A testing method and device for machine equipment
By loading the configuration file and initializing the machine equipment, it solves the problem of semiconductor chip manufacturers being unable to simulate the equipment automation control system for automated production testing, realizes automated production testing, reduces the workload and error rate of testers, and simulates automated production .
Patent Information
- Application Number
- CN202010706155.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2020-07-21
- Publication Date
- 2024-10-25
- Estimated Expiration
- 2040-07-21
AI Technical Summary
Semiconductor chip manufacturers are unable to simulate equipment automation control systems for automated production testing, resulting in reliance on FASTsim testing software and manual testing, and the inability to identify differences in formats of the same instruction at different times.
By loading the first configuration file and the second configuration file, the machine equipment is initialized, and the two configuration files are used to test the production process of the machine equipment according to the preset production sequence, thereby realizing automated production testing of the equipment.
It realizes automated production testing of machine equipment, reduces the workload of testers, reduces the error rate during testing, and allows multiple instructions to be issued at the same time, simulating automated production to the greatest extent.
Smart Images

Figure CN111984528B_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of testing technology, and in particular to a testing method and device for machine equipment. Background Art
[0002] Currently, semiconductor chip manufacturers achieve automated production through the manufacturing execution system MES system, the automated material handling system AMHS system and the equipment automation control system EAP.
[0003] At present, semiconductor chip manufacturers generally use FASTsim test software to simulate EAP system to realize the test of automated production of machine equipment. Specifically, during the automated test process of FASTsim test software, it is necessary to manually issue control instructions one by one according to the production sequence to realize the automated production test of EAP system. At present, semiconductor chip manufacturers have also tried to build simulated EAP system to realize automated production process, but none of them have been realized. The main reason is that the automated production process of building simulated EAP system is a solidified program, which can only recognize instructions of the same format. Therefore, different formats of the same instruction issued at different times cannot be recognized, which makes it impossible for semiconductor chip manufacturers to simulate the equipment automation control system for automated production testing. Therefore, they can only rely on FASTsim test software combined with manual methods to realize automated production testing of equipment automation control system. Summary of the invention
[0004] The present application provides a testing method and device for machine equipment to solve the problem that manufacturers are currently unable to simulate equipment automation control systems to perform automated production testing.
[0005] In order to solve the above technical problems, the present application discloses a testing method for a machine device, comprising:
[0006] Load a first configuration file, wherein the first configuration file stores a first association relationship between a trigger event CEID of a machine device and production process data SVID of the machine device;
[0007] Loading a second configuration file, where the second configuration file is used to load production process data of the machine equipment;
[0008] Determine whether the machine device is connected, and if the determination result is yes, use the first configuration file to initialize the machine device;
[0009] After the machine equipment is initialized, the preset production process of the machine equipment is tested using the first configuration file and the second configuration file according to the preset production sequence.
[0010] Optionally, the step of loading the first configuration file includes:
[0011] Acquire a second association relationship between a trigger event CEID of a machine device and production process data SVID of the machine device pre-stored in the machine device;
[0012] Removing the acquired second association relationship;
[0013] Creating a relationship between the production process data identifier and the trigger event CEID of the machine equipment;
[0014] Creating a relationship between the production process data identifier and the production process data SVID of the machine equipment;
[0015] The first association relationship between the trigger event CEID of the machine equipment and the production process data SVID of the machine equipment is re-established.
[0016] Optionally, the step of testing the production process of the machine device using the first configuration file and the second configuration file according to the production sequence includes:
[0017] Invoke the first association relationship between different triggering events of the machine equipment and different production process data in the first configuration file, so that the machine equipment is tested according to different production process data corresponding to different triggering events;
[0018] Calling the instruction for obtaining the process recipe in the second configuration file, and obtaining the production recipe information to be detected of the machine device according to the process recipe instruction;
[0019] When it is detected that the triggering event of the machine equipment is a production recipe detection event, obtaining the generated recipe information to be detected, and determining whether the production recipe information to be detected is modified;
[0020] If the production formula information to be detected has not been modified, calling the second configuration file to obtain a material box door opening instruction;
[0021] When it is detected that the triggering event of the machine equipment is receiving a first material location information event, the first material location information corresponding to the first material location information event is obtained, and the first material location information is loaded through the second configuration file to form the second material location information.
[0022] Optionally, when it is detected that the triggering event of the machine device is receiving a first material location information event, obtaining first material location information corresponding to the first material location information event, and loading the first material location information through the second configuration file to form the second material location information step includes:
[0023] According to the production sequence, load the pre-generated different information instructions corresponding to the first material position information in the second configuration file;
[0024] Determine whether the different information instructions are the smallest item. If so, modify the different production process data corresponding to the different information instructions, generate second material location information, and send the second material location information to the machine equipment.
[0025] Optionally, if it is determined that the production formula information to be detected is modified, the second configuration file is called to obtain a material box unlocking instruction;
[0026] Obtaining the pre-generated edit unlocking cartridge instruction in the second configuration file;
[0027] Determine whether the process data object instruction corresponding to the pre-generated edited unlocking material box is the smallest item, and if so, modify the object value of the process data action object to unlock, and generate an unlocking instruction;
[0028] The unlocking instruction is sent to the machine equipment, so that the machine equipment removes the material box from the machine equipment.
[0029] In order to solve the above technical problems, the present application also discloses a testing device for a machine device, comprising:
[0030] A first configuration module is used to load a first configuration file, wherein the first configuration file stores a first association relationship between a trigger event CEID of a machine device and production process data SVID of the machine device;
[0031] A second configuration module, used to load a second configuration file, where the second configuration file is used to load the production process data of the machine equipment;
[0032] A judgment module, used to judge whether the device is connected to the machine;
[0033] an initialization module, configured to initialize the machine device using the first configuration file if the determination result of the determination module is yes;
[0034] The testing module is used to test the preset production process of the machine equipment by using the first configuration file and the second configuration file according to the preset production sequence after the machine equipment is initialized.
[0035] Optionally, the first configuration module includes:
[0036] A first acquisition module, used for acquiring a second association relationship between a trigger event CEID of a machine device and production process data SVID of the machine device pre-stored in the machine device;
[0037] A releasing module, used for releasing the acquired second association relationship;
[0038] A first creation module is used to create a relationship between the production process data identifier and the trigger event CEID of the machine equipment;
[0039] A second creation module is used to create a relationship between the production process data identifier and the production process data SVID of the machine equipment;
[0040] The establishing module is used to re-establish the first association relationship between the triggering event CEID of the machine equipment and the production process data SVID of the machine equipment.
[0041] Optionally, the test module includes:
[0042] A first calling module, used for calling the first association relationship between different triggering events of the machine equipment and different production process data in the first configuration file, so that the machine equipment is tested according to different production process data corresponding to different triggering events;
[0043] A second calling module is used to call the instruction for obtaining the process recipe in the second configuration file, and obtain the production recipe information to be detected of the machine device according to the process recipe instruction;
[0044] A first judgment module is used to judge whether the production recipe information to be detected is modified when it is detected that the triggering event of the machine equipment is a production recipe detection event;
[0045] The second calling module is further configured to call the second configuration file to obtain a door opening instruction for the material box if the judgment result of the judgment module is that the production formula information to be detected has not been modified;
[0046] The generation module is used to obtain the first material location information corresponding to the first material location information event when it is detected that the triggering event of the machine equipment is the receipt of the first material location information event, and load the first material location information through the second configuration file to form the second material location information.
[0047] Optionally, the generating module includes:
[0048] A second loading module, used for loading the pre-generated different information instructions corresponding to the first material position information in the second configuration file according to the production sequence;
[0049] The second judgment module is used to judge whether the different information instructions are the smallest items. If so, the different production process data corresponding to the different information instructions are modified accordingly to generate second material location information, and the second material location information is sent to the machine equipment.
[0050] Optionally, if the judgment result of the first judgment module is modification, the second configuration file is called to obtain a material box unlocking instruction;
[0051] An unlocking module, used for obtaining the editing and unlocking cartridge instruction pre-generated in the second configuration file;
[0052] The third judgment module is used to judge whether the process data object instruction corresponding to the pre-generated edited unlocking material box is the smallest item, and if so, modify the object value of the process data action object to unlock, and generate an unlocking instruction;
[0053] The sending module is used to send the unlocking instruction to the machine equipment, so that the machine equipment removes the material box from the machine equipment.
[0054] Compared with the prior art, this application has the following advantages:
[0055] In this embodiment, the device software is initialized by loading the first configuration file and the second configuration file. After the test software establishes a connection with the machine device, the first configuration file is used to initialize the machine device. After the machine device is initialized, the first configuration file and the second configuration file are used to test the preset production process of the machine device according to the preset production sequence. The entire test process does not require the tester to issue instructions, thereby realizing the test of the automated production of the machine device. Compared with the existing test method, the tester no longer needs to issue instructions one by one, reducing the workload of the tester. At the same time, the test software controls the timing of issuing instructions, reducing the error rate during the test, and can also realize the issuance of multiple instructions at the same time, simulating the automated production of the machine device to the greatest extent.
[0056] Of course, any product implementing the present application does not necessarily need to achieve all of the advantages described above at the same time. BRIEF DESCRIPTION OF THE DRAWINGS
[0057] Figure 1 is a flow chart of a method for testing a machine device according to an embodiment of the present application;
[0058] Figure 2 is a flow chart of a method for testing a machine device according to an embodiment of the present application;
[0059] Figure 3 It is a structural schematic diagram of a testing device for a machine equipment according to an embodiment of the present application. DETAILED DESCRIPTION
[0060] In order to make the above-mentioned objects, features and advantages of the present application more obvious and easy to understand, the present application is further described in detail below in conjunction with the accompanying drawings and specific implementation methods.
[0061] Reference Figure 1 , which shows a flow chart of a testing method for a machine device according to an embodiment of the present application. The testing method is mainly applied to different semiconductor chip manufacturers. Different semiconductor chip manufacturers can implement testing of machine devices through the testing method, which specifically includes:
[0062] Step 101: Load a first configuration file, wherein the first configuration file stores a first association relationship between a trigger event CEID of a machine device and production process data SVID of the machine device.
[0063] Among them, many trigger events are defined on the machine equipment. The trigger event can be abbreviated as CE. Each trigger event has an identity ID, so the trigger event of the machine equipment can be abbreviated as CEID.
[0064] Many Status Variable data are defined on the machine equipment, referred to as SV data for short. Each SV data has an identity ID, so the production process data of the machine equipment can be referred to as SVID for short.
[0065] In order to achieve unified control of different machine equipment manufacturers, the present application proposes to use a first configuration file, where the first configuration file stores a first association relationship between a trigger event CEID of the machine equipment and production process data SVID of the machine equipment.
[0066] Specifically, a separate name is defined for different trigger events of a machine device, and a unique ID is assigned to each name. Different machine devices have different IDs, but for the test software, although different machine devices have different IDs, the corresponding trigger events are the same, thereby achieving control over different machine devices.
[0067] For example, taking the task start (Cjob start) event as an example, the test software will define the Cjob start event as ControlJobStart. For the machine device, this event is a CEID. The corresponding identifier of machine device A is 10010, and the corresponding identifier of machine device B is 74. The first configuration file allows the test software to recognize that no matter whether the identifier is 10010 or 74, it corresponds to ControlJobStart.
[0068] In practical applications, trigger events CEID of different equipments correspond to production process data SVID of different equipments, and a trigger event of one equipment corresponds to production process data SVID of different equipments.
[0069] In this embodiment, step 101 includes the following sub-steps:
[0070] Sub-step 1011: Acquire a second association relationship between a triggering event of a machine device and production process data of the machine device pre-stored in the machine device.
[0071] Specifically, the relationship between the pre-generated production process data identifier reportID and SVID is obtained, the pre-generated relationship between reportID and CEID is loaded, and the second association relationship between CEID and SVID is established through reportID.
[0072] Sub-step 1012: cancel the acquired second association relationship.
[0073] The test software needs to be initialized before working. The reason for software initialization is that different machine manufacturers provide different software. When entering the FAB for the first time, the status of each machine equipment cannot be the same. Therefore, it is necessary to initialize the machine equipment when the machine equipment is connected to the test software to ensure that the status of the machine equipment is the status the software system wants. Therefore, it is necessary to release the second association relationship, and then re-establish the association relationship between the trigger event CEID of the machine equipment and the production process data SVID of the machine equipment. Sub-step 1013: Create the relationship between the production process data identifier and the trigger event CEID of the machine equipment.
[0074] Sub-step 1014: Create a relationship between the production process data identifier and the production process data SVID of the machine equipment.
[0075] Sub-step 1015: re-establishing the first association relationship between the trigger event CEID of the tool equipment and the production process data SVID of the tool equipment.
[0076] The trigger event of each machine device may correspond to the production process data of multiple machines devices, so that when the trigger event is triggered, an automated test may be performed according to the production process data.
[0077] The re-established first association relationship is sent to the machine device. If the machine device receives the first association relationship, the initialization of the machine device is completed. If the machine device does not receive the first association relationship, the initialization is abnormal and the process ends.
[0078] Step 102: Load a second configuration file, where the second configuration file is used to load production process data of the machine equipment.
[0079] A plurality of instructions are stored in the second configuration file, and loading of different production process data can be achieved by loading the instructions in the second configuration file.
[0080] The first configuration file is used to realize unified management of different equipment using the same software, and the second configuration file is used to realize loading of production process data of the equipment, that is, the second configuration file is used to realize loading of production process data instructions to be issued.
[0081] Step 103: Determine whether the machine device is connected. If the determination result is yes, initialize the machine device using the first configuration file.
[0082] If the judgment result is no, continue to judge whether it is connected to the machine device.
[0083] Step 104: After the machine equipment is initialized, the preset production process of the machine equipment is tested using the first configuration file and the second configuration file according to a preset production sequence.
[0084] In this embodiment, the device software is initialized by loading the first configuration file and the second configuration file. After the test software establishes a connection with the machine device, the first configuration file is used to initialize the machine device. After the machine device is initialized, the first configuration file and the second configuration file are used to test the preset production process of the machine device according to the preset production sequence. The entire test process does not require the tester to issue instructions, thereby realizing the test of the automated production of the machine device. Compared with the existing test method, the tester no longer needs to issue instructions one by one, reducing the workload of the tester. At the same time, the test software controls the timing of issuing instructions, reducing the error rate during the test, and can also implement the issuance of multiple instructions at the same time, simulating the automated production of the machine device to the greatest extent.
[0085] Reference Figure 2 , which shows a flow chart of a testing method for a machine device according to an embodiment of the present application. The testing method is mainly applied to different semiconductor chip manufacturers and specifically includes:
[0086] Step 201: Load a first configuration file, wherein the first configuration file stores a first association relationship between a trigger event CEID of a machine device and production process data SVID of the machine device.
[0087] Step 202: Load a second configuration file, where the second configuration file is used to load the production process data of the machine equipment.
[0088] Step 203: Determine whether the machine device is connected. If yes, use the first configuration file to initialize the machine device.
[0089] Step 204: calling the first association relationship between different triggering events of the machine equipment and different production process data in the first configuration file, so that the machine equipment is tested according to different production process data corresponding to different triggering events.
[0090] In practical applications, when it is detected that the triggering event of the machine equipment is a material box arrival event, the material box arrival event of the machine equipment is tested according to the first association relationship between the material box arrival event and the production process data.
[0091] The generated process data corresponding to the material box arrival event may be whether the material box has arrived.
[0092] When it is detected that the triggering event of the machine equipment is a material box identification receiving event, the material box identification receiving event of the machine equipment is tested according to a first association relationship between the material box identification receiving event and the production process data.
[0093] Step 205: calling the instruction for obtaining the process recipe in the second configuration file, and obtaining the production recipe information to be detected of the machine device according to the process recipe instruction.
[0094] In actual applications, the second configuration file has pre-stored the process recipe acquisition instruction, so that the generation recipe information to be detected can be acquired by calling the process recipe acquisition instruction in the second configuration file.
[0095] Step 206: When it is detected that the triggering event of the machine equipment is a production recipe detection event, it is determined whether the production recipe information to be detected is modified. If not, step 207 is executed; if modified, step 211 is executed.
[0096] In a specific application, the production formula information to be detected is compared with the production formula information pre-stored in the machine equipment. If they are the same, it means that they have not been modified, and step 207 is executed. If they are different, it means that the production formula information has been modified, and step 211 is executed.
[0097] Step 207: Call the second configuration file to obtain the instruction for issuing the material box door opening.
[0098] Step 208: When it is detected that the triggering event of the machine device is receiving the first material location information event, the first material location information corresponding to the first material location information event is obtained, and the first material location information is loaded through the second configuration file to form the second material location information.
[0099] In practical applications, step 208 may form the second material location information in the following manner:
[0100] According to the preset production sequence, the pre-generated different information instructions corresponding to the first material position information in the second configuration file are loaded.
[0101] Determine whether the different information instructions are the smallest items. If so, modify the different production process data object values corresponding to the different information instructions, generate second material location information, and send the second material location information to the machine equipment.
[0102] The following takes the material location information as an example to illustrate the process of forming the second material location information in step 208, which is as follows:
[0103] In actual applications, the format of the instructions pre-generated in the second configuration file is L5, which is a separate List. There are 5 sub-items under L5, which are the data identifier DATAID, the process parameter action CARRIERACTION, the material box identifier CARRIERID, the machine port PTN, and the material port number ln. Under the sub-item Ln of L5, there is a sub-item l2, and under the sub-item l2, there are two sub-items, namely CATTRID and CATTRDATA.
[0104] According to the preset production sequence, the material location information instructions pre-generated by the second configuration file are loaded.
[0105] It is determined whether the material location information instruction is the smallest item. If so, the object value of the production process data object corresponding to the pre-generated material location information instruction is modified to the number of wafers in the material box.
[0106] If the material location information instruction is not the smallest item, assign the format of Item to List and assign the value to its child Item.
[0107] The above two steps are to change the ACATTRID of the sub-Item of l2 to <nothing>-Camer Attnbute Object <nothing>Modified to <capacity>。
[0108] V CATTRDATA= <nothing>-Camer Attnbute Value <nothing>Modified to <25> , the modified program is as follows:
[0109] A CATTRID='Capacity'-Camer Attnbute Object.
[0110] U1CATTRDATA='25'-Camer Attnbute Value.
[0111] The wafer information instructions pre-generated by the second configuration file are loaded.
[0112] Determine whether the wafer information instruction is the smallest item, and if so, modify the production process data object value corresponding to the wafer information instruction to the actual number of wafers in the material box.
[0113] The above two steps are to change the A CATTRID of the sub-Item of l2 to <nothing>-Camer AttnbuteObject <nothing>Modified to <substratecount>。
[0114] V CATTRDATA= <nothing>-Camer Attnbute Value <nothing>Modified to <25> , the modified program is as follows:
[0115] A CATTRID='SubstrateCount'-Camer Attnbute Object.
[0116] U1CATTRDATA='25'-Camer Attnbute Value.
[0117] If the material location information instruction is not the smallest item, assign the format of Item to List and assign the value to its child Item.
[0118] The cartridge status information instruction pre-generated by the second configuration file is loaded.
[0119] Determine whether the material box status information instruction is the smallest item, and if so, modify the production process data object value corresponding to the material box status information instruction.
[0120] If the material location information instruction is not the smallest item, assign the format of Item to List and assign the value to its child Item.
[0121] The above two steps are to change the A CATTRID of the sub-Item of l2 to <nothing>-Camer AttnbuteObject <nothing>Modified to <usage>。
[0122] A CATTRDATA= <nothing>-Camer Attnbute Value <nothing>Modified to <product>, the modified program is as follows:
[0123] A CATTRID='Usage'-Camer Attnbute Object.
[0124] U1CATTRDATA='PRODUCT'-Camer Attnbute Value.
[0125] Load the material information instructions pre-generated in the second configuration file;
[0126] Determine whether the material information instruction is the smallest item, and if so, modify the production process data object value corresponding to the material information instruction.
[0127] If the material location information instruction is not the smallest item, assign the format of Item to List and assign the value to its child Item.
[0128] The above two steps are to change the A CATTRID of the sub-Item of l2 to <nothing>-Camer AttnbuteObject <nothing>Modified to <contentmap>.
[0129] A CATTRID='ContentMap'-Camer Attnbute Object.
[0130] If there is a wafer in the slot of the material box, A-LotID and A SubstrateID are assigned values. If there is no wafer, the values are empty.
[0131] The wafer information instructions pre-generated by the second configuration file are loaded.
[0132] Determine whether the chip information instruction in the material box slot is the smallest item. If so, modify the production process data object value corresponding to the chip information instruction in the material box slot to generate second material position information, and send the second material position information to the machine equipment.
[0133] The above two steps are to change the A CATTRID of the sub-Item of l2 to <nothing>-Camer AttnbuteObject <nothing>Modified to <slotmap>.
[0134] A CATTRID='SlotMap'-Camer Attnbute Object.
[0135] If there is a wafer in the slot of the material box, U1 is assigned a value of 3, if there is no wafer, U1 is assigned a value of 1.
[0136] Step 209: When it is detected that the triggering event of the machine equipment is a material entering the production equipment event, determine whether the material enters the production equipment based on the first association relationship between the material entering the production equipment event and the production process data; if so, execute step 210; if not, execute steps 211-213.
[0137] Step 210: When it is detected that the triggering event of the machine equipment is a production end event, it is determined whether the generated process data is normally completed, and after the production is completed, an instruction for the material box to exit the equipment is created and sent to the equipment to complete the automatic material return process.
[0138] Step 211: Call the second configuration file to obtain a material box unlocking instruction.
[0139] Step 212: Obtain the edit unlocking cartridge instruction pre-generated in the second configuration file.
[0140] Step 213: Determine whether the process data object instruction corresponding to the pre-generated edited unlocking material box is the smallest item. If so, modify the object value of the process data action object to unlock and generate an unlocking instruction.
[0141] Step 214: Send the unlocking instruction to the machine device, so that the machine device removes the material box from the machine device.
[0142] In this embodiment, after the software establishes a connection with the machine equipment, you only need to put the material box on the machine equipment, and the test software can simulate the factory automation system to send instructions to the machine equipment, open the material box, and verify the material information in the material box. After successful verification, it will automatically send instructions to the equipment to start production. After the production is completed, it can automatically send instructions to the equipment to close and unlock the material box, so that the material box can be automatically exited. The whole process no longer requires people to send any instructions, all of which are sent by the test software in a time sequence, thereby realizing the test of the automated production of the equipment software.
[0143] It should be noted that, for the aforementioned method embodiments, for the sake of simplicity, they are all described as a series of action combinations, but those skilled in the art should be aware that the present application is not limited by the order of the actions described, because according to the present application, certain steps can be performed in other orders or simultaneously. Secondly, those skilled in the art should also be aware that the embodiments described in the specification are all preferred embodiments, and the actions involved are not necessarily required for the present application.
[0144] Based on the description of the above method embodiments, the present application also provides corresponding device embodiments to implement the contents described in the above method embodiments.
[0145] Reference Figure 3 , which shows a structural diagram of a testing device for a machine equipment according to an embodiment of the present application, specifically comprising:
[0146] The first configuration module 301 is used to load a first configuration file, wherein the first configuration file stores a first association relationship between a trigger event CEID of a machine device and production process data SVID of the machine device;
[0147] A second configuration module 302, used to load a second configuration file, where the second configuration file is used to load the production process data of the machine equipment;
[0148] A determination module 303 is used to determine whether the device is connected to the machine;
[0149] An initialization module 304, configured to initialize the machine device using the first configuration file if the determination result of the determination module is yes;
[0150] The testing module 305 is used to test the preset production process of the machine equipment by using the first configuration file and the second configuration file according to the preset production sequence after the machine equipment is initialized.
[0151] Optionally, the first configuration module includes:
[0152] A first loading module is used to obtain a second association relationship between a trigger event CEID of a machine device and production process data SVID of the machine device pre-stored in the machine device;
[0153] A releasing module, used for releasing the acquired second association relationship;
[0154] A first creation module, used to create a relationship between the production process data identifier and the triggering event of the machine equipment;
[0155] A second creation module is used to create a relationship between the production process data identifier and the production process data of the machine equipment;
[0156] The establishing module is used to re-establish the first association relationship between the triggering event CEID of the machine equipment and the production process data SID of the machine equipment.
[0157] Optionally, the test module includes:
[0158] A first calling module, used for calling the first association relationship between different triggering events of the machine equipment and different production process data in the first configuration file, so that the machine equipment is tested according to different production process data corresponding to different triggering events;
[0159] A second calling module is used to call the instruction for obtaining the process recipe in the second configuration file, and obtain the production recipe information to be detected of the machine device according to the process recipe instruction;
[0160] A first judgment module is used to obtain the generated recipe information to be detected and judge whether the generated recipe information to be detected is modified when it is detected that the triggering event of the machine equipment is a production recipe detection event;
[0161] The second calling module is further configured to call the second configuration file to obtain a door opening instruction for the material box if the judgment result of the judgment module is that the production formula information to be detected has not been modified;
[0162] The generation module is used to obtain the first material location information corresponding to the first material location information event when it is detected that the triggering event of the machine equipment is the receipt of the first material location information event, and load the first material location information through the second configuration file to form the second material location information.
[0163] Optionally, the generating module includes:
[0164] A second loading module, used for loading the pre-generated different information instructions corresponding to the first material position information in the second configuration file according to the production sequence;
[0165] The second judgment module is used to judge whether the different information instructions are the smallest items. If so, the different production process data corresponding to the different information instructions are modified accordingly to generate second material location information, and the second material location information is sent to the machine equipment.
[0166] Optionally, if the judgment result of the first judgment module is modification, the second configuration file is called to obtain a material box unlocking instruction;
[0167] An unlocking module, used for obtaining the editing and unlocking cartridge instruction pre-generated in the second configuration file;
[0168] The third judgment module is used to judge whether the process data object instruction corresponding to the pre-generated edited unlocking material box is the smallest item, and if so, modify the object value of the process data action object to unlock, and generate an unlocking instruction;
[0169] The sending module is used to send the unlocking instruction to the machine equipment, so that the machine equipment removes the material box from the machine equipment.
[0170] In this embodiment, the device software is initialized by loading the first configuration file and the second configuration file. After the test software establishes a connection with the machine device, the first configuration file is used to initialize the machine device. After the machine device is initialized, the first configuration file and the second configuration file are used to test the preset production process of the machine device according to the preset production sequence. The entire test process does not require the tester to issue instructions, thereby realizing the test of the automated production of the machine device. Compared with the existing test method, the tester no longer needs to issue instructions one by one, reducing the workload of the tester. At the same time, the tester controls the timing of issuing instructions, reducing the error rate during the test, and can also implement the issuance of multiple instructions at the same time, simulating the automated production of the machine device to the greatest extent.
[0171] As for the above-mentioned device embodiment, since it is basically similar to the method embodiment, the description is relatively simple, and the relevant parts may refer to the partial description of the method embodiment.
[0172] The various embodiments in this specification are described in a progressive manner, and each embodiment focuses on the differences from other embodiments. The same or similar parts between the various embodiments can be referenced to each other.
[0173] It is easy for a person skilled in the art to think that any combination of the above embodiments is feasible, so any combination of the above embodiments is an implementation scheme of the present application. However, due to space limitations, this specification will not describe them in detail here.
[0174] Those skilled in the art will appreciate that the embodiments of the present application may be provided as methods, systems, or computer program products. Therefore, the present application may adopt the form of a complete hardware embodiment, a complete software embodiment, or an embodiment in combination with software and hardware. Moreover, the present application may adopt the form of a computer program product implemented in one or more computer-usable storage media (including but not limited to disk storage, CD-ROM, optical storage, etc.) that include computer-usable program code.
[0175] The present application is described with reference to the flowcharts and / or block diagrams of the methods, devices (systems), and computer program products according to the embodiments of the present application. It should be understood that each process and / or box in the flowchart and / or block diagram, as well as the combination of the processes and / or boxes in the flowchart and / or block diagram, can be implemented by computer program instructions. These computer program instructions can be provided to a processor of a general-purpose computer, a special-purpose computer, an embedded processor, or other programmable data processing device to generate a machine, so that the instructions executed by the processor of the computer or other programmable data processing device generate instructions for implementing the processes in the flowchart and / or block diagram. Figure 1 A process or multiple processes and / or boxes Figure 1 A device that provides the functions specified in a block or multiple blocks.
[0176] These computer program instructions may also be stored in a computer-readable memory capable of directing a computer or other programmable data processing device to operate in a specific manner, so that the instructions stored in the computer-readable memory produce an article of manufacture comprising an instruction device, which implements the process Figure 1 A process or multiple processes and / or boxes Figure 1 A function specified in one or more boxes.
[0177] These computer program instructions can also be loaded onto a computer or other programmable data processing device so that a series of operating steps are executed on the computer or other programmable device to produce a computer-implemented process, thereby providing instructions for implementing the process. Figure 1 A process or multiple processes and / or boxes Figure 1 The steps for the functions specified in one or more boxes.
[0178] Although the preferred embodiments of the present application have been described, those skilled in the art may make additional changes and modifications to these embodiments once they have learned the basic creative concept. Therefore, the appended claims are intended to be interpreted as including the preferred embodiments and all changes and modifications falling within the scope of the present application.
[0179] The above is a detailed introduction to a testing method and device for a machine device provided by the present application. Specific examples are used in this article to illustrate the principles and implementation methods of the present application. The description of the above embodiments is only used to help understand the method and core idea of the present application. At the same time, for general technicians in this field, according to the idea of the present application, there will be changes in the specific implementation method and application scope. In summary, the content of this specification should not be understood as a limitation on the present application.< / slotmap> < / nothing> < / nothing> < / contentmap> < / nothing> < / nothing> < / product> < / nothing> < / nothing> < / usage> < / nothing> < / nothing> < / nothing> < / nothing> < / substratecount> < / nothing> < / nothing> < / nothing> < / nothing> < / capacity> < / nothing> < / nothing>
Claims
1. A testing method for a machine device, It is characterized in that include: Load a first configuration file, wherein the first configuration file stores a first association relationship between a trigger event CEID of a machine device and production process data SVID of the machine device; Loading a second configuration file, where the second configuration file is used to load production process data of the machine equipment; Determine whether the machine device is connected, and if the determination result is yes, use the first configuration file to initialize the machine device; After the machine equipment is initialized, the preset production process of the machine equipment is tested using the first configuration file and the second configuration file according to the preset production sequence; The step of testing the preset production process of the machine equipment using the first configuration file and the second configuration file according to the preset production sequence includes: Invoke the first association relationship between different triggering events of the machine equipment and different production process data in the first configuration file, so that the machine equipment is tested according to different production process data corresponding to different triggering events; The process recipe acquisition instruction in the second configuration file is called, and the production recipe information to be detected of the machine equipment is acquired according to the process recipe instruction.
2. The test method according to claim 1, It is characterized in that The step of loading the first configuration file comprises: Acquire a second association relationship between a trigger event CEID of a machine device and production process data SVID of the machine device pre-stored in the machine device; Removing the acquired second association relationship; Creating a relationship between the production process data identifier and the trigger event CEID of the machine equipment; Creating a relationship between the production process data identifier and the production process data SVID of the machine equipment; The first association relationship between the trigger event CEID of the machine equipment and the production process data SVID of the machine equipment is re-established.
3. The testing method according to claim 1, It is characterized in that The step of testing the preset production process of the machine equipment using the first configuration file and the second configuration file according to the preset production sequence also includes: When it is detected that the triggering event of the machine equipment is a production recipe detection event, obtaining the generated recipe information to be detected, and determining whether the production recipe information to be detected is modified; If the production formula information to be detected has not been modified, calling the second configuration file to obtain a material box door opening instruction; When it is detected that the triggering event of the machine equipment is receiving a first material location information event, the first material location information corresponding to the first material location information event is obtained, and the first material location information is loaded through the second configuration file to form the second material location information.
4. The test method according to claim 3, It is characterized in that The step of obtaining first material location information corresponding to the first material location information event when detecting that the triggering event of the machine equipment is receiving the first material location information event, and loading the first material location information through the second configuration file to form the second material location information includes: According to the production sequence, load the pre-generated different information instructions corresponding to the first material position information in the second configuration file; Determine whether the different information instructions are the smallest item. If so, modify the different production process data corresponding to the different information instructions, generate second material location information, and send the second material location information to the machine equipment.
5. The testing method according to claim 3, It is characterized in that If it is determined that the production recipe information to be detected is modified, calling the second configuration file to obtain a material box unlocking instruction; Obtaining the pre-generated edit unlocking cartridge instruction in the second configuration file; Determine whether the process data object instruction corresponding to the pre-generated edited unlocking material box is the smallest item, and if so, modify the object value of the process data action object to unlock, and generate an unlocking instruction; The unlocking instruction is sent to the machine equipment, so that the machine equipment removes the material box from the machine equipment.
6. A testing device for machine equipment, It is characterized in that include: A first configuration module is used to load a first configuration file, wherein the first configuration file stores a first association relationship between a trigger event CEID of a machine device and production process data SVID of the machine device; A second configuration module, used to load a second configuration file, where the second configuration file is used to load the production process data of the machine equipment; A judgment module, used to judge whether the device is connected to the machine; an initialization module, configured to initialize the machine device using the first configuration file if the determination result of the determination module is yes; A testing module, configured to test a preset production process of the machine equipment using the first configuration file and the second configuration file according to a preset production sequence after the machine equipment is initialized; The test module includes: A first calling module, used for calling the first association relationship between different triggering events of the machine equipment and different production process data in the first configuration file, so that the machine equipment is tested according to different production process data corresponding to different triggering events; The second calling module is used to call the instruction for obtaining the process recipe in the second configuration file, and obtain the production recipe information to be detected of the machine device according to the process recipe instruction.
7. The testing device according to claim 6, It is characterized in that The first configuration module includes: A first acquisition module, used for acquiring a second association relationship between a trigger event CEID of a machine device and production process data SVID of the machine device pre-stored in the machine device; A releasing module, used for releasing the acquired second association relationship; A first creation module is used to create a relationship between the production process data identifier and the trigger event CEID of the machine equipment; A second creation module is used to create a relationship between the production process data identifier and the production process data SVID of the machine equipment; The establishing module is used to re-establish the first association relationship between the triggering event CEID of the machine equipment and the production process data SVID of the machine equipment.
8. The testing device according to claim 6, It is characterized in that The test module also includes: A first judgment module is used to judge whether the production recipe information to be detected is modified when it is detected that the triggering event of the machine equipment is a production recipe detection event; The second calling module is further configured to call the second configuration file to obtain a door opening instruction for the material box if the judgment result of the judgment module is that the production formula information to be detected has not been modified; The generation module is used to obtain the first material location information corresponding to the first material location information event when it is detected that the triggering event of the machine equipment is the receipt of the first material location information event, and load the first material location information through the second configuration file to form the second material location information.
9. The testing device according to claim 8, It is characterized in that The generation module comprises: A second loading module, used for loading the pre-generated different information instructions corresponding to the first material position information in the second configuration file according to the production sequence; The second judgment module is used to judge whether the different information instructions are the smallest items. If so, the different production process data corresponding to the different information instructions are modified accordingly to generate second material location information, and the second material location information is sent to the machine equipment.
10. The testing device according to claim 8, It is characterized in that If the judgment result of the first judgment module is modification, calling the second configuration file to obtain the material box unlocking instruction; An unlocking module, used for obtaining the editing and unlocking cartridge instruction pre-generated in the second configuration file; The third judgment module is used to judge whether the process data object instruction corresponding to the pre-generated edited unlocking material box is the smallest item, and if so, modify the object value of the process data action object to unlock, and generate an unlocking instruction; The sending module is used to send the unlocking instruction to the machine equipment, so that the machine equipment removes the material box from the machine equipment.