A 220KV system load shedding control device to prevent grounding faults

By designing a load-sheltering control device to prevent grounding faults in the 220KV system, the 110KV side voltage imbalance caused by single-phase grounding failure in the 220KV system is solved by using a fast vacuum circuit breaker and terminal controller to disconnect the neutral point grounding circuit within 16ms, the 110KV side voltage imbalance caused by single-phase grounding failure in the 220KV system is solved. and large-scale load-shelving issues ensure the safe operation of the system.

CN113765078BActive Publication Date: 2024-12-06ANHUI HEKAI ELECTRICAL TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202111051001.5
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Priority Date
2021-08-17
Filing Date
2021-09-08
Publication Date
2024-12-06
Estimated Expiration
2041-09-08

AI Technical Summary

Technical Problem

The 220KV neutral point direct grounding system is prone to single-phase grounding failure during operation, resulting in unbalanced three-phase voltage on the 110KV side and causing large-scale load-shelving accidents.

Method used

A 220KV system load-shelting control device designed to prevent grounding faults, including fast vacuum circuit breaker, upper insulation cylinder, lower insulation cylinder, high-precision power supply, terminal controller, Lock coil, isolation transformer, backstage controller and optical fiber, through the terminal When the controller determines that the current exceeds the set threshold, it issues a switch-opening command to cause the fast vacuum circuit breaker to disconnect the neutral point grounding circuit within 16ms, and converts it into a neutral point without grounding system for a short time.

Benefits of technology

It effectively prevents voltage drop and large-area load-shelter accidents on the 110KV side, ensuring the safety and stability of system operation.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN113765078B_ABST
    Figure CN113765078B_ABST
Patent Text Reader

Abstract

The present invention relates to the field of electrical technology, and in particular to a 220KV system ground fault load shedding control device, comprising a fast vacuum circuit breaker, an upper insulating cylinder, a lower insulating cylinder, a high-precision power supply, a terminal controller, a Locke coil, an isolation transformer, a background controller, a maintenance node and an optical fiber; the 220KV system ground fault load shedding control device provided by the present invention, when a single-phase ground short circuit accident occurs, the device terminal controller determines whether the current of the Locke coil exceeds a set threshold by sampling, and if it exceeds the set threshold, a trip pulse is sent to the fast vacuum circuit breaker to quickly trip the fast vacuum circuit breaker, and within 16ms, the neutral point of the original directly grounded 110KV main transformer is converted into a neutral point short-term ungrounded system, so that the three-phase voltage of the 110KV system is quickly restored to a balanced value, and there will be no voltage sag problem, and large-scale load shedding accidents are suppressed to protect the safe operation of the system.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of electrical technology, and in particular to a 220KV system load shedding control device for preventing grounding faults. Background Art

[0002] When the 220KV neutral point direct grounding system is in operation, single-phase grounding faults often occur, causing the zero-sequence protection of the short-circuit fault line to operate and trip the grounding line. On the other hand, the neutral point of the 110KV side of the transformer in the substation at the end of the 220KV line must be directly grounded according to regulations. When a single-phase grounding occurs on the 220KV side line, a serious three-phase voltage imbalance will occur on the 110KV side during the transient process, causing the load on the 110KV side to temporarily drop due to a large-scale load shedding accident. Therefore, it is necessary to adopt a new device so that when a single-phase grounding short circuit occurs in the 220KV system, the problem of large-scale load shedding on the 110KV side will not occur. Summary of the invention

[0003] The purpose of the present invention is to provide a 220KV system to prevent ground fault load shedding control device, so that when a single-phase ground short circuit occurs in the 220KV system, it can prevent large-scale load shedding and power outage accidents caused by voltage sag due to serious mismatch of three-phase voltage on the 110KV side.

[0004] In order to achieve the above object, the present invention adopts the following technical solutions:

[0005] A 220KV system ground fault load shedding control device, comprising a fast vacuum circuit breaker, an upper insulating cylinder, a lower insulating cylinder, a high-precision power supply, a terminal controller, a Locke coil, an isolation transformer, a background controller, a maintenance section and an optical fiber;

[0006] The upper end interface of the fast vacuum circuit breaker is connected to the upper outlet line of the upper insulating cylinder to form a first lead-out line and lead out of the upper insulating cylinder, and the first lead-out line is connected to the neutral point of the main transformer 110KV;

[0007] The lower end interface of the fast vacuum circuit breaker is connected to the lower outlet line of the lower insulating cylinder to form a second lead-out line and lead out of the lower insulating cylinder, and the second lead-out line is connected to the existing system grounding line;

[0008] The Locke coil is fixed on the outgoing line side of the fast vacuum circuit breaker to meet the current measurement requirements;

[0009] The input power supply of the terminal controller is connected to the AC 220V output lead of the isolation transformer, and the two pairs of output lines are respectively connected to the opening trigger interface and the closing trigger interface of the high-precision power supply; the other pair of input interfaces of the terminal controller is connected to the output line of the Locke coil;

[0010] The input power of the high-precision power supply is connected to the AC 220V output lead of the isolation transformer, and the other two pairs of input interfaces of the high-precision power supply are respectively connected to the opening trigger output interface and the closing trigger output interface of the terminal controller.

[0011] In a further technical solution, the two pairs of optical fiber interfaces of the terminal controller are connected to the input terminal of the main control board of the background controller through optical fibers to meet the demand for information transmission.

[0012] Compared with the prior art, the present invention has the following technical effects:

[0013] The 220KV system ground fault load shedding control device provided by the present invention, when a single-phase ground short circuit accident occurs, the device terminal controller determines whether the current exceeds the set threshold value by sampling the current of the Locke coil. If it exceeds the set threshold value, it sends a trip pulse to the fast vacuum circuit breaker to make the fast vacuum circuit breaker quickly trip. Within 16ms, the neutral point of the 110KV main transformer that was originally directly grounded is converted into a neutral point short-term ungrounded system, so that the three-phase voltage of the 110KV system is quickly restored to the equilibrium value, and there will be no voltage sag problem. Large-scale load shedding accidents are also suppressed, protecting the safe operation of the system.

[0014] Other features and advantages of the present invention will be described in detail in the following detailed description. BRIEF DESCRIPTION OF THE DRAWINGS

[0015] Figure 1 The schematic diagram of the 220KV system ground fault load shedding control device of the present invention is shown;

[0016] Explanation of the numbers in the figure: 1- fast vacuum circuit breaker, 2- upper insulating cylinder, 3- lower insulating cylinder, 4- high-precision power supply, 5- terminal controller, 6- Locke coil, 7- isolation transformer, 8- backstage controller, 9- maintenance section, 10- optical fiber. DETAILED DESCRIPTION

[0017] In order to make the technical means, creative features, objectives and effects achieved by the present invention easy to understand, the present invention is further explained below in conjunction with specific drawings.

[0018] As mentioned above, combined with Figure 1 As shown, the present invention provides a 220KV system ground fault load shedding control device, comprising a fast vacuum circuit breaker 1, an upper insulating cylinder 2, a lower insulating cylinder 3, a high-precision power supply 4, a terminal controller 5, a Locke coil 6, an isolation transformer 7, a background controller 8, a maintenance node 9 and an optical fiber 10;

[0019] The upper end interface of the fast vacuum circuit breaker 1 is connected to the upper outlet line of the upper insulating tube 2 to form a first lead-out line and lead out of the upper insulating tube 2. The first lead-out line is connected to the neutral point of the main transformer 110KV;

[0020] The lower end interface of the fast vacuum circuit breaker 1 is connected to the lower outlet row of the lower insulating tube 3 to form a second lead-out row and lead out of the lower insulating tube 3, and the second lead-out row is connected to the existing system grounding row;

[0021] The Locke coil 6 is fixed on the outgoing line side of the fast vacuum circuit breaker 1 to meet the current measurement requirements;

[0022] The input power supply of the terminal controller 5 is connected to the AC 220V output lead of the isolation transformer 7, and the two pairs of output lines are respectively connected to the opening trigger interface and the closing trigger interface of the high-precision power supply 4; the other pair of input interfaces of the terminal controller 5 is connected to the output line of the Locke coil 6;

[0023] The input power of the high-precision power supply 4 is connected to the AC 220V output lead of the isolation transformer 7, and the other two pairs of input interfaces of the high-precision power supply 4 are respectively connected to the opening trigger output interface and the closing trigger output interface of the terminal controller 5.

[0024] The two pairs of optical fiber interfaces of the terminal controller 5 are connected to the input end of the main control board of the background controller 8 through optical fibers 10 to meet the demand for information transmission.

[0025] The 220KV system ground fault prevention load shedding control device provided by the present invention is connected in series between the neutral point of the main transformer and the grounding electrode of the substation. During normal operation, the fast vacuum circuit breaker 1 in the device is in a closed state to ensure that the 110KV neutral point is directly grounded well.

[0026] When a single-phase ground short circuit occurs in the 220KV system, the terminal controller 5 determines that the current exceeds the set threshold in about 2ms, and issues a trip command to trip the contact of the fast vacuum circuit breaker 1, so that the neutral point grounding loop is quickly disconnected within 16ms, and the 110KV system is turned into a neutral point temporarily ungrounded system operation, so that the 110KV three-phase voltage remains in a coordinated state, and there will be no voltage drop problem, which also suppresses large-scale load shedding accidents and protects the safety of system operation. Subsequently, the terminal controller transmits the fault information and recorded waveform to the background controller through optical fiber, and the background controller transmits the information to the control neutral for processing.

[0027] The above shows and describes the basic principles, main features and characteristics of the present invention. It should be understood by those skilled in the art that the present invention is not limited to the above embodiments, and the above embodiments and descriptions are only for explaining the principles of the present invention. Without departing from the spirit and scope of the present invention, the present invention may have various changes and improvements, which fall within the scope of the present invention to be protected. The scope of the present invention to be protected is defined by the attached claims and their equivalents.

Claims

1. A 220KV system ground fault load shedding control device, characterized in that: It includes a fast vacuum circuit breaker (1), an upper insulating cylinder (2), a lower insulating cylinder (3), a high-precision power supply (4), a terminal controller (5), a Locke coil (6), an isolation transformer (7), a background controller (8), a maintenance section (9) and an optical fiber (10); The upper end interface of the fast vacuum circuit breaker (1) is connected to the upper outlet line of the upper insulating tube (2) to form a first lead-out line and is led out of the upper insulating tube (2), and the first lead-out line is connected to the neutral point of the main transformer 110KV; The lower end interface of the fast vacuum circuit breaker (1) is connected to the lower outlet row of the lower insulating cylinder (3) to form a second lead-out row and is led out of the lower insulating cylinder (3), and the second lead-out row is connected to the existing system grounding row; The Locke coil (6) is fixed on the outgoing line side of the fast vacuum circuit breaker (1) to meet the current measurement requirements; The input power supply of the terminal controller (5) is connected to the AC 220V output lead of the isolation transformer (7), and the two pairs of output lines are respectively connected to the opening trigger interface and the closing trigger interface of the high-precision power supply (4); the other pair of input interfaces of the terminal controller (5) is connected to the output line of the Locke coil (6); The input power of the high-precision power supply (4) is connected to the AC 220V output lead of the isolation transformer (7), and the other two pairs of input interfaces of the high-precision power supply (4) are respectively connected to the opening trigger output interface and the closing trigger output interface of the terminal controller (5).

2. The 220KV system ground fault load shedding control device according to claim 1 is characterized in that: The two pairs of optical fiber interfaces of the terminal controller (5) are connected to the main control board input end of the background controller (8) through optical fibers (10) to meet the demand for information transmission.