Glass curtain wall hoisting construction method and equipment

By using adsorption fixing components and other auxiliary structures in glass curtain wall hoisting equipment, the problem of damage and inconvenience of existing equipment during hoisting and disassembly is solved, the glass curtain wall panels are reliably fixed and easily disassembled, and the construction efficiency is improved. Convenience and reliability.

CN114620588BActive Publication Date: 2024-10-01ZHEJIANG CLASSIC BUILDING DECORATION CO LTD
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
CN202210231104.8
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-03-10
Publication Date
2024-10-01
Estimated Expiration
2042-03-10

AI Technical Summary

Technical Problem

Existing glass curtain wall hoisting equipment is easily damaged during hoisting and disassembly and is inconvenient to operate, making it difficult to meet construction needs.

Method used

A glass curtain wall hoisting construction method including a spreader device and a receiving device is designed. It adopts structures such as adsorption fixing components, ventilation valves, pressure detection components, and locking components. The glass is realized through components such as annular suction cups, pistons, adjusting screws, and flexible pads. The curtain wall panels are reliably adsorbed, fixed and easily disassembled, and the adsorption force is detected and fed back in real time, improving the convenience and reliability of construction.

Benefits of technology

It effectively avoids damage to the glass curtain wall panels during the hoisting process, improves the fixing effect and convenience of disassembly and assembly, saves manpower, and improves the reliability and convenience of construction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114620588B_ABST
    Figure CN114620588B_ABST
Patent Text Reader

Abstract

The present invention discloses a glass curtain wall hoisting construction method and equipment, and relates to the technical field of glass curtain wall hoisting construction; in order to improve the hoisting and conveying effect; specifically includes a hoisting device, the hoisting device includes a hanger and a plurality of adsorption and fixing components, the adsorption and fixing components are detachably installed on the hanger; the adsorption and fixing components include: an adsorption cylinder, the adsorption cylinder is installed on the hanger; a piston, the piston seals and slides on the inner wall of the adsorption cylinder; the method includes the following steps: according to the actual situation, the adsorption and fixing components are installed in the corresponding fixing seat, and the adsorption and fixing components are fixed by tightening the knob. The present invention can attach the glass curtain wall panel to one side of the annular suction cup by setting the adsorption and fixing components and other structures, and the adjusting screw is screwed by rotating the handle, thereby driving the piston to slide in the adsorption cylinder, so that the distance between the piston and the glass curtain wall panel is increased, so that the glass curtain wall panel is reliably adsorbed and fixed by the annular suction cup.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of glass curtain wall hoisting construction, in particular to a glass curtain wall hoisting construction method and equipment thereof. Background Art

[0002] Glass curtain wall refers to the building's external protective structure or decorative structure that has a certain displacement capacity relative to the main structure and does not share the effects on the main structure. In the construction of high-altitude glass curtain walls, it is often necessary to hoist and transport the glass curtain wall panels to the designated location, and then install the glass curtain wall panels. The current glass curtain wall hoisting equipment, such as the Chinese patent with application number CN202011041278.5, discloses a high-rise building glass curtain wall hoisting system, including a hoisting box and buckles fixedly connected to the four corners of the hoisting box, a clamping device is provided at the left end of the interior of the hoisting box, a disassembly device is provided above the clamping device, and a fixing device is provided at the left end of the hoisting box. Although the glass curtain wall hoisting system in the above patent can meet certain construction requirements, the glass curtain wall panels are fixed by clamping during hoisting, which can easily cause damage to the glass curtain wall panels, and disassembly and assembly are relatively inconvenient, so it needs to be improved. Summary of the invention

[0003] The purpose of the present invention is to solve the shortcomings of the prior art and to propose a glass curtain wall hoisting construction method and equipment.

[0004] In order to achieve the above object, the present invention adopts the following technical solutions:

[0005] A glass curtain wall hoisting construction equipment includes a hoisting device, the hoisting device includes a hanger and a plurality of adsorption and fixing components, the adsorption and fixing components are detachably mounted on the hanger; the adsorption and fixing components include:

[0006] Adsorption cylinder, the adsorption cylinder is installed on the hanger;

[0007] The piston seal slides on the inner wall of the adsorption cylinder, and a metal seat is fixed on the inner wall of one side of the piston;

[0008] An adjusting screw, the adjusting screw is connected to the inner wall of one end of the adsorption cylinder through a thread, a rotating head is provided at one end of the adjusting screw, the rotating head is rotatably connected to the inner wall of the metal seat, and a rotating handle is fixed to the side wall of the other end of the adjusting screw;

[0009] An annular suction cup, the annular suction cup is fixed to the circumferential outer wall of one end of the adsorption cylinder;

[0010] The pressure detection component is arranged in the adsorption cylinder, and the pressure detection component is located between the piston and the annular suction cup.

[0011] Preferably, the sling device further comprises a sling rod and a sling ring, wherein the sling rod is arranged on the top outer wall of the hanger, and the sling ring is arranged on the top of the sling rod.

[0012] Further: A vent valve is provided at the bottom of the adsorption cylinder, and the vent valve includes:

[0013] A valve housing, which is fixed to the outer wall of the bottom of the adsorption cylinder;

[0014] A valve plug, the valve plug is sealingly and slidably connected to the inner wall of the valve housing;

[0015] A movable plate is movably installed on the top of the valve housing through a first spring, the bottom of the movable plate is connected to the top of the valve plug through a connecting rod, a through hole is opened on the outer wall of the top of the movable plate, and bumps are arranged on the outer walls on both sides of the movable plate. The inner walls of the bumps are slidably connected with guide rods, and the bottom end of the guide rods is fixed to the top of the valve housing.

[0016] Further preferably, the outer wall of one side of the hanger is provided with evenly distributed fixing seats, the adsorption cylinder is detachably installed in the fixing seat, and the top of the fixing seat is threadedly connected with a fastening knob for fixing the adsorption cylinder.

[0017] As a preferred embodiment of the present invention: the pressure detection component includes a pressure sensor, a control unit, an indicator light and a power supply unit; the pressure sensor, the control unit and the indicator light are electrically connected through a signal line, and the indicator light is fixed to the top of the adsorption cylinder.

[0018] As a further preferred embodiment of the present invention: the glass curtain wall hoisting construction equipment also includes a receiving device used in conjunction with the hoisting device, and the receiving device includes:

[0019] Base;

[0020] L-shaped receiving frame, the L-shaped receiving frame is installed on the base;

[0021] Flexible pad, the flexible pad is fixed on the L-shaped support frame;

[0022] The push rod is fixed to the outer wall of one side of the L-shaped receiving frame away from the movable baffle through a bracket. The diameter of the top of the push rod gradually decreases, and the position and size of the push rod are adapted to the valve housing.

[0023] As a further solution of the present invention: a movable baffle is provided on one side of the L-shaped receiving frame, and rotating shafts are fixed on both sides of the movable baffle. The rotating shafts are installed on the inner walls of both sides of the L-shaped receiving frame through springs; and the flexible pad is located between the L-shaped receiving frame and the movable baffle.

[0024] On the basis of the above solution: locking components are arranged on both sides of the valve housing, and the locking components include:

[0025] A mounting seat, the mounting seat being arranged on the outer wall of the valve housing;

[0026] The limit frame is slidably installed in the mounting seat, and limit teeth are arranged at both ends of the limit frame. The limit teeth are located on the inner side of the valve housing, and the two limit teeth are triangular in structure. The oblique sides of the two limit teeth are arranged on the side away from the valve plug;

[0027] A center rod, the center rod is fixed to the inner walls on both sides of the mounting seat, and the limit frame is slidably connected to the outer wall of the center rod;

[0028] A second spring, one end of the second spring is fixed to an outer wall of a side of the limiting frame away from the valve housing, and the other end of the second spring is fixed to an inner wall of a side of the mounting seat.

[0029] Based on the above solution, it is preferred that: the base includes:

[0030] Base;

[0031] The slide rail is fixed on the top of the base, and a slider adapted to the slide rail is fixed on the bottom of the L-shaped receiving frame, and the L-shaped receiving frame is slidably connected to the slide rail through the slider.

[0032] A glass curtain wall hoisting construction method comprises the following steps:

[0033] S1: According to the actual situation, install the adsorption fixing component in the corresponding fixing seat, and fix the adsorption fixing component by tightening the knob;

[0034] S2: Attach the glass curtain wall panel to be hoisted to one side of the annular suction cup;

[0035] S3: By turning the handle to screw the adjusting screw, the piston is driven to slide in the adsorption cylinder, and the glass curtain wall panels are reliably adsorbed and fixed by the annular suction cup;

[0036] S4: Connect the lifting rings with the crane and lift the lifting device to the designated location;

[0037] S5: guide the valve housing to align with the ejector rod and then lower it so that the ejector rod is inserted into the valve housing;

[0038] S6: Use the push rod to push the valve plug upward into the adsorption cylinder, so that the gas enters the adsorption cylinder, thereby causing the glass curtain wall panel to fall down and be received by the flexible pad;

[0039] S7: Construction workers remove the glass curtain wall panels and then carry out installation.

[0040] The beneficial effects of the present invention are:

[0041] 1. The present invention can attach the glass curtain wall panel to one side of the annular suction cup by arranging structures such as an adsorption fixing component, and the adjusting screw is screwed by rotating the handle, thereby driving the piston to slide in the adsorption cylinder, so that the distance between the piston and the glass curtain wall panel is increased, so that the annular suction cup is used to reliably adsorb and fix the glass curtain wall panel. Since the metal seat is rotatably connected to the rotating head, the slipping and self-rotation of the adjusting screw is avoided, thereby improving the fixing effect.

[0042] 2. By setting up the vent valve, the valve plug can be pushed into the adsorption cylinder under the guidance of the guide rod, thereby opening the vent valve and allowing the glass curtain wall panel to be easily removed.

[0043] 3. By setting up a pressure detection component, the pressure sensor can be used to detect the pressure in the adsorption cylinder in real time when adsorbing the glass curtain wall panels, and the status feedback can be provided through the indicator light, which is beneficial for the user to make judgments, thereby controlling the adsorption force within an appropriate value and improving reliability.

[0044] 4. By setting up a receiving device, when hoisting to the specified position, the valve housing can be guided to align with the push rod and then lowered so that the push rod is inserted into the valve housing, thereby pushing the valve plug upward into the adsorption cylinder, allowing the gas to enter the adsorption cylinder, so that the glass curtain wall panel falls and is received by the flexible pad, saving manpower and improving construction convenience.

[0045] 5. By setting up a locking assembly, the elastic force of the second spring can be used to make the limiting teeth extend into the valve housing, thereby limiting the valve plug and ensuring the sealing effect of the valve plug; when the push rod is inserted, the limiting teeth at the bottom can be squeezed to both sides, so that the limiting teeth at the top can be moved synchronously into the mounting seat, thereby releasing the limiting effect on the valve plug. As the push rod continues to be inserted, the valve plug can be pushed into the adsorption cylinder. After the valve plug is pushed into the adsorption cylinder, the vent valve is turned on, allowing outside gas to enter and the glass curtain wall panel to be removed. BRIEF DESCRIPTION OF THE DRAWINGS

[0046] Figure 1 A structural schematic diagram of a hoisting device and a receiving device for hoisting construction equipment of a glass curtain wall proposed by the present invention;

[0047] Figure 2 This is a structural schematic diagram of a hoisting device for glass curtain wall hoisting construction equipment proposed by the present invention;

[0048] Figure 3 This is a structural schematic diagram of the back of a hoisting device for glass curtain wall hoisting construction equipment proposed by the present invention;

[0049] Figure 4 This is a schematic structural diagram of a cross-section of an adsorption and fixing component of a glass curtain wall hoisting construction equipment proposed by the present invention;

[0050] Figure 5 This is a schematic structural diagram of a glass curtain wall hoisting construction equipment installation seat and a vent valve cross-section proposed by the present invention;

[0051] Figure 6 for Figure 5 The enlarged view of point A in the middle;

[0052] Figure 7 This is a structural schematic diagram of the split L-shaped receiving frame and slide rail of a glass curtain wall hoisting construction equipment proposed by the present invention.

[0053] In the figure: 1 hanger, 2 hanger rod, 3 lifting ring, 4 adsorption fixing component, 5 annular suction cup, 6 L-type receiving frame, 7 movable baffle, 8 base, 9 slide rail, 10 push rod, 11 adsorption cylinder, 12 indicator light, 13 valve housing, 14 mounting seat, 15 fastening knob, 16 fixing seat, 17 adjusting screw, 18 rotating handle, 19 metal seat, 20 piston, 21 guide rod, 22 movable plate, 23 rotating head, 24 center rod, 25 second spring, 26 limit frame, 27 limit tooth, 28 valve plug, 29 first spring, 30 connecting rod, 31 protrusion, 32 through hole, 33 rotating shaft, 34 flexible pad, 35 slider. DETAILED DESCRIPTION

[0054] The technical solution of this patent is further described in detail below in conjunction with specific implementation methods.

[0055] The embodiments of the present invention are described in detail below, and examples of the embodiments are shown in the accompanying drawings, wherein the same or similar reference numerals throughout represent the same or similar elements or elements having the same or similar functions. The embodiments described below with reference to the accompanying drawings are exemplary and are only used to explain the present invention, and cannot be understood as limiting the present invention.

[0056] In the description of this patent, it should be understood that the terms "center", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", etc., indicating the orientation or position relationship, are based on the orientation or position relationship shown in the drawings, and are only for the convenience of describing this patent and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on this patent.

[0057] In the description of this patent, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", and "set" should be understood in a broad sense, for example, it can be fixedly connected or set, or it can be detachably connected or set, or connected or set in one piece. For ordinary technicians in this field, the specific meanings of the above terms in this patent can be understood according to specific circumstances.

[0058] Embodiment 1:

[0059] A glass curtain wall hoisting construction equipment, such as Figure 1-7 As shown, it includes a sling device, which includes a hanger 1 and a plurality of adsorption and fixing components 4, and the adsorption and fixing components 4 are detachably mounted on the hanger 1; the adsorption and fixing components 4 include:

[0060] Adsorption cylinder 11, the adsorption cylinder 11 is installed on the hanger 1;

[0061] A piston 20, the piston 20 is sealed and slides on the inner wall of the adsorption cylinder 11, and a metal seat 19 is bonded to the inner wall of one side of the piston 20;

[0062] An adjusting screw 17, which is connected to the inner wall of one end of the adsorption cylinder 11 through a thread, and a rotating head 23 is integrally provided at one end of the adjusting screw 17, and the rotating head 23 is rotatably connected to the inner wall of the metal seat 19, and a rotating handle 18 is welded to the side wall of the other end of the adjusting screw 17;

[0063] An annular suction cup 5, the annular suction cup 5 is bonded to the circumferential outer wall of one end of the adsorption cylinder 11;

[0064] A pressure detection component is disposed in the adsorption cylinder 11, and the pressure detection component is located between the piston 20 and the annular suction cup 5;

[0065] By providing structures such as the adsorption fixing component 4, the glass curtain wall panel can be attached to one side of the annular suction cup 5, and the adjusting screw 17 is screwed by rotating the handle 18, thereby driving the piston 20 to slide in the adsorption cylinder 11, so that the distance between the piston 20 and the glass curtain wall panel is increased, so that the annular suction cup 5 is used to reliably adsorb and fix the glass curtain wall panel. Since the metal seat 19 is rotatably connected to the rotating head 23, the adjusting screw 17 is prevented from slipping and rotating, thereby improving the fixing effect.

[0066] In order to facilitate lifting; Figure 1 As shown, the sling device also includes a sling rod 2 and a sling ring 3. The sling rod 2 is integrally arranged on the top outer wall of the hanger 1, and the sling ring 3 is integrally arranged on the top of the sling rod 2.

[0067] In order to facilitate the disassembly of glass curtain wall panels; Figure 4-6 As shown, a vent valve is provided at the bottom of the adsorption cylinder 11, and the vent valve includes:

[0068] The valve housing 13 is welded to the outer wall of the bottom of the adsorption cylinder 11;

[0069] A valve plug 28, the valve plug 28 is sealingly and slidably connected to the inner wall of the valve housing 13;

[0070] The movable plate 22 is movably mounted on the top of the valve housing 13 through a first spring 29. The bottom of the movable plate 22 is connected to the top of the valve plug 28 through a connecting rod 30. A through hole 32 is provided on the outer wall of the top of the movable plate 22. The outer walls of both sides of the movable plate 22 are integrally provided with protrusions 31. The inner wall of the protrusion 31 is slidably connected to the guide rod 21. The bottom end of the guide rod 21 is fixed to the top of the valve housing 13.

[0071] By providing the vent valve, the valve plug 28 can be pushed into the adsorption cylinder 11 under the guidance of the guide rod 21, thereby connecting the vent valve and allowing the glass curtain wall panel to be easily removed.

[0072] In order to facilitate the adjustment of the installation position of the adsorption fixing component 4 according to the needs; Figure 1-3 As shown, the outer wall of one side of the hanger 1 is integrally provided with evenly distributed fixing seats 16, the adsorption cylinder 11 is detachably installed in the fixing seat 16, and the top of the fixing seat 16 is threadedly connected with a fastening knob 15 for fixing the adsorption cylinder 11.

[0073] In order to facilitate the determination of the adsorption force of the adsorption fixing component 4; Figure 2 As shown, the pressure detection component includes a pressure sensor, a control unit, an indicator light 12 and a power supply unit; the pressure sensor, the control unit, and the indicator light 12 are electrically connected via a signal line, and the indicator light 12 is fixed to the top of the adsorption cylinder 11; by setting the pressure detection component, when adsorbing the glass curtain wall panels, the pressure sensor can be used to detect the pressure in the adsorption cylinder 11 in real time, and the indicator light 12 can be used for status feedback, which is beneficial for the user to make judgments, thereby controlling the adsorption force within an appropriate value and improving reliability.

[0074] In order to facilitate the installation of glass curtain wall panels at designated locations; Figure 1 , Figure 7 As shown, the glass curtain wall hoisting construction equipment also includes a receiving device used in conjunction with the hoisting device, and the receiving device includes:

[0075] Base;

[0076] An L-shaped receiving frame 6 is installed on the base;

[0077] A flexible pad 34, which is fixed to the L-shaped receiving frame 6 and is used to play a buffering role when receiving the glass curtain wall panels;

[0078] The push rod 10 is fixed to the outer wall of the L-shaped receiving frame 6 away from the movable baffle 7 through a bracket. The top diameter of the push rod 10 gradually decreases, and the position and size of the push rod 10 and the valve housing 13 are adapted.

[0079] Wherein; the L-shaped receiving frame 6 is provided with a movable baffle 7 on one side, and a rotating shaft 33 is fixed on both sides of the movable baffle 7. The rotating shaft 33 is installed on the inner walls of both sides of the L-shaped receiving frame 6 through a clockwork spring; the flexible pad 34 is located between the L-shaped receiving frame 6 and the movable baffle 7.

[0080] By providing a receiving device, when hoisting to a specified position, the valve housing 13 can be guided to be aligned with the push rod 10 and then lowered so that the push rod 10 is inserted into the valve housing 13, thereby pushing the valve plug 28 upward into the adsorption cylinder 11, allowing the gas to enter the adsorption cylinder 11, so that the glass curtain wall panel falls and is received by the flexible pad 34, saving manpower and improving construction convenience.

[0081] To improve reliability; Figure 4-6 As shown, locking components are provided on both sides of the valve housing 13, and the locking components include:

[0082] A mounting seat 14, the mounting seat 14 is integrally arranged on the outer wall of the valve housing 13;

[0083] The limiting frame 26 is slidably mounted in the mounting seat 14. The limiting teeth 27 are integrally arranged at both ends of the limiting frame 26. The limiting teeth 27 are located inside the valve housing 13, and the two limiting teeth 27 are triangular in structure. The oblique sides of the two limiting teeth 27 are both arranged on the side away from the valve plug 28.

[0084] A center rod 24, the center rod 24 is fixed to the inner walls of both sides of the mounting seat 14, and the limit frame 26 is slidably connected to the outer wall of the center rod 24;

[0085] A second spring 25, one end of the second spring 25 is fixed to the outer wall of the limiting frame 26 away from the valve housing 13, and the other end of the second spring 25 is fixed to the inner wall of the mounting seat 14;

[0086] By setting up a locking assembly, the elastic force of the second spring 25 can be used to make the limiting teeth 27 extend into the valve housing 13, thereby limiting the valve plug 28 and ensuring the sealing effect of the valve plug 28; when the push rod 10 is inserted, the limiting teeth 27 at the bottom can be squeezed to both sides, so that the limiting teeth 27 at the top can be moved synchronously into the mounting seat 14, thereby releasing the limiting effect on the valve plug 28. As the push rod 10 continues to be inserted, the valve plug 28 can be pushed into the adsorption cylinder 11. After the valve plug 28 is pushed into the adsorption cylinder 11, the vent valve is turned on, external gas can enter, and the glass curtain wall panel can be removed.

[0087] In order to facilitate construction; Figure 7 As shown, the base comprises:

[0088] Base 8;

[0089] The slide rail 9 is fixed to the top of the base 8 , and a slider 35 adapted to the slide rail 9 is fixed to the bottom of the L-shaped receiving frame 6 , and the L-shaped receiving frame 6 is slidably connected to the slide rail 9 through the slider 35 .

[0090] Embodiment 2:

[0091] A glass curtain wall hoisting construction method comprises the following steps:

[0092] S1: According to the actual situation, the adsorption fixing component 4 is installed in the corresponding fixing seat 16, and the adsorption fixing component 4 is fixed by tightening the knob 15;

[0093] S2: attaching the glass curtain wall panel to be hoisted to one side of the annular suction cup 5;

[0094] S3: The adjusting screw 17 is screwed by rotating the handle 18, thereby driving the piston 20 to slide in the adsorption cylinder 11, and the glass curtain wall plate is reliably adsorbed and fixed by the annular suction cup 5;

[0095] S4: connect the lifting ring 3 via a crane and lift the lifting device to a designated location;

[0096] S5: guide the valve housing 13 to align with the push rod 10 and then lower it so that the push rod 10 is inserted into the valve housing 13;

[0097] S6: Use the push rod 10 to push the valve plug 28 upward into the adsorption cylinder 11, so that the gas enters the adsorption cylinder 11, thereby causing the glass curtain wall panel to fall down and be received by the flexible pad 34;

[0098] S7: Construction workers remove the glass curtain wall panels and then carry out installation.

[0099] The above is a preferred specific embodiment of the present invention, but it is not the only specific embodiment of the present invention. The protection scope of the present invention is not limited thereto. Any technician familiar with the art who, within the technical scope disclosed by the present invention, combines the prior art or public common sense, makes equivalent, equivalent replacement or change according to the technical solution and inventive concept of the present invention, shall be covered by the protection scope of the present invention.

Claims

1. A glass curtain wall hoisting construction equipment, comprising a hoisting device, characterized in that: The hanger device comprises a hanger (1) and a plurality of adsorption and fixing components (4), wherein the adsorption and fixing components (4) are detachably mounted on the hanger (1); the adsorption and fixing components (4) comprise: An adsorption cylinder (11), the adsorption cylinder (11) being mounted on the hanger (1); A piston (20), the piston (20) sealingly slides on the inner wall of the adsorption cylinder (11), and a metal seat (19) is fixed to the inner wall of one side of the piston (20); An adjusting screw (17), the adjusting screw (17) being connected to the inner wall of one end of the adsorption cylinder (11) through a thread, a rotating head (23) being provided at one end of the adjusting screw (17), the rotating head (23) being rotatably connected to the inner wall of the metal seat (19), and a rotating handle (18) being fixed to the side wall of the other end of the adjusting screw (17); An annular suction cup (5), the annular suction cup (5) being fixed to the circumferential outer wall of one end of the adsorption cylinder (11); A pressure detection component, the pressure detection component is arranged in the adsorption cylinder (11), and the pressure detection component is located between the piston (20) and the annular suction cup (5); A vent valve is provided at the bottom of the adsorption cylinder (11), and the vent valve comprises: A valve housing (13), the valve housing (13) being fixed to the outer wall of the bottom of the adsorption cylinder (11); A valve plug (28), the valve plug (28) is sealingly and slidably connected to the inner wall of the valve housing (13); A movable plate (22), the movable plate (22) being movably mounted on the top of the valve housing (13) via a first spring (29), the bottom of the movable plate (22) being connected to the top of the valve plug (28) via a connecting rod (30), a through hole (32) being provided on the outer wall of the top of the movable plate (22), protrusions (31) being provided on the outer walls of both sides of the movable plate (22), the inner wall of the protrusion (31) being slidably connected to a guide rod (21), the bottom end of the guide rod (21) being fixed to the top of the valve housing (13); The outer wall of one side of the hanger (1) is provided with evenly distributed fixing seats (16), the adsorption cylinder (11) is detachably mounted in the fixing seat (16), and the top of the fixing seat (16) is connected to a fastening knob (15) for fixing the adsorption cylinder (11) via a thread; The glass curtain wall hoisting construction equipment also includes a receiving device used in conjunction with the hoisting device, and the receiving device includes: Base; An L-shaped receiving frame (6), the L-shaped receiving frame (6) being mounted on the base; A flexible pad (34), the flexible pad (34) is fixed on the L-shaped receiving frame (6); A push rod (10), the push rod (10) being fixed to an outer wall of a side of the L-shaped receiving frame (6) away from the movable baffle (7) through a bracket, the top diameter of the push rod (10) gradually decreasing, and the position and size of the push rod (10) being adapted to the valve housing (13); Locking components are provided on both sides of the valve housing (13), and the locking components include: A mounting seat (14), the mounting seat (14) being arranged on an outer wall of the valve housing (13); A limit frame (26), the limit frame (26) is slidably mounted in the mounting seat (14), and limit teeth (27) are arranged at both ends of the limit frame (26), the limit teeth (27) are located on the inner side of the valve housing (13), and the two limit teeth (27) are triangular in structure, and the oblique edges of the two limit teeth (27) are arranged on a side away from the valve plug (28); A center rod (24), the center rod (24) is fixed to the inner walls on both sides of the mounting seat (14), and the limit frame (26) is slidably connected to the outer wall of the center rod (24); A second spring (25), one end of the second spring (25) is fixed to an outer wall of a side of the limiting frame (26) away from the valve housing (13), and the other end of the second spring (25) is fixed to an inner wall of a side of the mounting seat (14).

2. The glass curtain wall hoisting construction equipment according to claim 1, characterized in that: The sling device further comprises a sling rod (2) and a sling ring (3); the sling rod (2) is arranged on the top outer wall of the hanger (1), and the sling ring (3) is arranged on the top of the sling rod (2).

3. The glass curtain wall hoisting construction equipment according to claim 1, characterized in that: The pressure detection assembly comprises a pressure sensor, a control unit, an indicator light (12) and a power supply unit; the pressure sensor, the control unit and the indicator light (12) are electrically connected via a signal line, and the indicator light (12) is fixed to the top of the adsorption cylinder (11).

4. The glass curtain wall hoisting construction equipment according to claim 1, characterized in that: A movable baffle (7) is provided on one side of the L-shaped receiving frame (6), and rotating shafts (33) are fixed on both sides of the movable baffle (7). The rotating shafts (33) are installed on the inner walls of both sides of the L-shaped receiving frame (6) through springs; and the flexible pad (34) is located between the L-shaped receiving frame (6) and the movable baffle (7).

5. The glass curtain wall hoisting construction equipment according to claim 1, characterized in that: The base comprises: Base (8); The slide rail (9) is fixed to the top of the base (8); a slider (35) adapted to the slide rail (9) is fixed to the bottom of the L-shaped receiving frame (6); the L-shaped receiving frame (6) is slidably connected to the slide rail (9) via the slider (35).

6. A method for hoisting and constructing a glass curtain wall, using the glass curtain wall hoisting and constructing equipment as described in any one of claims 1 to 5, characterized in that: The steps include: S1: According to the actual situation, the adsorption fixing component (4) is installed in the corresponding fixing seat (16), and the adsorption fixing component (4) is fixed by tightening the knob (15); S2: attaching the glass curtain wall panel to be hoisted to one side of the annular suction cup (5); S3: The adjusting screw (17) is screwed by rotating the handle (18), thereby driving the piston (20) to slide in the adsorption cylinder (11), and the glass curtain wall plate is reliably adsorbed and fixed by the annular suction cup (5); S4: Connect the lifting ring (3) with a crane and lift the lifting device to a designated location; S5: The valve housing (13) is guided to be aligned with the push rod (10) and then lowered so that the push rod (10) is inserted into the valve housing (13); S6: using the push rod (10) to push the valve plug (28) upward into the adsorption cylinder (11), so that the gas enters the adsorption cylinder (11), thereby causing the glass curtain wall panel to fall down and be received by the flexible pad (34); S7: Construction workers remove the glass curtain wall panels and then carry out installation.

Citation Information

Patent Citations

  • Hoisting system for glass curtain wall of high-rise building

    CN112141880A

  • Glass attaching executing machine, and glass sucking device

    JP2001019386A

  • Apparatus for railway car window and lift door replacement

    KR101487794B1

  • Multi-purpose plate lifting system with fixing means for descent and acent moving

    KR102190090B1