Chamber support structure and chamber

By adopting a reinforced concrete arch structure in the large-section cave, the problem of poor support effect of thick and soft rock layers is solved, and the construction space is small, difficult, good quality and low cost are achieved, ensuring the stability of the cave. properties and surrounding rock stability.

CN111648795BActive Publication Date: 2024-10-18CHINA ENFI ENG CORP
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
CN202010494648.4
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2020-06-03
Publication Date
2024-10-18
Estimated Expiration
2040-06-03

AI Technical Summary

Technical Problem

The existing large-section tunnels have poor support effects in thick and soft rock strata. They require pull-out tests and are expensive. They have large construction spaces, insufficient support for the middle and lower side walls, difficulty in sealing, and difficult to control the construction quality.

Method used

Use reinforced concrete and a reinforced concrete arch frame set outside the cave, including arch beams, columns and foundation parts, to form an integrated structure through pouring, which is synchronized with the construction of the cave wall, increasing the reinforcement of the top and side walls, and reducing large-scale mechanical operations , reduce construction space and cost.

Benefits of technology

The stability of the chamber has been improved, the construction space is small, the difficulty is low, the quality is good, the cost is reduced, and the stability of the surrounding rock and the efficiency of the chamber excavation are improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN111648795B_ABST
    Figure CN111648795B_ABST
Patent Text Reader

Abstract

The present invention provides a chamber support structure and a chamber, comprising: reinforced concrete and a reinforced concrete arch frame arranged outside the chamber; wherein the reinforced concrete arch frame comprises an arch beam arranged outside the top of the chamber, columns arranged at both ends of the bottom of the arch beam, and a foundation arranged at the bottom of the column; the column is arranged on the outer wall of the chamber; the arch beam and the column form an integrated structure with the top of the chamber and the side wall of the chamber by pouring reinforced concrete. The present invention can solve the problems that the current joint support method of spray anchor net + anchor cable + reinforced concrete has poor support effect in thick and soft rock formations, requires a pull-out test for the anchor cable, and has high construction cost; requires equipment for drilling holes and setting up anchor cables, and requires a large construction space; has less support for the middle and lower side walls of the chamber; has great sealing difficulty, and is difficult to control construction quality.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of mine engineering support, and more specifically, to a chamber support structure and a chamber. Background Art

[0002] As the mining depth of mines in my country continues to increase, the surrounding rock of deep tunnels is increasingly affected by the "three highs and one disturbance"; at the same time, due to the continuous expansion of mining scale, the excavation section of underground chambers is getting larger and larger. The excavation and support of deep large-section chambers is a dynamic construction process that changes with time and space. The stress of the surrounding rock of the chamber shows nonlinear characteristics, with obvious stress concentration and a large range of surrounding rock damage. Large-section chambers often serve the entire mine, have a long service life, and play an important role. The stability of the chamber is one of the main factors restricting the efficient and safe production of mines. Therefore, the support of large-section chambers underground is one of the key points to ensure the safe production of mines. Therefore, when selecting a site for a mining project, a location with better rock conditions is generally selected to arrange a large-section chamber.

[0003] Judging from the existing large-section chamber support design, most of its combined support contains anchor cable support, and the support effect is quite good. When the rock formation is good, the joint support type of shotcrete mesh + anchor cable or anchor cable + concrete is adopted; when the rock formation conditions are poor, the joint support method of shotcrete mesh + anchor cable + reinforced concrete is adopted; the anchor cable plays a great role in the above support methods. However, affected by the layout of the mining engineering system, some large-section chambers can only be excavated in thick and soft rocks (such as mudstone, coal seam, sandstone, and rock formations that are easily weathered or softened by water). In such cases, the anchor cable support effect is not ideal.

[0004] For large-section chambers, the support type of shotcrete + anchor cable + reinforced concrete has the following disadvantages:

[0005] 1. It is necessary to conduct a pull-out test on the anchor cable, and the cost of anchor cable construction is high;

[0006] 2. Equipment that requires drilling and anchoring requires a larger construction space;

[0007] 3. The anchor cable support area is generally the chamber arch and the upper part of the side wall, and the support for the middle and lower side walls is less;

[0008] 4. It is difficult to construct the anchor cable of the chamber arch, especially the anchor cable mortar anchoring time is long and the sealing of the opening is difficult, and the construction quality is difficult to control;

[0009] 5. The supporting effect of anchor cables in thick and soft rock layers cannot be guaranteed, resulting in poor results or even failure. Summary of the invention

[0010] In view of the above problems, the purpose of the present invention is to provide a chamber support structure and a chamber to solve the problems that the current combined support method of shotcrete mesh + anchor cable + reinforced concrete has poor support effect in thick and soft rock formations, requires a pull-out test on the anchor cable, and has high construction costs; equipment for drilling and installing anchor cables is required, and a larger construction space is required; there is less support for the middle and lower side walls of the chamber; sealing is difficult, and construction quality is difficult to control, etc.

[0011] The present invention provides a cavern support structure, comprising reinforced concrete and a reinforced concrete arch frame arranged outside the cavern; wherein the reinforced concrete arch frame comprises an arch beam arranged outside the top of the cavern, columns arranged at both ends of the bottom of the arch beam and a base portion arranged at the bottom of the column; the column is arranged on the outer wall of the cavern; the arch beam and the column form an integrated structure with the top of the cavern and the side wall of the cavern through the pouring of the reinforced concrete.

[0012] In addition, a preferred solution is to further include a sprayed anchor net arranged outside the reinforced concrete arch frame.

[0013] In addition, a preferred solution is that the shape of the arch beam is the same as the shape of the top end of the chamber.

[0014] In addition, a preferred solution is that the arch beam is formed by at least two beam steel bars bundled together through beam reinforcement; and / or the column is formed by at least two column steel bars bundled together through column reinforcement.

[0015] In addition, a preferred solution is that the arch beam is connected to the top of the chamber by overlapping the beam reinforcement and the top reinforcement of the chamber; the column is connected to the side wall of the chamber by overlapping the column reinforcement and the side wall reinforcement of the chamber.

[0016] In addition, a preferred solution is that the arch beam and the column form an integrated structure with the inner side of the top end of the chamber and the side wall of the chamber by pouring the reinforced concrete on the inner side of the top end of the chamber and the inner wall of the chamber.

[0017] In addition, a preferred solution is that the arch beam is overlapped and connected to the column.

[0018] In addition, a preferred solution is that the foundation portion includes a basic base plate and a column fixing structure arranged on the top of the basic base plate.

[0019] The present invention provides a chamber, comprising a chamber body and a chamber bottom plate arranged at the bottom of the chamber body; the chamber support structure as described above is arranged on the side walls and the top of the chamber body.

[0020] In addition, a preferred solution is that the base portion is arranged on the bottom plate of the chamber.

[0021] From the above technical scheme, it can be known that the chamber support structure and the chamber provided by the present invention are made of reinforced concrete and a reinforced concrete arch frame arranged outside the chamber; the reinforced concrete arch frame includes an arch beam arranged outside the top of the chamber, columns arranged at both ends of the bottom of the arch beam, and a foundation arranged at the bottom of the column; the column is arranged on the outer wall of the chamber; the arch beam and the column form an integrated structure with the top of the chamber and the side wall of the chamber by pouring reinforced concrete. The construction can be cast synchronously with the chamber wall, and the support structure has good integrity; during the support process, there is no large-scale mechanical operation; the reinforced concrete arch frame reinforces the top and side walls of the chamber, which can ensure the stability of the entire chamber; it has the advantages of small construction space, low construction difficulty, good construction quality control, and is conducive to the stability of the entire surrounding rock and the excavation of the chamber, and low cost.

[0022] In order to achieve the above and related purposes, one or more aspects of the present invention include the features that will be described in detail later. The following description and the accompanying drawings describe some exemplary aspects of the present invention in detail. However, these aspects indicate only some of the various ways in which the principles of the present invention can be used. In addition, the present invention is intended to include all these aspects and their equivalents. BRIEF DESCRIPTION OF THE DRAWINGS

[0023] By referring to the following description in conjunction with the accompanying drawings, and with a more comprehensive understanding of the present invention, other objects and results of the present invention will become more apparent and easy to understand. In the accompanying drawings:

[0024] Figure 1 Schematic diagram of the structure of a chamber support structure according to an embodiment of the present invention;

[0025] Figure 2 for Figure 1 A schematic diagram of part II-II;

[0026] Figure 3 for Figure 1 Schematic diagram of part III-III.

[0027] In the attached drawings, 1-chamber main body, 11-chamber floor, 2-reinforced concrete arch frame, 21-arch beam, 22-column, 23-foundation, 3-reinforced concrete, 4-sprayed anchor net, 5-corbel column.

[0028] The same reference numerals throughout the drawings indicate similar or corresponding features or functions. DETAILED DESCRIPTION

[0029] In the following description, for the purpose of explanation, numerous specific details are set forth in order to provide a thorough understanding of one or more embodiments. However, it is apparent that these embodiments may also be implemented without these specific details.

[0030] In view of the above-mentioned problems that the current combined support method of shotcrete mesh + anchor cable + reinforced concrete has a poor support effect in thick and soft rock formations, and needs to carry out a pull-out test on the anchor cable, and the cost of anchor cable construction is high; equipment for drilling holes and setting up anchor cables is required, and a larger construction space is needed; there is less support for the middle and lower side walls of the chamber; sealing is difficult, and construction quality is difficult to control, etc., a chamber support structure and a chamber are proposed. The chamber support structure and the chamber of the present invention can solve the problems that the current combined support method of shotcrete mesh + anchor cable + reinforced concrete has a poor support effect in thick and soft rock formations, and needs to carry out a pull-out test on the anchor cable, and the cost of anchor cable construction is high; equipment for drilling holes and setting up anchor cables is required, and a larger construction space is needed; there is less support for the middle and lower side walls of the chamber; sealing is difficult, and construction quality is difficult to control, etc.

[0031] The specific embodiments of the present invention will be described in detail below with reference to the accompanying drawings.

[0032] In order to illustrate the chamber support structure and the chamber provided by the present invention, Figure 1 The structure of the chamber support structure according to the embodiment of the present invention is shown; Figure 2 Shows Figure 1 The structure of part II-II; Figure 3 Shows Figure 1 The structure of part III-III.

[0033] like Figures 1 to 3 As shown together, the cavern support structure provided by the present invention includes reinforced concrete 3 and a reinforced concrete arch frame 2 arranged outside the cavern; wherein, the reinforced concrete arch frame 2 includes an arch beam 21 arranged outside the top of the cavern, columns 22 arranged at both ends of the bottom of the arch beam 21, and a base portion 23 arranged at the bottom of the column 22; the column 22 is arranged on the outer wall of the cavern; the arch beam 21 and the column 22 form an integrated structure with the top and side walls of the cavern through the pouring of the reinforced concrete 3.

[0034] Through reinforced concrete 3 and reinforced concrete arch frame 2 set outside the cavern; reinforced concrete arch frame 2 includes arch beam 21 set outside the top of the cavern, columns 22 set at both ends of the bottom of arch beam 21 and base 23 set at the bottom of column 22; column 22 is set on the outer wall of the cavern; arch beam 21 and column 22 form an integrated structure with the top of the cavern and the side wall of the cavern by pouring reinforced concrete 3. It can be poured and constructed synchronously with the cavern wall, and the support structure has good integrity; during the support process, there is no large-scale mechanical operation; the reinforced concrete arch frame reinforces the top and side walls of the cavern, which can ensure the stability of the entire cavern; it has the advantages of small construction space, low construction difficulty, good construction quality control, conducive to the stability of the entire surrounding rock and cavern excavation, and low cost.

[0035] Among them, the reinforced concrete arch frame 2 calculates the height of the loose circle according to the loose circle theory, and obtains the external force load of the entire chamber; in the direction perpendicular to the width of the chamber, the number and spacing of the reinforced concrete arch frames are reasonably arranged, and the spacing must meet the construction space and ensure that the specifications of the reinforced concrete arch frames are not too large; according to the external load of each reinforced concrete arch frame, its overall dimensions, concrete grade and reinforcement parameters are calculated, which include arch beam design, column design and foundation design.

[0036] As a preferred solution of the present invention, it also includes a sprayed anchor net 4 arranged outside the reinforced concrete arch frame 2. According to the engineering analogy method, combined with the span and height of the chamber and the quality grade of the rock engineering and the "Technical Specifications for Rock and Soil Anchors and Sprayed Concrete Support Engineering", the relevant technical parameters of the sprayed anchor net 4 are determined; the technical parameters include the thickness and strength grade of the sprayed concrete, the specifications of the anchors and the arrangement spacing. The sprayed anchor net 4 can not only seal the rock layer to prevent the rock layer from weathering and falling off, but also reinforce the broken loose circle so that the loose circle forms a natural rock arch to resist external stress.

[0037] As a preferred solution of the present invention, the shape of the arch beam 21 is the same as the top shape of the chamber, so that the two can be better combined.

[0038] As a preferred embodiment of the present invention, the arch beam 21 is formed by at least two beam steel bars tied together by beam reinforcement; and / or, the column 22 is formed by at least two column steel bars tied together by column reinforcement. In order to enable the reinforced concrete arch frame 2 to achieve the bearing strength required for construction, during the design process, it can be set according to the calculation of relevant technical parameters. However, in general, in order to ensure the bearing strength of the reinforced concrete arch frame 2, the arch beam 21 is composed of at least two beam steel bars, and the column 22 is composed of at least two column steel bars. The beam reinforcement and the column reinforcement not only play the role of tying the beam reinforcement and the column reinforcement, but also are used for overlapping with the reinforcement of the chamber.

[0039] As a preferred solution of the present invention, the arch beam 21 is overlapped with the top of the chamber through beam reinforcement and the top reinforcement of the chamber; the column 22 is overlapped with the side wall of the chamber through column reinforcement and the side wall reinforcement of the chamber. During the construction process, the reinforcement (beam reinforcement and column reinforcement) of the reinforced concrete arch frame 2 and the chamber wall reinforcement (top and side wall) of the chamber are overlapped according to the design to ensure the integrity of the reinforced concrete arch frame 2 and the chamber wall of the chamber.

[0040] As a preferred solution of the present invention, the arch beam 21 and the column 22 form an integrated structure with the top inner side of the chamber and the side wall of the chamber by pouring the reinforced concrete 3 on the top inner side of the chamber and the inner wall of the chamber. Pouring on the inner wall of the chamber makes the construction more convenient and does not affect the appearance of the chamber.

[0041] As a preferred solution of the present invention, the arch beam 21 is overlapped with the column 22. The arch beam 21 and the column 22, and the column 22 and the foundation 23 can be overlapped by reinforcement according to the design to ensure the integrity of the reinforced concrete arch frame 2.

[0042] As a preferred solution of the present invention, the foundation part 23 includes a foundation bottom plate and a column fixing structure arranged on the top of the foundation bottom plate. The foundation bottom plate and the column fixing structure facilitate the construction of the column. Among them, the force on the foundation bottom plate should be less than the compressive strength of the rock, otherwise the size of the foundation bottom plate should be increased.

[0043] The present invention provides a chamber, comprising a chamber body 1 and a chamber bottom plate 11 arranged at the bottom of the chamber body 1; the chamber support structure 2 as described above is arranged on the side walls and the top of the chamber body 11.

[0044] Through reinforced concrete 3 and reinforced concrete arch frame 2 set outside the cavern; reinforced concrete arch frame 2 includes arch beam 21 set outside the top of the cavern, columns 22 set at both ends of the bottom of arch beam 21 and base 23 set at the bottom of column 22; column 22 is set on the outer wall of the cavern; arch beam 21 and column 22 form an integrated structure with the top of the cavern and the side wall of the cavern by pouring reinforced concrete 3. It can be poured and constructed synchronously with the cavern wall, and the support structure has good integrity; during the support process, there is no large-scale mechanical operation; the reinforced concrete arch frame reinforces the top and side walls of the cavern, which can ensure the stability of the entire cavern; it has the advantages of small construction space, low construction difficulty, good construction quality control, conducive to the stability of the entire surrounding rock and cavern excavation, and low cost.

[0045] As a preferred solution of the present invention, the base part 23 is arranged on the chamber bottom plate 11. By fixing the base part 23 on the chamber bottom plate 11, the chamber bottom plate 11 can be reinforced to prevent uneven settlement of the chamber.

[0046] As a preferred solution of the present invention, a corbel column 5 is provided on the side wall of the chamber body 1. The corbel column 5 can support the side wall of the chamber body 1.

[0047] It can be seen from the above specific implementation methods that the chamber support structure and the chamber provided by the present invention are made of reinforced concrete and a reinforced concrete arch frame arranged outside the chamber; the reinforced concrete arch frame includes an arch beam arranged outside the top of the chamber, columns arranged at both ends of the bottom of the arch beam, and a foundation arranged at the bottom of the column; the column is arranged on the outer wall of the chamber; the arch beam and the column form an integrated structure with the top of the chamber and the side wall of the chamber by pouring reinforced concrete. The construction can be cast synchronously with the chamber wall, and the support structure has good integrity; during the support process, there is no large-scale mechanical operation; the reinforced concrete arch frame reinforces the top and side walls of the chamber, which can ensure the stability of the entire chamber; it has the advantages of small construction space, low construction difficulty, good construction quality control, and is conducive to the stability of the entire surrounding rock and the excavation of the chamber, and low cost.

[0048] As described above, the chamber support structure and the chamber proposed according to the present invention are described by way of example with reference to the accompanying drawings. However, those skilled in the art should understand that various improvements can be made to the chamber support structure and the chamber proposed by the present invention without departing from the content of the present invention. Therefore, the protection scope of the present invention should be determined by the content of the attached claims.

Claims

1. A chamber support structure, characterized in that: It includes reinforced concrete and reinforced concrete arch frame arranged outside the chamber; wherein, The reinforced concrete arch frame includes an arch beam arranged outside the top of the chamber, columns arranged at both ends of the bottom of the arch beam, and a base portion arranged at the bottom of the column; wherein the arch beam is formed by at least two beam steel bars bundled by beam reinforcement; the column is formed by at least two column steel bars bundled by column reinforcement; wherein the shape of the arch beam is the same as the shape of the top of the chamber; The columns are arranged on the outer wall of the chamber; the arch beam is connected to the top of the chamber by overlapping the beam reinforcement and the top reinforcement of the chamber; the columns are connected to the side wall of the chamber by overlapping the column reinforcement and the side wall reinforcement of the chamber; The arch beam and the column form an integrated structure with the top end of the chamber and the side wall of the chamber by pouring the reinforced concrete; wherein, the arch beam and the column form an integrated structure with the inner side end of the top end of the chamber and the side wall of the chamber by pouring the reinforced concrete on the inner side end of the top end of the chamber and the inner wall of the chamber.

2. The chamber support structure according to claim 1, characterized in that: It also includes a sprayed anchor net arranged outside the reinforced concrete arch frame.

3. The chamber support structure according to claim 1, characterized in that: The arch beam is overlapped and connected with the column.

4. The chamber support structure according to claim 1, characterized in that: The foundation part includes a foundation base plate and a column fixing structure arranged on the top of the foundation base plate.

5. A chamber, comprising a chamber body and a chamber bottom plate arranged at the bottom of the chamber body; characterized in that: The chamber support structure according to any one of claims 1 to 4 is arranged on the side walls and the top of the chamber body.

6. The chamber according to claim 5, characterized in that: The base portion is arranged on the chamber bottom plate.

Citation Information

Patent Citations

  • Excavating construction method for special stratum cave

    CN109488347A

  • Construction method suitable for ultra-large fracture surface underground chamber excavating and steel arch frame fixing

    CN110159323A

  • Dark cave section of colliery inclined shaft excavation supporting construction structure

    CN205805579U

  • Chamber supporting structure and chamber

    CN212614773U

  • Concrete shell construction method

    US20150259942A1