Tower deviation correction method, device and system

By monitoring the status information of the tower and automatically adjusting the height of the foundation beam, the problem of low tower deviation correction efficiency is solved and the safety and efficiency of the tower are improved.

CN112648146BActive Publication Date: 2024-10-18HUANENG COAL TECH RES CO LTD
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202011509185.0
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2020-12-18
Publication Date
2024-10-18
Estimated Expiration
2040-12-18

AI Technical Summary

Technical Problem

The existing tower deviation correction technology is inefficient, resulting in low tower safety and requiring manual inspection for maintenance, which is slow and costly.

Method used

By monitoring the status information of the tower, using inclinometer sensors and settlement deflection sensors to detect the deflection and settlement status, the jacking equipment is automatically controlled to adjust the height of the foundation beam to achieve automatic deviation correction of the tower.

Benefits of technology

It reduces the workload of manual inspections, improves the efficiency of tower deviation correction, improves the safety of the tower, and saves manpower and material resources.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN112648146B_ABST
    Figure CN112648146B_ABST
Patent Text Reader

Abstract

The present invention provides a tower deviation correction method, device and system, the tower deviation correction method comprising: monitoring the state information of the target tower; wherein the state information comprises deflection state information and / or settlement state information; judging whether the target tower is deflected and / or settled based on the state information; and when the target tower is deflected and / or settled, performing deviation correction control on the target tower based on the state information. The present invention can automatically perform deviation correction control on the tower when the tower is deflected and / or settled, thereby reducing the workload of manual inspection, saving manpower and material resources, improving the tower deviation correction efficiency, and improving the safety of the tower.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of safety monitoring, and in particular to a tower deviation correction method, device and system. Background Art

[0002] The tower is a tall metal structure. Different shapes of tower structures can be designed according to the project requirements. The tower is widely used and can be used in communication projects, monitoring projects or power transmission projects. Take the tower in the power transmission project as an example. The transmission tower is an important part of the transmission line. The transmission line is usually supported by multiple towers. The tower body is usually fixed to the ground through the foundation column to ensure that the tower does not tilt, collapse or sink.

[0003] However, since transmission towers are usually located in the wild, they are greatly affected by the environment. For example, they are prone to tilting due to long-term strong winds. When transmission towers are located in mining areas, the surface of the mining areas is prone to sinking, collapse or tilt deformation, which seriously threatens the safety of transmission towers on the surface of the mining areas. Therefore, it is very necessary to monitor the posture of transmission towers.

[0004] At present, tower deviation correction mainly relies on manual inspection of transmission towers. After the transmission tower deflects or sinks, the staff will perform on-site maintenance on the transmission tower, which is time-consuming, labor-intensive, and inefficient. Therefore, the existing tower deviation correction technology still has the problem of low deviation correction efficiency and low tower safety. Summary of the invention

[0005] In view of this, the object of the present invention is to provide a tower correction method, device and system, which can automatically correct the tower when the tower is skewed and / or settled, thereby reducing the workload of manual inspections, saving manpower and material resources, improving the tower correction efficiency, and improving the safety of the tower.

[0006] In order to achieve the above purpose, the technical solution adopted by the embodiment of the present invention is as follows:

[0007] In a first aspect, an embodiment of the present invention provides a tower correction method, comprising: monitoring status information of a target tower; wherein the status information includes deflection status information and / or settlement status information; judging whether the target tower is deflected and / or settled based on the status information; when the target tower is deflected and / or settled, performing correction control on the target tower based on the status information.

[0008] Further, an embodiment of the present invention provides a first possible implementation of the first aspect, wherein the target tower includes a plurality of foundation columns, a tower body and a foundation beam, the foundation columns are arranged below the tower body, and the foundation beams are fixedly arranged between any two foundation columns; the status information includes skew status information; the step of performing correction control on the target tower based on the status information includes: determining a skewed target tower body based on the skew status information; taking the foundation beam associated with the foundation column below the target tower body as the target foundation beam, and controlling the height of the target foundation beam based on the status information to restore the target tower body to a horizontal state.

[0009] Further, an embodiment of the present invention provides a second possible implementation of the first aspect, wherein the target tower includes a plurality of foundation columns, a tower body and a foundation beam, the foundation columns are arranged below the tower body, and the foundation beams are fixedly arranged between pairs of foundation columns; the status information includes settlement status information; the step of performing correction control on the target tower based on the status information comprises: taking the foundation beam associated with each foundation column of the target tower as the target foundation beam, and controlling the height of the target foundation beam based on the status information to restore the target tower body to a horizontal state.

[0010] Furthermore, an embodiment of the present invention provides a third possible implementation of the first aspect, wherein the tower correction method is applied to a tower correction system, the tower correction system includes a jacking device, and the step of controlling the height of the target foundation beam based on the status information includes: controlling the lifting height of the jacking device under the target foundation beam based on the status information to adjust the height of the target foundation beam.

[0011] Furthermore, an embodiment of the present invention provides a fourth possible implementation of the first aspect, wherein the tower correction system includes an alarm device, and the method further includes: obtaining a current rising height of the jacking device, and when the current rising height reaches a preset height, issuing an alarm based on the alarm device; wherein the preset height is related to the range of the jacking device.

[0012] Furthermore, an embodiment of the present invention provides a fifth possible implementation of the first aspect, wherein the tower correction method is applied to a tower correction system, and the tower correction system includes an inclination sensor; the status information includes deflection status information; the step of monitoring the status information of the target tower includes: detecting the deflection status information of the target tower based on the inclination sensor; wherein the inclination sensor is arranged on the tower body.

[0013] Furthermore, an embodiment of the present invention provides a sixth possible implementation of the first aspect, wherein the tower correction method is applied to a tower correction system, and the tower correction system includes a settlement deflection sensor; the status information includes settlement status information; the step of monitoring the status information of the target tower includes: detecting the settlement status information of the target tower based on the settlement deflection sensor; wherein the settlement deflection sensor is arranged on the tower body or the foundation column.

[0014] In the second aspect, an embodiment of the present invention further provides a tower correction device, comprising: an information monitoring module, used to monitor the status information of a target tower; wherein the status information includes deflection status information and / or settlement status information; a status judgment module, used to judge whether the target tower is deflected and / or settled based on the status information; and a control module, used to perform correction control on the target tower based on the status information when the target tower is deflected and / or settled.

[0015] In a third aspect, an embodiment of the present invention provides a tower correction system, comprising: a controller, a lifting device, an alarm device, an inclinometer sensor and a settlement deflection sensor; the controller comprises a processor and a storage device; a computer program is stored on the storage device, and the computer program, when executed by the processor, executes the method described in any one of the first aspects.

[0016] In a fourth aspect, an embodiment of the present invention provides a computer-readable storage medium, on which a computer program is stored. When the computer program is executed by a processor, the steps of the method described in any one of the above-mentioned first aspects are executed.

[0017] The embodiments of the present invention provide a tower correction method, device and system, which monitor the status information of the tower and determine whether the tower is skewed and / or settled based on the monitored status information. When the tower is skewed and / or settled, the tower can be automatically corrected in time, thereby reducing the workload of manual inspections, saving manpower and material resources, improving the tower correction efficiency, and improving the safety of the tower.

[0018] Other features and advantages of the embodiments of the present invention will be described in the following description, or some features and advantages can be inferred or determined without doubt from the description, or can be learned by implementing the above-mentioned techniques of the embodiments of the present invention.

[0019] In order to make the above-mentioned objects, features and advantages of the present invention more obvious and easy to understand, preferred embodiments are given below and described in detail with reference to the accompanying drawings. BRIEF DESCRIPTION OF THE DRAWINGS

[0020] In order to more clearly illustrate the specific implementation methods of the present invention or the technical solutions in the prior art, the drawings required for use in the specific implementation methods or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some implementation methods of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0021] Figure 1 A flow chart of a tower deviation correction method provided by an embodiment of the present invention is shown;

[0022] Figure 2 A schematic diagram of a target tower structure provided by an embodiment of the present invention is shown;

[0023] Figure 3 A schematic structural diagram of a tower deviation correction device provided by an embodiment of the present invention is shown;

[0024] Figure 4 A schematic diagram of the structure of a controller provided by an embodiment of the present invention is shown.

[0025] icon:

[0026] 211~214-foundation columns; 221~224-tower body; 231~234-foundation beams; 24-tower pole; 25-inclinometer sensor; 26-lifting equipment. DETAILED DESCRIPTION

[0027] In order to make the purpose, technical solution and advantages of the embodiments of the present invention clearer, the technical solution of the present invention will be described below in conjunction with the drawings. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all of the embodiments.

[0028] At present, the main method for correcting the deviation of the tower is to rely on walking inspections by personnel. The inspection time is long and the field conditions are difficult. If the transmission line fails, it is difficult for repair personnel and materials to arrive at the site in time. Moreover, the manual inspection method is difficult to monitor the instability process of the tower foundation, which will miss the opportunity to strengthen it. In addition, when the transmission tower deflects, workers are required to go to the site to maintain and adjust the transmission tower. In the process of manual adjustment, there are problems of slow efficiency and high labor costs.

[0029] Considering that the existing tower deviation correction technology still has the problem of low deviation correction efficiency leading to low tower safety, in order to improve this problem, the embodiments of the present invention provide a tower deviation correction method, device and system, which can be used to improve the safety of the tower. The embodiments of the present invention are described in detail below.

[0030] This embodiment provides a tower deviation correction method, which can be applied to a tower automatic deviation correction system. Figure 1 The tower deviation correction method flow chart shown in the figure mainly includes the following steps S102 to S106:

[0031] Step S102: monitoring the status information of the target tower.

[0032] The above-mentioned state information includes deflection state information and / or settlement state information. The above-mentioned target tower may include one or more towers, and the tower may be a transmission tower in a mining area. The above-mentioned target tower includes a plurality of foundation columns (also referred to as tower feet), a tower body and a foundation beam, wherein the foundation columns are arranged below the tower body, and the foundation beams are fixedly arranged between two foundation columns. The above-mentioned target tower may be a tower structure in various forms such as a triangular tower and a quadrangular tower.

[0033] The above-mentioned tower correction method can be applied to a tower correction system, which includes a controller, a jacking device, an alarm device, an inclinometer sensor and a settlement deflection sensor, wherein the inclinometer sensor is arranged on the tower body, and the settlement deflection sensor is arranged on the tower body or the foundation column. The number of inclinometer sensors can be the same as the number of tower bodies, and the number of jacking devices can be the same as the number of foundation beams.

[0034] The deflection state information of the target tower is detected in real time or at a preset time interval based on the inclinometer sensor, and / or the settlement state information of the target tower is detected in real time or at a preset time interval based on the settlement deflection sensor. The inclinometer sensor sends the detected deflection state information to the controller, and the settlement deflection sensor sends the detected settlement state information to the controller, so as to realize accurate monitoring of the state of the target tower.

[0035] Step S104: determining whether the target tower is deflected and / or subsided based on the status information.

[0036] The deflection state information detected by the above-mentioned inclinometer sensor can be the relative coordinate values ​​of each inclinometer sensor relative to the same reference point. When there are abnormal coordinate values ​​in each relative coordinate value, it is determined that the target tower is deflected. The settlement state information detected by the above-mentioned settlement deflection sensor can be the height change value of the settlement deflection sensor relative to the measured point. When each height change value is greater than the set height value (the height change value that can affect the safety of the tower), it is determined that the target tower is settled, that is, the target tower has sunk a certain height (height change value).

[0037] Step S106: when the target tower is deflected and / or subsided, the target tower is corrected based on the status information.

[0038] When the target tower is deflected, the height of the foundation beam that causes the deflection of the target tower is adjusted according to the degree of deflection of the target tower to achieve the level of the tower. When the target tower is subsided, the height of each foundation beam is controlled according to the degree of subsidence of the target tower to restore the target tower to a normal height. When the target tower is deflected and subsided at the same time, the height of each foundation beam is controlled based on the degree of deflection and subsidence of the target tower to ensure the stability of the center of gravity of the tower. The deflection of the above-mentioned target tower refers to the subsidence of some foundation columns, and the subsidence of the target tower refers to the subsidence of all foundation columns.

[0039] The tower correction method provided in the present embodiment monitors the status information of the tower and determines whether the tower is skewed and / or sunk based on the monitored status information. When the tower is skewed and / or sunk, the tower can be corrected and controlled automatically in a timely manner, thereby reducing the workload of manual inspections, saving manpower and material resources, improving the tower correction efficiency, and improving the safety of the tower.

[0040] This embodiment takes a four-corner tower as an example. Figure 2 As shown in the target tower structure schematic diagram, the target tower includes four foundation columns 211-214, an iron tower body 221-224 and four foundation beams 231-234, the foundation columns 211-214 are respectively arranged below the iron tower body 221-224, the foundation columns 211-214 are fixedly arranged on the ground, and are used to support the tower pole 24 and transfer the load borne by the tower pole 24 to the ground. The tower pole 24 is used to support the conductor, the ground wire and its accessories, so that a certain safety distance is guaranteed between the conductor and the conductor, the conductor and the ground wire, and the conductor and the ground or buildings.

[0041] like Figure 2 As shown, the upper ends of four tower bodies 221-224 respectively fixedly connected to the foundation columns 211-214 are fixedly connected by connecting pieces, and the connection of the upper ends of the tower bodies 221-224 forms the upper end face of the tower. The tower pole 24 is fixed at the centroid position of the upper end face of the target tower to ensure that the tower pole 24 is perpendicular to the upper end face of the tower, thereby making the force on the tower uniform. The foundation beam 231 is fixedly arranged between the foundation column 211 and the foundation column 212, the foundation beam 232 is fixedly arranged between the foundation column 212 and the foundation column 213, the foundation beam 233 is fixedly arranged between the foundation column 213 and the foundation column 214, and the foundation beam 234 is fixedly arranged between the foundation column 214 and the foundation column 211. The connection of the lower ends of the four tower bodies 221 to 224 forms the lower end face of the iron tower. The centroid of the lower end face of the iron tower and the centroid of the upper end face of the iron tower are in the same straight line and are both located in the axial direction of the tower pole 24. At the same time, the area of ​​the upper end face of the tower is smaller than the area of ​​the lower end face of the iron tower. The tower bodies 221 to 224 have the same inclination angle toward the tower pole 24 to form a uniform and effective support for the tower pole 24. Figure 2As shown, an inclinometer sensor 25 is provided on each tower body, and a jacking device 26 is provided under each foundation beam.

[0042] In order to improve the accuracy of the target tower deviation correction control, this embodiment provides an implementation method of performing deviation correction control on the target tower based on the state information, which can be specifically performed with reference to the following implementation methods 1 and 2:

[0043] Implementation method 1: In this implementation method, the above-mentioned status information includes skew status information. Based on the skew status information, a target tower body with a skew is determined; the foundation beam associated with the foundation column below the target tower body is used as the target foundation beam, and the height of the target foundation beam is controlled based on the status information to restore the target tower body to a horizontal state. Based on the inclination status information detected by the inclinometer sensor, a skewed tower body (which may be one or more) can be determined, and the skewed tower body is used as the target tower body. Figure 2 As an example, assume that the deflected tower body is 221, the tower body 221 is used as the target tower body, and the foundation beam associated with the foundation column 211 below the target tower body 221 is used as the target foundation beam. Figure 2 It can be seen that the foundation column 211 is connected to the foundation beam 231 and the foundation beam 234 respectively, that is, the foundation column 211 is associated with the foundation beam 231 and the foundation beam 234, and the foundation beam 231 and the foundation beam 234 are used as target foundation beams.

[0044] Based on the deflection state information obtained by the inclinometer sensor, the lifting height of the lifting equipment under the target foundation beam is controlled to adjust the height of the target foundation beam. Based on the difference between the abnormal coordinate value and the normal coordinate value in the relative coordinate value of the deflection state information obtained by the inclinometer sensor, the deflection degree of the target tower is determined. The greater the difference between the abnormal coordinate value and the normal coordinate value, the greater the deflection degree of the target tower, and the greater the height value of the target foundation beam to be controlled to rise. When the deflected tower body is 221, the lifting equipment under the target foundation beams 231 and 234 is controlled to rise to a certain height value, which is proportional to the above-mentioned deflection degree, and the proportionality coefficient can be determined according to the structural size of the target tower.

[0045] Embodiment 2: In this embodiment, the above-mentioned state information includes settlement state information. The foundation beam associated with each foundation column of the target tower is used as the target foundation beam, and the height of the target foundation beam is controlled based on the state information so that the target tower body is restored to a horizontal state. The lifting height of the jacking equipment below the target foundation beam is controlled based on the settlement state information to adjust the height of the target foundation beam.

[0046] Since the settlement of the target tower refers to the settlement of all foundation columns, the foundation beams associated with all foundation columns of the target tower are taken as target foundation beams. The settlement status information of each foundation column detected by each settlement deflection sensor is used to determine the settlement degree of each foundation column. The greater the height change value detected by the settlement deflection sensor, the greater the settlement degree of the foundation column. Based on the settlement degree of each foundation column, the target foundation beams associated with each foundation column are controlled to rise to a corresponding height value. The rising height value of each target foundation beam is proportional to the settlement degree of the associated foundation column. By adjusting the height of each foundation beam based on the jacking equipment, the target tower is restored to a normal height, and the force on the tower body above each foundation column is balanced.

[0047] When the above-mentioned state information includes deflection state information and settlement state information, the lifting height of the jacking equipment under each foundation beam is controlled based on the deflection state information and the settlement state information to adjust the height of the target foundation beam. According to the deflection degree and settlement degree of the target tower, the lifting height of the jacking equipment under each foundation beam is controlled to keep the target tower horizontal and at a normal height.

[0048] In order to further improve the safety of the target tower, the method provided in this embodiment also includes: obtaining the current rising height of the jacking equipment, and when the current rising height reaches the preset height, an alarm is issued based on the alarm device; wherein the preset height is related to the range of the jacking equipment. The above-mentioned jacking equipment may be, for example, a hydraulic jacking equipment. Since the jacking equipment has a certain range, when the current rising height of the jacking equipment reaches the preset height, it will affect the safety of the target tower. The above-mentioned preset height may be, for example, any value between 80% and 90% of the range of the jacking equipment, that is, when the current rising height of the jacking equipment reaches the preset height, in order not to affect the next automatic deviation correction of the target tower, a remote alarm is issued through the alarm device to remind the staff to maintain the target tower to avoid danger to the target tower.

[0049] The tower correction method provided in this embodiment can obtain the status information of the target tower in time, and control the jacking equipment under the foundation beam according to the status information of the target tower, thereby realizing automatic correction control of the target tower and reducing the workload of manual inspection.

[0050] Corresponding to the tower deviation correction method provided in the above embodiment, the embodiment of the present invention provides a tower deviation correction device, see Figure 3 The structure diagram of a tower correction device shown in FIG. 1 includes the following modules:

[0051] The information monitoring module 31 is used to monitor the status information of the target tower; wherein the status information includes deflection status information and / or settlement status information.

[0052] The state judgment module 32 is used to judge whether the target tower is deflected and / or subsided based on the state information.

[0053] The control module 33 is used to perform deviation correction control on the target tower based on the status information when the target tower is deflected and / or subsided.

[0054] The tower correction device provided in the present embodiment monitors the status information of the tower and determines whether the tower is skewed and / or sunk based on the monitored status information. When the tower is skewed and / or sunk, the tower can be automatically and timely corrected, thereby reducing the workload of manual inspections, saving manpower and material resources, improving the tower correction efficiency, and improving the safety of the tower.

[0055] In one embodiment, the target tower comprises a plurality of foundation columns, a tower body and a foundation beam, wherein the foundation columns are arranged below the tower body, and the foundation beams are fixedly arranged between any two foundation columns; the status information comprises deflection status information; the control module 33 is further used to determine a deflected target tower body based on the deflection status information; the foundation beam associated with the foundation column below the target tower body is used as the target foundation beam, and the height of the target foundation beam is controlled based on the status information so as to restore the target tower body to a horizontal state.

[0056] In one embodiment, the target tower comprises a plurality of foundation columns, a tower body and a foundation beam, wherein the foundation columns are arranged below the tower body, and the foundation beams are fixedly arranged between any two foundation columns; the status information comprises skew status information; the control module 33 is further used to take the foundation beams associated with the foundation columns of the target tower as the target foundation beams, and to control the height of the target foundation beams based on the status information so as to restore the target tower body to a horizontal state.

[0057] In one embodiment, the control module 33 is further used to control the lifting height of the jacking equipment below the target foundation beam based on the status information to adjust the height of the target foundation beam.

[0058] In one embodiment, the tower deviation correction system includes an alarm device, and the device further includes:

[0059] The alarm module is used to obtain the current rising height of the jacking equipment, and when the current rising height reaches a preset height, an alarm is issued based on the alarm device; wherein the preset height is related to the range of the jacking equipment.

[0060] In one embodiment, the tower correction system includes an inclinometer sensor; the information monitoring module 31 is further used to detect the inclination state information of the target tower based on the inclinometer sensor; wherein the inclinometer sensor is arranged on the tower body.

[0061] In one embodiment, the tower correction system includes a settlement deflection sensor; the information monitoring module 31 is further used to detect the settlement status information of the target tower based on the settlement deflection sensor; wherein the settlement deflection sensor is arranged on the tower body or the foundation column.

[0062] The tower correction device provided in this embodiment can obtain the status information of the target tower in time, and control the jacking equipment under the foundation beam according to the status information of the target tower, thereby realizing automatic correction control of the target tower and reducing the workload of manual inspection.

[0063] The implementation principle and technical effects of the device provided in this embodiment are the same as those of the aforementioned embodiments. For the sake of brief description, for matters not mentioned in the device embodiment, reference may be made to the corresponding contents in the aforementioned method embodiment.

[0064] Corresponding to the method and device provided in the above-mentioned embodiment, the embodiment of the present invention further provides a tower correction system, which includes: a controller, a jacking device, an alarm device, an inclinometer sensor and a settlement deflection sensor. Among them, the jacking device, the alarm device, the inclinometer sensor and the settlement deflection sensor can communicate with the controller through a wireless communication module (such as 5G+) or a cable, and the controller can be a PLC controller (Programmable Logic Controller). When the above-mentioned jacking device, the alarm device, the inclinometer sensor and the settlement deflection sensor are respectively arranged on multiple towers, each jacking device, the alarm device, the inclinometer sensor and the settlement deflection sensor can be associated with the ID information of the tower, so as to automatically correct the multiple towers through the controller, realize "one control multiple" multi-channel remote control, and realize centralized control for a limited number of towers within a limited mining subsidence range, reduce the workload of manual inspection, and ensure the safety of tower operation.

[0065] In practical applications, the tower correction system may also include solar panels, which are arranged above the tower and used to power various devices in the tower correction system. When powering the tower correction system over a long distance, it will cause problems of large engineering workload and high cost; and the long-distance transmission lines will increase power loss and cause energy waste. By using solar panels to power the tower correction system, the power supply (solar panels) at the tower end can be directly used to power the tower correction system, and the electric energy converted from solar energy can be used to reduce costs and reduce losses on transmission lines.

[0066] The controller includes a processor and a storage device, such as Figure 4As shown in the schematic diagram of the controller structure, the controller includes a processor 41 and a memory 42. The memory stores a computer program that can be run on the processor. When the processor executes the computer program, the steps of the method provided in the above embodiment are implemented.

[0067] See also Figure 4 The controller further includes: a bus 44 and a communication interface 43, and the processor 41, the communication interface 43 and the memory 42 are connected via the bus 44. The processor 41 is used to execute executable modules stored in the memory 42, such as computer programs.

[0068] The memory 42 may include a high-speed random access memory (RAM), and may also include a non-volatile memory, such as at least one disk memory. The communication connection between the system network element and at least one other network element is realized through at least one communication interface 43 (which may be wired or wireless), and the Internet, wide area network, local area network, metropolitan area network, etc. may be used.

[0069] The bus 44 may be an ISA (Industry Standard Architecture) bus, a PCI (Peripheral Component Interconnect) bus, or an EISA (Extended Industry Standard Architecture) bus. The bus may be divided into an address bus, a data bus, a control bus, etc. For ease of representation, Figure 4 Only one bidirectional arrow is used in the diagram, but this does not mean that there is only one bus or only one type of bus.

[0070] Among them, the memory 42 is used to store programs, and the processor 41 executes the program after receiving the execution instruction. The method executed by the device for flow process definition disclosed in any embodiment of the above-mentioned embodiment of the present invention can be applied to the processor 41, or implemented by the processor 41.

[0071] The processor 41 may be an integrated circuit chip with signal processing capabilities. In the implementation process, each step of the above method can be completed by the hardware integrated logic circuit in the processor 41 or the instruction in the form of software. The above processor 41 can be a general-purpose processor, including a central processing unit (CPU), a network processor (NP), etc. It can also be a digital signal processor (DSP), an application-specific integrated circuit (ASIC), a field-programmable gate array (FPGA), or other programmable logic devices, discrete gates or transistor logic devices, discrete hardware components. The methods, steps and logic block diagrams disclosed in the embodiments of the present invention can be implemented or executed. The general-purpose processor can be a microprocessor or the processor can also be any conventional processor, etc. The steps of the method disclosed in the embodiment of the present invention can be directly embodied as a hardware decoding processor for execution, or a combination of hardware and software modules in the decoding processor for execution. The software module may be located in a storage medium mature in the art, such as a random access memory, a flash memory, a read-only memory, a programmable read-only memory, or an electrically erasable programmable memory, a register, etc. The storage medium is located in the memory 42, and the processor 41 reads the information in the memory 42 and completes the steps of the above method in combination with its hardware.

[0072] An embodiment of the present invention provides a computer-readable medium, wherein the computer-readable medium stores computer-executable instructions. When the computer-executable instructions are called and executed by a processor, the computer-executable instructions prompt the processor to implement the method described in the above embodiment.

[0073] Those skilled in the art can clearly understand that, for the convenience and brevity of description, the specific working process of the system described above can refer to the corresponding process in the aforementioned embodiment, and will not be repeated here.

[0074] The computer program product of the tower correction method, device and system provided in the embodiments of the present invention includes a computer-readable storage medium storing program code. The instructions included in the program code can be used to execute the methods described in the previous method embodiments. The specific implementation can be found in the method embodiments, which will not be repeated here.

[0075] In addition, in the description of the embodiments of the present invention, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0076] If the functions are implemented in the form of software functional units and sold or used as independent products, they can be stored in a computer-readable storage medium. Based on this understanding, the technical solution of the present invention, or the part that contributes to the prior art or the part of the technical solution, can be embodied in the form of a software product. The computer software product is stored in a storage medium, including several instructions for a computer device (which can be a personal computer, a server, or a network device, etc.) to perform all or part of the steps of the methods described in each embodiment of the present invention. The aforementioned storage medium includes: U disk, mobile hard disk, read-only memory (ROM, Read-Only Memory), random access memory (RAM, Random Access Memory), disk or optical disk, etc., which can store program codes.

[0077] In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", etc., indicating the orientation or positional relationship, are based on the orientation or positional relationship shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as limiting the present invention. In addition, the terms "first", "second", and "third" are used for descriptive purposes only, and cannot be understood as indicating or implying relative importance.

[0078] Finally, it should be noted that the above-described embodiments are only specific implementations of the present invention, which are used to illustrate the technical solutions of the present invention, rather than to limit them. The protection scope of the present invention is not limited thereto. Although the present invention is described in detail with reference to the above-described embodiments, ordinary technicians in the field should understand that any technician familiar with the technical field can still modify the technical solutions recorded in the above-described embodiments within the technical scope disclosed by the present invention, or can easily think of changes, or make equivalent replacements for some of the technical features therein; and these modifications, changes or replacements do not make the essence of the corresponding technical solutions deviate from the spirit and scope of the technical solutions of the embodiments of the present invention, and should be included in the protection scope of the present invention. Therefore, the protection scope of the present invention shall be based on the protection scope of the claims.

Claims

1. A tower deviation correction method, characterized in that: Applied to a tower correction system, the tower correction system includes a jacking device, an inclinometer sensor and a settlement deflection sensor, and the method includes: S102, monitoring the status information of the target tower; wherein the status information includes deflection status information and / or settlement status information; wherein the target tower includes a plurality of foundation columns, a tower body and a foundation beam, wherein the foundation columns are arranged below the tower body, and the foundation beam is fixedly arranged between two foundation columns; S104, judging whether the target tower is deflected and / or subsided based on the state information; S106, when the target tower is deflected and / or subsided, performing deviation correction control on the target tower based on the state information; Step S102 includes: Detecting the deflection state information of the target tower based on the inclinometer sensor; wherein the inclinometer sensor is arranged on the tower body, and the deflection of the target tower refers to the settlement of part of the foundation column; Detecting the settlement state information of the target tower based on the settlement deflection sensor; wherein the settlement deflection sensor is arranged on the tower body or the foundation column, and the settlement of the target tower refers to the settlement of all foundation columns; Step S104 includes: The deflection state information detected by the inclinometer sensor is the relative coordinate value of each inclinometer sensor relative to the same reference point. When there is an abnormal coordinate value among the relative coordinate values, it is determined that the target tower is deflected. The settlement state information detected by the settlement deflection sensor is a height change value of the settlement deflection sensor relative to the measured point. When each height change value is greater than a set height value, it is determined that the target tower has settled. Step S106 includes: Determine a target tower body that is deflected based on the deflection state information; take a foundation beam associated with a foundation column below the target tower body as a target foundation beam, and control the lifting height of a jacking device below the target foundation beam based on the state information to adjust the height of the target foundation beam so that the target tower body returns to a horizontal state; wherein the state information is deflection state information; The foundation beam associated with each foundation column of the target tower is taken as the target foundation beam, and the lifting height of the jacking equipment below the target foundation beam is controlled based on the status information to adjust the height of the target foundation beam so that the target tower body is restored to a horizontal state, wherein the status information is settlement status information.

2. The method according to claim 1, characterized in that The tower deviation correction system includes an alarm device, and the method further includes: The current lifting height of the lifting device is obtained, and when the current lifting height reaches a preset height, an alarm is issued based on the alarm device; wherein the preset height is related to the range of the lifting device.

3. A tower deviation correction device, characterized in that: The method applied to claim 1 or 2, wherein the tower deviation correction device comprises: An information monitoring module, used to monitor the status information of the target tower; wherein the status information includes deflection status information and / or settlement status information; A state judgment module, used for judging whether the target tower is deflected and / or subsided based on the state information; A control module is used to perform deviation correction control on the target tower based on the state information when the target tower is deflected and / or subsided.

4. A tower correction system, characterized in that: The tower deviation correction system comprises: a controller; the controller comprises a processor and a storage device; The storage device stores a computer program, which, when executed by the processor, performs the method according to claim 1 or 2.

5. A computer-readable storage medium having a computer program stored thereon, characterized in that: When the computer program is executed by a processor, the steps of the method according to claim 1 or 2 are performed.

Citation Information

Patent Citations

  • Continuous adjustable anti-mining-out foundation for mountainous region mined-out slope high-voltage power transmission tower

    CN108824476A

  • Building foundation adapting to foundation deformation of worked-out area

    CN201962689U