A device for detecting abnormal connection of electric energy meter terminals

By designing the electrical energy meter terminal interpolation abnormal detection device, the structure of anti -falling plates, suction cups, blocking boards, and bearing substrates solves the problem of easy drop in the detection process during the detection process, and realizes a stable and efficient detection process.

CN113884971BActive Publication Date: 2025-01-28YUNNAN POWER GRID CO LTD
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202111153003.5
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2021-09-29
Publication Date
2025-01-28
Estimated Expiration
2041-09-29

AI Technical Summary

Technical Problem

The existing power meter detection device can easily cause the product to be tested to fall during the loading and testing process, causing damage and affecting the detection efficiency.

Method used

A kind of electrical meter terminal interpolation abnormal detection device is designed, including the material mechanism, the operation detection agency, the bearer mechanism and the material output mechanism. The feeding mechanism is used to test the power meter to be measured by the anti -falling board, and the operational mechanism is detected by the suction cup and the detection probe. The loading mechanism stabilizes the carrier of the electric energy meter through the blocking board and the bearing substrate to ensure that it is not easy to drop during the detection process.

Benefits of technology

Through the mechanized testing process, it is not easy to drop the power meter to be detected during the detection process, protect the power meter, improve the detection efficiency, and realize the stability and efficiency of the electrical table terminal interpolation detection.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN113884971B_ABST
    Figure CN113884971B_ABST
Patent Text Reader

Abstract

The present invention is a terminal plug-in abnormality detection device for an electric energy meter, comprising a frame, on which a feeding mechanism, an operation detection mechanism, a bearing mechanism and a material output mechanism are further provided; wherein the feeding mechanism is arranged on the frame, and the feeding mechanism can transmit the electric energy meter to be tested; the operation detection mechanism is arranged on the frame, and is located at the end of the feeding mechanism, and the operation detection mechanism can clamp the electric energy meter to be tested at the end of the feeding mechanism to the intermediate bearing mechanism for detection; the bearing mechanism is arranged on the frame, and is located beside the operation detection mechanism, and the bearing mechanism can carry the electric energy meter to be tested until the detection is completed when detecting the electric energy meter to be tested; the material output mechanism is arranged on the frame, and is located at the end of the bearing mechanism, and the material output mechanism can output the electric energy meter that has completed the detection. The present invention realizes that the electric energy meter terminal is not easy to fall off before the plug-in detection, thereby protecting the electric energy meter, and at the same time, the electric energy meter will not fall off during the detection process, thereby improving the detection efficiency.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of detection devices, and in particular to a terminal plugging abnormality detection device for an electric energy meter. Background Art

[0002] An electric energy meter is an instrument used to measure electric energy. It is also called an electric meter, a fire meter, or a kilowatt-hour meter. It refers to an instrument that measures various electrical quantities. When using an electric energy meter, please note that in the case of low voltage, that is, no more than 500 volts and small current, such as tens of amperes, the electric energy meter can be directly connected to the circuit for measurement. In the case of high voltage or high current, the electric energy meter cannot be directly connected to the line and must be used in conjunction with a voltage transformer or a current transformer.

[0003] At present, before the electric energy meter leaves the factory, it is necessary to conduct terminal plug-in abnormality detection on the semi-finished products. The purpose of the detection is to screen out defective products and mark the semi-finished products, thereby achieving efficient production. However, the existing detection device often causes the product to be tested to fall during loading, and the product to be demolded during the detection process, which causes the product to be damaged after falling, thus affecting the detection. Summary of the invention

[0004] The object of the present invention is to provide a device for detecting abnormal plugging of electric energy meter terminals, aiming to solve the technical problem in the prior art that the electric energy meter is susceptible to detection due to easy falling of the plugged-in terminals when detecting the plugged-in terminals.

[0005] The technical solution adopted by the present invention is:

[0006] A terminal plug-in abnormality detection device for an electric energy meter comprises a frame, and the frame is also provided with a feeding mechanism, an operation detection mechanism, a bearing mechanism and a material output mechanism; wherein the feeding mechanism is arranged on the frame, and the feeding mechanism can transmit the electric energy meter to be tested; the operation detection mechanism is arranged on the frame and is located at the end of the feeding mechanism, and the operation detection mechanism can clamp the electric energy meter to be tested at the end of the feeding mechanism to the intermediate bearing mechanism for detection; the bearing mechanism is arranged on the frame and is located beside the operation detection mechanism, and the bearing mechanism can carry the electric energy meter to be tested until the detection is completed when detecting the electric energy meter to be tested; the material output mechanism is arranged on the frame and is located at the end of the bearing mechanism, and the material output mechanism can output the electric energy meter that has completed the detection.

[0007] Furthermore, the feeding mechanism includes a feeding rack, a first driving mechanism and an anti-fall plate; wherein, the feeding rack is arranged on the frame, the first driving mechanism is arranged on the feeding rack, the anti-fall plates are symmetrically arranged on both sides of the top of the feeding rack, and the electric energy meter to be tested is located between the anti-fall plates for transmission.

[0008] Furthermore, the first driving mechanism includes a first driving motor and a feeding conveyor belt; wherein, the first driving motor and the feeding conveyor belt are both arranged on a feeding frame, and the first driving motor is drivingly connected to the discharging conveyor belt through a rotating wheel.

[0009] Furthermore, the supporting mechanism includes a plurality of supporting platforms, which are arranged in a straight line in sequence; the supporting platform includes a column, a supporting substrate and a blocking plate; wherein the column is arranged on a frame, the supporting substrate is installed on the top of the column, and the blocking plates are symmetrically arranged on both sides of the supporting substrate.

[0010] Furthermore, the operation detection mechanism includes a transfer frame, a second driving mechanism, a transfer plate, a suction cup and a detection probe; wherein, the transfer frame is arranged on the frame, the second driving mechanism is installed on the transfer frame, the transfer plate is connected to the second driving mechanism, and the transfer plate is driven by the second driving mechanism to move up and down in an arc shape; the suction cup and the detection probe are both installed on the transfer plate, the suction cup and the detection probe are arranged in a cross-spaced manner, and the suction cup is connected to the vacuum pump, and the detection probe is connected to the electrical performance detection device.

[0011] Furthermore, the second driving mechanism includes a transport plate, a second driving motor, a first connecting piece and a longitudinal plate; wherein, the transport plate and the second driving motor are both installed on the transfer frame, and an arc-shaped hole is provided on the transport plate; the output shaft of the second driving motor passes through the arc-shaped holes of the transfer frame and the transport plate, and is connected to the longitudinal plate through the first connecting piece; the bottom of the longitudinal plate is connected to the transfer plate through a guide rail; the second driving motor drives the first connecting piece to slide along the arc-shaped hole, and the first connecting piece drives the longitudinal plate to make the transfer plate move up and down in an arc shape.

[0012] Furthermore, the second driving mechanism also includes a longitudinal guide component; the longitudinal guide component includes a longitudinal slider and a longitudinal support plate; the longitudinal slider is arranged on the transfer frame, and the longitudinal support plate can be horizontally slidably arranged on the longitudinal slider, and the longitudinal plate can slide up and down relative to the longitudinal support plate through the guide rail at its bottom; wherein the longitudinal slider and the longitudinal support plate can guide the horizontal movement and up and down movement of the longitudinal plate.

[0013] Furthermore, the material output mechanism includes an output bracket and a third driving mechanism; wherein the output bracket is mounted on the frame, and the third driving mechanism is mounted on the output bracket.

[0014] Furthermore, the third driving mechanism includes a third driving motor and a discharging conveyor belt. The third driving motor is installed on the output bracket, and the discharging conveyor belt is drivingly connected to the third driving motor.

[0015] Furthermore, the electric energy meter terminal plug-in abnormality detection device also includes an image acquisition mechanism and a control screen; the image acquisition mechanism is arranged on the frame, and the camera end of the image acquisition mechanism faces the supporting mechanism; the control screen is electrically connected to the image acquisition mechanism.

[0016] The beneficial effects of the present invention are:

[0017] The terminal plug-in abnormality detection device for electric energy meters is configured with a feeding mechanism, an operation detection mechanism, a bearing mechanism and a material output mechanism on a frame, so that when the electric energy meter is tested, the electric energy meter to be tested is first transmitted to the end through the feeding mechanism, and then the operation detection mechanism clamps the electric energy meter to be tested at the end of the feeding mechanism to the intermediate bearing mechanism for detection, and the electric energy meter that has been tested is transferred to the material output mechanism for output by the material output mechanism.

[0018] The terminal plug-in abnormality detection device of the electric energy meter can realize mechanized detection, wherein, during loading, anti-drop plates are respectively arranged on both sides of the feeding rack, so that the electric energy meter to be detected can be smoothly transported when it is transported to the detection position; when in the detection position, blocking plates are respectively symmetrically arranged on both sides of the supporting substrate, and then cooperate with the suction cup of the operating detection mechanism, so that the electric energy meter to be detected can be smoothly transported when it is transported to the output position; thereby, the electric energy meter terminals are not easy to fall during the plug-in detection process, thereby protecting the electric energy meter, and at the same time preventing the electric energy meter from falling during the detection process, thereby improving the detection efficiency. BRIEF DESCRIPTION OF THE DRAWINGS

[0019] Figure 1 It is a schematic diagram of the overall structure of the present invention;

[0020] Figure 2 , Figure 3 It is a schematic diagram of the combined structure of the operation detection mechanism and the bearing mechanism of the present invention;

[0021] Figure 4 It is a schematic diagram of the split structure of the second driving mechanism and the longitudinal guide assembly of the present invention;

[0022] Figure 1—3, 100—frame, 200—feeding mechanism, 300—operation detection mechanism, 400—carrying mechanism, 500—material output mechanism, 600—image acquisition mechanism, 700—control screen; 110—feeding rack, 120—first driving mechanism, 130—anti-fall plate; 121—first driving motor, 122—feeding conveyor belt; 310—transfer rack, 320—second driving mechanism, 330—transfer plate, 340—suction cup, 35 0—detection probe; 321—transport plate, 322—second drive motor, 323—first connecting piece, 324—longitudinal plate, 325—arc hole, 326—longitudinal guide assembly, 327—longitudinal slider, 328—longitudinal support plate; 410—carrying platform, 411—column, 412—carrying substrate, 413—blocking plate; 510—output bracket, 520—third drive mechanism; 521—third drive motor, 522—discharging conveyor belt. DETAILED DESCRIPTION

[0023] The following will be combined with the accompanying drawings of the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0024] like Figure 1 As shown in FIG. 2 , the present invention provides an abnormality detection device for plugging terminals of an electric energy meter, which comprises a frame 100. The frame 100 is also provided with a feeding mechanism 200, a running detection mechanism 300, a bearing mechanism 400 and a material output mechanism 500.

[0025] Among them, the feeding mechanism 200 is arranged on the rack 100, and the feeding mechanism 200 can transmit the electric energy meter to be tested; the operation detection mechanism 300 is arranged on the rack 100 and is located at the end of the feeding mechanism 200, and the operation detection mechanism 300 can clamp the electric energy meter to be tested at the end of the feeding mechanism 200 to the intermediate carrying mechanism 400 for detection; the carrying mechanism 400 is arranged on the rack 100 and is located next to the operation detection mechanism 300, and the carrying mechanism 400 can carry the electric energy meter to be tested until the detection is completed when detecting the electric energy meter to be tested; the material output mechanism 500 is arranged on the rack 100 and is located at the end of the carrying mechanism 400, and the material output mechanism 500 can output the electric energy meter that has completed the detection.

[0026] Specifically, the feeding mechanism 200 includes a feeding rack 110, a first driving mechanism 120 and an anti-drop plate 130; wherein the feeding rack 110 is arranged on the frame 100; the first driving mechanism 120 is arranged on the feeding rack 110; the anti-drop plate 130 is arranged on both sides of the top of the feeding rack 110, and the electric energy meter to be tested is located between the anti-drop plates 130 for transmission. Furthermore, before the electric energy meter to be tested is tested, due to the setting of the anti-drop plate 130, the electric energy meter to be tested will not fall during transportation, thereby ensuring stable transportation during transportation to the detection process.

[0027] Furthermore, in this embodiment, the electric energy meter to be tested is a semi-finished product, which includes a part of a smooth shell and a part of an exposed plug-in terminal. The present application is mainly for realizing the detection of whether the plug-in terminal is abnormally plugged in.

[0028] The present invention sets a feeding mechanism 200, an operation detection mechanism 300, a bearing mechanism 400 and a material output mechanism 500 on a frame 100, so that when testing an electric energy meter, the electric energy meter to be tested is first transmitted to the end by the feeding mechanism 200, and then the operation detection mechanism 300 clamps the electric energy meter to be tested at the end of the feeding mechanism 200 to the intermediate bearing mechanism 400 for detection, and transfers the electric energy meter after the detection to the material output mechanism 500, and is output by the material output mechanism 500, thereby realizing mechanized detection. Among them, during the feeding, the anti-drop plate 130 is set on both sides of the top of the feeding rack 110, so that the electric energy to be tested is transported smoothly when it is transported to the detection, thereby realizing that it is not easy to fall before the electric energy meter terminal is plugged in for detection, thereby protecting the electric energy meter, and at the same time preventing the electric energy meter from falling during the detection process, thereby improving the detection efficiency.

[0029] In another embodiment of the present invention, Figure 1 As shown in FIG. 2 , the first driving mechanism 120 includes a first driving motor 121 and a feeding conveyor belt 122. The first driving motor 121 and the feeding conveyor belt 122 are both arranged on the feeding rack 110, and the first driving motor 121 is drivingly connected to the discharging conveyor belt 522. Specifically, after the electric energy meter to be tested is placed on the feeding conveyor belt 122, the first driving motor 121 drives the feeding conveyor belt 122 to transport the electric energy meter to be tested. Furthermore, the first driving motor 121 drives the feeding conveyor belt 122 through a rotating wheel, which is not shown in the figure.

[0030] In another embodiment of the present invention, Figure 1 As shown in FIG. 2 , the supporting mechanism 400 includes a plurality of supporting platforms 410, and the plurality of supporting platforms 410 are arranged in sequence in a straight line; specifically, by providing the supporting platforms 410, and arranging the plurality of supporting platforms 410 in sequence, linear sequential detection is achieved, thereby achieving efficient and orderly detection.

[0031] In another embodiment of the present invention, Figure 1 As shown, the support platform 410 includes a column 411, a support substrate 412 and a blocking plate 413; wherein the column 411 is arranged on the frame 100; the support substrate 412 is installed on the top of the column 411; and the blocking plates 413 are symmetrically arranged on both sides of the support substrate 412. Specifically, during detection, the electric energy meter to be tested is placed between the blocking plates 413, and the space formed between the blocking plates 413 just accommodates the electric energy meter to be tested. During detection, the setting of the blocking plates 413 ensures that the electric energy meter is not easy to fall during the detection process, realizes stability and reliability during the detection process, and improves the stability during the detection process.

[0032] In another embodiment of the present invention, Figure 2 As shown in FIG. 3 , the operation detection mechanism 300 includes a transfer frame 310, a second driving mechanism 320, a transfer plate 330, a suction cup 340 and a detection probe 350. The transfer frame 310 is arranged on the frame 100, the second driving mechanism 320 is installed on the transfer frame 310, the transfer plate 330 is connected to the second driving mechanism 320 by driving, and the transfer plate 330 is driven by the second driving mechanism 320 to move up and down in an arc shape; the suction cup 340 and the detection probe 350 are both installed on the transfer plate 330, and the suction cup 340 and the detection probe 350 are arranged in a cross-spaced manner. Specifically, the suction cup 340 is also connected to a vacuum pump, which is not shown in the figure. The suction cup 340 is used to absorb the outer shell of the electric energy meter to be tested when transferring the electric energy meter to be tested, thereby driving the electric energy meter to be tested from the end of the feed conveyor belt 122 to the carrier 410. Furthermore, the detection probe 350 is connected to an electrical performance detection device, which is not shown in the figure. When the detection probe 350 contacts the electric energy meter to be tested, the electrical performance detection device is used to detect whether it is abnormal.

[0033] It should be noted that, in this embodiment, the electrical performance detection device is a mature and established technology in the prior art, so how to perform abnormal detection of plug-in terminals should be well known to those skilled in the art, and therefore this application will not elaborate on it in detail.

[0034] Furthermore, the suction cup 340 and the detection probe 350 are arranged in a cross-spaced manner, with the first suction cup 340 being arranged beside the end of the discharge conveyor belt 522, followed by the first detection probe 350, and then the second suction cup 340, and so on. The first suction cup 340 first sucks the electric energy meter to be tested and transfers it to the carrier 410, so that when the first suction cup 340 sucks other electric energy meters to be tested, the first detection probe 350 just detects the electric energy meter to be tested, and then the second suction cup 340 sucks the electric energy meter to be tested that has been tested once and transfers it to the next station, thereby achieving efficient and rapid detection.

[0035] In another embodiment of the present invention, Figure 2 As shown in FIG. 4, the second driving mechanism 320 includes a transport plate 321, a second driving motor 322, a first connecting member 323 and a longitudinal plate 324. The transport plate 321 and the second driving motor 322 are both mounted on the transfer frame 310, and an arc-shaped hole 325 is provided on the transport plate 321; the output shaft of the second driving motor 322 passes through the arc-shaped hole 325 of the transfer frame 310 and the transport plate 321, and is connected to the longitudinal plate 324 through the first connecting member 323, and the bottom of the longitudinal plate 324 is connected to the transfer plate 330 through a guide rail. Specifically, the second driving motor 322 drives the first connecting member 323 to slide along the arc-shaped hole 325, and then the first connecting member 323 drives the longitudinal plate 324 to make the transfer plate 330 move up and down in an arc shape, thereby realizing the transfer of the electric energy meter to be tested.

[0036] In another embodiment of the present invention, Figure 2 As shown in FIG. 4 , the second driving mechanism 320 further includes a longitudinal guide assembly 326. The longitudinal guide assembly 326 includes a longitudinal slider 327 and a longitudinal support plate 328; the longitudinal slider 327 is disposed on the transfer frame 310, the longitudinal support plate 328 is horizontally slidably disposed on the longitudinal slider 327, and the longitudinal plate 324 can slide up and down relative to the longitudinal support plate 328 through the guide rail at the bottom thereof; specifically, the longitudinal slider 327 and the longitudinal support plate 328 can guide the horizontal movement and up and down movement of the longitudinal plate 324.

[0037] In another embodiment of the present invention, Figure 1 As shown, the material output mechanism 500 includes an output bracket 510 and a third driving mechanism 520; wherein the output bracket 510 is mounted on the frame 100, and the third driving mechanism 520 is mounted on the output bracket 510. Specifically, the output bracket 510 is used to output the tested electric energy meter.

[0038] In another embodiment of the present invention, Figure 1 As shown, the third driving mechanism 520 includes a third driving motor 521 and a discharging conveyor belt 522. The third driving motor 521 is mounted on the output bracket 510, and the discharging conveyor belt 522 is drivingly connected to the third driving motor 521. Specifically, when the electric energy meter to be tested is transported, the electric energy meter to be tested is placed on the discharging conveyor belt 522, and the third driving motor 521 drives the discharging conveyor belt 522 to transport the electric energy meter to be tested to the next station.

[0039] In another embodiment of the present invention, Figure 1As shown, the terminal plug-in abnormality detection device for electric energy meter further includes an image acquisition mechanism 600, which is arranged on the frame 100, and the camera end of the image acquisition mechanism 600 faces the carrying mechanism 400. Specifically, the image acquisition mechanism 600 can be set as a CCD camera, and the image acquisition of the electric energy meter to be tested is realized by the CCD camera, thereby realizing the acquisition work in the detection process.

[0040] In another embodiment of the present invention, the electric energy meter terminal plug-in abnormality detection device also includes a control panel 700 disposed on the frame 100, and the control panel 700 is electrically connected to the image acquisition mechanism 600. The control panel 700 is used to display the image acquired by the image acquisition mechanism 600. The control panel 700 may also have a touch function, so as to be used as a touch control of the electric energy meter terminal plug-in abnormality detection device by the staff. It should be noted that the image acquisition mechanism 600 and the control panel 700 are both mature technologies in the prior art, so they are not specifically described in this application.

Claims

1. A device for detecting abnormal plugging of electric energy meter terminals, characterized in that: The electric energy meter terminal plug-in abnormality detection device comprises a frame, and the frame is provided with a feeding mechanism, an operation detection mechanism, a bearing mechanism and a material output mechanism; wherein the feeding mechanism is arranged on the frame, and the feeding mechanism can transmit the electric energy meter to be tested; the operation detection mechanism is arranged on the frame, and is located at the end of the feeding mechanism, and the operation detection mechanism can clamp the electric energy meter to be tested at the end of the feeding mechanism to the intermediate bearing mechanism for testing; the bearing mechanism is arranged on the frame, and is located beside the operation detection mechanism, and the bearing mechanism can carry the electric energy meter to be tested until the testing is completed when testing the electric energy meter to be tested; the material output mechanism is arranged on the frame, and is located at the end of the bearing mechanism, and the material output mechanism can output the electric energy meter that has completed the testing; The feeding mechanism comprises a feeding rack, a first driving mechanism and an anti-drop plate; wherein the feeding rack is arranged on a frame, the first driving mechanism is arranged on the feeding rack, the anti-drop plates are symmetrically arranged on both sides of the top of the feeding rack, and the electric energy meter to be tested is located between the anti-drop plates for transmission; The operation detection mechanism comprises a transfer frame, a second driving mechanism, a transfer plate, a suction cup and a detection probe; wherein the transfer frame is arranged on a frame, the second driving mechanism is installed on the transfer frame, the transfer plate is drivingly connected to the second driving mechanism, and the transfer plate is driven by the second driving mechanism to move up and down in an arc shape; the suction cup and the detection probe are both installed on the transfer plate, the suction cup and the detection probe are arranged crosswise and at intervals, the suction cup is connected to a vacuum pump, and the detection probe is connected to an electrical performance detection device; The second driving mechanism comprises a transport plate, a second driving motor, a first connecting piece and a longitudinal plate; wherein the transport plate and the second driving motor are both mounted on the transfer frame, and an arc-shaped hole is provided on the transport plate; the output shaft of the second driving motor passes through the arc-shaped holes of the transfer frame and the transport plate, and is connected to the longitudinal plate through the first connecting piece; the bottom of the longitudinal plate is connected to the transfer plate through a guide rail; the second driving motor drives the first connecting piece to slide along the arc-shaped hole, and the first connecting piece drives the longitudinal plate to make the transfer plate move up and down in an arc shape; The second driving mechanism also includes a longitudinal guide component; the longitudinal guide component includes a longitudinal slider and a longitudinal support plate; the longitudinal slider is arranged on the transfer frame, and the longitudinal support plate can be horizontally slidably arranged on the longitudinal slider, and the longitudinal plate can slide up and down relative to the longitudinal support plate through the guide rail at the bottom of the longitudinal plate; wherein the longitudinal slider and the longitudinal support plate can guide the horizontal movement and up and down movement of the longitudinal plate.

2. The electric energy meter terminal plug-in abnormality detection device according to claim 1, characterized in that: The first driving mechanism includes a first driving motor and a feeding conveyor belt; wherein, the first driving motor and the feeding conveyor belt are both arranged on a feeding frame, and the first driving motor is drivingly connected to the feeding conveyor belt through a rotating wheel.

3. The device for detecting abnormal plugging of electric energy meter terminals according to claim 1, characterized in that: The supporting mechanism includes a plurality of supporting platforms, which are arranged in a straight line in sequence; the supporting platform includes a column, a supporting substrate and a blocking plate; wherein the column is arranged on a frame, the supporting substrate is installed on the top of the column, and the blocking plates are symmetrically arranged on both sides of the supporting substrate.

4. The electric energy meter terminal plug-in abnormality detection device according to claim 1, characterized in that: The material output mechanism includes an output bracket and a third driving mechanism; wherein the output bracket is mounted on the frame, and the third driving mechanism is mounted on the output bracket.

5. The device for detecting abnormal plugging of electric energy meter terminals according to claim 4, characterized in that: The third driving mechanism includes a third driving motor and a discharging conveyor belt. The third driving motor is installed on the output bracket, and the discharging conveyor belt is drivingly connected to the third driving motor.

6. The device for detecting abnormal plugging of electric energy meter terminals according to claim 1, characterized in that: The electric energy meter terminal plug-in abnormality detection device also includes an image acquisition mechanism and a control screen; the image acquisition mechanism is arranged on the frame, and the camera end of the image acquisition mechanism faces the supporting mechanism; the control screen is electrically connected to the image acquisition mechanism.

Citation Information

Patent Citations

  • Detection device for abnormal plugging of terminals of electric energy meter

    CN216209834U