Four-arm automatic sand accumulation wall artificial island

The four-arm automatic sand accumulation wall uses seawater quicksand to automatically accumulate, which solves the problems of high cost and complicated construction of island reclamation projects, achieves cost saving and improvement of construction efficiency, and enhances the stability and erosion resistance of the artificial island.

CN113668466BInactive Publication Date: 2024-10-25DALIAN OCEAN UNIV
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202110985163.X
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2021-08-26
Publication Date
2024-10-25
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

Existing sea reclamation and island building projects are costly and complex, with many manual steps and poor corrosion resistance of concrete cast-in-place piles, resulting in a large project volume and high cost, and the artificial islands are susceptible to erosion.

Method used

A four-arm automatic sand accumulation wall is adopted. Through the design of flooded sand dunes and four-arm automatic sand accumulation wall, quicksand in seawater is automatically accumulated to reduce manual sand filling steps and reduce costs. The wall is strengthened with the dunes through oblique extension. Cooperate to enhance structural stability and reduce erosion.

Benefits of technology

It achieves cost savings in the construction of artificial islands, reduces project volume, improves construction efficiency, reduces the erosion risk of artificial islands, and improves structural stability and strength.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN113668466B_ABST
    Figure CN113668466B_ABST
Patent Text Reader

Abstract

The present invention provides an artificial island with a four-arm automatic sand accumulation wall, which belongs to the field of artificial islands and comprises a flooded sand dune and a four-arm automatic sand accumulation wall. The four-arm automatic sand accumulation wall is respectively arranged around the top of the flooded sand dune. The four-arm automatic sand accumulation wall is provided with an upper extending sand accumulation wall, an inner flat anti-turnover wall, an oblique outward extending reinforcement wall and a bottom stabilizing wall. The advantages and effects of the present invention are that the artificial island mainly adopts the four-arm automatic sand accumulation wall to accumulate sand naturally, and can capture sand flowing with the nearshore current, thereby greatly reducing labor costs and machinery costs, and facilitating the construction of the artificial island; the technology is reasonably designed and easy to operate; it effectively reduces the amount of engineering work and improves construction efficiency.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the field of artificial islands, and in particular relates to an artificial island with four-arm automatic sand accumulation walls. Background Art

[0002] With the rapid development of economy, land resources have become increasingly scarce, and land reclamation has become an important measure for human beings to develop and utilize the ocean. With the development and progress of science and technology, land reclamation has developed from land reclamation projects in coastal areas to land reclamation projects based on islands and reefs in the ocean.

[0003] The existing method of land reclamation is to use dredgers to blow sand from the sea to fill the islands. The land reclamation materials used are generally sea sand and silt from nearby shallows and some soil transported from land. The soil is mined and transported on land specifically for land reclamation, which is costly both in terms of material collection and transportation.

[0004] In addition, my country's island reclamation projects mainly use concrete bored pile technology to form enclosures, then blow sand and fill the enclosures, and finally carry out foundation treatment. However, concrete bored piles have a complex construction process, many manual operation steps, high labor and machinery costs, and poor corrosion resistance. Summary of the invention

[0005] In order to solve the above-mentioned technical problems, the present invention provides a method for solving the problem of large engineering workload and high cost of artificial island construction, which adopts natural sand accumulation to build islands, minimizes manual labor and reduces construction costs.

[0006] The technical solution of the present invention is: an artificial island with four-arm automatic sand accumulation wall, comprising a flooded sand dune and a four-arm automatic sand accumulation wall, wherein the top surface height of the flooded sand dune is between the average low tide water level line and the average high tide water level line, and a flooded sand dune slope is arranged around the flooded sand dune, and the four-arm automatic sand accumulation wall is respectively arranged around the top of the flooded sand dune, and the four-arm automatic sand accumulation wall is provided with an upper extended sand accumulation wall, an inner flat anti-turnover wall, an oblique outward reinforcement wall and a bottom stabilizing wall, and the upper extended sand accumulation wall is arranged vertically, and the top height of the upper extended sand accumulation wall is At the average high tide water level line, the upper extended sand accumulation wall is provided with sand accumulation holes, the inner flat anti-turnover wall is located on the inner side of the four-arm automatic sand accumulation wall and extends to the top of the flooded sand dune, the oblique outwardly extended reinforcing wall cooperates with the slope of the flooded sand dune, the bottom stabilizing wall is embedded in the flooded sand dune, and the part enclosed by the upper extended sand accumulation wall of the four-arm automatic sand accumulation wall and the top of the flooded sand dune is an automatic sand accumulation pit, an inner pit sand accumulation layer is provided in the automatic sand accumulation pit, a fill layer is provided on the top of the inner pit sand accumulation layer, and outer pit sand is provided on the outer side of the four-arm automatic sand accumulation wall.

[0007] Preferably, the upper extended sand accumulation wall and the bottom stabilizing wall are vertically aligned, the lower edge of the inner flat anti-overturning wall is horizontal, the upper edge of the inner flat anti-overturning wall is a slope, and the upper edge of the inner flat anti-overturning wall is inclined downward away from the end of the intersection node, the connection point between the inner flat anti-overturning wall, the upper extended sand accumulation wall and the bottom stabilizing wall is the intersection node, the oblique outward extending reinforcing wall is respectively connected to the upper extended sand accumulation wall and the bottom stabilizing wall at the intersection node, the oblique outward extending reinforcing wall is located outside the four-arm automatic sand accumulation wall, and the oblique outward extending reinforcing wall extends obliquely downward, and the slope angle of the oblique outward extending reinforcing wall is 30-60°.

[0008] Preferably, the four-arm automatic sand accumulation wall is provided with inner bent anti-bending steel bars and outer bent anti-bending steel bars, the inner bent anti-bending steel bars are provided with sand accumulation wall bending steel bars, anti-flapping wall bending steel bars, horizontal bending sections, vertical bending sections, hoop bottom angles and inner hoop staggered angles, the hoop bottom angles are located at both ends of the horizontal bending sections, the anti-flapping wall bending steel bars and the vertical bending sections are connected through the inner hoop staggered angles, the sand accumulation wall bending steel bars are located in the upper extended sand accumulation wall, the anti-flapping wall bending steel bars are located in the inner extended anti-flapping wall, the horizontal The bending section and the bottom angle of the hoop are located in the bottom stable wall, the outer bent anti-bending steel bars include sand-accumulating wall reinforcing steel bars, reinforced wall bending steel bars, reinforced wall reinforcing steel bars, vertical bending sections, hoop outer angles and outer hoop staggered angles, the hoop outer angles are located at both ends of the vertical bending section, the sand-accumulating wall reinforcing steel bars are located in the extended sand-accumulating wall, the reinforced wall bending steel bars, the reinforced wall reinforcing steel bars, the vertical bending sections and the hoop outer angles are all located in the obliquely extended reinforced wall, and the outer hoop staggered angle is located at the intersection node.

[0009] Preferably, the sand accumulation wall bending steel bars are located on a side of the upper extended sand accumulation wall close to the automatic sand accumulation pit, the sand accumulation wall reinforcing steel bars are located on a side of the upper extended sand accumulation wall away from the automatic sand accumulation pit, the anti-flapping wall bending steel bars are located on a side of the inner flat anti-flapping wall close to the automatic sand accumulation pit, the horizontal bending section is located at the bottom of the bottom stabilizing wall, longitudinal steel bars are arranged in the bottom angle of the hoop, and a number of evenly distributed longitudinal steel bars are arranged at the bottom of the anti-flapping wall bending steel bars; the outer hoop staggered angle intersects with the inner hoop staggered angle, and longitudinal steel bars are arranged at the intersecting portion of the two.

[0010] Preferably, the sand accumulation wall bending steel bars are vertically arranged, the vertical bending section is perpendicular to the horizontal bending section, and then bent in the direction of the sand accumulation wall bending steel bars, the anti-flapping wall bending steel bars are horizontally inclined downward and intersect with the sand accumulation wall bending steel bars, and the sand accumulation wall bending steel bars, the anti-flapping wall bending steel bars, the horizontal bending section, the vertical bending section, the hoop bottom angle and the inner hoop staggered angle are an integrated structure.

[0011] Preferably, the sand-accumulated wall reinforcing steel bars, the reinforced wall bending steel bars, the reinforced wall reinforcing steel bars, the vertical bending section, the outer angle of the hoop and the outer hoop staggered angle are an integrated structure, the sand-accumulated wall reinforcing steel bars are vertically arranged, the reinforced wall reinforcing steel bars are formed by bending the bottom of the sand-accumulated wall reinforcing steel bars by 30°~60° in a clockwise direction, the vertical bending section is vertically arranged, the reinforced wall bending steel bars intersect the sand-accumulated wall reinforcing steel bars, and the outer hoop staggered angle is formed by the angle between the sand-accumulated wall reinforcing steel bars and the reinforced wall reinforcing steel bars.

[0012] Preferably, the top of the upper extended sand wall is 0.5m~3m higher than the average high tide water level, the top surface of the filling soil layer is flush with the top surface of the upper extended sand wall, the distance between the top of the sand layer in the pit and the average high tide water level is 0mm~100mm, and the slope of the sand dune side slope is the same as the slope of the oblique extended reinforcement wall.

[0013] Preferably, the height of the upper extended sand wall is 5 to 10 times the height of the bottom stable wall, the length of the inner flat anti-overturning wall is 0.5 to 0.8 times the length of the upper extended sand wall, and the length of the oblique outward extending reinforcing wall is 0.5 to 1 times the length of the upper extended sand wall.

[0014] Preferably, the four-arm automatic sand accumulation wall is made of concrete material.

[0015] The advantages of the present invention are as follows: the artificial island of the present invention mainly adopts natural sand accumulation by a four-arm automatic sand accumulation wall, which can capture sand flowing with the nearshore current. When the quicksand enters the automatic sand accumulation pit from the sand accumulation hole, sand accumulation is formed in the automatic sand accumulation pit, which saves the operation steps of manual sand filling, thereby greatly reducing labor costs and machinery costs, and is conducive to the construction of artificial islands; at the same time, the present invention uses a four-arm sand accumulation wall, which can effectively cooperate with the sand dunes, realizes convenient operation, effectively reduces the amount of engineering and improves construction efficiency, and can effectively reduce the erosion of the artificial island. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] Figure 1 It is a schematic diagram of the structure after the construction of the present invention is completed;

[0017] Figure 2 This is a schematic diagram of the structure of the automatic sand accumulation in the middle stage of the present invention;

[0018] Figure 3 This is a structural schematic diagram of the late stage of automatic sand accumulation of the present invention;

[0019] Figure 4 This is a schematic diagram of the structure of the present invention after the soil filling layer is completed;

[0020] Figure 5This is a schematic diagram of the internal structure of the four-arm automatic sand accumulation wall of the present invention;

[0021] Figure 6 This is a schematic diagram of the external facade of the four-arm automatic sand accumulation wall of the present invention;

[0022] Figure 7 for Figure 6 Sectional view along the AA direction;

[0023] Figure 8 This is a schematic diagram of the inner side bent anti-bending steel bar structure of the present invention;

[0024] Fig. 9 It is a schematic diagram of the outer side bent anti-bending steel bar structure of the present invention.

[0025] In the figure, 1. Four-arm automatic sand accumulation wall; 2. Automatic sand accumulation pit; 3. Flooded sand dune; 4. Flooded sand dune slope; 5. Sand accumulation layer in the pit; 6. Sand accumulation outside the pit; 7. Filling layer;

[0026] 1-1, upward sand accumulation wall; 1-2, inner flat anti-overturning wall; 1-3, oblique outward reinforcement wall; 1-4, bottom stabilizing wall; 1-5, junction node; 1-6, inner bending and bending steel bars; 1-7, outer bending and bending steel bars; 1-8, longitudinal steel bars; 1-9, sand accumulation hole;

[0027] 1-6-1, bending reinforcement of sand accumulation wall; 1-6-2, bending reinforcement of anti-overturning wall; 1-6-3, horizontal bending section; 1-6-4, vertical bending section; 1-6-5, bottom angle of hoop; 1-6-6, staggered angle of inner hoop;

[0028] 1-7-1, reinforcement of sand-accumulated wall; 1-7-2, reinforcement of bending wall; 1-7-3, reinforcement of wall; 1-7-4, vertical bending section; 1-7-5, outer angle of hoop; 1-7-6, staggered angle of outer hoop. DETAILED DESCRIPTION

[0029] In order to further illustrate the present invention, the present invention is described in detail below in conjunction with the accompanying drawings and embodiments, but they should not be construed as limiting the protection scope of the present invention.

[0030] Reference Figures 1 to 9The present invention proposes an artificial island with four-arm automatic sand accumulation wall 1, an artificial island with four-arm automatic sand accumulation wall 1, comprising a flooded sand dune 3 and a four-arm automatic sand accumulation wall 1, wherein the top surface height of the flooded sand dune 3 is between the average low tide water level line and the average high tide water level line, and a flooded sand dune 3 slope is arranged around the flooded sand dune 3, and the four-arm automatic sand accumulation wall 1 is respectively arranged around the top of the flooded sand dune 3. Preferably, the four-arm automatic sand accumulation wall 1 is respectively arranged on the four sides of the top of the flooded sand dune 3, and the four-arm automatic sand accumulation wall 1 is provided with an upper extended sand accumulation wall 1-1, an inner flat anti-turnover wall 1-2, an oblique outwardly extended reinforcing wall 1-3 and a bottom stabilizing wall 1-4, the upper extended sand accumulation wall 1-1 is vertically arranged, and the top of the upper extended sand accumulation wall 1-1 is higher than the average high tide water level line, The upper extended sand accumulation wall 1-1 is provided with a sand accumulation hole 1-9, and the sand accumulation hole 1-9 is located at one end of the inner side of the upper extended sand accumulation wall 1-1 and is inclined downward. The inner flat anti-turnover wall 1-2 is located on the inner side of the four-arm automatic sand accumulation wall 1 and extends to the top of the flooded sand dune 3. The oblique outwardly extending reinforcing wall 1-3 cooperates with the slope of the flooded sand dune 3, and the bottom stabilizing wall 1-4 is embedded in the flooded sand dune 3. The part surrounded by the upper extended sand accumulation wall 1-1 and the top of the flooded sand dune 3 is an automatic sand accumulation pit 2. Preferably, the inner flat anti-turnover wall 1-2 of each four-arm automatic sand accumulation wall 1 is assembled into a rectangular frame at the bottom of the automatic sand accumulation pit 2. An inner pit sand accumulation layer 5 is provided in the automatic sand accumulation pit 2, and a fill layer 7 is provided on the top of the inner pit sand accumulation layer 5. The outer side of the four-arm automatic sand accumulation wall 1 is provided with outer pit sand 6.

[0031] The present invention adopts this structure, by installing a four-arm automatic sand accumulation wall 1 on the top of the flooded sand dune 3, the quicksand in the sea water enters the automatic sand accumulation pit 2 through the sand accumulation holes 1-9 as the tide rises and falls, and automatically forms a pit sand accumulation layer 5 in the automatic sand accumulation pit 2. Moreover, due to the angle between the oblique outwardly extending reinforcing wall 1-3 and the upper extended sand accumulation wall 1-1, the quicksand in the sea will continuously accumulate on the outside of the four-arm automatic sand accumulation wall 1 to form 6 layers of sand accumulation outside the pit; as there is no need to blow sand and Artificial sand filling greatly saves construction costs. At the same time, the inner flat anti-turnover wall 1-2 is located on the inner side of the four-arm automatic sand accumulation wall 1 and extends to the top of the flooded sand dune 3 to form a rectangular frame. When the sand accumulation layer 5 is formed in the automatic sand accumulation pit 2, the stability of the four-arm automatic sand accumulation wall 1 can be increased; the oblique outwardly extending reinforcing wall 1-3 can effectively fit the edge of the slope of the flooded sand dune 3, thereby increasing the stability of the four-arm automatic sand accumulation wall 1 and effectively reducing the erosion of the slope of the flooded sand dune 3.

[0032] Preferably, the upper extended sand accumulation wall 1-1 and the bottom stabilizing wall 1-4 are vertically aligned, the lower edge of the inner flat anti-turnover wall 1-2 is horizontal, the upper edge of the inner flat anti-turnover wall 1-2 is a slope, and the upper edge of the inner flat anti-turnover wall 1-2 is inclined downward away from the end of the intersection node 1-5, the connection point between the inner flat anti-turnover wall 1-2, the upper extended sand accumulation wall 1-1 and the bottom stabilizing wall 1-4 is the intersection node 1-5, the oblique outwardly extending reinforcing wall 1-3 is respectively connected to the upper extended sand accumulation wall 1-1 and the bottom stabilizing wall 1-4 at the intersection node 1-5, the oblique outwardly extending reinforcing wall 1-3 is located outside the four-arm automatic sand accumulation wall 1, and the oblique outwardly extending reinforcing wall 1-3 extends obliquely downward, and the slope angle of the oblique outwardly extending reinforcing wall 1-3 is 30-60°;

[0033] The plane design of the bottom of the inner flat anti-overturning wall 1-2 can effectively increase the stability between the inner flat anti-overturning wall 1-2 and the flooded sand dune 3. The inclined surface at the top can form a conical structure at the bottom of the automatic sand accumulation pit 2, increase the fixing effect of the sand accumulation layer 5 in the pit on the four-arm automatic sand accumulation wall 1, and increase the stability of the entire artificial island; connecting the oblique outward reinforcement wall 1-3 with the intersection node 1-5 can increase the overall strength of the four-arm automatic sand accumulation wall 1.

[0034] Preferably, the four-arm automatic sand accumulation wall 1 is provided with inner bent anti-bending steel bars 1-6 and outer bent anti-bending steel bars 1-7, the inner bent anti-bending steel bars 1-6 are provided with sand accumulation wall bending steel bars 1-6-1, anti-flapping wall bending steel bars 1-6-2, horizontal bending sections 1-6-3, vertical bending sections 1-6-4, hoop bottom angles 1-6-5 and inner hoop staggered angles 1-6-6, the hoop bottom angles 1-6-5 are located at both ends of the horizontal bending sections 1-6-3, the anti-flapping wall bending steel bars 1-6-2 and the vertical bending sections 1-6-4 are connected by the inner hoop staggered angles 1-6-6, the sand accumulation wall bending steel bars 1-6-1 are located in the upper extended sand accumulation wall 1-1, the anti-flapping wall bending steel bars 1-6-2 are located in the inner extended anti-flapping wall 1-2, the horizontal bending sections 1-6- 3 and the hoop bottom angle 1-6-5 are located in the bottom stabilizing wall 1-4, the outer bent anti-bending steel bar 1-7 includes a sand accumulation wall reinforcing steel bar 1-7-1, a reinforcing wall bending steel bar 1-7-2, a reinforcing wall reinforcing steel bar 1-7-3, a vertical bending section 1-7-4, a hoop outer angle 1-7-5 and an outer hoop staggered angle 1-7-6, the hoop outer angle 1-7-5 is located at both ends of the vertical bending section 1-7-4, the sand accumulation wall reinforcing steel bar 1-7-1 is located in the upper extended sand accumulation wall 1-1, the reinforcing wall bending steel bar 1-7-2, the reinforcing wall reinforcing steel bar 1-7-3, the vertical bending section 1-7-4 and the hoop outer angle 1-7-5 are all located in the obliquely extended reinforcing wall 1-3, and the outer hoop staggered angle 1-7-6 is located at the intersection node 1-5.

[0035] By arranging inner bent flexural steel bars 1-6 and outer bent flexural steel bars 1-7 in the four-arm automatic sand accumulation wall 1, and at the same time, the inner bent flexural steel bars 1-6 and the outer bent flexural steel bars 1-7 are extended to various parts of the four-arm automatic sand accumulation wall 1, the overall structural strength of the four-arm automatic sand accumulation wall 1 can be increased, thereby increasing the overall structural strength of the artificial island, and the partial structures of the inner bent flexural steel bars 1-6 and the outer bent flexural steel bars 1-7 are staggered, which can further increase the structural strength of the staggered parts.

[0036] Preferably, the sand accumulation wall bending steel bar 1-6-1 is located on a side of the upper extended sand accumulation wall 1-1 close to the automatic sand accumulation pit 2, the sand accumulation wall reinforcing steel bar 1-7-1 is located on a side of the upper extended sand accumulation wall 1-1 away from the automatic sand accumulation pit 2, the anti-flapping wall bending steel bar 1-6-2 is located on a side of the inner flat anti-flapping wall 1-2 close to the automatic sand accumulation pit 2, the horizontal bending section 1-6-3 is located at the bottom of the bottom stabilizing wall 1-4, longitudinal steel bars 1-8 are arranged in the bottom angle 1-6-5 of the hoop, and a plurality of evenly distributed longitudinal steel bars 1-8 are arranged at the bottom of the anti-flapping wall bending steel bar 1-6-2; the outer hoop staggered angle 1-7-6 intersects with the inner hoop staggered angle 1-6-6, and longitudinal steel bars 1-8 are arranged at the intersecting part of the two.

[0037] The sand accumulation wall bending steel bars 1-6-1 and the sand accumulation wall reinforcing steel bars 1-7-1 are respectively located on both sides of the upper extended sand accumulation wall 1-1, which can increase the strength of the two sides of the upper extended sand accumulation wall 1-1 and increase the impact resistance. The setting of the longitudinal steel bars 1-8 further increases the overall strength of the four-arm automatic sand accumulation wall 1.

[0038] Preferably, the sand accumulation wall bending steel bar 1-6-1 is vertically arranged, the vertical bending section 1-7-41-6-4 is perpendicular to the horizontal bending section 1-6-3, and then bends in the direction of the sand accumulation wall bending steel bar 1-6-1, the anti-overturning wall bending steel bar 1-6-2 is horizontally inclined downward, and intersects with the sand accumulation wall bending steel bar 1-6-1, the sand accumulation wall bending steel bar 1-6-1, the anti-overturning wall bending steel bar 1-6-2, the horizontal bending section 1-6-3, the vertical bending section 1-6-4, the hoop bottom angle 1-6-5 and the inner hoop staggered angle 1-6-6 are an integrated structure; the sand accumulation wall reinforcement steel bar 1-7-1, the reinforcement wall bending steel bar 1-7- 2. The reinforced wall reinforcement steel bar 1-7-3, the vertical bending section 1-7-4, the hoop outer angle 1-7-5 and the outer hoop staggered angle 1-7-6 are an integrated structure. The sand accumulation wall reinforcement steel bar 1-7-1 is vertically arranged. The reinforced wall reinforcement steel bar 1-7-3 is formed by bending the bottom of the sand accumulation wall reinforcement steel bar 1-7-1 by 30°~60° in a clockwise direction. The vertical bending section 1-7-4 is vertically arranged. The reinforced wall bending steel bar 1-7-2 intersects with the sand accumulation wall reinforcement steel bar 1-7-1. The outer hoop staggered angle 1-7-6 is formed by the angle between the sand accumulation wall reinforcement steel bar 1-7-1 and the reinforced wall reinforcement steel bar 1-7-3.

[0039] With an integrated structure, it is only necessary to bend the inner bending flexural steel bars 1-6 and the outer bending flexural steel bars 1-7, which reduces the construction difficulty and increases the construction efficiency.

[0040] Preferably, the top of the upper extended sand wall 1-1 is 0.5m~3m higher than the average high tide water level, the top surface of the filling soil layer 7 is flush with the top surface of the upper extended sand wall 1-1, the distance between the top of the sand layer 5 in the pit and the average high tide water level is 0mm~100mm, and the slope of the sand dune side slope is the same as the slope of the oblique extended reinforcement wall 1-3;

[0041] When the sand layer 5 in the pit accumulates to a certain height, an artificial filling layer 7 is carried out to seal the sand layer 5 in the pit, and then an integral artificial island is formed. The top of the upper sand wall 1-1 is higher than the average high tide water level, which can effectively reduce the erosion of the artificial island by seawater.

[0042] Preferably, the height of the upper extended sand accumulation wall 1-1 is 5 to 10 times the height of the bottom stabilizing wall 1-4, the length of the inner flat anti-overturning wall 1-2 is 0.5 to 0.8 times the length of the upper extended sand accumulation wall 1-1, and the length of the oblique outward extending reinforcing wall 1-3 is 0.5 to 1 times the length of the upper extended sand accumulation wall 1-1. By adopting the above-mentioned proportional relationship, the structural stability of the four-arm automatic sand accumulation wall 1 can be further increased.

[0043] Preferably, the four-arm automatic sand accumulation wall 1 is made of concrete material. The four-arm automatic sand accumulation wall 1 made of concrete not only has high structural strength but also has a large deadweight, which can effectively increase the stability of the artificial island in the initial stage of construction.

[0044] The above is only a preferred embodiment of the present invention. It should be pointed out that for ordinary technicians in this technical field, several improvements and modifications can be made without departing from the principle of the present invention. These improvements and modifications should also be regarded as the scope of protection of the present invention.

Claims

1. A four-arm automatic sand accumulation wall artificial island, characterized by: The invention comprises a flooded sand dune (3) and a four-arm automatic sand accumulation wall (1), wherein the top surface height of the flooded sand dune (3) is located between the average low tide water level line and the average high tide water level line, and a flooded sand dune slope (4) is arranged around the flooded sand dune (3). The four-arm automatic sand accumulation wall (1) is respectively arranged around the top of the flooded sand dune (3), and the four-arm automatic sand accumulation wall (1) is provided with an upper extended sand accumulation wall (1-1), an inner flat anti-turnover wall (1-2), an oblique outwardly extended strengthening wall (1-3) and a bottom stabilizing wall (1-4). The upper extended sand accumulation wall (1-1) is arranged vertically, and the top of the upper extended sand accumulation wall (1-1) is higher than the average high tide water level line. 1) a sand accumulation hole (1-9) is provided, the inner flat anti-turnover wall (1-2) is located inside the four-arm automatic sand accumulation wall (1) and extends to the top of the flooded sand dune (3), the oblique outwardly extending reinforcing wall (1-3) cooperates with the flooded sand dune slope (4), the bottom stabilizing wall (1-4) is embedded in the flooded sand dune (3), the part surrounded by the upper extended sand accumulation wall (1-1) of the four-arm automatic sand accumulation wall (1) and the top of the flooded sand dune (3) is an automatic sand accumulation pit (2), an inner pit sand accumulation layer (5) is provided in the automatic sand accumulation pit (2), a filling layer (7) is provided on the top of the inner pit sand accumulation layer (5), and an outer pit sand accumulation layer (6) is provided on the outer side of the four-arm automatic sand accumulation wall (1); The upper extended sand wall (1-1) and the bottom stabilizing wall (1-4) are vertically aligned, the lower edge of the inner flat anti-turnover wall (1-2) is horizontal, the upper edge of the inner flat anti-turnover wall (1-2) is a slope, and the upper edge of the inner flat anti-turnover wall (1-2) is inclined downward away from one end of the upper extended sand wall (1-1), and the inner flat anti-turnover wall (1-2), the upper extended sand wall (1-1) and the bottom stabilizing wall (1-4) are vertically aligned, the lower edge of the inner flat anti-turnover wall (1-2) is horizontal, the upper edge of the inner flat anti-turnover wall (1-2) is sloped, and the upper edge of the inner flat anti-turnover wall (1-2) is inclined downward away from the end of the upper extended sand wall (1-1). The connection point between the upper and lower extending sand accumulation walls (1-1) and the lower stabilizing wall (1-4) is a junction node (1-5), the obliquely extending reinforcing wall (1-3) is respectively connected to the upper extending sand accumulation wall (1-1) and the lower stabilizing wall (1-4) at the junction node (1-5), the obliquely extending reinforcing wall (1-3) is located outside the four-arm automatic sand accumulation wall (1), and the obliquely extending reinforcing wall (1-3) extends obliquely downward, and the slope angle of the obliquely extending reinforcing wall (1-3) is 30-60°; The four-arm automatic sand accumulation wall (1) is made of concrete material.

2. The four-arm automatic sand accumulation wall artificial island according to claim 1 is characterized by: The four-arm automatic sand accumulation wall (1) is provided with inner bending anti-bending steel bars (1-6) and outer bending anti-bending steel bars (1-7), the inner bending anti-bending steel bars (1-6) are provided with sand accumulation wall bending steel bars (1-6-1), anti-turnover wall bending steel bars (1-6-2), horizontal bending sections (1-6-3), vertical bending sections (1-6-4), hoop bottom angles (1-6-5) and inner hoop staggered angles (1-6-6), the hoop bottom angles (1-6-5) and inner hoop staggered angles (1-6-6). -6-5) are located at both ends of the horizontal bending section (1-6-3), the anti-flapping wall bending steel bars (1-6-2) and the vertical bending section (1-6-4) are connected through the inner hoop staggered angle (1-6-6), the sand accumulation wall bending steel bars (1-6-1) are located in the upper extended sand accumulation wall (1-1), the anti-flapping wall bending steel bars (1-6-2) are located in the inner extended anti-flapping wall (1-2), the horizontal bending section (1-6-3) and The hoop bottom angle (1-6-5) is located inside the bottom stabilizing wall (1-4), the outer bending anti-bending steel bars (1-7) include sand accumulation wall reinforcement steel bars (1-7-1), reinforcement wall bending steel bars (1-7-2), reinforcement wall reinforcement steel bars (1-7-3), vertical bending sections (1-7-4), hoop outer angles (1-7-5) and outer hoop staggered angles (1-7-6), the hoop outer angles (1-7-5) are located inside the vertical bending sections. At both ends of the segment (1-7-4), the sand accumulation wall reinforcement steel bar (1-7-1) is located in the upper extended sand accumulation wall (1-1), the reinforcement wall bending steel bar (1-7-2), the reinforcement wall reinforcement steel bar (1-7-3), the vertical bending segment (1-7-4) and the outer corner of the hoop (1-7-5) are all located in the obliquely extended reinforcement wall (1-3), and the outer hoop staggered angle (1-7-6) is located at the intersection node (1-5).

3. The four-arm automatic sand accumulation wall artificial island according to claim 2 is characterized by: The sand accumulation wall bending steel bar (1-6-1) is located on a side of the upper extended sand accumulation wall (1-1) close to the automatic sand accumulation pit (2), the sand accumulation wall reinforcement steel bar (1-7-1) is located on a side of the upper extended sand accumulation wall (1-1) away from the automatic sand accumulation pit (2), the anti-flapping wall bending steel bar (1-6-2) is located on a side of the inner flat anti-flapping wall (1-2) close to the automatic sand accumulation pit (2), the horizontal bending section (1-6-3) is located at the bottom of the bottom stabilizing wall (1-4), longitudinal steel bars (1-8) are arranged in the hoop bottom angle (1-6-5), a plurality of evenly distributed longitudinal steel bars (1-8) are arranged at the bottom of the anti-flapping wall bending steel bar (1-6-2), the outer hoop staggered angle (1-7-6) intersects with the inner hoop staggered angle (1-6-6), and the longitudinal steel bars (1-8) are arranged at the intersection of the two.

4. The four-arm automatic sand accumulation wall artificial island according to claim 3 is characterized by: The sand accumulation wall bending steel bar (1-6-1) is vertically arranged, the vertical bending section (1-6-4) is perpendicular to the horizontal bending section (1-6-3), and then bends in the direction of the sand accumulation wall bending steel bar (1-6-1), the anti-overturning wall bending steel bar (1-6-2) is horizontally inclined downward, and intersects with the sand accumulation wall bending steel bar (1-6-1), the sand accumulation wall bending steel bar (1-6-1), the anti-overturning wall bending steel bar (1-6-2), the horizontal bending section (1-6-3), the vertical bending section (1-6-4), the hoop bottom angle (1-6-5) and the inner hoop staggered angle (1-6-6) are an integrated structure.

5. The four-arm automatic sand accumulation wall artificial island according to claim 3 is characterized by: The sand accumulation wall reinforcement steel bar (1-7-1), the reinforcement wall bending steel bar (1-7-2), the reinforcement wall reinforcement steel bar (1-7-3), the vertical bending section (1-7-4), the hoop outer angle (1-7-5) and the outer hoop staggered angle (1-7-6) are an integrated structure; the sand accumulation wall reinforcement steel bar (1-7-1) is vertically arranged; the reinforcement wall reinforcement steel bar (1-7-3) is formed by bending the bottom of the sand accumulation wall reinforcement steel bar (1-7-1) by 30° to 60° in a clockwise direction; the vertical bending section (1-7-4) is vertically arranged; the reinforcement wall bending steel bar (1-7-2) intersects with the sand accumulation wall reinforcement steel bar (1-7-1); and the outer hoop staggered angle (1-7-6) is formed by the angle between the sand accumulation wall reinforcement steel bar (1-7-1) and the reinforcement wall reinforcement steel bar (1-7-3).

6. The four-arm automatic sand accumulation wall artificial island according to claim 1 is characterized by: The top of the upper extended sand wall (1-1) is 0.5m to 3m higher than the average high tide water level, the top surface of the fill layer (7) is flush with the top surface of the upper extended sand wall (1-1), the distance between the top of the sand layer (5) in the pit and the average high tide water level is 0mm to 100mm, and the slope of the sand dune slope (4) is the same as the slope of the oblique outwardly extending reinforcement wall (1-3).

7. The four-arm automatic sand accumulation wall artificial island according to claim 1 is characterized by: The height of the upper extended sand wall (1-1) is 5 to 10 times the height of the bottom stabilizing wall (1-4), the length of the inner flat anti-turnover wall (1-2) is 0.5 to 0.8 times the length of the upper extended sand wall (1-1), and the length of the oblique outwardly extending reinforcing wall (1-3) is 0.5 to 1 times the length of the upper extended sand wall (1-1).