring system for a cantilever external protection frame, characterized in that: include: A detection device, comprising a plurality of BIM information sheets, wherein the plurality of BIM information sheets are correspondingly pasted on key parts of the cantilever external protective frame; A central processing unit is connected to the plurality of BIM information pieces by signal, and the central processing unit is used to establish a BIM data model and debug the BIM data model using information collected by the BIM information pieces; A display device, connected to the central processing unit by signal, for displaying the processing result of the central processing unit; as well as An alarm device, connected to the central processing unit signal, for issuing an alarm when the processing result of the central processing unit exceeds a preset value; The implementation method of the monitoring system comprises the following steps: Step 11: Install multiple BIM information sheets at key locations of the cantilever external protection frame; Step 12: The central processing unit receives and processes the data transmitted by the BIM information sheet, and determines whether the actual installation position of the cantilever external protective frame is within the tolerance range of the predetermined installation position. If it exceeds the tolerance range, an alarm is issued, and the on-site construction personnel adjust the actual installation position of the cantilever external protective frame, and return to step 11; if it does not exceed the tolerance range, proceed to the next step; The method for obtaining the predetermined installation position of the cantilever external protection frame and its corresponding tolerance range, as well as the stress-strain condition and its corresponding tolerance range includes: Step 21: Establish the BIM data model of the building structure; Step 22: using a plurality of BIM information sheets attached to key parts of the cantilever external protective frame to collect BIM data model information and load information of the cantilever external protective frame, and inputting the BIM data model information and load information into the BIM data model of the building structure; Step 23: judging whether there is an internal collision at the predetermined installation position of the cantilever external protection frame according to the BIM data model information of the cantilever external protection frame, and if there is an internal collision, returning to step 22 to adjust the BIM data model information of the cantilever external protection frame; if there is no internal collision, proceeding to the next step; Step 24: Calculate whether the stress and strain of the cantilever external protection frame exceeds the safety range according to the load information of the cantilever external protection frame. If yes, return to step 22 to adjust the BIM data model information of the cantilever external protection frame; if no, proceed to the next step; Step 25: outputting the predetermined installation position of the cantilever external protection frame and its corresponding tolerance range, as well as the stress-strain condition and its corresponding tolerance range; Step 13: The central processor detects whether the stress and strain of the cantilever external protection frame is within the tolerance range. If it is beyond the tolerance range, an alarm is issued to guide the on-site staff to check the safety problem. After the check is completed, return to step 11; if it is within the tolerance range, proceed to the next step; Step 14: Continue construction until it is completed.
2. The monitoring system of the cantilever external protection frame according to claim 1, characterized in that: The BIM information sheet includes at least a position sensor, a stress sensor and a strain sensor.
3. The monitoring system of the cantilever external protection frame according to claim 1, characterized in that: The key parts of the cantilever external protection frame at least include the cantilever beam and the fastening clamp.
4. The monitoring system of the cantilever external protection frame according to claim 1, characterized in that: A wireless transmitter is installed on the BIM information sheet, and a corresponding wireless receiver is installed on the central processing unit.
Citation Information
Patent Citations
Automatic monitoring system for scaffold having higher danger coefficient and automatic monitoring method thereof
CN106404229A
Monitoring system of cantilever type externally-hung protective frame
CN212642090U