A pile foundation steel cage positioning frame and underwater positioning method for pile foundation steel cage
By designing the positioning frame of the pile foundation steel cage and using the center axis alignment principle of the horizontal rod and the extended leg, the problem of difficulty in determining the position of the underwater steel cage was solved, fast and accurate positioning was achieved, and construction quality and safety were improved.
Patent Information
- Application Number
- CN202011577801.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2020-12-28
- Publication Date
- 2024-10-11
- Estimated Expiration
- 2040-12-28
AI Technical Summary
During bridge construction, it is difficult to determine the position of the underwater steel cage, which causes the cage to shift and affects the construction quality. Existing technologies such as the hole drilling method and the pad method have low accuracy and safety hazards.
A pile foundation steel cage positioning frame is designed, including at least two horizontal rods and three extension legs. The extension legs are set vertically on the horizontal rods to form a circle, ensuring that when the extension legs are connected to the steel cage, the center of the circle The connection point of the horizontal rod is located on the same axis, and the center of the steel cage is determined by measuring the position of the connection point to avoid underwater measurement.
It achieves rapid and accurate determination of the position of the steel cage, improves construction accuracy and safety, avoids the risk of underwater measurement, and simplifies the underwater positioning process of the steel cage.
Smart Images

Figure CN112663597B_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of bridge construction, and in particular to a pile foundation reinforcement cage positioning frame and an underwater positioning method for the pile foundation reinforcement cage. Background Art
[0002] With the vigorous development of road and bridge construction, large and extra-large bridges across rivers and straits are constantly being built, and the construction conditions and geological conditions of bridges are becoming more and more complex. Among them, underwater bored piles are mostly large-diameter and deep concrete bored piles. During the piling process, it is very important to ensure the position accuracy of the steel cage during the concrete pouring process. The deviation of the position of the steel cage will lead to insufficient thickness of the steel cage protective layer, thus affecting the quality of project construction.
[0003] In some related technologies, since most of the pile foundation holes are filled with water and mud, the water and mud will submerge the steel cage, making it difficult to measure the position of the underwater steel cage. It is necessary to pump out the mud in the hole to make the top surface of the steel cage leak out, and then compare it with the center point of the protective pile to determine whether the placement is accurate; however, when the top surface of the steel cage is far away from the upper surface of the mud, pumping out the mud is likely to cause landslides.
[0004] In other related technologies, the position of the steel cage is currently mainly controlled by the steel pad protective layer method during the underwater placement of the bridge pile foundation steel cage. However, when the pad protective layer method is used to control the position of the steel cage, on the one hand, it is necessary to accurately control the diameter and verticality of the pile foundation hole. In addition, the different geological conditions on site, the drilling equipment and processes are different, so that the diameter of the pile top will be larger than the designed diameter, and the actual verticality will deviate from the designed verticality, so that the position of the steel cage placed in the pile foundation hole will also deviate; on the other hand, during the placement of the steel cage, the steel cage itself is also prone to deviation. Both aspects lead to inaccurate positioning of the steel cage. Therefore, it is necessary to conveniently and quickly determine whether the position of the steel cage is accurate during the security process. Summary of the invention
[0005] The embodiments of the present application provide a pile foundation steel cage positioning frame and an underwater positioning method for a pile foundation steel cage, so as to solve the problem that the position of the underwater steel cage is difficult to determine in the related art.
[0006] In a first aspect, a pile foundation reinforcement cage positioning frame is provided, comprising:
[0007] at least two horizontal rods, the horizontal rods being connected to form a connection point at the connection;
[0008] At least three extension legs are vertically arranged on the horizontal rod and used to connect with the steel cage; the distances between each extension leg and the point where it is connected to the horizontal rod are equal, and each extension leg is located on the same circle.
[0009] In some embodiments, the number of the horizontal rods is two, and the two horizontal rods are connected in a cross shape or a T-shape.
[0010] In some embodiments, the number of the horizontal rods is two, the two horizontal rods are cross-arranged, and a rotating shaft for connecting the two horizontal rods is provided at the intersection.
[0011] In some embodiments,
[0012] The number of the horizontal rods is three, and one ends of the three horizontal rods are connected to form the connection point.
[0013] In some embodiments, a connecting piece is further provided on the horizontal rod, and the connecting piece is detachably connected to the extending leg.
[0014] In some embodiments, the connector includes:
[0015] A connecting sleeve connected to the horizontal rod, wherein one end of the extending leg is located in the connecting sleeve;
[0016] The first locking portion is arranged on the connecting sleeve and is used to lock the extending leg on the connecting sleeve.
[0017] In some embodiments, there are multiple connecting members, which are arranged along the length direction of the horizontal rod.
[0018] In some embodiments, the extending leg comprises:
[0019] outside rod;
[0020] An inner rod, which is telescopically arranged with the outer rod;
[0021] The second locking portion is arranged on the outer rod and is used to lock the inner rod and the outer rod.
[0022] In some embodiments, a plug-in portion for connecting to a steel cage is provided at the end of the extending leg.
[0023] In a second aspect, a method for underwater positioning of a pile foundation reinforcement cage positioning frame is provided, comprising the following steps:
[0024] Installing the pile foundation steel cage positioning frame on the steel cage so that the connection point passes through the central axis of the steel cage;
[0025] Determine the center point of the pile position based on the guard pile;
[0026] The relative positions of the connection points and the center point are compared to adjust the steel cage.
[0027] The beneficial effects of the technical solution provided by this application include:
[0028] The embodiment of the present application provides a pile foundation steel cage positioning frame and an underwater positioning method for the pile foundation steel cage. Since at least two connected horizontal rods are connected, at least three extended legs are vertically arranged on the horizontal rod, and the extended legs are used to connect with the steel cage; the distances from each extended leg to the point where the horizontal rod is connected are equal, and each extended leg is located on the same circle. The above arrangement ensures that the extended legs are always located on the same circle, and the distance from the extended leg to the connection point is the radius, so that the center of the circle where the extended leg is located and the connection point of the horizontal rod are located on the same axis. When connected to the steel cage, the center of the circle where the extended leg is located is made to coincide with the center of the steel cage, so that the position of the connection point of the horizontal rod is measured, and the position of the center of the steel cage can be determined. This method lifts the measuring point above water, avoids the problem of measuring the position of the underwater steel cage, and has a simple structure, and can quickly determine the center of the steel cage. Therefore, the purpose of conveniently determining the position of the underwater steel cage is achieved. BRIEF DESCRIPTION OF THE DRAWINGS
[0029] In order to more clearly illustrate the technical solutions in the embodiments of the present application, the drawings required for use in the description of the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.
[0030] Figure 1 A top view of a reinforcement cage positioning frame provided in an embodiment of the present application;
[0031] Figure 2 A front view of a reinforcement cage positioning frame provided in an embodiment of the present application;
[0032] Figure 3 A top view of another type of reinforcement cage positioning frame provided in an embodiment of the present application;
[0033] Figure 4 A top view of another type of reinforcement cage positioning frame provided in an embodiment of the present application;
[0034] Figure 5 A top view of another type of reinforcement cage positioning frame provided in an embodiment of the present application;
[0035] Figure 6 A top view of another form of reinforcement cage positioning frame provided in an embodiment of the present application.
[0036] In the figure: 1, horizontal rod; 10, connection point; 2, extended leg; 20, outer rod; 21, inner rod; 22, second locking part; 3, plug-in part; 4, connecting piece; 40, connecting sleeve; 41, first locking part; 5, extension part; 6, third locking part. DETAILED DESCRIPTION
[0037] In order to make the purpose, technical solution and advantages of the embodiments of the present application clearer, the technical solution in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of this application.
[0038] The embodiments of the present application provide a pile foundation steel cage positioning frame and an underwater positioning method for a pile foundation steel cage, so as to solve the problem that the position of the underwater steel cage is difficult to determine in the related art.
[0039] See also Figures 1 to 6 ,, provides a pile foundation reinforcement cage positioning frame, which includes at least two horizontal rods 1, the horizontal rods 1 are connected to form a connection point 10 at the connection;
[0040] At least three extension legs 2 are vertically arranged on the horizontal rod 1 and extend downward, and the extended ends are connected to the steel cage. The distances between each extension leg 2 and the connection point 10 of the horizontal rod 1 are equal, and each of the extension legs 2 is located on the same circle.
[0041] The above arrangement ensures that the extended leg 2 on the positioning frame is always located on the same circle, and the center of the circle where the extended leg 2 is located is located on the same axis as the connection point 10 of the horizontal rod 1. When the end of the extended leg 2 is connected to the underwater steel cage, since the three points of the extended leg 2 are located on the same circle, they are all connected to the steel cage. According to the principle that three points form a circle, the extended leg 2 is also located on the circle where the steel cage is located, that is, the center of the circle where the extended leg 2 is located and the center of the circle where the steel cage is located are on the same central axis. Therefore, the connection point 10 and the center point of the steel cage are located on the same central axis. The position of the steel cage can be obtained by detecting the position of the connection point. This structure does not require underwater measurement or water drainage for measurement of the center of the steel cage. It is convenient and safe. It only requires connecting the extended leg 2 and the steel cage.
[0042] And if the precise coordinate position of the center of the steel cage needs to be determined, it is only necessary to subtract the length of the extended leg 2 from the coordinate position of the connection point 10 .
[0043] like Figure 1 , Figure 5 , Figure 6 As shown, in some preferred embodiments, the number and connection formation of the horizontal rods 1 are proposed in the following ways:
[0044] The first type is that the number of horizontal rods 1 is two, and the two horizontal rods 1 are fixedly connected in a cross shape or a T shape. When connected in a cross shape, the extended legs 2 are connected to both ends of each horizontal rod 1, and the distances between each extended leg 2 and the connection point 10 of the horizontal rod 1 are equal. The number can be four, and each of the extended legs 2 is located on the same circle; when fixedly connected in a T shape, the number of the extended legs 2 is three, which are respectively located at the three ends of the T shape.
[0045] The second type is that there are two horizontal rods 1, which are cross-connected and rotatably connected through a rotating shaft. The rotating shaft passes through the intersection of the two horizontal rods 1, and the intersection is the midpoint of the two horizontal rods 1. There are four extended legs 2, which are located at both ends of the horizontal rods 1. When in use, the angle between the horizontal rods 1 is preferably 90 degrees, but the angle cannot be 0 or 180 degrees.
[0046] The third type is that there are three horizontal rods 1, one ends of the three horizontal rods 1 are connected to form a connection point 10, and the extended legs 2 are connected to one end of the three horizontal rods 1 away from the connection point 10, wherein the angle formed by the connection of the three horizontal rods 1 is 120 degrees, or other angles.
[0047] The above structural setting is only a preferred solution. As long as the distances from each extended leg 2 to the connection point 10 of the horizontal rod 1 are equal, the number can be four, and each of the extended legs 2 can be located on the same circle. The length of the horizontal rod 1 can be selected according to actual conditions.
[0048] like Figure 2 As shown, in some preferred embodiments, in order to facilitate the assembly and use and carrying of the positioning frame, a connecting piece 4 is added so that the extended legs 2 can be detachably connected to the horizontal rod 1. The specific structure is as follows:
[0049] The connecting member 4 includes a connecting sleeve 40 and a first locking portion 41. The connecting sleeve 40 is fixedly connected to the horizontal rod 1, and the connecting sleeve 40 is a sleeve body with a hollow interior. One end of the extension leg 2 is inserted into the connecting sleeve 40. The first locking portion 41 is arranged on the connecting sleeve 40 and is used to lock the extension leg 2 on the connecting sleeve 40.
[0050] The first locking portion 41 may be a screw threaded on the connecting sleeve 40, and locking is performed by utilizing the resisting effect of the screw when rotating. The first locking portion 41 may also be a brake valve or other locking and braking structures.
[0051] like Figure 3 and Figure 4 As shown, due to the different sizes of steel cages, in order to adapt to steel cages of different diameters and to make the positioning frame match different steel cages and increase its scope of use, the following settings are made, as follows:
[0052] The first type is that there are multiple connecting pieces 4, and they are arranged along the length direction of the horizontal rod 1. When in use, when the diameter of the steel cage is small, the extended leg 2 is connected to the connecting piece 4 close to the connection point 10. When the diameter of the steel cage is large, the extended leg 2 is connected to the connecting piece 4 far away from the connection point 10.
[0053] The second method is to make the horizontal rod 1 a retractable rod structure based on the first method. In order to match the different diameters of the steel cages, and the difference is small, the first method has a small application range, and the retractable rod structure is also provided with a scale, so that the positioning frame can accurately adapt to different types of steel cages.
[0054] like Figure 2 As shown, in some preferred embodiments, the position of the steel cage underwater is deep or shallow. In order to make the positioning frame applicable to such a situation, the following structure is set:
[0055] The extended leg 2 is a structure with adjustable length, which includes an inner rod 21 and an outer rod 20. The inner rod 21 and the outer rod 20 are telescopically arranged. The second locking portion 22 is arranged on the outer rod 20 and is used to lock the inner rod 21 and the outer rod 20. The inner rod 21 and the outer rod 20 are composed of two different types of square steels, with a large square steel inside a small square steel. The second locking portion 22 can be a screw threaded on the outer rod 20, and the locking is performed by utilizing the resisting effect of the screw when it rotates. The second locking portion 22 can also be a brake valve or other locking and braking structure.
[0056] Furthermore, a plug-in portion 3 is provided at the end of the extension leg 2, and a connecting hole is provided on the plug-in portion 3. The connecting hole matches the steel cage and is used to connect to the steel cage. This structure enables the extension leg 2 and the steel cage to be quickly connected.
[0057] In addition, a method for underwater positioning of a pile foundation reinforcement cage is proposed, which comprises the following steps:
[0058] Install the pile foundation steel cage positioning frame on the steel cage so that the connection point 10 passes through the center axis of the steel cage;
[0059] Determine the center point of the pile position based on the guard pile;
[0060] Compare the relative positions of the connection point 10 and the center point to adjust the steel cage.
[0061] Specifically, it uses the above-mentioned several embodiments for explanation, taking a steel cage with a diameter of 1.89m as an example, the horizontal rod 1 is 1.89m long, and the extended leg 2 is 1m long.
[0062] Construction step 1: Installation of positioning frame.
[0063] First, open the two horizontal rods 1 of the positioning frame in a clockwise direction to a 90° right angle, and then adjust the length of the extension leg 2 according to the length of the lowered steel cage suspension rod. After the adjustment, install the extension leg on the connecting sleeve 40, tighten the first locking part 41, and the positioning frame is installed.
[0064] Construction step 2: Install the positioning frame on the steel cage.
[0065] The positioning frame is unfolded at 90 degrees (this angle can also be other angles), and there is a plug-in part 3 under the extended leg 2, and the plug-in part 3 has a plug-in hole. The corresponding steel bar of the steel cage can be inserted into the plug-in hole.
[0066] Construction step 3: Positioning the positioning frame.
[0067] After the positioning frame is lowered to the designed height along with the steel cage, the center point of the pile position is found by pulling out the cross line according to the guard pile, and whether the position of the connection point 10 and the center point of the cross line are on the same central axis is determined by the following two methods:
[0068] ① Set a plumb line at the connection point 10. If the projection of the plumb line falls on the center point of the pile position, the position of the steel cage is correct. If not, it needs to be adjusted. The steel cage is positioned until the center point of the pile position and the connection point 10 are on the same central axis.
[0069] ② Adjust the positioning frame so that the extended leg 2 can be retracted and dropped, and compare the connection of the positioning frame with the center point of the pile position. If the two points coincide, the center position of the steel cage is correct, otherwise, adjustment is required.
[0070] Construction step 4: Make adjustments based on the positioning results.
[0071] This method does not require underwater measurement of the position of the steel cage, which effectively solves the accuracy and quality problems in the steel cage placement process, and the steel cage placement and positioning process is extremely convenient.
[0072] In the description of the present application, it should be noted that the terms "upper", "lower", etc. indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present application and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present application. Unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be an indirect connection through an intermediate medium, or it can be a connection between the two elements. For those of ordinary skill in the art, the specific meanings of the above terms in the present application can be understood according to the specific circumstances.
[0073] It should be noted that, in this application, relational terms such as "first" and "second" are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. In the absence of further restrictions, the elements defined by the sentence "comprise a ..." do not exclude the presence of other identical elements in the process, method, article or device including the elements.
[0074] The above description is only a specific implementation of the present application, so that those skilled in the art can understand or implement the present application. Various modifications to these embodiments will be apparent to those skilled in the art, and the general principles defined herein can be implemented in other embodiments without departing from the spirit or scope of the present application. Therefore, the present application will not be limited to the embodiments shown herein, but will conform to the widest range consistent with the principles and novel features applied for herein.
Claims
1. An underwater positioning method for a pile foundation steel cage positioning frame, characterized in that: The pile foundation reinforcement cage positioning frame comprises: Two horizontal rods (1), the horizontal rods (1) are connected to form a connection point (10) at the connection point; At least three extension legs (2), the extension legs (2) being vertically arranged on the horizontal rod (1) and used to be connected to the steel cage; the distances between each of the extension legs (2) and the point where they are connected to the horizontal rod (1) are equal, and each of the extension legs (2) is located on the same circle; The two horizontal rods (1) are connected in a cross shape or a T shape; The two horizontal rods (1) are arranged crosswise, and a rotating shaft for connecting the two horizontal rods (1) is provided at the intersection; The horizontal rod (1) is also provided with a connecting piece (4), and the connecting piece (4) is detachably connected to the extending leg (2); The connecting member (4) comprises: A connecting sleeve (40) connected to the horizontal rod (1), one end of the extending leg (2) being located in the connecting sleeve (40); A first locking portion (41), which is arranged on the connecting sleeve (40) and is used to lock the extending leg (2) on the connecting sleeve (40); The extended leg (2) comprises: Outer rod (20); An inner rod (21) which is telescopically arranged with the outer rod (20); A second locking portion (22), which is disposed on the outer rod (20) and is used to lock the inner rod (21) and the outer rod (20); The end of the extended leg (2) is provided with a plug-in portion (3) for connecting to the steel cage; The underwater positioning method comprises the following steps: Installing the pile foundation steel cage positioning frame on the steel cage so that the connection point (10) passes through the center axis of the steel cage; Determine the center point of the pile position based on the guard pile; Comparing the relative positions of the connection point (10) and the center point to adjust the steel cage; Specifically, Construction step 1: Installation of positioning frame; First, the two horizontal rods (1) of the positioning frame are opened clockwise to a 90° right angle, and then the length of the extension leg (2) is adjusted according to the length of the steel cage suspension bar. After the adjustment is completed, the extension leg (2) is installed on the connecting sleeve (40), and the first locking part (41) is tightened. The installation of the positioning frame is completed; Construction step 2: Install the positioning frame on the steel cage; The positioning frame is unfolded at 90 degrees, and a plug-in portion (3) is provided below the extended leg (2), and the plug-in portion (3) has a plug-in hole, and the steel bars corresponding to the steel cage are inserted into the plug-in hole; Construction step 3: Positioning the positioning frame; After the positioning frame is lowered to the designed height along with the steel cage, the center point of the pile position is found by drawing a cross line on the guard pile, and it is determined whether the position of the connection point (10) and the center point of the cross line are on the same central axis; Construction step 4: Make adjustments based on the positioning results.
2. The underwater positioning method of the pile foundation reinforcement cage positioning frame according to claim 1, characterized in that: The connecting members (4) are multiple in number and are arranged along the length direction of the horizontal rod (1).