Transmission line crossing construction method based on UAV modeling and BIM technology
Through drone modeling and BIM technology, the problems of different management units and time points of high-speed railways and highways are solved, and the safety and efficiency of transmission lines are improved across construction are achieved, reducing the impact of construction on site and personnel.
Patent Information
- Application Number
- CN202111189235.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2021-10-12
- Publication Date
- 2024-11-01
- Estimated Expiration
- 2041-10-12
AI Technical Summary
During the construction of transmission lines, different management units and allowed crossing time points of high-speed railways and highways are different, resulting in increased construction difficulty, restricted site and repeated personnel entry and exit.
Using construction methods based on drone modeling and BIM technology, three-dimensional real-life modeling is carried out through drones, refined three-dimensional models are generated, and leapfrog models are built with BIM technology, collision tests and optimized layouts are carried out, and construction is carried out using dynamic demonstration functions. Progress planning and safety technical briefings should be carried out simultaneously with high-speed railways and highways as a whole.
The safety and efficiency improvement across construction has been achieved, the impact of complex on-site environment on construction has been reduced, the site damage and personnel risks during construction have been reduced, and the visualization and rationality of construction have been improved.
Smart Images

Figure CN113901554B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to a transmission line crossing construction method, and in particular to a transmission line crossing construction method based on unmanned aerial vehicle modeling and BIM technology. Background Art
[0002] With the vigorous development of infrastructure projects in my country, high-speed railways and highways have spread across the country, transportation pipelines are densely covered, and it is common for power transmission lines to intersect with high-speed railways and highways and run in close parallel. During the construction of continuous crossing of transmission lines, the two crossed objects, railways and highways, have different management units, departments approving the crossing and time points for allowing the crossing, which adds difficulty to the crossing construction. Summary of the invention
[0003] The technical problem to be solved by the present invention is to overcome the shortcomings of the prior art and provide a transmission line crossing construction method based on drone modeling and BIM technology, which can treat the high-speed railway and the highway as a whole to be crossed and perform simultaneous crossing construction, and solve the problems of limited site and repeated entry and exit of personnel when crossing separately.
[0004] The technical solution adopted by the present invention to solve the technical problem is:
[0005] At the beginning of the project, kml files were produced based on the design and re-survey data, and a preliminary construction plan was agreed upon in combination with the on-site survey. RTK drones were used to plan oblique photography routes and collect real-life scenes at the crossing sites of high-speed railways, highways, and power transmission lines. UAV image processing software such as DJI Zhitu and Smart 3D were used to generate a detailed three-dimensional model of the crossing site.
[0006] According to the relevant requirements of regulations, specifications, drawings, etc., based on the three-dimensional model of the crossing site, the crossing plan is determined through calculations. Based on BIM technology, models of towers, crossing frames, and sealing nets are built and integrated with the three-dimensional model of the site; collision tests are carried out to optimize the layout and construction process.
[0007] Utilize the dynamic demonstration function of the BIM model, insert the timeline according to the construction schedule, and create a BIM dynamic model to conduct a rehearsal of the crossing plan and safety technology briefing.
[0008] According to the railway management department, the construction window time for crossing the high-speed railway is between 0:00 and 5:00 in the morning. However, the highway management department does not have clear requirements for the specific time of wire construction after the protective crossing frame is erected. The high-speed railway and highway are regarded as a whole object to be crossed and the crossing construction is carried out simultaneously to solve the problems of limited site and repeated entry and exit of personnel when crossing separately.
[0009] The specific steps include:
[0010] S1: On-site real-life 3D modeling:
[0011] 1) Plan the modeling scope: Based on the design pole position information and re-measurement records, generate a kml file for the crossing section route separately, import it into DJI Map software, and adjust the required modeling scope in DJI Map software according to the actual situation of the route;
[0012] 2) Plan the modeling route: Generate oblique photography routes according to the modeling scope, with no less than 5 routes in each direction and angle; and set the UAV flight parameters, such as completion action, mission altitude, flight speed, heading overlap rate, lateral overlap rate, photo ratio, white balance mode, gimbal pitch angle, etc.
[0013] 3) Oblique photography and real-scene photo collection: Import the set route into the DJI Phantom 4 RTK drone, select an open area without interference, wind speed not exceeding level 3, and clear weather, to collect real-scene photos on the spot with the drone.
[0014] 4) Generate 3D model: Create a new 3D reconstruction task on the computer, import the collected photos into DJI Zhitu software, set the coordinate system and image control points, perform aerial triangulation and optimization processing, and then perform 3D modeling. When modeling, the reconstruction results should be in a format that can be recognized and imported by BIM software such as PLY and OBJ.
[0015] 5) Model checking and saving: After completing the modeling, check the modeling effect in time, and export and save the 3D model in time.
[0016] S2: Cross-cutting solution design
[0017] 1) According to the relevant requirements of regulations, specifications, drawings, etc., based on the three-dimensional model of the crossing site, measure the specific parameters such as the height, width, and crossing angle of each spanning object at the crossing site, consult the construction drawings, and obtain parameters such as the tower height and crossarm width.
[0018] 2) Calculate the safe distance of the sealing net from the crossing point, the installation position of the supporting bracket and the anchor, the sag value of the load-bearing cable, the shielding width and length of the crossing frame, the initial stress of the crossing frame, the stress of the accident state, the stress of the anchor, etc. According to the calculation results, determine the type of crossing frame, the type of sealing net, the location of the tensioning field for the wire construction, the location of the anchor wire, etc.
[0019] 3) Draw a simple crossing schematic diagram to assist in the design of the scheme and determine the crossing scheme.
[0020] S3: BIM cross-model construction
[0021] 1) Import real-life 3D models
[0022] Import the OBJ or PLY format 3D models created with DJI Terra software into software such as Blender for rendering, merging, and other optimizations to make the 3D models more realistic and natural.
[0023] 2) Use CAD or Blender and other software to draw three-dimensional models of tower foundation, tension tower, straight tower, steel pipe spanning frame, supporting beam, load-bearing cable, sealing mesh, ground anchor, guy wire, etc.
[0024] 3) The real-life 3D model, tower foundation, tension tower, straight tower, steel pipe spanning frame, supporting beam, load-bearing cable, sealing mesh, ground anchor, and wire model are synthesized, optimized, rendered, and other operations are performed to form a spanning effect BIM model.
[0025] 4) Input the schedule, construction period and other information into the BIM model and conduct model review.
[0026] 5) Conduct dynamic simulation of construction progress, model collision detection, etc., and further deepen the design of the construction plan based on the simulation and detection results to form a BIM cross-model that can be used for 3D safety technical briefing.
[0027] S4: After the crossing plan is determined to be feasible, the crossing procedures will be carried out: After the crossing plan is determined, the project chief engineer will prepare the construction plan according to the predetermined plan. After the preparation is completed, it will be submitted to the company for approval. After the company's approval, the company will organize experts to review the construction plan. After the expert review is completed, modifications will be made according to the expert opinions.
[0028] The construction plan modified according to the expert opinions will be submitted to the owner and the supervision unit for review. At the same time, all the design and owner information required for crossing the high-speed railway and the highway will be collected and completed; and the procedures for crossing the high-speed railway and the highway will be carried out.
[0029] S5: After the procedures for crossing the high-speed railway and expressway are completed, construction preparations will begin; 15 days before the crossing construction is confirmed, the construction personnel will enter the site for safety training and education and pass the examination. All construction personnel will participate in the safety technical briefing organized by the project department. The briefing is divided into two parts: meeting briefing and on-site briefing to ensure that every person involved in the construction has a comprehensive understanding of the construction technology, safety and quality.
[0030] Construction tools and materials must pass relevant tests before they can be used in construction.
[0031] All construction tools and materials should be delivered to the designated location at the construction site one week before construction.
[0032] S6: Erection of spanning frame and wiring construction
[0033] 1) Erection of spanning frame and installation of temporary beams:
[0034] The high-speed railway and highway are considered as an integrated crossing and crossed simultaneously and continuously.
[0035] The steel pipe span frame of the expressway and the anchors of all span frames shall be erected three days before the approved construction window of the high-speed railway. After acceptance by the expressway management, owner, supervisor and construction party, the main rope of the sealing net shall be deployed to one side of the expressway in advance to reduce the duration of the expressway closure;
[0036] Three days before the approved construction window of the high-speed railway, temporary beams (500×500×18m brackets) will be installed at appropriate positions of the towers on both sides of the high-speed railway, and all load-bearing cable anchors will be buried. After acceptance by the highway management, owner, supervisor and construction party, the load-bearing cable capping net will be arranged at one side of the tower in advance to reduce the high-speed railway network closure time.
[0037] The capping net of the expressway is made of Φ16 Dyneema and 24-core ADSS optical cable connected by U type; because there is a live contact line under the high-speed railway, its capping net is made of insulated dry Φ18 and Φ12 Dyneema connected by insulated shackles;
[0038] One day before the approved construction window of the high-speed railway, the highway will be closed (using 24-core ADSS optical cable to form a protective mesh) with the cooperation of the relevant highway management departments (highway traffic police, road administration), and the traffic control will be lifted after acceptance.
[0039] Since the long-term retention of the capping net of the highway crossing frame increases the risk of crossing, the capping net should be completed one day before or on the day when the high-speed railway is approved for construction.
[0040] The high-speed railway network closure was completed at the first construction window point.
[0041] Since the span of the highway crossing is large and it is impossible to set up supports in the middle to prevent the capping net from shrinking under its own gravity, bamboo poles need to be installed in the middle to prevent the capping net from shrinking.
[0042] High-speed railways are built by burying anchors on both sides of the railway.
[0043] 2) Wireline construction
[0044] Since the installation of tension wires and accessories across the high-speed railway is carried out at night, the tension wire section should not be too long, and only two independent tension sections are required.
[0045] Because of the high-speed railway crossing, all wiring construction is carried out at night. Sufficient lighting measures must be set up on site. During the traction of the ground wire, there must be someone on guard above the crossing frame and the tower beam to prevent the situation of the wires above the frame from being unable to be clearly observed from below.
[0046] Designed in accordance with the specifications, the middle tower between the highway and the high-speed railway will be set as a tension tower. When the traction of one-phase conductor and the ground wire is completed within the construction window and there is insufficient time to tighten the wires, the high-speed railway side wires can be double-anchored and then disconnected during the day, and the highway side wires can be tightened during the day. This can improve the safety factor and better control the construction quality.
[0047] In principle, the wire tightening and accessory installation work is only carried out on the tension section above the high-speed railway at night, while the wire tightening and accessory installation work is carried out on the tension section above the highway during the day.
[0048] S7: Acceptance and defect elimination: After the wiring construction is completed, contact the supervisor to conduct the wiring acceptance work of the wiring section in advance, and complete the three-span hydraulic pipe flaw detection test at the same time;
[0049] S8: Removal of capping net and crossing frame: After all acceptances are qualified, contact the highway and high-speed railway management to remove the capping net, and then remove the temporary beams and steel pipe crossing frame on the tower. After the highway frame is removed and the landform, fences, etc. are restored, the relevant highway management departments must be notified for acceptance.
[0050] S9: All construction tools must be removed and when construction is complete, all materials and site must be cleared.
[0051] The positive beneficial effects of the present invention are:
[0052] 1. This method uses drones for three-dimensional real-scene modeling and uses BIM to build a crossing model for crossing scheme design, optimization, scheme disclosure, and construction management. It successfully completed the construction of transmission lines continuously crossing high-speed railways and highways, solved the connection sequence of processes across high-speed railways and highways, optimized the construction process, ensured construction safety, and reduced the impact of complex on-site environment on construction.
[0053] 2. This construction method realizes the visualization of construction plan through the application of BIM technology, ensures the feasibility of the plan and the rationality of the construction process through collision tests, and conducts safety technical briefings through dynamic simulation models, ensuring that construction participants have a grasp of information such as site layout, safety technical requirements, and construction process.
[0054] 3. This construction method adopts simultaneous continuous crossing over high-speed railways and highways. The crossing construction can make the intermediate tension towers between the highway and the high-speed railway use balanced hanging wires for tight hanging wire operations. In this way, the intermediate tension towers no longer need temporary tension wires, which reduces the accident rate of tower collapse and wire running caused by temporary tension wires not being tight or temporary tension wire anchors not being buried deep enough by half, thus improving the safety guarantee for the safe operation of high-speed railways and highways related to the crossing construction.
[0055] 4. The reduction of traction vehicles and tensioning sites in this method can reduce the damage to young crops and vegetation during construction, and the reduction of anchor burials brought about by the reduction of tensioning sites can reduce the damage to the original soil of the construction site. BRIEF DESCRIPTION OF THE DRAWINGS
[0056] Figure 1 It is a flow chart of a transmission line crossing construction method based on drone modeling and BIM technology of the present invention;
[0057] Figure 2 It is a flow chart of on-site real scene three-dimensional modeling in the present invention;
[0058] Figure 3 It is a flowchart of the BIM spanning model construction in the present invention;
[0059] Figure 4 It is a flow chart from determining the crossing plan to handling the crossing procedures in the present invention. DETAILED DESCRIPTION
[0060] The following is combined with Figure 1 , Figure 2 , Figure 3 , Figure 4 The present invention will be further explained and illustrated with specific embodiments:
[0061] Embodiment: A transmission line crossing construction method based on drone modeling and BIM technology,
[0062] First, we need to carry out on-site real-scene 3D modeling:
[0063] 1) Plan the modeling scope: Based on the design pole position information and re-measurement records, generate a kml file for the crossing section route separately, import it into DJI Map software, and adjust the required modeling scope in DJI Map software according to the actual situation of the route;
[0064] 2) Plan the modeling route: Generate oblique photography routes according to the modeling scope, with no less than 5 routes in each direction and angle; and set the UAV flight parameters, such as completion action, mission altitude, flight speed, heading overlap rate, lateral overlap rate, photo ratio, white balance mode, gimbal pitch angle, etc.
[0065] 3) Oblique photography and real-scene photo collection: Import the set route into the DJI Phantom 4 RTK drone, select an open area without interference, wind speed not exceeding level 3, and clear weather, to collect real-scene photos on the spot with the drone.
[0066] 4) Generate 3D model: Create a new 3D reconstruction task on the computer, import the collected photos into DJI Zhitu software, set the coordinate system and image control points, perform aerial triangulation and optimization processing, and then perform 3D modeling. When modeling, the reconstruction results should be in a format that can be recognized and imported by BIM software such as PLY and OBJ.
[0067] 5) Model checking and saving: After completing the modeling, check the modeling effect in time, and export and save the 3D model in time.
[0068] Then design a crossover plan:
[0069] 1) According to the relevant requirements of regulations, specifications, drawings, etc., based on the three-dimensional model of the crossing site, measure the specific parameters such as the height, width, and crossing angle of each spanning object at the crossing site, consult the construction drawings, and obtain parameters such as the tower height and crossarm width.
[0070] 2) Calculate the safe distance of the sealing net from the crossing point, the installation position of the supporting bracket and the anchor, the sag value of the load-bearing cable, the shielding width and length of the crossing frame, the initial stress of the crossing frame, the stress of the accident state, the stress of the anchor, etc. According to the calculation results, determine the type of crossing frame, the type of sealing net, the location of the tensioning field for the wire construction, the location of the anchor wire, etc.
[0071] 3) Draw a simple crossing schematic diagram to assist in the design of the scheme and determine the crossing scheme.
[0072] Then the BIM spanning model is constructed:
[0073] 1) Import real-life 3D models
[0074] Import the OBJ or PLY format 3D models created with DJI Terra software into software such as Blender for rendering, merging, and other optimizations to make the 3D models more realistic and natural.
[0075] 2) Use CAD or Blender and other software to draw three-dimensional models of tower foundation, tension tower, straight tower, steel pipe spanning frame, supporting beam, load-bearing cable, sealing mesh, ground anchor, guy wire, etc.
[0076] 3) The real-life 3D model, tower foundation, tension tower, straight tower, steel pipe spanning frame, supporting beam, load-bearing cable, sealing mesh, ground anchor, and wire model are synthesized, optimized, rendered, and other operations are performed to form a spanning effect BIM model.
[0077] 4) Input the schedule, construction period and other information into the BIM model and conduct model review.
[0078] 5) Conduct dynamic simulation of construction progress, model collision detection, etc., and further deepen the design of the construction plan based on the simulation and detection results to form a BIM cross-model that can be used for 3D safety technical briefing.
[0079] After the crossing plan is determined to be feasible, the crossing procedures will be carried out: After the crossing plan is determined, the project chief engineer will prepare the construction plan according to the predetermined plan. After the preparation is completed, it will be submitted to the company for approval. After the company's approval, the company will organize an expert review of the construction plan. After the expert review is completed, modifications will be made according to the expert opinions.
[0080] The construction plan modified according to the expert opinions will be submitted to the owner and the supervision unit for review. At the same time, all the design and owner information required for crossing the high-speed railway and the highway will be collected and completed; and the procedures for crossing the high-speed railway and the highway will be carried out.
[0081] After the procedures for crossing the high-speed railway and expressway are completed, construction preparation begins; 15 days before the crossing construction is confirmed, the construction personnel enter the site for safety training and education and pass the examination. All construction personnel participate in the safety technical briefing organized by the project department. The briefing is divided into two parts: meeting briefing and on-site briefing to ensure that every person involved in the construction has a comprehensive understanding of the construction technology, safety, and quality.
[0082] Construction tools and materials must pass relevant tests before they can be used in construction.
[0083] All construction tools and materials should be delivered to the designated location at the construction site one week before construction.
[0084] Then, erect the spanning frame and string the wires: First, erect the spanning frame and install the temporary beams:
[0085] The high-speed railway and highway are considered as an integrated crossing and crossed simultaneously and continuously.
[0086] The steel pipe span frame of the expressway and the anchors of all span frames shall be erected three days before the approved construction window of the high-speed railway. After acceptance by the expressway management, owner, supervisor and construction party, the main rope of the sealing net shall be deployed to one side of the expressway in advance to reduce the duration of the expressway closure;
[0087] Three days before the approved construction window of the high-speed railway, temporary beams (500×500×18m brackets) will be installed at appropriate positions of the towers on both sides of the high-speed railway, and all load-bearing cable anchors will be buried. After acceptance by the highway management, owner, supervisor and construction party, the load-bearing cable capping net will be arranged at one side of the tower in advance to reduce the high-speed railway network closure time.
[0088] The capping net of the expressway is made of Φ16 Dyneema and 24-core ADSS optical cable connected by U type; because there is a live contact line under the high-speed railway, its capping net is made of insulated dry Φ18 and Φ12 Dyneema connected by insulated shackles;
[0089] One day before the approved construction window of the high-speed railway, the highway will be closed (using 24-core ADSS optical cable to form a protective mesh) with the cooperation of the relevant highway management departments (highway traffic police, road administration), and the traffic control will be lifted after acceptance.
[0090] Since the long-term retention of the capping net of the highway crossing frame increases the risk of crossing, the capping net should be completed one day before or on the day when the high-speed railway is approved for construction.
[0091] The high-speed railway network closure was completed at the first construction window point.
[0092] Since the span of the highway crossing is large and it is impossible to set up supports in the middle to prevent the capping net from shrinking under its own gravity, bamboo poles need to be installed in the middle to prevent the capping net from shrinking.
[0093] High-speed railways are built by burying anchors on both sides of the railway.
[0094] Then the line construction is carried out: since the tensioning line and accessory installation construction across the high-speed railway are all carried out at night, the line-laying section should not be too long, and only two independent tension sections are required.
[0095] Because of the high-speed railway crossing, all wiring construction is carried out at night. Sufficient lighting measures must be set up on site. During the traction of the ground wire, there must be someone on guard above the crossing frame and the tower beam to prevent the situation of the wires above the frame from being unable to be clearly observed from below.
[0096] Designed in accordance with the specifications, the middle tower between the highway and the high-speed railway will be set as a tension tower. When the traction of one-phase conductor and the ground wire is completed within the construction window and there is insufficient time to tighten the wires, the high-speed railway side wires can be double-anchored and then disconnected during the day, and the highway side wires can be tightened during the day. This can improve the safety factor and better control the construction quality.
[0097] In principle, the wire tightening and accessory installation work is only carried out on the tension section above the high-speed railway at night, while the wire tightening and accessory installation work is carried out on the tension section above the highway during the day.
[0098] After the wire construction is completed, the supervisor will contact the owner to conduct the wire inspection of the wire section in advance, and complete the three-span hydraulic pipe flaw detection test. After all the acceptances are qualified, the highway and high-speed railway management will be contacted to remove the capping net, and then the temporary beams and steel pipe spanning frame on the tower will be removed. After the highway frame is removed, the landform, fences, etc. are restored, and the relevant highway management departments must be notified for acceptance. Withdraw all construction tools and equipment, and the site must be cleared after the work is completed and the materials are clean.
[0099] The spanning construction is divided into four phases for staffing. Since the load-bearing cables and the steel pipe spanning frames are erected at different times, the personnel can be deployed crosswise.
[0100] The relevant quality documents for construction execution are as follows: "110kV~750kV Overhead Transmission Line Construction and Acceptance Specifications" (GB50233-2014), "State Grid Corporation of China Transmission and Transformation Project Construction Quality Acceptance Unified Form (Line Engineering)", "Safety Technical Specifications for Fastener-Type Steel Pipe Scaffolding in Construction" (JGJ130-2011), "Technical Specifications for Hydraulic Crimping of Overhead Conductors (Below 800mm2) and Ground Wires in Transmission and Transformation Projects" (DL / T5285-2018), "Construction Specifications for Crossing Power Lines" (DL / T5016-2017) and relevant construction drawings of engineering design.
[0101] Quality control measures: Before erecting the span, the center of the new line must be accurately found at the spanning point using a theodolite to prevent the span from deviating from the center of the line; the width of the span should exceed the protected wire rope by 2m on both sides, and outward horns should be provided on both sides of the top of the frame; the location of the pole pit and the position of the wire should be determined according to the on-site conditions; the steel pipes and fasteners used in the steel pipe span are strictly prohibited from use if they are severely bent, dented and deformed, or have severe corrosion, cracks or desoldering on the surface; a sweeping rod is provided at the lower end of the frame uprights of the steel pipe frame, and the bottom of the steel pipe uprights should be reliably connected to the sweeping rod to ensure the integrity of the span; the crossbar of the span should be erected at right angles to the uprights, with a distance of 2m between the uprights; scissor braces or support rods should be provided at both ends of the span and every 6-7 uprights. A guy wire is installed on each side of the spanning frame. The hanging point of the guy wire or the binding point of the support rod or scissor brace should be set at the intersection of the vertical rod and the horizontal rod, and the angle with the ground should not be greater than 45°; the support rod and the sweeping rod should be reliably connected; the vertical rod and the large horizontal rod of the steel pipe spanning equipment should be staggered and overlapped, and the overlap length should be not less than 0.5m;
[0102] The spacing between the uprights of the steel pipe crossing frame shall not be greater than 2m, the spacing between the large cross bars shall not be greater than 1.2m, and the spacing between the small cross bars shall not be greater than 1.5m.
[0103] The crossing frame can only be used after it has passed the acceptance and has been hung with eye-catching warning signs in accordance with relevant regulations;
[0104] When determining the level of the pulleys used to deploy the guide and ground wires, the length of the vertical control rope and the number of pulleys, the safe distance between the load-bearing cables and the crossed power lines should be ensured;
[0105] When determining the height of the load-bearing cable, it should be considered that the maximum arc point of the load-bearing cable after the impact of the broken wire is sufficient safety distance from the crossed power line;
[0106] When erecting the load-bearing cables, the initial arc of the load-bearing cables should be close to the pay-out arc of the deployed conductors.
[0107] A tension adjustment device should be provided at one end of the load-bearing cable;
[0108] When using the spanning tower as the supporting rod of the load-bearing cable, the spanning tower shall be strength-checked and reinforced if necessary;
[0109] Safety measures: Personnel entering the construction site must wear safety helmets and rubber-soled shoes. Personnel working at heights must wear safety belts and fall arresters. During work, the safety belts must be fastened in a secure place to prevent falling from heights.
[0110] Before the crossing construction, contact the highway and high-speed railway management departments, submit the construction plan and other relevant information for review, and apply for the construction notice of the off-road construction project.
[0111] The construction personnel involved in the crossing and stringing of wires shall pass the training and examination and obtain the corresponding special operation personnel operation certificate. The climbing workers involved in the crossing construction shall undergo occupational health examinations and shall not engage in climbing work without passing the examinations.
[0112] Before construction workers enter the site, the technical person in charge must conduct safety and technical briefings. All workers must clearly understand their respective construction tasks and be familiar with this construction plan.
[0113] All personnel participating in the construction must be serious and conscientious, obey the coordination and command of the on-site construction commander, and use safety protection equipment correctly.
[0114] The lifting equipment, tools and temporary anchors used at the construction site should be inspected in advance and can only be used after passing the inspection.
[0115] During the installation of crossing facilities and ground wires, personnel with live working qualifications must be on site for safety supervision, and the relevant operating units are requested to send personnel to the site to supervise the construction. The construction project department arranges special personnel to stay at the construction site for 24-hour supervision.
[0116] The center of the span must coincide with the center line of the shield width.
[0117] When transferring materials and tools up and down, ropes must be used and they must not be thrown.
[0118] Before construction, the safety protection tools, tools and equipment used must be used in accordance with the specifications and models specified in the plan, and small ones must not be used instead of large ones.
[0119] Insulated nylon ropes and load-bearing cables should be kept dry and free from dust and dirt when in use. They should be placed on dry waterproof canvas on site and should not be placed directly on wet ground. It is forbidden to set up or remove load-bearing cables in wet weather.
[0120] During construction operations, care should be taken not to make the bending radius of the load-bearing cable less than 1.5 times the radius of the load-bearing cable, and check whether the load-bearing cable is damaged before use.
[0121] During operation, insulation materials should be prevented from abrading against the ground, towers, etc.
[0122] Keep communications open during construction.
[0123] Work should be stopped in the event of lightning, rain, relative humidity greater than 85%, or strong winds of level 5 or above.
[0124] Any construction worker involved in the crossing construction should pass through the culvert when crossing the road, and it is strictly prohibited to cross the expressway directly.
[0125] Strictly follow the construction procedures of the high-speed railway management department to arrange the construction steps:
[0126] Before the construction point, the construction workers will enter the vicinity of the construction site in advance to carry out construction preparation work. After the preparation is completed, they will report the preparation status to the on-site responsible personnel of the high-speed railway infrastructure section and other departments. The person in charge of the construction unit will register and sign with the station duty personnel one hour in advance to prepare for the power outage.
[0127] After the railway contact network is out of power, the on-site responsible personnel of the high-speed railway infrastructure section and other departments will notify the on-site construction personnel, and the construction personnel will begin to carry out construction according to the work plan, refine the time nodes, strictly abide by the safety regulations of the railway management department, and carry out construction within the blockade area designated by the railway management department.
[0128] Materials and tools should be arranged reasonably and stacked neatly; the site should be cleaned up in time after the work is completed, and the anchor pit should be backfilled to ensure that the work is completed and the materials are used up and the site is clear.
[0129] Environmental protection measures: Strengthen education and all construction workers must establish a strong environmental awareness.
[0130] The layout of the construction site must comply with the technological process and occupy as little arable land as possible.
[0131] Temporary facilities at the construction site, including production, office, living quarters, warehouses, material yards, lighting, power lines, etc., shall be arranged, erected or buried in strict accordance with the locations determined by the construction organization design.
[0132] Reasonably arrange construction work time, appropriately control the density of machinery layout, and avoid noise pollution caused by concentrated machinery; noise prevention measures such as adding soundproof sheds must be taken.
[0133] The layout of ground anchor burial should be reasonable, and manual burial should be used as much as possible to reduce mechanical damage to young trees.
[0134] Materials, equipment and tools are arranged reasonably and stacked neatly to ensure that the site is clean when work is completed.
[0135] Pay attention to reducing damage to the environment. Take up as little space as possible, destroy as little vegetation as possible, and do not expand the construction site.
[0136] After the construction is completed, all the ground disturbed by the construction must be revegetated.
[0137] Use the DJI Phantom 4 RTK drone to take oblique photography of the intersection sites of power transmission lines, high-speed railways and highways, and use DJI Zhitu and Smart 3D software to build a refined three-dimensional digital model to make the construction plan design more scientific and reasonable; use BIM technology to complete key construction simulations such as crossing frame erection and network closure, collision inspection, and conduct safety technical briefings and progress control, etc., to verify the rationality, safety and feasibility of the plan, while improving the quality of safety technical briefings, making it easier for construction personnel to grasp construction points and precautions, so as to achieve the goal of reducing construction risks and construction costs and accelerating construction progress.
[0138] Reasonably arrange the overall construction coordination progress, use the previous experience of handling the procedures of crossing expressways and highways, and create a time difference in handling the crossing procedures to ensure that the high-speed railway approval window point is within the approved construction time period of the highway.
[0139] The high-speed railway and the highway are regarded as a whole crossing object and the crossing construction is carried out simultaneously, which solves the problem that the terrain between the high-speed railway and the highway is not suitable for setting up a tensioning field, reduces the damage of the tensioning field to farmland, saves construction period and reduces construction cost.
[0140] Specific application 1:
[0141] Project name: Xuchang Changge Xiyanchi 220kV transmission and transformation project line project.
[0142] Project Overview: Xuchang Changge Xiyanchi 220kV transmission and transformation project line project (Changle-Yingchuan π-into-Xiyanchi transformation 220kV line) is located in Changge City, Xuchang City, Henan Province. The total length of the line is 8.49km, of which 0.17km is double-circuit cable laying, and 8.32km is double-circuit overhead laying on the same tower. The line has a total of 25 pole towers, including 13 straight towers and 12 tension towers.
[0143] Application effect: This construction method was formed and applied in this project. During the construction, N10-N11 nai-nai across Beijing-Hong Kong-Macao Expressway and N11-N13 nai-straight-nai across Zhengzhou-Wanzhou High-speed Railway (N11 tower is between the expressway and the high-speed railway) were used to carry out crossing line construction. The line-laying section was N10-N13. The whole construction process was safe, fast, high-quality and controllable. No quality accidents or production safety accidents occurred, which was well received by all parties.
[0144] Specific application 2:
[0145] Project name: Zhumadian Queshan Zhugudong 110kV transmission and transformation project.
[0146] Project Overview: Zhumadian Queshan Zhugudong 110kV Transmission and Transformation Project (Chu'an-Zhugudong 110kV Line Project) is located in Zhumadian City, Henan Province. The line is 8.0km long and is erected in a single circuit. A total of 54 new towers were built, including 40 single-circuit straight steel tube poles, 10 single-circuit load-bearing steel tube poles, 2 single-circuit straight towers, 1 single-circuit corner tower, and 1 double-circuit terminal tower.
[0147] Application effect: This method has been fully applied in the continuous span construction of this project. The whole construction process is in a safe, fast, high-quality and controllable state. No quality accidents or production safety accidents occurred, which has been well received by all parties.
[0148] Of course, the invention is not limited to the above-mentioned embodiments, and those skilled in the art may make equivalent modifications or substitutions without violating the spirit of the invention, and these equivalent modifications or substitutions are all included in the scope defined by the claims of this application.
Claims
1. A transmission line crossing construction method based on drone modeling and BIM technology, characterized in that: The following steps are involved: S1: On-site real-life 3D modeling: 1) Plan the modeling scope: Based on the design pole position information and re-measurement records, generate a kml file for the crossing section route separately, import it into DJI Map software, and adjust the required modeling scope in DJI Map software according to the actual situation of the route; 2) Plan the modeling route: Generate oblique photography routes according to the modeling scope, with no less than 5 routes in each direction and angle; and set the UAV flight parameters; 3) Oblique photography and real-scene photo collection: Import the set route into the DJI Phantom 4 RTK drone, select an open area without interference, wind speed not exceeding level 3, and clear weather to collect real-scene photos on the spot with the drone; 4) Generate 3D model: Create a new 3D reconstruction task on the computer, import the collected photos into DJI Map software, set the coordinate system and image control points, perform aerial triangulation and optimization, and then perform 3D modeling. When saving the reconstruction results during modeling, select a format that can be recognized and imported by the BIM software; 5) Model inspection and preservation: After completing the modeling, check the modeling effect in time and export and save the 3D model in time; S2: Cross-cutting solution design 1) According to the relevant requirements of the regulations and drawings, based on the three-dimensional model of the crossing site, measure the specific parameters of the height, width and span angle of each spanning object at the crossing site, consult the construction drawings, and obtain the parameters of the tower height and cross arm width; 2) Calculate the safe distance of the sealing net from the crossing point, the installation position of the supporting pole and anchor, the sag value of the load-bearing cable, the shielding width and length of the crossing frame, the initial stress of the crossing frame, the stress of the accident state, and the stress of the anchor. According to the calculation results, determine the type of the crossing frame, the type of sealing net, the location of the cable construction tensioning field, and the location of the anchor wire; 3) Draw a simple crossing diagram to assist in the design of the plan and determine the crossing plan; S3: BIM cross-model construction 1) Import real-life 3D models. Import the 3D models created with DJI Terra software into Blender software for rendering, merging and optimization to make the 3D models more realistic and natural. 2) Use CAD or Blender software to draw the three-dimensional models of the tower foundation, tension tower, straight tower, steel pipe spanning frame, supporting beam, load-bearing cable, sealing mesh, ground anchor, and guy wire; 3) Synthesize, optimize and render the real-life 3D model, tower foundation, tension tower, straight tower, steel pipe spanning frame, supporting beam, load-bearing cable, sealing mesh, ground anchor and cable model to form a spanning effect BIM model; 4) Input the schedule and construction period information into the BIM model and conduct model review; 5) Conduct dynamic simulation of construction progress and model collision detection, further deepen the design of the construction plan based on the simulation and detection results, and form a BIM spanning model that can be used for 3D safety technical disclosure; S4: After the crossing plan is confirmed to be feasible, the crossing procedures are carried out; S5: After the high-speed railway and highway crossing procedures are completed, construction preparations begin: personnel training and equipment inspection; S6: Erection of spanning frame and wiring construction: 1) Erection of spanning frame and installation of temporary beams: The high-speed railway and the expressway are considered as an integrated crossing structure and are crossed simultaneously and continuously: the steel pipe crossing frame of the expressway and the anchors of all crossing frames shall be erected 3 days before the approved construction window of the high-speed railway. After acceptance by the expressway management, owner, supervisor and construction party, the main rope of the sealing net shall be deployed to one side of the expressway in advance; 3 days before the approved construction window of the high-speed railway, complete the installation of temporary crossbeams and the burial of all anchors of the load-bearing cables at the appropriate positions of the iron towers on both sides of the high-speed railway. After acceptance by the expressway management, the owner, the supervisor and the construction party, the capping net of the load-bearing cables shall be arranged in advance at the iron tower on one side; 2) Wire construction: Because there is a high-speed railway crossing, all wire construction is carried out at night. Sufficient lighting measures must be set up on site. During the traction of the ground wire, there must be someone on top of the crossing frame and the tower beam to monitor. The wire laying section should not be too long. Only two independent tension sections of the crossing are required; S7: Acceptance and defect elimination: After the wiring construction is completed, contact the supervisor to conduct the wiring acceptance work of the wiring section in advance, and complete the three-span hydraulic pipe flaw detection test at the same time; S8: Removal of capping net and span frame: After all acceptances are qualified, contact the highway and high-speed railway management to remove the capping net, and then remove the temporary crossbeams and steel pipe span frame on the tower. After the highway frame is removed and the landform and fence are restored, the relevant highway management department shall be notified for acceptance; S9: All construction tools are removed and construction is completed.
2. The transmission line crossing construction method based on drone modeling and BIM technology according to claim 1 is characterized in that: One day before or on the day of the approved construction window point for the high-speed railway, with the cooperation of the relevant management departments of the expressway to close the road, Φ16 Dyneema and 24-core ADSS optical cable are used to connect with U-shaped buckles to form a protective mesh to complete the closure of the expressway, and the traffic control is lifted after acceptance. The high-speed railway closure is completed at the first construction window point, using insulated and dry Φ18 Dyneema and Φ12 Dyneema connected with insulated shackles.
3. The power transmission line crossing construction method based on drone modeling and BIM technology according to claim 2 is characterized in that: The span of the highway crossing frame is large and it is impossible to set up supports in the middle to prevent the capping net from shrinking under its own gravity. Therefore, bamboo poles need to be installed in the middle to prevent the capping net from shrinking. The high-speed railway adopts the method of burying anchors on both sides of the railway to achieve side pulling.
Citation Information
Patent Citations
BIM standardized modeling method for high-speed railway swivel bridge