Photovoltaic power station area division method and device
Through the regional division method based on photovoltaic power station layout information, the problem of unreasonable division of photovoltaic arrays and confluence areas in photovoltaic power stations is solved, the adjacency and high aggregation of photovoltaic strings are achieved, the installed cost is reduced, and the efficiency is improved zoning efficiency.
Patent Information
- Application Number
- CN202110593996.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2021-05-28
- Publication Date
- 2024-10-18
- Estimated Expiration
- 2041-05-28
AI Technical Summary
The division of photovoltaic arrays and confluence areas in existing photovoltaic power plants relies on manual experience, and the results of the clustering algorithm are unstable, resulting in messy divisions and different specifications, which cannot meet the needs of reasonable division in actual sites, especially in complex concave factory areas where it is easy to cross Hilltop or red line areas increase the cost of installed hardware.
Adopting a regional division method based on photovoltaic power station layout information, through preliminary division, capacity matching and regional processing, ensure that photovoltaic strings are adjacent to each other, forming a high-aggregation regional division to meet on-site needs, and through adjacent relationships and string exchanges Optimize trace length and cost.
It achieves the adjacency and high aggregation of photovoltaic strings in the photovoltaic power station area, ensuring controllable regional capacity, the shortest wiring and the lowest cost, improving the efficiency of regional division, and is suitable for photovoltaic arrays, confluence areas and inverters with different parameters. Change area.
Smart Images

Figure CN113297712B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of photovoltaic power stations, and more specifically, to a method and device for dividing regions of a photovoltaic power station. Background Art
[0002] At present, before the construction of photovoltaic power stations, the division of photovoltaic arrays / confluence areas in photovoltaic power stations still relies heavily on manual experience. Although there is a method of using clustering algorithms to divide the confluence area, the number of string point sets of each cluster obtained by the clustering algorithm is different and cannot be controlled, resulting in a large difference in the number of strings connected to each junction box. If applied to the actual site, it will lead to messy divisions, different specifications of junction boxes, and no possibility of investment, construction, and construction. Especially when encountering a complex concave plant area (that is, the outer envelope of the photovoltaic plant area is concave), the photovoltaic array divided by the clustering algorithm has a poor shape and will cross the hill or the red line area, which is easy to increase the hardware cost of low-voltage cable installation.
[0003] Therefore, the existing methods do not meet the actual on-site requirements for reasonable division of photovoltaic arrays / confluence areas and other areas. Summary of the invention
[0004] In view of this, the present invention discloses a method and device for dividing regions of a photovoltaic power station to meet the actual on-site demand for reasonable division of regions such as photovoltaic arrays / confluence areas.
[0005] A method for dividing regions of a photovoltaic power station, comprising:
[0006] Based on the arrangement information of the photovoltaic power station, the photovoltaic power station is divided into regions to obtain a plurality of preliminary divided regions;
[0007] Based on the adjacent relationship between each of the preliminary divided areas and the capacity of the first preset area, performing capacity matching on the plurality of the preliminary divided areas to obtain a plurality of first optimized areas;
[0008] Based on the adjacent relationship between each of the first optimized regions, the adjacent relationship between photovoltaic strings, and the adjacent relationship between blocks, the plurality of first optimized regions are processed to obtain a plurality of second optimized regions;
[0009] When the capacities of all the second optimization areas reach the second preset area capacity, each of the second optimization areas is determined as a target optimization area.
[0010] Optionally, the dividing the photovoltaic power station into multiple preliminary divided areas based on the arrangement information of the photovoltaic power station specifically includes:
[0011] Dividing the photovoltaic power station into regions based on the arrangement information to obtain a plurality of original regions;
[0012] Based on the neighboring relationship of photovoltaic strings and the neighboring relationship of blocks, the multiple original areas are processed to obtain the multiple preliminary divided areas.
[0013] Optionally, the step of dividing the photovoltaic power station into regions based on the arrangement information of the photovoltaic power station to obtain a plurality of original regions specifically includes:
[0014] Taking the minimum horizontal coordinate, the minimum vertical coordinate, the maximum horizontal coordinate and the maximum vertical coordinate of the area where the photovoltaic power station is located as the starting point and the number of areas to be divided as the parameter, the area where the photovoltaic power station is located is divided into k*k grid units, where k is determined based on the number of areas;
[0015] Determine the number of grids including photovoltaic strings from the k*k grid units;
[0016] Determining a target number of grids required for each area in the photovoltaic power station based on the number of grids and the number of areas to be divided;
[0017] The adjacent grid cells of the target grid quantity are merged in sequence to obtain the original regions of the region quantity.
[0018] Optionally, the processing of the plurality of original regions to obtain the plurality of preliminary divided regions based on the photovoltaic string neighbor relationship and the block neighbor relationship specifically includes:
[0019] Based on the adjacent relationship of photovoltaic strings and the adjacent relationship of blocks, each original area is divided into blocks to obtain a plurality of first blocks;
[0020] Determine the first block with the largest number of photovoltaic strings in all the first blocks of each of the original areas as a first main block, and determine blocks other than the first main block as first sub-blocks;
[0021] The first sub-block closest to the first main block in each of the original areas is merged into the first main block to obtain the corresponding preliminary divided area.
[0022] Optionally, the performing capacity matching on the plurality of the preliminary divided areas based on the adjacent relationship between the respective preliminary divided areas and the capacity of the first preset area to obtain the plurality of first optimized areas specifically includes:
[0023] Determining adjacent areas of each of the preliminarily divided areas;
[0024] Determine, from all the preliminary divided areas, a preliminary divided area with the least number of adjacent areas as an area to be processed;
[0025] Calculating the capacity difference between the capacity of the area to be processed and the capacity of the first preset area;
[0026] Based on the size relationship between the capacity difference and 0, capacity matching is performed on the area to be processed to obtain a corresponding first optimized area.
[0027] Optionally, the determining of adjacent areas of each of the preliminary divided areas specifically includes:
[0028] If the shortest distances between the preliminary division region boundary group string points of the current preliminary division region and all the preliminary division region boundary group string points are greater than the second distance threshold, the preliminary division region closest to the current preliminary division region is determined as an adjacent region of the current preliminary division region;
[0029] If the closest distance between the preliminary division area boundary group string points of the current preliminary division area and all the preliminary division area boundary group string points is less than the second distance threshold, the preliminary division area whose closest distance is less than the second distance threshold is determined as an adjacent area of the current preliminary division area.
[0030] Optionally, performing capacity matching on the area to be processed based on the size relationship between the capacity difference and 0 to obtain the corresponding first optimized area specifically includes:
[0031] If the capacity difference is equal to 0, the area to be processed is removed from the entire plant string unit of the photovoltaic power station, and a new plant string unit is formed;
[0032] If the capacity difference is less than 0, the first target photovoltaic string in the adjacent area is re-divided into the area to be processed;
[0033] If the capacity difference is greater than 0, the second target photovoltaic string in the area to be processed is re-divided into the adjacent area.
[0034] Optionally, the processing of the plurality of first optimized regions to obtain the plurality of second optimized regions based on the adjacent relationship between the first optimized regions, the adjacent relationship between photovoltaic strings, and the adjacent relationship between blocks specifically includes:
[0035] Based on the adjacent relationship between the first optimization areas, target photovoltaic strings in different first optimization areas are exchanged to obtain multiple local optimization areas;
[0036] Based on the neighboring relationship of photovoltaic strings and the neighboring relationship of blocks, the multiple local optimization areas are processed to obtain multiple second optimization areas.
[0037] Optionally, based on the adjacent relationship between the first optimization regions, the target photovoltaic strings in different first optimization regions are exchanged to obtain multiple local optimization regions, specifically including:
[0038] Based on the adjacent relationship between each of the first optimized areas, the cable length from the center point of each first optimized area to the boundary group string point of the corresponding adjacent area is calculated, recorded as the first cable length, and the cable length from the center point of each first optimized area to its own boundary group string point is calculated, recorded as the second cable length;
[0039] Based on each of the first cable lengths and each of the second cable lengths, determining whether there is a third optimization area and a fourth optimization area that meet the preset cable length requirements in each of the first optimization areas;
[0040] Exchanging photovoltaic strings that meet preset photovoltaic string exchange conditions in the third optimization area and the fourth optimization area;
[0041] Update all the first optimization area center points and the group string point sets of each cluster, and return to search for the optimization area combination that meets the preset cable length requirement again, until there is no optimization area combination whose cable length difference in the preset cable length requirement is greater than 0, and generate a local optimization area division result with the shortest cable length and the highest concentration.
[0042] Optionally, the preset cable length requirement includes the following conditions:
[0043] The third optimized region is named a, and the fourth optimized region is named b;
[0044] The cable length from the center point a to the boundary point b of the string group Pb1 is recorded as: M a-pb1 ;
[0045] The cable length from the center point of b to the boundary point of b string Pb1 is recorded as: M b-pb1 ;
[0046] The cable length from the boundary point Pa1 of the string in a to the center point of a is recorded as M pa1-a ;
[0047] The cable length from the center point b to the boundary point Pa1 of the string in a is recorded as: M b-pa1 ;
[0048] If M a-pb1 <M b-pb1 , and there exists M in a pa1-a >M b-pa1 The string boundary point Pa1 is determined, and the combination of a and b that satisfies the maximum cable length difference is determined;
[0049] The expression of cable length difference △M is as follows:
[0050] ΔM=(M b-pb1 +M pa1-a )-(M a-pb1 +M b-pa1 ).
[0051] Optionally, the preset photovoltaic string exchange condition includes:
[0052] When the third optimized region and the fourth optimized region are mutually the only adjacent regions, the boundary group string points in the third optimized region and the boundary group string points in the fourth optimized sub-region b are interchanged;
[0053] When the fourth optimization area and the third optimization area are not mutually uniquely adjacent areas, and the closest distance from the center point of the third optimization area to the boundary group string points of the fourth optimization area is less than the third distance threshold, and the closest distance from the center point of the fourth optimization area to the boundary group string points of the third optimization area is less than the third distance threshold, the boundary group string points in the third optimization area and the boundary group string points in the fourth optimization area are interchanged.
[0054] Optionally, the processing of the plurality of local optimization regions based on the photovoltaic string neighboring relationship and the block neighboring relationship to obtain the plurality of second optimization regions specifically includes:
[0055] Based on the photovoltaic string association relationship and the block proximity relationship, each of the local optimization areas is divided into blocks to obtain a plurality of second blocks;
[0056] Determine the second block with the largest number of photovoltaic strings in all the second blocks in each of the local optimization areas as a second main block, and determine blocks other than the second main block as second sub-blocks;
[0057] The second sub-block closest to the second main block in each of the local optimized regions is merged into the second main block to obtain the corresponding second optimized region.
[0058] Optionally, also include:
[0059] Determining the second optimized area whose capacity does not reach the capacity of the second preset area as the capacity area to be adjusted;
[0060] Finding adjacent intersection points between the capacity areas to be adjusted;
[0061] Each of the adjacent intersection points is transferred until the capacity of all the second optimization areas reaches the capacity of the second preset area, thereby obtaining a plurality of the target optimization areas.
[0062] A photovoltaic power station area division device, comprising:
[0063] A region division unit, configured to divide the photovoltaic power station into regions based on the arrangement information of the photovoltaic power station to obtain a plurality of preliminary divided regions;
[0064] A capacity matching unit, configured to perform capacity matching on the plurality of the preliminary divided areas to obtain a plurality of first optimized areas based on the adjacent relationship between the respective preliminary divided areas and the first preset area capacity;
[0065] A region processing unit, configured to process the plurality of first optimized regions to obtain a plurality of second optimized regions based on the adjacent relationship between the first optimized regions, the adjacent relationship between photovoltaic strings, and the adjacent relationship between blocks;
[0066] The area determination unit is used to determine each of the second optimization areas as a target optimization area when the capacities of all the second optimization areas reach the second preset area capacity.
[0067] Optionally, the area division unit specifically includes:
[0068] An original area division subunit, configured to divide the photovoltaic power station into multiple original areas based on the arrangement information;
[0069] The area processing subunit is used to process the plurality of original areas to obtain the plurality of preliminary divided areas based on the adjacent relationship of photovoltaic strings and the adjacent relationship of blocks.
[0070] Optionally, the regional processing unit specifically includes:
[0071] A string exchange subunit, configured to exchange target photovoltaic strings in different first optimization areas to obtain a plurality of local optimization areas based on the adjacent relationship between the first optimization areas;
[0072] The local optimization region processing subunit is used to process the multiple local optimization regions based on the photovoltaic string adjacent relationship and the block adjacent relationship to obtain multiple second optimization regions.
[0073] As can be seen from the above technical solution, the present invention discloses a method and device for regional division of a photovoltaic power station, which divides the photovoltaic power station into regions based on the arrangement information of the photovoltaic power station to obtain multiple preliminary divided regions, and performs capacity matching on the multiple preliminary divided regions based on the adjacent relationship between each preliminary divided region and the capacity of the first preset region to obtain multiple first optimized regions, and processes the multiple first optimized regions based on the adjacent relationship between each first optimized region, the adjacent relationship of photovoltaic strings, and the adjacent relationship of blocks to obtain multiple second optimized regions, and when the capacity of all second optimized regions reaches the capacity of the second preset region, each second optimized region is determined as a target optimized region. The present invention takes into account the arrangement information of the photovoltaic power station when performing preliminary division of the photovoltaic power station, so that the photovoltaic strings in the preliminary divided region are adjacent, there will be no isolated string points, with high concentration, which meets the actual requirements of the site, and the capacity of each region is controllable by matching the capacity of the region. In addition, while ensuring that the strings in the region are adjacent, the concentration of each region is the highest, and the region is processed based on the adjacent relationship between the regions, the adjacent relationship of the photovoltaic strings, and the adjacent relationship of the blocks, so that the routing of each region is the shortest and the cost is the lowest. The present invention can realize the division of any one or several areas in the photovoltaic array, the confluence area and the inverter area based on different parameters, which greatly improves the area division efficiency compared with manual area division. BRIEF DESCRIPTION OF THE DRAWINGS
[0074] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on the disclosed drawings without paying creative work.
[0075] Figure 1 A flow chart of a method for dividing regions of a photovoltaic power station disclosed in an embodiment of the present invention;
[0076] Figure 2 A flowchart of a method for dividing a photovoltaic power station into regions to obtain multiple original regions based on the arrangement information of the photovoltaic power station disclosed in an embodiment of the present invention;
[0077] Figure 3 This is a schematic diagram of a photovoltaic power station divided into regions using a grid method disclosed in an embodiment of the present invention;
[0078] Figure 4 A flowchart of a method for processing multiple original areas to obtain multiple preliminary divided areas based on the adjacent relationship of photovoltaic strings disclosed in an embodiment of the present invention;
[0079] Figure 5A flowchart of a method disclosed in an embodiment of the present invention for performing capacity matching on a plurality of preliminary divided areas to obtain a plurality of first optimized areas based on the adjacent relationship of the preliminary divided areas and the capacity of the first preset area;
[0080] Figure 6 A flowchart of a method disclosed in an embodiment of the present invention for exchanging target photovoltaic strings in different first optimization areas to obtain multiple local optimization areas based on the adjacent relationship between the first optimization areas;
[0081] Figure 7 A flowchart of a method disclosed in an embodiment of the present invention for processing multiple local optimization areas to obtain multiple second optimization areas based on the neighboring relationship of photovoltaic strings and the neighboring relationship of blocks;
[0082] Figure 8 A flow chart of another method for dividing regions of a photovoltaic power station disclosed in an embodiment of the present invention;
[0083] FIG9( a ) is a schematic diagram of the positions of adjacent intersection points disclosed in an embodiment of the present invention;
[0084] FIG9( b ) is a schematic diagram of the positions of another adjacent intersection point disclosed in an embodiment of the present invention;
[0085] FIG9( c ) is a schematic diagram of the positions of another adjacent intersection point disclosed in an embodiment of the present invention;
[0086] FIG9( d ) is a schematic diagram of the positions of another adjacent intersection point disclosed in an embodiment of the present invention;
[0087] Fig.10 A schematic diagram of a regional division result of a photovoltaic power station disclosed in an embodiment of the present invention;
[0088] Fig.11 A schematic diagram of merging sub-blocks in each area into a main block disclosed in an embodiment of the present invention;
[0089] Fig.12 A schematic diagram of capacity matching of various areas disclosed in an embodiment of the present invention;
[0090] Fig.13 A schematic diagram of an optimal cost / highest concentration area division scheme (including flattening processing) disclosed in an embodiment of the present invention;
[0091] Fig.14 A schematic diagram of adjacent junction points after transmission disclosed in an embodiment of the present invention;
[0092] Fig.15 The present invention is a schematic structural diagram of a region division device for a photovoltaic power station disclosed in an embodiment of the present invention. DETAILED DESCRIPTION
[0093] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0094] The embodiment of the present invention discloses a method and device for dividing the region of a photovoltaic power station. Based on the arrangement information of the photovoltaic power station, the photovoltaic power station is divided into regions to obtain a plurality of preliminary divided regions. Based on the adjacent relationship between each preliminary divided region and the capacity of the first preset region, the plurality of preliminary divided regions are capacity matched to obtain a plurality of first optimized regions. Based on the adjacent relationship between each first optimized region, the adjacent relationship of photovoltaic strings and the adjacent relationship of blocks, the plurality of first optimized regions are processed to obtain a plurality of second optimized regions. When the capacity of all the second optimized regions reaches the capacity of the second preset region, each second optimized region is determined as a target optimized region. The present invention takes into account the arrangement information of the photovoltaic power station when performing preliminary division of the photovoltaic power station. Therefore, the photovoltaic strings in the preliminary divided region can be adjacent, no isolated string points will appear, and the photovoltaic strings have a high degree of aggregation, which meets the actual requirements of the site. The capacity of each region is controllable by matching the capacity of the region. In addition, while ensuring that the strings in the region are adjacent, the degree of aggregation of each region is the highest. By processing the region based on the adjacent relationship between the regions, the adjacent relationship of the photovoltaic strings and the adjacent relationship of the blocks, the routing of each region is the shortest and the cost is the lowest.
[0095] In addition, the present invention can realize the division of any one or several areas in the photovoltaic array, the confluence area and the inverter area based on different parameters, which greatly improves the efficiency of area division compared with manual area division.
[0096] See also Figure 1 , a flow chart of a method for dividing a region of a photovoltaic power station disclosed in an embodiment of the present invention, the method comprising:
[0097] Step S101: dividing the photovoltaic power station into regions based on the arrangement information of the photovoltaic power station to obtain a plurality of preliminary divided regions;
[0098] Specifically, the photovoltaic power station is first divided into regions based on the arrangement information of the photovoltaic power station to obtain a plurality of original regions, and then the plurality of original regions are processed based on the adjacent relationship of photovoltaic strings and the adjacent relationship of blocks to obtain a plurality of preliminary divided regions.
[0099] In practical applications, a grid method can be used to divide the photovoltaic power station into multiple original areas. In addition to the grid method, other aggregation / blocking algorithms can also be used. For example, a clustering algorithm can be used to divide the photovoltaic power station into multiple original areas.
[0100] Step S102: Based on the adjacent relationship between the preliminary divided areas and the capacity of the first preset area, capacity matching is performed on the plurality of the preliminary divided areas to obtain a plurality of first optimized areas;
[0101] Step S103, based on the adjacent relationship between each of the first optimized regions, the adjacent relationship between photovoltaic strings, and the adjacent relationship between blocks, the plurality of first optimized regions are processed to obtain a plurality of second optimized regions;
[0102] In practical applications, based on the adjacent relationship between each of the first optimization areas, the target photovoltaic strings in different first optimization areas can be exchanged to obtain multiple local optimization areas, and then based on the adjacent relationship between the photovoltaic strings and the adjacent relationship between the blocks, the multiple local optimization areas can be processed to obtain multiple second optimization areas.
[0103] Among them, when processing the local optimization area, the isolated blocks in each local optimization area are merged into the corresponding main block mainly based on the adjacent relationship of photovoltaic strings and the adjacent relationship of blocks.
[0104] Step S104: when the capacities of all the second optimization regions reach the second preset region capacity, each of the second optimization regions is determined as a target optimization region.
[0105] It should be particularly noted that the regions in the present invention include: photovoltaic arrays and / or busbar regions and / or inverter regions.
[0106] In summary, the present invention discloses a method for regional division of a photovoltaic power station, which divides the photovoltaic power station into regions based on the arrangement information of the photovoltaic power station to obtain a plurality of preliminary divided regions, performs capacity matching on the plurality of preliminary divided regions based on the adjacent relationship between each preliminary divided region and the capacity of the first preset region to obtain a plurality of first optimized regions, processes the plurality of first optimized regions based on the adjacent relationship between each first optimized region, the adjacent relationship of photovoltaic strings and the adjacent relationship of blocks to obtain a plurality of second optimized regions, and when the capacity of all second optimized regions reaches the capacity of the second preset region, each second optimized region is determined as a target optimized region. The present invention takes into account the arrangement information of the photovoltaic power station when performing preliminary division of the photovoltaic power station, so that the photovoltaic strings in the preliminary divided region are adjacent, no isolated string points appear, and the photovoltaic strings have a high degree of aggregation, which meets the actual requirements of the site, and the capacity of each region is controllable by matching the capacity of the region, and in addition, the degree of aggregation of each region is the highest while ensuring the adjacent strings in the region, and the region is processed based on the adjacent relationship between the regions, the adjacent relationship of the photovoltaic strings and the adjacent relationship of the blocks, so that the routing of each region is the shortest and the cost is the lowest.
[0107] In addition, the present invention can realize the division of any one or several areas in the photovoltaic array, the confluence area and the inverter area based on different parameters, which greatly improves the efficiency of area division compared with manual area division.
[0108] See also Figure 2 , a flowchart of a method for dividing a photovoltaic power station into regions based on the arrangement information of the photovoltaic power station to obtain multiple original regions is disclosed in an embodiment of the present invention, the method comprising:
[0109] Step S201, taking the minimum horizontal coordinate, the minimum vertical coordinate, the maximum horizontal coordinate and the maximum vertical coordinate of the area where the photovoltaic power station is located as the starting point and taking the number of areas to be divided as the parameter, dividing the area where the photovoltaic power station is located into k*k grid units;
[0110] Wherein, k is determined based on the number of regions and is a positive integer.
[0111] In this embodiment, the minimum horizontal coordinate, the minimum vertical coordinate, the maximum horizontal coordinate and the maximum vertical coordinate of the area where the photovoltaic power station is located are the arrangement information of the photovoltaic power station.
[0112] The present invention can ensure that photovoltaic strings in the same area are adjacent to each other by dividing the area where the photovoltaic power station is located into grids, thereby making the area highly concentrated.
[0113] See Figure 3The schematic diagram of the photovoltaic power station after the grid method is used to divide the area, the minimum horizontal coordinate, the minimum vertical coordinate, the maximum horizontal coordinate and the maximum vertical coordinate of the photovoltaic power station area are respectively used as the four vertices of the rectangular area, and the photovoltaic power station area is divided into k*k grid units according to the required number of divided areas k_num. If k_num is a prime number, k=2*k_num; if k_num is a non-prime number, k=k_num.
[0114] Step S202, determining the number of grids including photovoltaic strings from the k*k grid units;
[0115] Specifically, the grid cells that do not include the photovoltaic strings are removed from the k*k grid cells, and the number of remaining grid cells that include the photovoltaic strings is counted N_Grid_glo.
[0116] Step S203: determining a target number of grids required for each area in the photovoltaic power station based on the number of grids and the number of areas to be divided;
[0117] The expression of the target grid number N_Grid_single is as follows:
[0118] N_Grid_single=floor(N_Grid_glo / k_num);
[0119] In the formula, the function of the floor function is to "round down", or "round down" or "round down to zero", that is, to take the largest integer not greater than x. Different from "rounding up", rounding down means directly taking the left value closest to the required value on the number axis, that is, the largest integer value not greater than the required value.
[0120] Step S204: sequentially merge adjacent grid cells of the target grid number to obtain original regions of the region number.
[0121] In this embodiment, specifically k_num original regions can be obtained.
[0122] See also Figure 4 , a flowchart of a method for processing multiple original areas to obtain multiple preliminary divided areas based on the adjacent relationship of photovoltaic strings disclosed in an embodiment of the present invention, the method comprising:
[0123] Step S301: Based on the neighboring relationship of photovoltaic strings and the neighboring relationship of blocks, each original area is divided into blocks to obtain a plurality of first blocks;
[0124] The distance between adjacent photovoltaic strings in each first block is less than a first distance threshold.
[0125] Specifically, each original area is divided into blocks. Based on the association relationship and block adjacency relationship between the PV strings in the original area, PV strings with a distance less than the first distance threshold Dist between adjacent PV strings are divided into the same block, that is, if the distance DIS (ZCi-ZCj) < between adjacent PV strings is less than Dist, it indicates that PV string i and PV string j are in the same block.
[0126] Step S302: Among all the first blocks in each original area, the first block with the largest number of PV strings is determined as the first main block, and the blocks other than the first main block are determined as the first sub-blocks;
[0127] After obtaining the block division results of all original areas, the blocks can be sorted in descending (or ascending) order according to the number of PV strings they contain. The block with the largest number of PV strings is determined as the first main block, and the blocks other than the first main block are determined as the first sub-blocks. By looping through all the original areas, the block division results of all original areas are obtained.
[0128] Step S303: The first sub-block closest to the first main block in each original area is merged into the first main block to obtain the corresponding preliminary division area.
[0129] Specifically, calculate the closest distance between the boundary string points of each sub-block and the boundary string points of the first main block in each original area. The first sub-block with the closest distance is paired with the first main block and merged into the first main block to obtain the preliminary division area.
[0130] It should be noted that by merging the first sub-block into the first main block and establishing the adjacent relationship between blocks to guide the direction of the transfer of the string point set, the present invention can solve the problem that the clustering algorithm is not applicable to the area division of concave-shaped factory areas / concave-convex mixed factory areas. A concave-shaped factory area refers to a photovoltaic factory area with a concave outer envelope, and a concave-convex mixed factory area refers to a photovoltaic factory area with a mixed concave and convex outer envelope.
[0131] See Figure 5 , a method flowchart for performing capacity matching on multiple preliminary division areas based on the adjacent relationship and the first preset area capacity of each preliminary division area to obtain multiple first optimized areas is disclosed in the embodiment of the present invention. The method includes:
[0132] Step S401: Determine the adjacent areas of each preliminary division area;
[0133] Specifically, calculate the closest distance between the boundary string points of each preliminary division area;
[0134] If the shortest distance between the preliminary division area boundary group string points of the current preliminary division area and all the preliminary division area boundary group string points is greater than the second distance threshold e, the preliminary division area closest to the current preliminary division area is determined as the adjacent area of the current preliminary division area.
[0135] If the nearest distance between the preliminary division area boundary group string points of the current preliminary division area and all the preliminary division area boundary group string points is less than the second distance threshold e, the preliminary division area whose nearest distance is less than the second distance threshold e is determined as the adjacent area of the current preliminary division area.
[0136] The boundary group string points of the preliminary divided area are: the outermost boundary group string points of the preliminary divided area. The outer boundary group string will be updated after each transfer or exchange of the group string point set.
[0137] Step S402, determining the preliminary divided area with the least number of adjacent areas from all the preliminary divided areas as the area to be processed;
[0138] Find the preliminary division area with the least number of adjacent areas. If there are multiple preliminary division areas with the same number of adjacent areas, sort them according to any one of the indicators: the center of the preliminary division area, the smallest horizontal coordinate of the boundary group string point, the largest horizontal coordinate of the boundary group string point, the smallest vertical coordinate of the boundary group string point, and the largest horizontal coordinate of the boundary group string point.
[0139] A smaller number of adjacent regions indicates that the initially divided region is a corner matrix; conversely, a larger number of adjacent regions indicates that the initially divided region is an intermediate region.
[0140] Step S403, calculating the capacity difference between the capacity of the area to be processed and the capacity of the first preset area;
[0141] Step S404: Based on the size relationship between the capacity difference and 0, capacity matching is performed on the area to be processed to obtain a corresponding first optimized area.
[0142] Specifically, if the capacity difference deltaP=0, it indicates that the area to be processed is in a capacity saturation state. At this time, the area to be processed is removed from the entire plant string unit of the photovoltaic power station and a new plant string unit is formed.
[0143] If deltaP<0, the first target PV string in the adjacent area is re-divided into the area to be processed. Specifically, the distance between the center of the area to be processed and the boundary string point of the adjacent area is calculated, which is recorded as the first distance Dis1, and the distance between the center of the adjacent area and its own boundary string point is recorded as the second distance Dis2. The distance difference (Dis1-Dis2) between the first distance and the second distance is calculated, which is recorded as the first distance difference. The PV string at the boundary string point of the adjacent area corresponding to the minimum first distance difference is recorded as the first target PV string and re-divided into the area to be processed. This cycle is repeated until deltaP=0 to determine that the capacity matching of the area to be processed is completed, and the first optimized area corresponding to the area to be processed is obtained.
[0144] If deltaP>0, the second target photovoltaic string in the area to be processed is re-divided into adjacent areas. Specifically, the distance between the center of the area to be processed and its own boundary string point is calculated, which is recorded as the third distance Dis3, and the distance between the adjacent area and the boundary string point of the area to be processed is recorded as the fourth distance Dis4. The distance difference (Dis4-Dis3) between the fourth distance and the third distance is calculated, which is recorded as the second distance difference. The boundary string point of the area to be processed corresponding to the minimum second distance difference and the corresponding adjacent area number are determined. The photovoltaic string at the boundary string point of the area to be processed is recorded as the second target photovoltaic string, and is re-divided into adjacent areas corresponding to the adjacent area number. This cycle is repeated until deltaP=0 to determine that the capacity matching of the area to be processed is completed, and the first optimized area corresponding to the area to be processed is obtained.
[0145] Steps S401 to S404 are executed in a loop to obtain the first optimized region corresponding to each preliminary divided region.
[0146] In summary, the present invention starts capacity matching from the preliminary divided area with the least number of adjacent areas as the starting point, which is equivalent to squeezing from the corner array to the middle. The array at the edge first meets the capacity requirement, and the array in the middle meets the capacity requirement last, so as to ensure the effectiveness of the transmission of the photovoltaic string point set.
[0147] See also Figure 6 , a flowchart of a method disclosed in an embodiment of the present invention for exchanging target photovoltaic strings in different first optimization areas to obtain multiple local optimization areas based on the adjacent relationship between the first optimization areas, the method comprising:
[0148] Step S501: Based on the adjacent relationship between the first optimized areas, the cable length from the center point of each first optimized area to the boundary group string point of the corresponding adjacent area is calculated, which is recorded as the first cable length, and the cable length from the center point of each first optimized area to its own boundary group string point is calculated, which is recorded as the second cable length;
[0149] Since the longer the cable is, the higher the cable cost is, in practical applications, the cable length in this embodiment may also be the cable cost.
[0150] Step S502: Based on the lengths of the first cables and the lengths of the second cables, it is determined whether there are third optimization areas and fourth optimization areas in the first optimization areas that meet the preset cable length requirements;
[0151] Specifically, the third optimized area is named a, and the fourth optimized area is named b:
[0152] The pre-set cable length requirements include the following conditions:
[0153] The cable length from the center point a to the boundary point b of the string group Pb1 is recorded as: M a-pb1 ;
[0154] The cable length from the center point of b to the boundary point of b string Pb1 is recorded as: M b-pb1 ;
[0155] The cable length from the boundary point Pa1 of the string in a to the center point of a is recorded as M pa1-a ;
[0156] The cable length from the center point b to the boundary point Pa1 of the string in a is recorded as: M b-pa1 ;
[0157] If M a-pb1 <M b-pb1 , and there exists M in a pa1-a >M b-pa1 The string boundary point Pa1 is determined, and the combination of a and b that satisfies the maximum cable length difference is determined;
[0158] The expression of cable length difference △M is as follows:
[0159] ΔM=(M b-pb1 +M pa1-a )-(M a-pb1 +M b-pa1 );
[0160] Step S503, exchanging the photovoltaic strings that meet the preset photovoltaic string exchange conditions in the third optimization area and the fourth optimization area;
[0161] Specifically, determine whether the third optimized region a and the fourth optimized region b are mutually unique adjacent regions. If yes, execute (1); if no, execute (2);
[0162] (1) When the third optimization region a and the fourth optimization region b are the only adjacent regions to each other, the boundary group point Pa1 in the third optimization region a and the boundary group point Pb1 in the fourth optimization region b are interchanged, so that the boundary group point Pa1 belongs to the fourth optimization region b, and the boundary group point Pb1 belongs to the third optimization region a.
[0163] The third optimized region a and the fourth optimized region b are the only adjacent regions to each other, which means that the third optimized region a is only adjacent to the fourth optimized region b, and at the same time, the fourth optimized region b is only adjacent to the third optimized region a.
[0164] (2) When the fourth optimized region b and the third optimized region a are not mutually unique adjacent regions, and the shortest distance Dmin from the center point of the third optimized region a to the boundary string point of the fourth optimized region b is a-bound(b) < the third distance threshold e, and the shortest distance Dmin from the center point of the fourth optimized area b to the boundary group string point of the third optimized area a b-bound(a) <the third distance threshold e, then the boundary group point Pa1 in the third optimization area a and the boundary group point Pb1 in the fourth optimization area b are interchanged, so that the boundary group point Pa1 belongs to the fourth optimization area b, and the boundary group point Pb1 belongs to the third optimization area a.
[0165] If Dmin a-bound(b) >The third distance threshold e or Dmin b-bound(a) >the third distance threshold e, the third optimization area a and the fourth optimization area b do not exchange the boundary group points Pa1 and the boundary group points Pb1, and perform the next point set distance calculation.
[0166] Step S504, update all the first optimization area center points and the group string point sets of each cluster, and return to step S502 until there is no optimization area combination in which the cable length difference in the preset cable length requirement is greater than 0, and generate a local optimization area division result with the shortest cable length and the highest concentration.
[0167] After executing step S503, this embodiment updates all the first optimization region center points and the group string point sets of each cluster, and repeats steps S502 to S503 until there is no first optimization region combination with ΔM>0.
[0168] In this embodiment, the rows and columns of the clamped photovoltaic strings, which have only one or more photovoltaic strings in a row, are merged into adjacent areas for processing to achieve area flattening.
[0169] Assuming that string A belongs to the first region, and strings B and C that are in the same column or row as the clamped string A and are adjacent to the clamped string A both belong to the second region, string A is the clamped string.
[0170] See Figure 7 , a method flowchart for processing a plurality of local optimization regions to obtain a plurality of second optimization regions based on the adjacent relationship of photovoltaic strings and the adjacent relationship of blocks disclosed in an embodiment of the present invention. The method includes:
[0171] Step S601: Based on the association relationship of photovoltaic strings and the adjacent relationship of blocks, perform block division on each local optimization region to obtain a plurality of second blocks;
[0172] Among them, the distance between adjacent photovoltaic strings in each second block is less than the fourth distance threshold.
[0173] Specifically, perform block division on each initial division region. Based on the association relationship between photovoltaic strings and the adjacent relationship of blocks in the initial division region, divide those with a distance less than the fourth distance threshold DIST between adjacent photovoltaic strings into the same block, that is, if the distance dis(ZCi - ZCj) between adjacent photovoltaic strings is less than DIST, it indicates that photovoltaic string i and photovoltaic string j are in the same block.
[0174] Step S602: In all the second blocks of each local optimization region, determine the second block with the largest number of photovoltaic strings as the second main block, and determine the blocks other than the second main block as second sub - blocks;
[0175] After obtaining the block division results of all initial division regions, the blocks can be sorted in descending (or ascending) order according to the number of photovoltaic strings they contain. Determine the block with the largest number of photovoltaic strings as the second main block, and determine the blocks other than the second main block as second sub - blocks. Cycle through all initial division regions to obtain the block division results of all initial division regions.
[0176] Step S603: Merge the second sub - block closest to the second main block in each local optimization region into the second main block to obtain the corresponding second optimization region.
[0177] Specifically, calculate the closest distance between the boundary string points of each sub - block and the boundary string points of the second main block in each local optimization region. Bind the second sub - block with the closest distance and the second main block into a pair, and merge the second sub - block bound to the second main block into the second main block to obtain the second optimization region.
[0178] When there is a second optimization region whose capacity does not reach the capacity of the second preset region among all the second optimization regions, see Figure 8 , another method flowchart for regional division of a photovoltaic power station disclosed in an embodiment of the present invention. On the basis of the embodiment shown in Figure 1 , after step S103, it may further include:
[0179] Step S105: determining the second optimized area whose capacity does not reach the capacity of the second preset area as the capacity area to be adjusted;
[0180] Step S106, searching for adjacent intersection points between the capacity areas to be adjusted;
[0181] Specifically including: 1) dividing the photovoltaic strings into rows and columns, specifically including: the floating value of the longitudinal coordinates of the photovoltaic strings in the same row is within the first threshold delta_y_row, and the lateral coordinates between adjacent photovoltaic strings do not exceed the second threshold delta_x_row; the lateral coordinates of the photovoltaic strings in the same column float within the third threshold delta_x_col, and the longitudinal coordinates between adjacent photovoltaic strings do not exceed the fourth threshold delta_y_col.
[0182] 2) Finding adjacent intersection points between each of the capacity areas to be adjusted, specifically including: based on the row and column division result, there is a target point in the same row that satisfies any one of the categories in Figure 9(a), Figure 9(b), Figure 9(c) and Figure 9(d) as the adjacent intersection point between the capacity areas to be adjusted.
[0183] Figure 9(a) to Figure 9(d) In the figure, the square and the circle are two different capacity areas to be adjusted, and the square in the schematic diagram is the adjacent intersection point of the capacity areas to be adjusted.
[0184] The right side and bottom side of the target point (square) in the same row in Figure 9(a) are strings in another capacity area to be adjusted;
[0185] In Figure 9(b), the right and upper sides of the same target point (square) are strings in another capacity area to be adjusted;
[0186] The left and bottom sides of the target point (square) in the same row in Figure 9(c) are strings in another capacity area to be adjusted;
[0187] The left and upper sides of the target point (square) in the same row of Figure 9(d) are strings in another capacity area to be adjusted.
[0188] Step S107: transfer each of the adjacent intersection points until the capacity of all the second optimization areas reaches the capacity of the second preset area, thereby obtaining a plurality of the target optimization areas.
[0189] In summary, the present invention can ensure that the transmission of photovoltaic strings between target optimization areas will not cause isolated photovoltaic strings by searching for adjacent intersection points, and can also ensure the capacity requirements of the target optimization area.
[0190] It should be particularly noted that, in practical applications, the regional division method of the photovoltaic power station disclosed in the present invention can be used to divide the confluence area of the photovoltaic power station, and then the photovoltaic array can be divided according to the present invention.
[0191] The purpose of the present invention to use multiple boundary points for distance calculation is to reduce the amount of calculation. In practical applications, all point sets in the photovoltaic array may also be used to calculate the distance.
[0192] To facilitate understanding of the working principle of the disclosed method for dividing the regions of a photovoltaic power station, the present invention further provides a specific embodiment as follows:
[0193] use Figure 3 The grid method shown in the figure divides the photovoltaic power station into regions and obtains Fig.10 The regional division result of the photovoltaic power station is shown in FIG. The sub-blocks in each area are merged into the main block to obtain Fig.11 ; Capacity matching for each area Fig.12 , ensuring that the photovoltaic strings in the area are adjacent and highly concentrated; the optimal cost / highest concentration area division scheme (including leveling treatment) is as follows Fig.13 as shown; Fig.14 As shown, the capacity requirements of each area are met by transferring to adjacent junction points.
[0194] Corresponding to the above method embodiment, the present invention further discloses a region division device for a photovoltaic power station.
[0195] See also Fig.15 , a schematic diagram of a structure of a region division device for a photovoltaic power station disclosed in an embodiment of the present invention, the device comprising:
[0196] A region division unit 701 is used to divide the photovoltaic power station into regions based on the arrangement information of the photovoltaic power station to obtain a plurality of preliminary divided regions;
[0197] The area division unit 701 may specifically include:
[0198] An original area division subunit, configured to divide the photovoltaic power station into multiple original areas based on the arrangement information;
[0199] The area processing subunit is used to process the plurality of original areas to obtain the plurality of preliminary divided areas based on the adjacent relationship of photovoltaic strings and the adjacent relationship of blocks.
[0200] A capacity matching unit 702 is used to perform capacity matching on the plurality of the preliminary divided areas to obtain a plurality of first optimized areas based on the adjacent relationship between the respective preliminary divided areas and the first preset area capacity;
[0201] A region processing unit 703 is used to process the plurality of first optimization regions to obtain a plurality of second optimization regions based on the adjacent relationship between the first optimization regions, the adjacent relationship between the photovoltaic strings, and the adjacent relationship between the blocks;
[0202] The region determining unit 704 is configured to determine each of the second optimization regions as a target optimization region when the capacities of all the second optimization regions reach the second preset region capacity.
[0203] It should be particularly noted that the regions in the present invention include: photovoltaic arrays and / or busbar regions and / or inverter regions.
[0204] In summary, the present invention discloses a regional division device for a photovoltaic power station, which divides the photovoltaic power station into regions based on the arrangement information of the photovoltaic power station to obtain a plurality of preliminary divided regions, performs capacity matching on the plurality of preliminary divided regions based on the adjacent relationship between each preliminary divided region and the capacity of the first preset region to obtain a plurality of first optimized regions, processes the plurality of first optimized regions based on the adjacent relationship between each first optimized region, the adjacent relationship of photovoltaic strings and the adjacent relationship of blocks to obtain a plurality of second optimized regions, and when the capacity of all second optimized regions reaches the capacity of the second preset region, each second optimized region is determined as a target optimized region. The present invention takes into account the arrangement information of the photovoltaic power station when performing preliminary division of the photovoltaic power station, so that the photovoltaic strings in the preliminary divided region are adjacent, no isolated string points appear, and have a high degree of aggregation, which meets the actual requirements of the site, and the capacity of each region is controllable by matching the capacity of the region, and in addition, while ensuring that the strings in the region are adjacent, the degree of aggregation of each region is the highest, and the region is processed based on the adjacent relationship between the regions, the adjacent relationship of the photovoltaic strings and the adjacent relationship of the blocks, so that the routing of each region is the shortest and the cost is the lowest.
[0205] In addition, the present invention can realize the division of any one or several areas in the photovoltaic array, the confluence area and the inverter area based on different parameters, which greatly improves the efficiency of area division compared with manual area division.
[0206] In the above embodiment, the original area division subunit can be specifically used for:
[0207] Taking the minimum horizontal coordinate, the minimum vertical coordinate, the maximum horizontal coordinate and the maximum vertical coordinate of the area where the photovoltaic power station is located as the starting point and the number of areas to be divided as the parameter, the area where the photovoltaic power station is located is divided into k*k grid units, where k is determined based on the number of areas;
[0208] Determine the number of grids including photovoltaic strings from the k*k grid units;
[0209] Determining a target number of grids required for each area in the photovoltaic power station based on the number of grids and the number of areas to be divided;
[0210] The adjacent grid cells of the target grid quantity are merged in sequence to obtain the original regions of the region quantity.
[0211] In the above embodiment, the region processing subunit may be specifically used for:
[0212] Based on the adjacent relationship of photovoltaic strings and the adjacent relationship of blocks, each original area is divided into blocks to obtain a plurality of first blocks;
[0213] Determine the first block with the largest number of photovoltaic strings in all the first blocks of each of the original areas as a first main block, and determine blocks other than the first main block as first sub-blocks;
[0214] The first sub-block closest to the first main block in each of the original areas is merged into the first main block to obtain the corresponding preliminary divided area.
[0215] To further optimize the above embodiment, the capacity matching unit 702 may specifically include:
[0216] An adjacent region determination subunit, used to determine adjacent regions of each of the initially divided regions;
[0217] A to-be-processed region determination subunit, configured to determine, from among all the preliminary divided regions, a preliminary divided region with the least number of adjacent regions as a to-be-processed region;
[0218] A capacity difference calculation subunit, used for calculating the capacity difference between the capacity of the area to be processed and the capacity of the first preset area;
[0219] The capacity matching subunit is used to perform capacity matching on the area to be processed based on the size relationship between the capacity difference and 0 to obtain a corresponding first optimized area.
[0220] The adjacent region determination subunit is specifically used for:
[0221] If the shortest distances between the preliminary division region boundary group string points of the current preliminary division region and all the preliminary division region boundary group string points are greater than the second distance threshold, the preliminary division region closest to the current preliminary division region is determined as an adjacent region of the current preliminary division region;
[0222] If the closest distance between the preliminary division area boundary group string points of the current preliminary division area and all the preliminary division area boundary group string points is less than the second distance threshold, the preliminary division area whose closest distance is less than the second distance threshold is determined as an adjacent area of the current preliminary division area.
[0223] The capacity matching subunit may be specifically used for:
[0224] If the capacity difference is equal to 0, the area to be processed is removed from the entire plant string unit of the photovoltaic power station, and a new plant string unit is formed;
[0225] If the capacity difference is less than 0, the first target photovoltaic string in the adjacent area is re-divided into the area to be processed;
[0226] If the capacity difference is greater than 0, the second target photovoltaic string in the area to be processed is re-divided into the adjacent area.
[0227] To further optimize the above embodiment, the region processing unit 703 may specifically include:
[0228] A string exchange subunit, configured to exchange target photovoltaic strings in different first optimization areas to obtain a plurality of local optimization areas based on the adjacent relationship between the first optimization areas;
[0229] The local optimization region processing subunit is used to process the multiple local optimization regions based on the photovoltaic string adjacent relationship and the block adjacent relationship to obtain multiple second optimization regions.
[0230] The string switching subunit may be specifically used for:
[0231] Based on the adjacent relationship between each of the first optimized areas, the cable length from the center point of each first optimized area to the boundary group string point of the corresponding adjacent area is calculated, recorded as the first cable length, and the cable length from the center point of each first optimized area to its own boundary group string point is calculated, recorded as the second cable length;
[0232] Based on each of the first cable lengths and each of the second cable lengths, determining whether there is a third optimization area and a fourth optimization area that meet the preset cable length requirements in each of the first optimization areas;
[0233] Exchanging photovoltaic strings that meet preset photovoltaic string exchange conditions in the third optimization area and the fourth optimization area;
[0234] Update all the first optimization area center points and the group string point sets of each cluster, and return to search for the optimization area combination that meets the preset cable length requirement again, until there is no optimization area combination whose cable length difference in the preset cable length requirement is greater than 0, and generate a local optimization area division result with the shortest cable length and the highest concentration.
[0235] The local optimization region processing subunit may be specifically used for:
[0236] Based on the photovoltaic string association relationship and the block proximity relationship, each of the local optimization areas is divided into blocks to obtain a plurality of second blocks;
[0237] Determine the second block with the largest number of photovoltaic strings in all the second blocks in each of the local optimization areas as a second main block, and determine blocks other than the second main block as second sub-blocks;
[0238] The second sub-block closest to the second main block in each of the local optimized regions is merged into the second main block to obtain the corresponding second optimized region.
[0239] To further optimize the above embodiment, the area division device may further include:
[0240] a capacity adjustment region determining unit, configured to determine a second optimized region whose capacity does not reach the capacity of the second preset region as a capacity region to be adjusted;
[0241] A searching unit, used for searching adjacent boundary points between the capacity areas to be adjusted;
[0242] A transmission unit is used to transmit each of the adjacent intersection points until the capacity of all the second optimization areas reaches the capacity of the second preset area, thereby obtaining a plurality of the target optimization areas.
[0243] In summary, the present invention can ensure that the transmission of photovoltaic strings between target optimization areas will not cause isolated photovoltaic strings by searching for adjacent intersection points, and can also ensure the capacity requirements of the target optimization area.
[0244] It should be noted that for the specific working principles of each component in the device embodiment, please refer to the corresponding part of the method embodiment, which will not be repeated here.
[0245] Finally, it should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. In the absence of further restrictions, the elements defined by the sentence "comprise a ..." do not exclude the presence of other identical elements in the process, method, article or device including the elements.
[0246] The various embodiments in this specification are described in a progressive manner, and each embodiment focuses on the differences from other embodiments. The same or similar parts between the various embodiments can be referenced to each other.
[0247] The above description of the disclosed embodiments enables one skilled in the art to implement or use the present invention. Various modifications to these embodiments will be apparent to one skilled in the art, and the general principles defined herein may be implemented in other embodiments without departing from the spirit or scope of the present invention. Therefore, the present invention will not be limited to the embodiments shown herein, but rather to the widest scope consistent with the principles and novel features disclosed herein.
Claims
1. A method for dividing regions of a photovoltaic power station, characterized in that: include: Based on the arrangement information of the photovoltaic power station, the photovoltaic power station is divided into multiple preliminary divided areas, so that the photovoltaic strings in the preliminary divided areas are adjacent; Based on the adjacent relationship between each of the preliminary divided areas and the capacity of the first preset area, performing capacity matching on the plurality of the preliminary divided areas to obtain a plurality of first optimized areas; Based on the adjacent relationship between each of the first optimized regions, the adjacent relationship between photovoltaic strings, and the adjacent relationship between blocks, the plurality of first optimized regions are processed to obtain a plurality of second optimized regions; When the capacities of all the second optimization areas reach the second preset area capacity, each of the second optimization areas is determined as a target optimization area; The step of performing capacity matching on the plurality of the preliminary divided areas based on the adjacent relationship between the respective preliminary divided areas and the capacity of the first preset area to obtain the plurality of first optimized areas specifically includes: Determining adjacent areas of each of the preliminarily divided areas; Determine, from all the preliminary divided areas, a preliminary divided area with the least number of adjacent areas as an area to be processed; Calculating the capacity difference between the capacity of the area to be processed and the capacity of the first preset area; Based on the size relationship between the capacity difference and 0, capacity matching is performed on the area to be processed to obtain a corresponding first optimized area; The step of performing capacity matching on the area to be processed based on the size relationship between the capacity difference and 0 to obtain the corresponding first optimized area specifically includes: If the capacity difference is equal to 0, the area to be processed is removed from the entire plant string unit of the photovoltaic power station, and a new plant string unit is formed; If the capacity difference is less than 0, the first target photovoltaic string in the adjacent area is re-divided into the area to be processed; If the capacity difference is greater than 0, the second target photovoltaic string in the area to be processed is re-divided into the adjacent area.
2. The area division method according to claim 1, characterized in that: The step of dividing the photovoltaic power station into regions based on the arrangement information of the photovoltaic power station to obtain a plurality of preliminary divided regions specifically includes: Dividing the photovoltaic power station into regions based on the arrangement information to obtain a plurality of original regions; Based on the neighboring relationship of photovoltaic strings and the neighboring relationship of blocks, the multiple original areas are processed to obtain the multiple preliminary divided areas.
3. The area division method according to claim 2, characterized in that: The step of dividing the photovoltaic power station into regions based on the arrangement information of the photovoltaic power station to obtain a plurality of original regions specifically includes: Taking the minimum horizontal coordinate, the minimum vertical coordinate, the maximum horizontal coordinate and the maximum vertical coordinate of the area where the photovoltaic power station is located as the starting point and the number of areas to be divided as the parameter, the area where the photovoltaic power station is located is divided into k*k grid units, where k is determined based on the number of areas; Determine the number of grids including photovoltaic strings from the k*k grid units; Determining a target number of grids required for each area in the photovoltaic power station based on the number of grids and the number of areas to be divided; The adjacent grid cells of the target grid quantity are merged in sequence to obtain the original regions of the region quantity.
4. The area division method according to claim 2, characterized in that: The processing of the plurality of original regions based on the photovoltaic string neighboring relationship and the block neighboring relationship to obtain the plurality of preliminary divided regions specifically includes: Based on the adjacent relationship of photovoltaic strings and the adjacent relationship of blocks, each original area is divided into blocks to obtain a plurality of first blocks; Determine the first block with the largest number of photovoltaic strings in all the first blocks of each of the original areas as a first main block, and determine blocks other than the first main block as first sub-blocks; The first sub-block in each of the original areas that is closest to the first main block is merged into the first main block to obtain the corresponding preliminary divided area.
5. The area division method according to claim 1, characterized in that: The step of determining adjacent areas of each of the initially divided areas specifically includes: If the shortest distances between the preliminary division region boundary group string points of the current preliminary division region and all the preliminary division region boundary group string points are greater than the second distance threshold, the preliminary division region closest to the current preliminary division region is determined as an adjacent region of the current preliminary division region; If the closest distance between the preliminary division area boundary group string points of the current preliminary division area and all the preliminary division area boundary group string points is less than the second distance threshold, the preliminary division area whose closest distance is less than the second distance threshold is determined as an adjacent area of the current preliminary division area.
6. The area division method according to claim 1, characterized in that: The processing of the plurality of first optimized regions to obtain the plurality of second optimized regions based on the adjacent relationship between the first optimized regions, the adjacent relationship between photovoltaic strings, and the adjacent relationship between blocks specifically includes: Based on the adjacent relationship between the first optimization areas, target photovoltaic strings in different first optimization areas are exchanged to obtain multiple local optimization areas; Based on the neighboring relationship of photovoltaic strings and the neighboring relationship of blocks, the multiple local optimization areas are processed to obtain multiple second optimization areas.
7. The area division method according to claim 6, characterized in that: The step of exchanging target photovoltaic strings in different first optimization areas based on the adjacent relationship between the first optimization areas to obtain multiple local optimization areas specifically includes: Based on the adjacent relationship between each of the first optimized areas, the cable length from the center point of each first optimized area to the boundary group string point of the corresponding adjacent area is calculated, recorded as the first cable length, and the cable length from the center point of each first optimized area to its own boundary group string point is calculated, recorded as the second cable length; Based on each of the first cable lengths and each of the second cable lengths, determining whether there is a third optimization area and a fourth optimization area that meet the preset cable length requirements in each of the first optimization areas; Exchanging photovoltaic strings that meet preset photovoltaic string exchange conditions in the third optimization area and the fourth optimization area; Update all the first optimization area center points and the group string point sets of each cluster, and return to search for the optimization area combination that meets the preset cable length requirement again, until there is no optimization area combination whose cable length difference in the preset cable length requirement is greater than 0, and generate a local optimization area division result with the shortest cable length and the highest concentration.
8. The area division method according to claim 7, characterized in that: The preset cable length requirements include the following conditions: The third optimized region is named a, and the fourth optimized region is named b; The cable length from the center point a to the boundary point b of the string group Pb1 is recorded as: M a-pb1 ; The cable length from the center point of b to the boundary point of b string Pb1 is recorded as: M b-pb1 ; The cable length from the boundary point Pa1 of the string in a to the center point of a is recorded as M pa1 -a; The cable length from the center point b to the boundary point Pa1 of the string in a is recorded as: M b-pa1 ; If M a-pb1 <M b-pb1 , and there exists M in a pa1-a >M b-pa1 The string boundary point Pa1 is determined, and the combination of a and b that satisfies the maximum cable length difference is determined; The expression of cable length difference △M is as follows: ΔM=(M b-pb1 +M pa1-a )-(M a-pb1 +M b-pa1 )。 9. The area division method according to claim 7, characterized in that: The preset photovoltaic string switching conditions include: When the third optimized region and the fourth optimized region are mutually the only adjacent regions, the boundary group string points in the third optimized region and the boundary group string points in the fourth optimized sub-region b are interchanged; When the fourth optimization area and the third optimization area are not mutually uniquely adjacent areas, and the closest distance from the center point of the third optimization area to the boundary group string points of the fourth optimization area is less than the third distance threshold, and the closest distance from the center point of the fourth optimization area to the boundary group string points of the third optimization area is less than the third distance threshold, the boundary group string points in the third optimization area and the boundary group string points in the fourth optimization area are interchanged.
10. The area division method according to claim 6, characterized in that: The processing of the plurality of local optimization regions based on the photovoltaic string neighboring relationship and the block neighboring relationship to obtain the plurality of second optimization regions specifically includes: Based on the photovoltaic string association relationship and the block proximity relationship, each of the local optimization areas is divided into blocks to obtain a plurality of second blocks; Determine the second block with the largest number of photovoltaic strings in all the second blocks in each of the local optimization areas as a second main block, and determine blocks other than the second main block as second sub-blocks; The second sub-block closest to the second main block in each of the local optimized regions is merged into the second main block to obtain the corresponding second optimized region.
11. The area division method according to claim 1, characterized in that: Also includes: Determining the second optimized area whose capacity does not reach the capacity of the second preset area as the capacity area to be adjusted; Finding adjacent intersection points between the capacity areas to be adjusted; Each of the adjacent intersection points is transferred until the capacity of all the second optimization areas reaches the capacity of the second preset area, thereby obtaining a plurality of the target optimization areas.
12. A device for dividing regions of a photovoltaic power station, characterized in that: include: A region division unit, configured to divide the photovoltaic power station into regions based on the arrangement information of the photovoltaic power station to obtain a plurality of preliminary divided regions, so that the photovoltaic strings within the preliminary divided regions are adjacent; A capacity matching unit, configured to perform capacity matching on the plurality of the preliminary divided areas to obtain a plurality of first optimized areas based on the adjacent relationship between the respective preliminary divided areas and the first preset area capacity; A region processing unit, configured to process the plurality of first optimized regions to obtain a plurality of second optimized regions based on the adjacent relationship between the first optimized regions, the adjacent relationship between photovoltaic strings, and the adjacent relationship between blocks; an area determination unit, configured to determine each of the second optimization areas as a target optimization area when the capacities of all the second optimization areas reach the second preset area capacity; Wherein, the capacity matching unit comprises: An adjacent region determination subunit, used to determine adjacent regions of each of the initially divided regions; A to-be-processed region determination subunit, configured to determine, from among all the preliminary divided regions, a preliminary divided region with the least number of adjacent regions as a to-be-processed region; A capacity difference calculation subunit, used for calculating the capacity difference between the capacity of the area to be processed and the capacity of the first preset area; A capacity matching subunit, configured to perform capacity matching on the area to be processed based on a size relationship between the capacity difference and 0, to obtain a corresponding first optimized area; Wherein, the capacity matching subunit is specifically used for: If the capacity difference is equal to 0, the area to be processed is removed from the entire plant string unit of the photovoltaic power station, and a new plant string unit is formed; If the capacity difference is less than 0, the first target photovoltaic string in the adjacent area is re-divided into the area to be processed; If the capacity difference is greater than 0, the second target photovoltaic string in the area to be processed is re-divided into the adjacent area.
13. The area dividing device according to claim 12, characterized in that: The area division unit specifically includes: An original area division subunit, configured to divide the photovoltaic power station into multiple original areas based on the arrangement information; The area processing subunit is used to process the plurality of original areas to obtain the plurality of preliminary divided areas based on the adjacent relationship of photovoltaic strings and the adjacent relationship of blocks.
14. The area dividing device according to claim 12, characterized in that: The regional processing unit specifically includes: A string exchange subunit, configured to exchange target photovoltaic strings in different first optimization areas to obtain a plurality of local optimization areas based on the adjacent relationship between the first optimization areas; The local optimization region processing subunit is used to process the multiple local optimization regions based on the photovoltaic string adjacent relationship and the block adjacent relationship to obtain multiple second optimization regions.
Citation Information
Patent Citations
Distributed photovoltaic power station active power virtual acquisition method based on ICOA-BPNN
CN112100904A
Photovoltaic array automatic arrangement method and photovoltaic power station automatic arrangement method
CN112287529A