Tower crane support structure and method of implementation

By using a steel truss structure inside the building's core tube instead of reinforced concrete for fixing, the assembly and disassembly process of the tower crane is simplified, material recycling and construction efficiency are improved, and the problem of complex assembly and disassembly of internal climbing tower cranes is solved.

CN113911932BActive Publication Date: 2026-01-02THE SECOND CONSTRUCTION CO LTD OF CHINA CONSTRUCTION THIRD ENGINEERING BUREAU
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202111444440.2
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2021-11-30
Publication Date
2026-01-02
Estimated Expiration
2041-11-30

AI Technical Summary

Technical Problem

The existing internal climbing tower crane has a complicated assembly and disassembly process, and generates a lot of waste during disassembly, which affects the construction progress and resource utilization.

Method used

A steel truss structure is used to replace the traditional reinforced concrete fixing method. The steel truss is installed on the concrete connecting beams inside the building's core tube. The installation is completed by assembly and welding, and it is cut and removed during disassembly to avoid damaging the concrete structure.

Benefits of technology

It simplifies the installation and dismantling process of tower cranes, allows for the recycling of materials, reduces construction waste, and improves construction efficiency and safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN113911932B_ABST
    Figure CN113911932B_ABST
Patent Text Reader

Abstract

The application provides a tower crane supporting structure and an implementation method, the tower crane supporting structure is installed in a core tube of a building, the core tube comprises a shear wall, the shear wall is provided with at least one pair of horizontally and intervally arranged concrete coupling beams, and the tower crane supporting structure comprises: steel trusses, the two ends of the steel trusses are arranged on the concrete coupling beams respectively, the steel trusses are two, and the two steel trusses are arranged in parallel; a secondary beam, the secondary beam is arranged between the two steel trusses, and the two steel trusses are connected through the secondary beam. The tower crane supporting structure changes the fixing mode of the reinforced concrete into the mode of the steel truss, the steel truss has light self weight and large span, the installation and dismounting process is simplified while reliability is ensured, the concrete structure does not have to be damaged, the installation and dismounting steps are greatly simplified, the material can be recycled and used, energy saving and environmental protection are achieved, and safety is higher.
Need to check novelty before this filing date? Find Prior Art

Description

TECHNICAL FIELD

[0001] The present application relates to the technical field of building construction, in particular to a tower crane supporting structure and implementation method. BACKGROUND

[0002] In recent years, with the rapid development of cities, more and more commercial complexes and super high-rise buildings are built, and the developers are under great financial pressure. The construction of commercial complexes is fast, and the developers ensure the recovery of funds by operating the commercial complexes after the completion of the construction. The original external tower crane needs to be removed because the adjacent commercial shopping center needs to be opened in advance, but the main structure of the adjacent super high-rise tower has not been completed. The tower crane is an essential vertical transportation machinery in building construction, and it must be converted and reinstalled to ensure the smooth construction of the super high-rise building. However, the existing inner climbing tower crane usually uses reinforced concrete as the tower crane foundation, which is very troublesome to remove and produces a large amount of garbage. Therefore, how to simplify the installation and removal process of the inner climbing tower crane is a problem that needs to be solved in the field. SUMMARY

[0003] The main purpose of the present application is to provide a tower crane supporting structure and implementation method to solve the problem of complex installation and removal process of the existing inner climbing tower crane.

[0004] In order to achieve the above-mentioned purpose, according to one aspect of the present application, a tower crane supporting structure is provided, which is installed in the core tube of a building, the core tube comprising a shear wall having at least one pair of horizontally spaced concrete coupling beams, the tower crane supporting structure comprising: a steel truss, the steel truss being arranged at both ends of the concrete coupling beam, the steel truss being two, the two steel trusses being arranged in parallel; a secondary beam, the secondary beam being arranged between the two steel trusses, the two steel trusses being connected by the secondary beam.

[0005] Further, the steel truss comprises: an upper flange steel beam, a lower flange steel beam, a straight web steel beam, and an inclined web steel beam, the upper flange steel beam being arranged above the lower flange steel beam, the straight web steel beam being connected between the upper flange steel beam and the lower flange steel beam, and the inclined web steel beam being connected between the upper flange steel beam and the lower flange steel beam.

[0006] Further, the first end of the inclined web steel beam is connected at the connection position of the straight web steel beam and the upper flange steel beam, and the second end of the inclined web steel beam is connected at the connection position of the adjacent straight web steel beam and the lower flange steel beam.

[0007] Further, the concrete coupling beam comprises a first coupling beam and a second coupling beam, the first coupling beam and the second coupling beam are oppositely arranged, the first end of the upper flange steel beam is arranged on the first coupling beam, and the second end of the upper flange steel beam is arranged on the second coupling beam.

[0008] Further, the concrete coupling beam further comprises a third coupling beam and a fourth coupling beam, the third coupling beam and the fourth coupling beam are oppositely arranged, the third coupling beam is located below the first coupling beam, the fourth coupling beam is located below the second coupling beam, the first end of the lower flange steel beam is arranged on the third coupling beam, and the second end of the lower flange steel beam is arranged on the fourth coupling beam.

[0009] Further, the tower crane support structure further comprises: a first embedded part, the first embedded part is arranged on all the concrete coupling beams respectively; a first connecting plate, the first connecting plate is arranged on the first embedded part on the first coupling beam, and the first end of the upper flange steel beam is connected to the first connecting plate; and a second connecting plate, the second connecting plate is arranged on the first embedded part on the third coupling beam, and the first end of the lower flange steel beam is connected to the second connecting plate.

[0010] Further, the tower crane support structure further comprises: a first limiting frame, the first limiting frame is arranged on the first embedded part of the second coupling beam, the second end of the upper flange steel beam is in limiting cooperation with the first limiting frame, and the first limiting frame is used for limiting the movement of the upper flange steel beam in the vertical direction; and a second limiting frame, the second limiting frame is arranged on the first embedded part of the fourth coupling beam, the second end of the lower flange steel beam is in limiting cooperation with the second limiting frame, and the second limiting frame is used for limiting the movement of the lower flange steel beam in the vertical direction.

[0011] Further, the tower crane support structure further comprises: a pull rod, the pull rod is connected to the steel truss, and the steel truss is connected to the shear wall through the pull rod.

[0012] Further, the shear wall is provided with a second embedded part, and the pull rod is connected to the second embedded part.

[0013] According to another aspect of the present application, a construction method for the tower crane support structure is provided, comprising the following steps: S10, pouring the shear wall and the concrete coupling beam of the core tube, and embedding the embedded part in the shear wall and the concrete coupling beam before pouring; S20, installing two steel trusses on the poured concrete coupling beam, and fixedly connecting the trusses to the embedded part; S30, fixing the two steel trusses through the secondary beam; and S40, connecting the steel trusses to the embedded part through the connecting rod.

[0014] The technical scheme of the present application changes the original fixed mode of reinforced concrete into the mode of steel truss, the steel truss has light self weight and large span, the installation and dismounting process is simplified, during installation, the processed section is hoisted to the floor, the installation of the steel truss is completed through splicing and welding, during dismounting, the cutting and dismounting are carried out according to the hoisting calculation and the section is hoisted out of the field, the concrete structure is not damaged, the installation and dismounting steps are greatly simplified, the material can be recycled, energy saving and environmental protection are achieved, and the safety is high.

[0015] In addition to the objects, features and advantages described above, the present application has other objects, features and advantages. The present application will be further described below with reference to the drawings. BRIEF DESCRIPTION OF DRAWINGS

[0016] The drawings accompanying the specification of the present application form a part thereof, serve to provide further understanding of the application, and together with the description, explain the application. The present application will become more fully understood from the detailed description given herein and the accompanying drawings, wherein:

[0017] Figure 1 A structural schematic view of a tower crane support structure according to the embodiment one of the present application is shown; and

[0018] Figure 2 A structural schematic view of a steel truss of the tower crane support structure according to the embodiment one of the present application is shown;

[0019] Figure 3 An assembly view of the steel truss and the first and third coupling beams of the tower crane support structure according to the embodiment one of the present application is shown;

[0020] Figure 4 An assembly view of the steel truss and the second and fourth coupling beams of the tower crane support structure according to the embodiment one of the present application is shown;

[0021] Figure 5 A structural schematic view of a first embedded part of the tower crane support structure according to the embodiment one of the present application is shown.

[0022] Among the above drawings, the following reference signs are included:

[0023] 10, shear wall; 20, concrete coupling beam; 21, first coupling beam; 22, second coupling beam; 23, third coupling beam; 24, fourth coupling beam; 30, steel truss; 31, upper flange steel beam; 32, lower flange steel beam; 33, straight web steel beam; 34, inclined web steel beam; 40, secondary beam; 51, first embedded part; 52, second embedded part; 61, first connecting plate; 62, second connecting plate; 63, first limiting frame; 64, second limiting frame; 70, pull rod. DETAILED DESCRIPTION

[0024] It should be noted that the embodiments and features of the present application can be combined with each other, if there is no conflict. The present application will be described in detail below with reference to the drawings and in conjunction with embodiments.

[0025] In order to make the technical personnel in the art better understand the present application scheme, the following will be combined with the drawings in the embodiments of the present application, the technical solutions in the embodiments of the present application are described clearly and completely, obviously, the described embodiments are only a part of the embodiments of the present application, not all. Based on the embodiments of the present application, all other embodiments obtained by those of ordinary skill in the art without creative labor should belong to the scope of protection of the present application.

[0026] It should be noted that the terms "first", "second" and the like in the specification and claims of the present application and the above-described drawings are used to distinguish similar objects, and do not necessarily indicate a specific order or sequence. It should be understood that the terms thus used can be interchanged under appropriate circumstances, so that the embodiments of the present application described herein can be implemented. In addition, the terms "include" and "have" and any variations thereof are intended to cover non-exclusive inclusion, for example, a process, method, system, product or device including a series of steps or units does not necessarily limit to those clearly listed steps or units, but can include other steps or units not clearly listed or inherent to these processes, methods, products or devices.

[0027] It should be noted that the terms used herein are only for the purpose of describing specific embodiments, and are not intended to limit the exemplary embodiments according to the present application. As used herein, the singular form is intended to include the plural form, unless the context clearly indicates otherwise, and furthermore, it should be understood that when the terms "comprise" and / or "include" are used in the specification, there is a feature, step, operation, device, component and / or combination thereof.

[0028] As Figure 1The embodiment one of the application shown provides a tower crane supporting structure installed in a core tube of a building, the core tube comprises shear walls 10, the shear walls 10 are provided with at least one pair of horizontally spaced concrete coupling beams 20, the tower crane supporting structure comprises steel trusses 30 and secondary beams 40, the steel trusses 30 are arranged on the concrete coupling beams 20 at two ends respectively, the steel trusses 30 are two, and the two steel trusses 30 are arranged in parallel, the secondary beams 40 are arranged between the two steel trusses 30, and the two steel trusses 30 are connected through the secondary beams 40. The tower crane supporting structure of the application changes the original fixed mode of reinforced concrete into the mode of using steel trusses 30, the steel trusses 30 have light self-weight and large span, the installation and dismounting process is simplified while the reliability is ensured, during installation, only the processed section bars need to be hoisted to the floor, and the installation of the steel trusses 30 is completed through splicing and welding, during dismounting, the cutting and dismounting are carried out according to the hoisting calculation and the section bars are hoisted out of the field, the concrete structure does not need to be damaged, the installation and dismounting steps are greatly simplified, the materials can be recycled and energy saving and environmental protection are achieved, and the safety is higher.

[0029] It should be noted that, as Figure 1 shown, Figure 1 the shear wall 10 on the left side in the figure is provided with at least one concrete coupling beam 20, Figure 1 the shear wall 10 on the right side in the figure is also provided with at least one concrete coupling beam 20, the two concrete coupling beams 20 have the same height in the vertical direction, are arranged in parallel and are spaced in the horizontal direction, and the steel trusses 30 are arranged on the two concrete coupling beams 20.

[0030] As Figure 2 shown, the steel truss 30 comprises an upper flange steel beam 31, a lower flange steel beam 32, a straight web steel beam 33 and an inclined web steel beam 34, the upper flange steel beam 31 is arranged above the lower flange steel beam 32, the straight web steel beam 33 is connected between the upper flange steel beam 31 and the lower flange steel beam 32, and the inclined web steel beam 34 is connected between the upper flange steel beam 31 and the lower flange steel beam 32. By arranging the upper flange steel beam 31 and the lower flange steel beam 32 and connecting the straight web steel beam 33 and the inclined web steel beam 34 between the upper flange steel beam 31 and the lower flange steel beam 32, the stress system is simple, has strong bending resistance, large bearing capacity and can bear the great vertical load brought by the luffing-jib tower crane, thereby improving the safety and reliability. Preferably, the first end of the inclined web steel beam 34 is connected at the position where the straight web steel beam 33 and the upper flange steel beam 31 are connected, and the second end of the inclined web steel beam 34 is connected at the position where the adjacent straight web steel beam 33 and the lower flange steel beam 32 are connected, thereby improving the load performance.

[0031] In the embodiment, as Figure 3 and Figure 4As shown, the concrete coupling beam 20 includes a first coupling beam 21, a second coupling beam 22, a third coupling beam 23 and a fourth coupling beam 24, the first coupling beam 21 and the second coupling beam 22 are oppositely arranged, the first end of the upper flange steel beam 31 is arranged on the first coupling beam 21, and the second end of the upper flange steel beam 31 is arranged on the second coupling beam 22. The third coupling beam 23 is located below the first coupling beam 21, and the fourth coupling beam 24 is located below the second coupling beam 22, the first end of the lower flange steel beam 32 is arranged on the third coupling beam 23, and the second end of the lower flange steel beam 32 is arranged on the fourth coupling beam 24. In order to improve the load capacity of the steel truss 30, when pouring the concrete coupling beam 20, four concrete coupling beams 20, i.e. the first coupling beam 21, the second coupling beam 22, the third coupling beam 23 and the fourth coupling beam 24, need to be poured, the first coupling beam 21 and the second coupling beam 22 are arranged in parallel, the two ends of the upper flange steel beam 31 are connected to the first coupling beam 21 and the second coupling beam 22 respectively, the third coupling beam 23 is arranged below the first coupling beam 21, the fourth coupling beam 24 is arranged below the first coupling beam 21, and the two ends of the lower flange steel beam 32 are connected to the third coupling beam 23 and the fourth coupling beam 24 respectively. Through the steel truss 30 and the concrete coupling beam 20, the load can be uniformly distributed on the four concrete coupling beams 20, thereby improving the load capacity.

[0032] Further, the tower crane support structure further includes a first embedded part 51, a first connecting plate 61 and a second connecting plate 62, the first embedded part 51 is arranged on all the concrete coupling beams 20 respectively; the first connecting plate 61 is arranged on the first embedded part 51 on the first coupling beam 21, and the first end of the upper flange steel beam 31 is connected to the first connecting plate 61; the second connecting plate 62 is arranged on the first embedded part 51 on the third coupling beam 23, and the first end of the lower flange steel beam 32 is connected to the second connecting plate 62. The first connecting plate 61 is welded to the first embedded part 51 of the first coupling beam 21, and the first end of the upper flange steel beam 31 is welded to the first connecting plate 61, so as to realize the connection and fixation of the upper flange steel beam 31 and the first coupling beam 21. The second connecting plate 62 is welded to the first embedded part 51 of the third coupling beam 23, and the first end of the lower flange steel beam 32 is welded to the second connecting plate 62, so as to realize the connection and fixation of the upper flange steel beam 31 and the first coupling beam 21. Preferably, the first connecting plate 61 and the second connecting plate 62 are both steel plates,

[0033] Further, the tower crane support structure further comprises a first limiting frame 63 and a second limiting frame 64. The first limiting frame 63 is arranged on the first embedded part 51 of the second cross beam 22, and the second end of the upper flange steel beam 31 is in limiting cooperation with the first limiting frame 63. The first limiting frame 63 is used to limit the vertical movement of the upper flange steel beam 31. The second limiting frame 64 is arranged on the first embedded part 51 of the fourth cross beam 24, and the second end of the lower flange steel beam 32 is in limiting cooperation with the second limiting frame 64. The second limiting frame 64 is used to limit the vertical movement of the lower flange steel beam 32. A steel plate is welded on the first embedded part 51 of the second cross beam 22. A polytetrafluoroethylene plate is arranged on the steel plate. The second end of the upper flange steel beam 31 is slidingly arranged on the polytetrafluoroethylene plate. The first limiting frame 63 is L-shaped. Two first limiting frames 63 are oppositely arranged and simultaneously welded on the first embedded part 51 of the second cross beam 22. The two first limiting frames 63 and the first embedded part 51 form a clamping groove in the shape of an inverted T. The second end of the upper flange steel beam 31 is movably arranged in the clamping groove. The friction coefficient between the steel plates is reduced by the characteristics of the polytetrafluoroethylene plate. The first limiting frame 63 is used to limit the vertical movement of the second end of the upper flange steel beam 31. Since the upper flange steel beam 31 can move relative to the second cross beam 22 in the length direction of the upper flange steel beam 31, the lateral force transmitted by the steel truss 30 to the concrete cross beam 20 can be greatly eliminated.

[0034] Similarly, a steel plate is welded on the first embedded part 51 of the fourth cross beam 24. A polytetrafluoroethylene plate is arranged on the steel plate. The second end of the lower flange steel beam 32 is slidingly arranged on the polytetrafluoroethylene plate. The number and installation mode of the second limiting frame 64 are the same as those of the first limiting frame 63. The second end of the lower flange steel beam 32 is movably arranged in the clamping groove formed by the two second limiting frames 64 and the corresponding first embedded part 51. The lateral force transmitted by the steel truss 30 to the concrete cross beam 20 can be greatly eliminated.

[0035] Further, the tower crane support structure further comprises a pull rod 70. The pull rod 70 is connected to the steel truss 30. The steel truss 30 is connected to the shear wall 10 through the pull rod 70. It should be noted that the pull rod 70 is welded on the outer side of the steel truss 30. The pull rod 70 is connected to the shear wall 10 to balance the horizontal force of the steel truss 30. The steel material is Q355B. The connection is fully welded. The welding method is carbon dioxide gas shielded welding. In addition, in order to further improve the reliability, the pull rod 70 can also be connected to the concrete cross beam 20. It should be noted that the second embedded part 52 is arranged in the shear wall 10. The pull rod 70 is connected to the second embedded part 52.

[0036] It should also be noted that, as shown in Figure 5 the first embedded part 51 and the second embedded part 52 are both small-section I-shaped steel used as anchor rods. In the case of meeting the truss force requirement, the requirements of the concrete beam steel bar are considered. The whole is embedded, and the construction is convenient.

[0037] According to another aspect of the present application, a construction method for the tower crane supporting structure is also disclosed, comprising the following steps: S10: pouring the shear wall 10 and the concrete coupling beam 20 of the core tube, and embedding the embedded part in the shear wall 10 and the concrete coupling beam 20 before pouring; S20: installing two steel trusses 30 on the poured concrete coupling beam 20, and fixing the trusses with the embedded part; S30: fixing the two steel trusses 30 through the secondary beam 40; S40: connecting the upper steel truss 30 with the embedded part through the connecting rod.

[0038] It should be noted that, for different site conditions, the shear steel plate needs to be additionally arranged in the core tube concrete beam, and the shear wall 10 in the core tube needs to be additionally reinforced to improve the strength, ensure the safety and reliability. The main structure concrete is reinforced before the steel truss 30 is installed to ensure that the strength reaches 100%, and the counterforce design value acting on the main structure during the use of the tower crane should not be greater than the counterforce limit value of the tower crane foundation support; after the construction is completed, the welding part of the tower crane foundation is detected, and only after the detection is qualified, the tower crane can be used, and the stress and strain of the concrete coupling beam 20 and the steel truss 30 in the core tube are detected during the use of the tower crane to ensure the safety.

[0039] From the above description, it can be seen that the above-mentioned embodiments of the present application are convenient to assemble and disassemble, can shorten the foundation construction period, the materials can be recycled, and the safety is relatively high, so that the utilization rate of the tower crane can be improved.

[0040] The relative arrangement of the components and steps, numerical expressions, and numerical values set forth in these implementations do not limit the scope of the application, unless otherwise specified. It should also be understood that the dimensions of the various parts shown in the drawings are not drawn to scale for the purpose of convenience in description. Techniques, methods, and equipment known to those of ordinary skill in the relevant art can not be discussed in detail, but should be considered as part of the authorized description, if appropriate. In all examples shown and discussed here, any specific value should be interpreted as merely exemplary, and not as a limitation. Therefore, other examples of exemplary embodiments can have different values. It should be noted that similar reference numbers and letters represent similar items in the following drawings, so once an item is defined in one drawing, it does not need to be further discussed in subsequent drawings.

[0041] For purposes of the description hereinafter, the orientations in the various drawings will be described as they are depicted in the drawings. However, it is to be understood that these orientations are depicted and described only for purposes of illustrating the embodiments, and that other orientations of the described embodiments are possible. Therefore, the following description is not intended to limit the scope of the application. The terms "front," "back," "top," "bottom" and the like as used in this description should not be construed as limiting the present application in any manner. The terms "first," "second," "third," etc. as used in this description should not be construed as limiting the present application in any manner. The terms "including," "containing," "having," and the like as used herein are understood to be open-ended, i.e., meaning "including but not limited to." The terms "coupled" and "connected" as used herein, are intended to mean a direct connection or an indirect connection via one or more intervening elements. The terms "attached" and "connected" as used herein, are intended to mean a direct connection or an indirect connection via one or more intervening elements. The term "or" as used herein is intended to mean an inclusive "or" unless the context clearly indicates otherwise. The term "and / or" as used herein is intended to mean "and" or "or" unless the context clearly indicates otherwise. The term "at least one of" followed by a list of one or more items is intended to mean one or more items from the list, but not limited to a single item from the list or the list as a whole, unless the context clearly indicates otherwise. The term "plurality" as used herein is intended to indicate "one or more than one," unless the context clearly indicates otherwise. The term "about" as used herein is intended to mean approximately, nearly, almost, most

[0042] In the description of the present application, it is to be understood that the orientation words such as "front, back, up, down, left, right", "transverse, vertical, perpendicular, horizontal" and "top, bottom" and the like indicated orientation or position relationship are generally based on the orientation or position relationship shown in the drawings, only for the convenience of describing the present application and simplifying the description, without the opposite indication, these orientation words do not indicate and imply that the device or element referred to must have a particular orientation or be constructed and operated in a particular orientation, therefore cannot be understood as limiting the scope of protection of the present application; the orientation words "inner, outer" refer to the inner and outer relative to the contour of each component.

[0043] The above only describes the preferred embodiments of the present application and is not intended to limit the present application. The present application can have various modifications and changes for those skilled in the art. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present application shall be included in the protection scope of the present application.

Claims

1. A tower crane support structure, installed within the core tube of a building, the core tube comprising shear walls, the shear walls having at least one pair of horizontally spaced concrete connecting beams, characterized in that... Tower crane support structure includes: Two steel trusses are arranged in parallel, with each end mounted on a concrete connecting beam. The steel trusses include an upper flange steel beam, a lower flange steel beam, straight web members, and diagonal web members. The upper flange steel beam is positioned above the lower flange steel beam. The straight web members connect the upper and lower flange steel beams, and the diagonal web members connect the upper and lower flange steel beams. The first end of each diagonal web member connects to the connection between the straight web member and the upper flange steel beam, and the second end connects to the connection between the adjacent straight web member and the lower flange steel beam. Secondary beams are placed between two steel trusses, which are connected by secondary beams; the connection of secondary beams between two steel trusses does not require damage to the concrete structure. The concrete connecting beam includes a first connecting beam and a second connecting beam arranged opposite to and parallel to each other. The first end of the upper flange steel beam is located on the first connecting beam, and the second end of the upper flange steel beam is located on the second connecting beam. The concrete connecting beam also includes a third connecting beam and a fourth connecting beam arranged opposite to and parallel to each other. The third connecting beam is located below the first connecting beam, and the fourth connecting beam is located below the second connecting beam. The first end of the lower flange steel beam is located on the third connecting beam, and the second end of the lower flange steel beam is located on the fourth connecting beam. The upper flange steel beam can move relative to the second connecting beam in its own length direction. During installation, the pre-processed profiles are simply hoisted to the floor, and the steel trusses and secondary beams are installed through assembly and welding.

2. The tower crane support structure according to claim 1, characterized in that, A pair of concrete coupling beams are at the same height in the vertical direction and are spaced apart and parallel in the horizontal direction; shear steel plates are added inside the concrete coupling beams in the core tube to increase the reinforcement of the shear wall.

3. The tower crane support structure according to claim 1, characterized in that, Also includes: The first embedded part is set on all concrete connecting beams. Steel plates are welded on the first embedded parts on the second and fourth connecting beams. Polytetrafluoroethylene plates are placed on the steel plates. The second end of the upper flange steel beam is slidably set on the polytetrafluoroethylene plate, and the second end of the lower flange steel beam is slidably set on the polytetrafluoroethylene plate. The first connecting plate is set on the first embedded part on the first connecting beam, and the first end of the upper flange steel beam is connected to the first connecting plate. The second connecting plate is set on the first embedded part on the third connecting beam, and the first end of the lower flange steel beam is connected to the second connecting plate.

4. The tower crane support structure according to claim 3, characterized in that, Also includes: The first limiting frame is set on the first embedded part of the second connecting beam. The second end of the upper flange steel beam is limited and matched with the first limiting frame. The first limiting frame is used to restrict the vertical movement of the upper flange steel beam. There are two first limiting frames. The first limiting frames are L-shaped. The two first limiting frames are arranged opposite to each other and simultaneously welded to the first embedded part on the second connecting beam. The two first limiting frames and the first embedded part form a slot with an inverted T-shaped groove. The second end of the upper flange steel beam is movably set in the slot. The second limiting frame is set on the first embedded part of the fourth connecting beam. The second end of the lower flange steel beam is limited and matched with the second limiting frame. The second limiting frame is used to restrict the vertical movement of the lower flange steel beam. The number and installation method of the second limiting frame are the same as the first limiting frame. The second end of the lower flange steel beam is movably set in the slot formed by the two second limiting frames and the corresponding first embedded part.

5. The tower crane support structure according to claim 3, characterized in that, The tower crane support structure also includes: Tie rods are attached to the steel truss, which in turn connects to the shear wall.

6. The tower crane support structure according to claim 5, characterized in that, The tower crane support structure also includes a second embedded part, which is set inside the shear wall, and the tie rod is connected to the second embedded part; both the first and second embedded parts use small-section I-beams as anchor rods.

Citation Information

Patent Citations

  • Tower crane suspended foundation device for reinforced concrete core tube and construction method thereof

    CN113073677A

  • Tower crane supporting structure

    CN216613818U