Water cooling temperature control method for optimal water temperature difference of lining concrete with different thicknesses
A technology of water cooling and water temperature difference, applied in design optimization/simulation, special data processing application, geometric CAD, etc., can solve the problem of lack of scientific regulation of lining concrete cooling time, water temperature and temperature drop rate, etc., to achieve temperature control Anti-cracking, scientific effect
Patent Information
- Authority / Receiving Office
- CN · China
- Current Assignee / Owner
- Publication Date
- 2021-07-23
Smart Images

Figure 1 
Figure 2 
Figure 3
Abstract
Description
technical field
[0001] The invention belongs to the technical field of concrete temperature control and anti-cracking, and in particular relates to a temperature control method for cooling through water with optimal water temperature difference for lining concrete with different thicknesses. Background technique
[0002] Large-volume concrete such as gravity dams are buried with cooling water pipes for cooling. In the initial stage, cold water or low-temperature river water is passed to reduce the maximum temperature of concrete; For the initial water cooling, the time should be calculated and determined, preferably 10 to 20 days, and the difference between the concrete temperature and the water temperature should not exceed 25°C. Medium-term water cooling should be about 1-2 months, and the difference between the water temperature and the internal temperature of the concrete should not exceed 20-25 °C. The daily temperature drop does not exceed 1.0°C. Due to the expansion...
Examples
Embodiment 1
[0102] 3 # Optimal control of cooling through water for the 0.8m-thick A-type lining concrete of the first warehouse of the non-pressure gentle slope section of the spillway tunnel
[0103] For the 0.8m thick A-type lining structure of the gentle slope section of the spillway tunnel Figure 10 , the city gate tunnel-shaped section, along the axis of the flood discharge tunnel, set up circular construction joints every 9m, Class II surrounding rock, concrete strength C 90 35. The concrete is poured in two phases: first the side wall arch, then the floor. Here we introduce the optimal control of water cooling for side arch lining concrete pouring.
[0104] Such as figure 2 As shown, the optimal water temperature difference water cooling temperature control method for lining concrete with different thicknesses provided in this embodiment includes the following contents:
[0105] Step 1. Analyze the data related to water cooling and temperature control of lining concrete, i...
Embodiment 2
[0125] 3 # Optimal control of cooling through water for 1.0m-thick B-type lining concrete in the 11th warehouse of the non-pressure gentle slope section of the spillway tunnel
[0126] For the 1.0m-thick B-type lining structure of the 11th storehouse on the gentle slope section of the spillway tunnel, see Figure 11 , gate opening section, concrete strength C 90 35. Class III surrounding rock. The concrete is poured in two phases: first the side wall arch, then the floor. Here we introduce the optimal control of water cooling for side arch lining concrete pouring.
[0127] Such as figure 2 As shown, the optimal water temperature difference water cooling temperature control method for lining concrete with different thicknesses provided in this embodiment includes the following contents:
[0128] Step 1. Analyze the data related to water cooling and temperature control of lining concrete, including: collecting data related to temperature control and crack prevention of l...