A construction method for a phase-change concrete rectangular pipe gallery structure
Through the structure and assembly method of phase-change concrete rectangular pipe gallery, the problems of low space utilization and excessive temperature of circular pipe gallery are solved, more efficient space utilization and temperature adjustment are achieved, and construction and investment costs are reduced.
Patent Information
- Application Number
- CN202011237969.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2020-11-09
- Publication Date
- 2024-12-03
- Estimated Expiration
- 2040-11-09
AI Technical Summary
In the integrated pipeline corridor, when the buried depth is large, the space utilization rate of the circular section is low, and the heat generated by the cable causes too high temperature, requiring a large amount of ventilation machinery and equipment, which is relatively high in investment costs.
The rectangular pipe corridor structure and assembly method of phase-change concrete are adopted, and the temperature adjustment characteristics of phase-change concrete are used to combine foam strips and water-expanded rubber joints through the combination of prefabricated rectangular pipe rings, partition walls and cross-dividing partitions. Structure, reduce temperature fluctuations and reduce the use of ventilation machinery and equipment.
It improves space utilization, simplifies the construction process, reduces maintenance costs, reduces the number of ventilation machinery and equipment, reduces investment costs, and effectively regulates the temperature inside the pipe corridor.
Smart Images

Figure CN112343083B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to an urban integrated pipe gallery structure and a construction method, and in particular to a quasi-rectangular phase-change concrete integrated pipe gallery structure and a construction method. Background Art
[0002] The integrated pipeline corridor integrates various engineering pipelines such as electricity, communications, gas, heating, water supply and drainage, and is equipped with special inspection ports, lifting ports and monitoring systems. It implements unified planning, unified design, unified construction and management. It is an important infrastructure and "lifeline" to ensure the operation of the city. As an innovative development model of co-construction and sharing, it will lay a variety of municipal pipelines in an intensive manner. Compared with the direct burial of various municipal pipelines in the shallow space of the road, it has the advantages of beautifying the urban landscape, efficiently utilizing underground space, and avoiding repeated road excavation. It is a modern infrastructure to improve the resilience of urban development.
[0003] When the buried depth of the integrated pipe gallery is shallow, it is mostly designed as a rectangular section, and the open excavation method or rectangular jacking pipe construction is adopted. When the buried depth of the integrated pipe gallery is deep, most of them are designed as a circle, and the shield method is adopted for construction. It has the advantages of reasonable structural force, comprehensive cutting of the excavation surface of the shield machine equipment, and simple assembly construction process. However, the circular section has the weakness of low space utilization, which increases the pipeline maintenance operation process. From the perspective of use function, the rectangular section is the most suitable and economical. Compared with the circular section, the effective use area of the rectangular section is more than 20% larger than that of the circular section, and the tunnel cover can be greatly reduced.
[0004] Since the cables in the integrated pipe gallery will generate a certain amount of heat during operation, this part of the heat will easily accumulate in the urban pipe gallery if it is not dissipated in time, resulting in excessively high temperatures in the pipe gallery, which may cause fires in serious cases. Some cable tunnels are also equipped with various pipelines such as communications, gas, and heating. The increase in tunnel temperature is not conducive to the safe and stable operation of various pipelines, and may even cause the operation of various pipelines to be paralyzed. In addition, the integrated pipe gallery is a closed underground structure. The deposition of exhaust gas, the activities of personnel and microorganisms will cause the oxygen content in the pipe gallery to decrease. Therefore, the entire pipe gallery must be equipped with a ventilation system to ensure that the heat can be quickly dissipated, thereby ensuring the safe operation of the integrated pipe gallery. At present, the commonly used ventilation methods include natural ventilation, natural ventilation supplemented by ductless induced ventilation, and mechanical exhaust. The investment cost of natural ventilation is low, but the ventilation effect is limited. Therefore, strict requirements are placed on the setting of ventilation zones and shafts. A large number of air inlet and exhaust shafts need to be built, and the layout is difficult. Natural ventilation supplemented by ductless induced ventilation does not impose great restrictions on the length of the ventilation zone and the number and location of shafts, and this method has good ventilation effects, but the initial investment cost is high. Mechanical exhaust has good ventilation effects, a long exhaust zone distance, and a small number of shafts, but more mechanical equipment needs to be installed, and the investment cost is high.
[0005] In order to solve the above problems, the present invention proposes a phase change concrete rectangular pipe gallery structure and an assembly method. Summary of the invention
[0006] The purpose of the present invention is to overcome the deficiencies in the prior art and to provide a phase change concrete rectangular pipe gallery structure and a construction method, which are used to solve or partially solve the weakness of low space utilization of a circular cross-section integrated pipe gallery of the shield method under conditions of large burial depth, as well as the problem that cables and other pipelines generate a certain amount of heat during the operation of the integrated pipe gallery, resulting in excessively high temperatures in the pipe gallery, a large number of ventilation machinery and equipment, and high investment costs.
[0007] This phase-change concrete rectangular pipe gallery structure comprises a plurality of rectangular pipe segment rings (rectangular pipe gallery sections), an upper partition wall, a lower partition wall, a cast-in-place transverse diaphragm, connecting bolts and a joint waterproof structure which are connected in sequence along the longitudinal direction; the rectangular pipe segment rings are connected by longitudinal connecting bolts, and the pipe segments in the rectangular pipe segment ring are connected by pipe segment annular connecting bolts; the middle part of the rectangular pipe segment ring is connected to the upper partition wall and the lower partition wall by embedded steel bars; the upper partition wall is connected to the lower partition wall by partition wall connecting bolts; the cast-in-place transverse diaphragm is constructed by cast-in-place, is located between the partition wall and the pipe segment, and is connected to the partition wall and the pipe segment; a joint waterproof structure is provided between the longitudinal and annular seams of the pipe segment.
[0008] Preferably, any rectangular segment ring includes a vault circular arc segment located at the vault position, a right upper semicircular arc segment and a right lower semicircular arc segment located at the waist position, a bottom arc segment located at the bottom position, a left lower semicircular arc segment and a left upper semicircular arc segment located at the waist position; the radii R1 of the two waist arc segments are equal, the radius R2 of the vault circular arc segment and the bottom arc segment are equal, and the radius R1 of the waist arc segment is smaller than the radius R2 of the vault circular arc segment and the radius R2 of the bottom arc segment; the radii of the vault and the bottom arc segments are 8000mm to 12000mm, and the radius of the waist arc segment is 2500mm to 3000mm; the vault circular arc segment and the bottom arc segment are smoothly inscribed with the two waist circular arc segments respectively.
[0009] As a preferred embodiment: various rectangular segment rings (i.e., the first segment structure, the second segment structure, the third segment structure, and the fourth segment structure) are connected by longitudinal connecting bolts, the six segments in any rectangular segment ring are connected by segment annular connecting bolts, and the upper partition wall and the lower partition wall are connected by partition wall connecting bolts. Bolt holes are provided at the inner surface edge of each segment in the rectangular segment ring, and bolt holes are provided at the connection between the upper partition wall and the lower partition wall. The bolt holes are arc-shaped channels inside the segments, and the arc radius of the arc-shaped channels is equal everywhere. A gap is reserved in the arc-shaped channels to facilitate the smooth passage of the screw rod (segment annular connecting bolt). The cross-section of the connecting bolt is circular, and the end of the bolt hole is provided with an operating concave hole, i.e., a hand hole. The bolt holes and hand holes used for installing longitudinal connecting bolts, segment annular connecting bolts, and partition wall connecting bolts are designed in the same way.
[0010] As a preferred embodiment: the arch arc segment and the upper partition wall, the arch bottom arc segment and the lower partition wall are connected by embedded steel bars, and two rows of embedded steel bars are arranged longitudinally on each arch arc segment and each arch bottom arc segment, with three embedded steel bars in each row, and two rows of embedded steel bar sockets are arranged at positions corresponding to the upper partition wall and the lower partition wall, with three embedded steel bar sockets in each row. The cast-in-place transverse partition is cast with reinforced concrete, dividing the quasi-rectangular pipe gallery (or quasi-rectangular segment ring) into three or four compartments.
[0011] Preferably, the joint waterproofing structure between the longitudinal and circumferential seams of the pipe segments adopts foam strips and water-swellable rubber sealing pads for joint waterproofing; foam strips are respectively filled near the edges on both sides of the connection seam, and water-swellable rubber sealing pads are arranged on the outside of the foam strips; the water-swellable rubber sealing pad is completely pressed into the sealing pad groove, the cross-sectional area of the sealing pad groove is not less than the cross-sectional area of the sealing pad, the depth-to-width ratio of the caulking groove is not less than 2.5, the groove depth is 25-55mm, and the single-sided groove width is 5-10mm.
[0012] Preferably, six segments in any type of rectangular segment ring are provided with grouting holes for grouting behind the wall.
[0013] Preferably, the six segments in any type of rectangular segment ring are prefabricated reinforced concrete structures, which are cast by steel mesh (segment steel bars) and phase change concrete; the composite phase change material in the phase change concrete is mixed by capric acid + lauric acid, n-pentadecane + n-hexadecane in a certain proportion, the phase change temperature of the composite phase change material is 14-16°C in winter, and the phase change temperature in summer is 24-27°C, and the ratio of the composite phase change material can be 7:3, 6:4, 5:5, 4:6 and 3:7; the phase change concrete is prepared by cement, fly ash, sand, gravel, water, fly ash ceramsite and composite phase change material in a certain dosage.
[0014] The assembly construction method of the phase change concrete rectangular pipe gallery structure comprises the following steps:
[0015] S1. According to different strata and lithology and the cross-sectional dimensions of the quasi-rectangular tunnel, excavation is carried out by using the shield method or the jacking method, and the segments are assembled.
[0016] S2. The assembly of prefabricated segments by shield method mainly includes the following steps:
[0017] S2-1. Produce standard-sized arch top arc segment segments, upper semi-circular segment segments, lower semi-circular segment segments and arch bottom arc segment segments in a prefabricated component factory;
[0018] S2-2. During the construction process using the shield, the segments are hoisted in the order of arch bottom arc segment, right lower half arc segment, left lower half arc segment, right upper half arc segment, left upper half arc segment, and finally arch top arc segment;
[0019] S2-3. After the quasi-rectangular segment ring is positioned, the embedded steel bar sockets on the lower partition wall are connected to the embedded steel bars on the arch bottom arc segment, and the embedded steel bar sockets on the upper partition wall are connected to the embedded steel bars on the arch top arc segment;
[0020] S2-4. After positioning of each segment, insert the segment circumferential connection bolts, longitudinal connection bolts and partition wall connection bolts into the corresponding bolt holes. After passing through, fill the gaps of the arc-shaped bolt holes in the hand holes by grouting. Then install the bolt washers and nuts to connect and fix the bolts. First tighten the partition wall connection bolts and segment circumferential connection bolts (between segments), and finally tighten the longitudinal connection bolts (between rings).
[0021] S2-5. After the connection of the segments is completed, foam strips and water-expandable rubber sealing pads are placed between the longitudinal and circumferential seams of the segments to seal the seams;
[0022] S2-6. When two adjacent segments are spliced, waterproof material is applied to the segment joints for internal waterproofing, and external grouting is used for external waterproofing of the segments;
[0023] S2-7. After the quasi-rectangular pipe gallery is assembled, reinforced concrete diaphragms are cast on site according to the number of pipelines entering the gallery to divide the quasi-rectangular pipe gallery into three or four compartments;
[0024] S3. Pipe jacking method: the rectangular segment ring is assembled in the working pit and then jacking is carried out.
[0025] The beneficial effects of the present invention are:
[0026] (1) Compared with the traditional circular integrated pipe gallery, the rectangular structure of the present invention is easier to divide the spatial structure, improves the utilization rate of space, facilitates the laying, maintenance and repair of various pipelines, and reduces the maintenance cost.
[0027] (2) Compared with the traditional circular utility tunnel, the rectangular utility tunnel of the present invention has a simple shape and can change the width and height according to the requirements of the underground space. For the same underground depth, the rectangular utility tunnel can be buried deeper.
[0028] (3) The rectangular integrated pipe gallery segments and partition walls of the present invention are prefabricated and assembled, and the segments and upper and lower partition walls are connected by bent bolts, which greatly simplifies the construction operation and has relatively low requirements on construction personnel. The components are simple and easy to process, and the connection of the segments is carried out simultaneously with the construction, which is time-saving and efficient and can significantly shorten the construction period.
[0029] (4) The pipe segment concrete in the present invention adopts phase change concrete, which can effectively delay the temperature rise and temperature drop inside the phase change concrete, reduce the maximum adiabatic temperature rise, thereby reducing the temperature stress of the concrete structure in the pipe gallery, effectively regulating the ambient temperature changes inside the pipe gallery, narrowing the range of temperature fluctuations, improving its comfort, reducing the number of ventilation machinery and equipment, and reducing investment costs. BRIEF DESCRIPTION OF THE DRAWINGS
[0030] Figure 1 It is a schematic diagram of the rectangular pipe gallery segment structure;
[0031] Figure 2 It is a schematic diagram of the cross-sectional structure of a rectangular integrated pipe gallery segment;
[0032] Figure 3 It is a schematic diagram of the connection of the pipe segments of a quasi-rectangular integrated pipe gallery (cross section);
[0033] Figure 4 It is a schematic diagram of the connection of multiple segments of a rectangular utility corridor (in the longitudinal direction);
[0034] Figure 5 yes Figure 3 Schematic diagram of node A in the middle (Figure a is a schematic diagram of the longitudinal section of the partition wall, and Figure b is a schematic diagram of the embedded steel bars in the longitudinal direction);
[0035] Figure 6 yes Figure 3 Schematic diagram of the B node;
[0036] Figure 7 yes Figure 2 Schematic diagram of the middle C node (Figure a is a schematic diagram of the cross section of the joint waterproof structure, and Figure b is a schematic diagram of the longitudinal section of the joint waterproof structure);
[0037] Figure 8It is a reinforced concrete layout diagram of the rectangular integrated pipeline corridor segment structure.
[0038] Explanation of the accompanying drawings: 1-the first section of the tunnel section structure; 2-the second section of the tunnel section structure; 3-the third section of the tunnel section structure; 4-the fourth section of the tunnel section structure; 5-arch arc segment; 6-the upper half of the right side of the tunnel section; 7-the lower half of the right side of the tunnel section; 8-arch bottom arc segment; 9-the lower half of the left side of the tunnel section; 10-the upper half of the left side of the tunnel section; 11-upper partition wall; 12-lower partition wall; 13-longitudinal connecting bolts; 14-segment circumferential connecting bolts; 15-hand hole; 16-partition wall connecting bolts; 17-embedded steel bars; 18-partition wall embedded steel bar socket; 19-foam strip; 20-water-swelling rubber sealing pad; 21-grouting hole; 22-segment steel bars; 23-phase change concrete; 24-bolt hole; 25-cast-in-place diaphragm; 26-joint waterproof structure. DETAILED DESCRIPTION
[0039] The present invention is further described below in conjunction with embodiments. The description of the following embodiments is only used to help understand the present invention. It should be noted that for those of ordinary skill in the art, without departing from the principles of the present invention, several improvements and modifications may be made to the present invention, and these improvements and modifications also fall within the scope of protection of the claims of the present invention.
[0040] This patent adopts several smooth and conductive curves to form a closed outline similar to a rectangle, which improves space utilization and the operability of structural division and facilitates pipeline laying; the corridor structure adopts phase change reinforced concrete prefabricated segments and columns to avoid welding connections between steel plates, and utilizes the phase change energy storage technology of rectangular corridor structure concrete to absorb or release a large amount of phase change latent heat during the phase change process to store energy, effectively adjust the ambient temperature changes inside the corridor, narrow the range of temperature fluctuations, improve its comfort, reduce the number of ventilation machinery and equipment, and reduce investment costs.
[0041] Embodiment 1
[0042] like Figure 1-Figure 4 As shown, the phase change concrete rectangular pipe gallery structure includes a plurality of rectangular pipe segment rings (i.e., the first pipe gallery segment structure 1, the second pipe gallery segment structure 2, the third pipe gallery segment structure 3, and the fourth pipe gallery segment structure 4) connected in sequence along the longitudinal direction, an upper partition wall 11, a lower partition wall 12, a cast-in-place transverse partition 25, connecting bolts (i.e., longitudinal connecting bolts 13, hand holes 15, partition wall connecting bolts 16), and a joint waterproof structure. Figure 1The diagram is a segment block diagram of a quasi-rectangular tunnel structure. In this segment block method, the entire segment ring structure is formed by six segments being spliced together, and are respectively defined as the arch top circular arc segment located at the arch top position, the right upper semicircular arc segment and the right lower semicircular arc segment located at the arch waist position, the arch bottom circular arc segment located at the arch bottom position, the left lower semicircular arc segment and the left upper semicircular arc segment located at the arch waist position. Of course, the segment block method applicable to the segment structure of a quasi-rectangular shield tunnel of the present invention is not limited to this, and the segment structure applicable to the quasi-rectangular tunnel structure of the present invention can also be divided according to other division methods, as long as the cross-sectional form of the segment structure after the final splicing meets the cross-sectional form required by the above requirements, which will not be described one by one here.
[0043] In this embodiment, the radii R1 of the left and right haunch arc segments are equal, and the center of the circle is at Figure 1 At O1, the value range of R1 is 2500mm~3000mm. The radius R2 of the arch top arc segment and the arch bottom arc segment is centered at Figure 1 At O2, the value range of R2 is 8000mm~12000mm; R1 is smaller than R2; the arc segments of the arch crown and arch bottom are smoothly inscribed and connected with the two arch waist arc segments at E, F, G and H respectively.
[0044] The middle of the arch top arc section and the arch bottom arc section is connected by the upper partition wall 11 and the lower partition wall 12, which can make the overall pipe segment structure more stable. The cast-in-place transverse diaphragm 25 is cast-in-place and connected to the partition wall and the pipe segment structure.
[0045] According to different strata and lithology, shield tunneling and pipe jacking can be used for excavation. The rectangular pipe gallery segment structure is constructed by prefabrication and assembly, and the internal diaphragm is constructed by cast-in-place according to the number of compartments. For example, the first pipe gallery segment structure 1, the second pipe gallery segment structure 2, the third pipe gallery segment structure 3 and the fourth pipe gallery segment structure 4 given in this embodiment are prefabricated in advance by the factory, and each pipe gallery segment (each ring pipe segment) is connected by a longitudinal connecting bolt 13; the first pipe gallery segment structure 1, the second pipe gallery segment structure 2, the third pipe gallery segment structure 3 and the fourth pipe gallery segment structure 4 are all composed of six pipe segments, and each pipe segment is connected by an annular connecting bolt 14.
[0046] When the segments are prefabricated, in order to facilitate the connection of the segments with longitudinal connecting bolts 13, the inner edge of the segment is provided with a bolt hole 24 reserved for installation. The bolt hole 24 is an arc-shaped channel inside the segment. The arc radius of the arc-shaped channel is equal everywhere. A gap is reserved in the arc-shaped channel to facilitate the smooth passage of the installation bolts. The cross section of the bolt hole is circular, and an operating concave hole, i.e., a hand hole 15, is arranged at the end of the bolt hole.
[0047] The upper partition wall 11 and the lower partition wall 12 are connected by partition wall connecting bolts 16 , and the reserved mounting bolt holes and hand holes are designed in the same manner as the longitudinal connecting bolts 13 .
[0048] The arch top arc segment and the upper partition wall, and the arch bottom arc segment and the lower partition wall are connected by embedded steel bars 17. Each ring of the arch top arc segment 5 and the arch bottom arc segment 8 is provided with two rows of embedded steel bars in the longitudinal direction, with 3 embedded steel bars in each row. Two rows of embedded steel bar sockets are provided at positions corresponding to the upper partition wall 11 and the lower partition wall 12, with 3 embedded steel bar sockets in each row.
[0049] The rectangular pipe gallery section can be divided into three compartments or four compartments by a transverse partition according to the needs of the pipelines entering the gallery, and the transverse partition adopts a cast-in-place reinforced concrete structure. In this embodiment, a transverse partition is set in the right half of the pipe gallery to form a three-compartment structure. A transverse partition 25 can be set in the left half of the pipe gallery as needed to form a four-compartment structure.
[0050] Foam strips 19 and water-swelling rubber gaskets 20 are used to seal the joints between the longitudinal and circumferential seams of the segments. Foam strips 19 are filled near the edges on both sides of the joint, and water-swelling rubber gaskets 20 are set on the outside of the foam strips 19. The water-swelling rubber gasket is completely pressed into the gasket groove. The cross-sectional area of the gasket groove is not less than the cross-sectional area of the gasket. The depth-to-width ratio of the caulking groove is not less than 2.5, the groove depth is 25-55mm, and the single-sided groove width is 5-10mm. Grouting holes are set in the middle of the six segments for grouting reinforcement behind the wall.
[0051] The pipe segment structure of the phase change concrete rectangular pipe gallery of the present invention is a reinforced concrete structure, which is cast by a steel mesh and phase change concrete 23. The composite phase change material of the phase change concrete 23 can be selected from capric acid + lauric acid, n-pentadecane + n-hexadecane in a certain proportion, the phase change temperature of the composite phase change material is 14-16°C in winter, and the phase change temperature in summer is 24-27°C, and the ratio of the composite phase change material can be 7:3, 6:4, 5:5, 4:6 and 3:7.
[0052] It should be noted that the pipe segments of the quasi-rectangular pipe gallery are prefabricated, and the phase change concrete therein can be the phase change concrete in the prior art or the phase change concrete provided in this embodiment.
[0053] For example, in this embodiment, considering that the phase change temperature of the segment phase change concrete is 14-16°C in winter and 24-27°C in summer, the composite phase change material is selected from capric acid + lauric acid, n-pentadecane + n-hexadecane, and the blending ratio can be 7:3, 6:4, 5:5, 4:6, 3:7. The composition of the phase change concrete includes cement, fly ash, sand, gravel, water, fly ash ceramsite, phase change material, etc.
[0054] The material ratio and performance parameters of the phase change concrete in this embodiment are as follows:
[0055] (1) Configuration scheme of composite phase change materials
[0056] Table 1. Related data of phase change materials in the prior art
[0057] Phase change materials Phase transition temperature℃ Latent heat of phase change j / g Opening degree Molecular formula Molecular weight Pentadecane 9.5 207 282.65 C15H32 212.41 Hexadecane 16.7 236.6 289.85 C16H34 226.44 Decanoic acid 31.3 136 304.45 C10H20O2 172.26 Lauric acid 43.1 150.5 316.25 C14H26O2 226.35
[0058] Table 2 Target temperature of composite phase change material obtained by using phase change materials in the above table in this embodiment
[0059]
[0060] Table 3 DSC curves of composite phase change materials under different ratio conditions
[0061] Group Ratio Phase transition temperature℃ Latent heat of phase change j / g M-1 7:3 12.39 174.9 M-2 6:4 13.2 185.3 M-3 5:5 13.44 169.8 M-4 4:6 13.82 166.6 M-5 3:7 14.57 158.8 N-1 7:3 21.53 156.7 N-2 6:4 21.98 146.4 N-3 5:5 24.52 150.5 N-4 4:6 23.21 163.8 N-5 3:7 22.7 152.9
[0062] Among them, M-5 and N-3 meet the requirements.
[0063] (2) Mix design of phase change concrete
[0064] Table 4 Phase change concrete material list
[0065] name cement sand gravel Phase change ceramsite Fly ash Mineral powder graphite Admixtures water Specification PO 42.5 medium sand 5-20mm 8-15mm Level 2 Polycarboxylic acid
[0066] Table 5 Phase change concrete mix ratio
[0067] Serial number cement sand gravel Phase change ceramsite Fly ash Mineral powder graphite Admixtures water Ordinary concrete 380 770 1030 0 40 40 0 4.6 180 Phase change concrete t10 380 770 927 103 40 40 0 4.6 180 Phase change concrete t20 380 770 824 206 40 40 0 4.6 180 Phase change concrete t30 380 770 721 309 40 40 0 4.6 180 Phase change concrete s10 380 770 927 103 40 36 4 4.6 180 Phase change concrete s20 380 770 824 206 40 28 12 4.6 180 Phase change concrete s30 380 770 721 309 40 20 20 4.6 180
[0068] Embodiment 2
[0069] The assembly construction method of the phase change concrete rectangular pipe gallery structure comprises the following steps:
[0070] (1) According to different strata and lithologies and the cross-sectional dimensions of the rectangular utility corridor, shield or jacking methods are used for excavation and segment assembly.
[0071] (2) The assembly of prefabricated segments using the shield method mainly includes the following steps:
[0072] 1) Producing standard-sized arch top arc segment segments 5, upper semi-circular segment segments, lower semi-circular segment segments, and arch bottom arc segment segments 8 in a prefabricated component factory;
[0073] 2) During the construction process using the shield, the segments are hoisted and assembled in the order of arch bottom arc segment 8, right lower semi-circular arc segment 7, left lower semi-circular arc segment 9, right upper semi-circular arc segment 6, left upper semi-circular arc segment 10, and finally arch top arc segment 5.
[0074] 3) After the segment ring is positioned, the embedded steel bar holes on the lower partition wall 12 are connected to the embedded steel bars 17 on the arch bottom arc segment 8, and the embedded steel bar holes on the upper partition wall 11 are connected to the embedded steel bars 17 on the arch top arc segment 5.
[0075] 4) After completing the positioning of the pipe segment, insert the pipe segment circumferential connecting bolts 14, longitudinal connecting bolts 13 and partition wall connecting bolts 16 into the corresponding bolt holes. After passing through, fill the gaps in the arc-shaped bolt holes in the operator's hand hole by grouting, and then install bolt washers and nuts to fix and tighten the connecting bolts. First tighten the partition wall connecting bolts and circumferential (between pipe segments) connecting bolts, and finally tighten the longitudinal (between rings) connecting bolts.
[0076] 5) After the connection of the pipe segments is completed, foam strips 19 and water-swellable rubber sealing pads 20 are placed between the longitudinal and circumferential seams of the pipe segments to seal the seams.
[0077] 6) When two adjacent segments are spliced, waterproof material is applied to the segment joints for internal waterproofing, and external grouting is used for external waterproofing of the segments;
[0078] 7) According to the number of pipelines entering the corridor, reinforced concrete partitions are cast on site to divide the rectangular integrated pipeline corridor into three or four compartments.
[0079] (3) Pipe jacking method: the prefabricated pipe segment rings are assembled in the working pit and then pushed in by a pipe jacking machine.
[0080] The results of the embodiments show that the rectangular integrated pipe gallery of the present invention is easier to divide the spatial structure than the traditional circular integrated pipe gallery, and the rectangular structure can be easily divided into various pipelines, improve the utilization rate of the space, facilitate the laying, maintenance and repair of various pipelines, and reduce the maintenance cost. Compared with the traditional circular integrated pipe gallery, the shape is simple, and the width and height can be changed according to the requirements of the underground space. For the same underground depth, the rectangular can be buried deeper. The pipe segments and partition walls of the rectangular integrated pipe gallery adopt a prefabricated assembly method, and the pipe segments and the upper and lower partition walls are connected by bent bolts. The construction operation is greatly simplified, and the requirements for construction personnel are relatively low. The components are simple and easy to process. The connection of the pipe segments is carried out at the same time as the construction, which is time-saving and efficient, and can greatly shorten the construction period. The pipe segment concrete adopts phase change concrete, which can effectively delay the internal heating and cooling of the phase change concrete, reduce the maximum adiabatic temperature rise, reduce the temperature stress of the concrete structure in the pipe gallery, effectively adjust the ambient temperature changes inside the pipe gallery, reduce the range of temperature fluctuations, improve its comfort, reduce the number of ventilation machinery and equipment, and reduce investment costs.
Claims
1. A method for assembling and constructing a phase change concrete rectangular pipe gallery structure, characterized in that: The invention comprises a plurality of quasi-rectangular segment rings, an upper partition wall (11), a lower partition wall (12), a cast-in-place transverse diaphragm (25), connecting bolts and a joint waterproof structure, which are connected in sequence along the longitudinal direction; the quasi-rectangular segment rings are connected by longitudinal connecting bolts (13), and the segments in the quasi-rectangular segment rings are connected by segment annular connecting bolts (14); the middle of the quasi-rectangular segment ring is connected to the upper partition wall (11) and the lower partition wall (12) by embedded steel bars (17); the upper partition wall (11) and the lower partition wall (12) are connected by partition wall connecting bolts (16); the cast-in-place transverse diaphragm (25) is located between the partition wall and the segment, and is connected to the partition wall and the segment; a joint waterproof structure is provided between the longitudinal and annular seams of the segment; Any rectangular segment ring includes a vault circular arc segment located at the vault position, a right upper semicircular arc segment and a right lower semicircular arc segment located at the arch waist position, a arch bottom circular arc segment located at the arch bottom position, a left lower semicircular arc segment and a left upper semicircular arc segment located at the arch waist position; the radii R1 of the two arch waist circular arc segments are equal, the radius R2 of the vault circular arc segment and the arch bottom circular arc segment are equal, and R1 is smaller than R2; The six segments in any rectangular segment ring are prefabricated reinforced concrete structures, which are cast by segment steel bars (22) and phase change concrete (23); the composite phase change material in the phase change concrete is formed by mixing capric acid + lauric acid, n-pentadecane + n-hexadecane in a certain ratio, and the ratio is 7:3, 6:4, 5:5, 4:6 or 3:7; the phase change concrete is prepared by cement, fly ash, sand, gravel, water, fly ash ceramsite and the composite phase change material; The following steps are involved: S1. According to different strata and lithology, and the cross-sectional dimensions of the quasi-rectangular tunnel corridor, the shield method or the jacking method is used for excavation and segment assembly; S2. Shield method prefabricated segment assembly includes the following steps: S2-1, produce the arch top arc segment, upper half arc segment, lower half arc segment and arch bottom arc segment in the prefabricated component factory; S2-2. During the construction process using the shield, the segments are hoisted and assembled in the following order: arch bottom arc segment (8), right lower semi-circular segment (7), left lower semi-circular segment (9), right upper semi-circular segment (6), left upper semi-circular segment (10), and arch top arc segment (5). S2-3, after the quasi-rectangular segment ring is positioned, the embedded steel bar insertion holes on the lower partition wall (12) are connected to the embedded steel bars (17) on the arch bottom arc segment, and the embedded steel bar insertion holes on the upper partition wall (11) are connected to the embedded steel bars (17) on the arch top arc segment; S2-4, after completing the positioning of each segment, the segment circumferential connection bolts (14), the longitudinal connection bolts (13) and the partition wall connection bolts (16) are inserted into the corresponding bolt holes, and after passing through, the gaps in the arc-shaped bolt holes are filled in the hand holes (15) by grouting, and then the bolt washers and nuts are installed to connect and fix the bolts, first tightening the partition wall connection bolts and the segment circumferential connection bolts, and finally tightening the longitudinal connection bolts; S2-5, after the connection of the pipe segments is completed, foam strips (19) and water-swellable rubber sealing pads (20) are placed between the longitudinal and circumferential seams of the pipe segments to seal the seams; S2-6. When two adjacent segments are spliced, waterproof material is applied to the segment joints for internal waterproofing, and external grouting is used for external waterproofing of the segments; S2-7. After the quasi-rectangular pipe gallery is assembled, reinforced concrete diaphragms are cast on site according to the number of pipelines entering the gallery to divide the quasi-rectangular pipe gallery into three or four compartments; S3, pipe jacking method construction, the rectangular pipe segment ring is assembled in the working pit and then jacking is carried out.
2. The method for assembling and constructing a phase change concrete rectangular pipe gallery structure according to claim 1, characterized in that: The radius of the arch top circular arc segment and the arch bottom circular arc segment is 8000mm-12000mm, and the radius of the arch waist circular arc segment is 2500mm-3000mm; the arch top circular arc segment and the arch bottom circular arc segment are respectively smoothly inscribed and connected with the two arch waist circular arc segments.
3. The method for assembling and constructing a phase change concrete rectangular pipe gallery structure according to claim 1, characterized in that: Bolt holes (24) are provided at the inner surface edge of each segment in the quasi-rectangular segment ring, and bolt holes (24) are provided at the connection between the upper partition wall (11) and the lower partition wall (12). The bolt holes (24) are arc-shaped channels inside the segment, and the arc radius of the arc-shaped channels is equal everywhere, and a gap is reserved in the arc-shaped channels. The cross-section of the connecting bolts is circular. Hand holes (15) are arranged at the ends of the bolt holes (24). The bolt holes and hand holes used for installing the longitudinal connecting bolts (13), the segment annular connecting bolts (14) and the partition wall connecting bolts (16) have the same structure.
4. The method for assembling and constructing a phase change concrete rectangular pipe gallery structure according to claim 1, characterized in that: Grouting holes (21) are provided on the six segments in any rectangular segment ring.