By accessing photovoltaic and energy storage equipment, predicting the load curve and formulating a load adjustment plan with the maximum revenue target, it solves the problem of industrial users participating in demand response under a high proportion of distributed power sources, achieving the integration of factory resources and improving the reliability of the power grid. .

CN114865639BActive Publication Date: 2024-10-18STATE GRID JIANGSU ELECTRIC POWER CO LTD NANJING POWER SUPPLY COMPANY +1
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
CN202210445942.5
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-04-26
Publication Date
2024-10-18
Estimated Expiration
2042-04-26

AI Technical Summary

Technical Problem

In the presence of a high proportion of distributed power sources, it is difficult for industrial users to effectively participate in demand response activities, fail to fully utilize distributed power sources and energy storage equipment to obtain maximum benefits, and the reliability of the power grid is insufficient.

Method used

By connecting photovoltaic and energy storage equipment to the factory load dispatching system, we collect output information, predict the load curve, calculate the adjustment capacity of each process in the factory at each time, formulate a load adjustment plan with the maximum profit target, and adjust the photovoltaic and energy storage output to optimize the factory load. .

Benefits of technology

It achieves the integration and optimal allocation of factory resources, enhances the reliability of the power grid, and obtains the best participation in demand response by maximizing revenue objectives.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114865639B_ABST
    Figure CN114865639B_ABST
Patent Text Reader

Abstract

The present invention provides a factory load scheduling method based on a high proportion of distributed power sources, including the following steps: connecting photovoltaic and energy storage equipment to the factory load scheduling system, collecting photovoltaic and energy storage output information; predicting the load curve in the factory; calculating the regulation capacity of each process in the factory at each moment to form a load regulation plan; formulating an overall load regulation plan with the maximum benefit target. The present invention integrates factory resources by decomposing user power and load resources, formulates a demand response plan with the maximum benefit as the target, and achieves adaptation to different demand response scenarios. The present invention comprehensively considers the factory load, high access to distributed power sources and energy storage equipment, and proposes a method for obtaining the maximum benefit of participating in demand response in the presence of a high proportion of distributed power sources, thereby realizing factory resource integration and optimal configuration and enhancing the reliability of the power grid.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of factory load scheduling, and in particular to a factory load scheduling method based on a high-proportion distributed power source. Background Art

[0002] Demand Response (DR) is the abbreviation of power demand response. It refers to the short-term behavior of power users changing their inherent habitual electricity consumption patterns after receiving direct compensation notices of induced load reduction or power price increase signals from power suppliers when wholesale electricity market prices rise or system reliability is threatened, so as to reduce or shift the power load in a certain period of time and respond to power supply, thereby ensuring the stability of the power grid and suppressing the rise in electricity prices. With the promotion of dual carbon goals and the development of new energy technologies and energy storage technologies, more and more industrial users have access to distributed power sources such as photovoltaics and wind power, and can also be equipped with energy storage equipment. In this case, industrial users also have a large space for load regulation capabilities, and can participate in demand response activities to obtain additional benefits. Therefore, there is an urgent need for methods to obtain the maximum benefits of participating in demand response in the presence of a high proportion of distributed power sources. Summary of the invention

[0003] In order to overcome the problems of the prior art, the present invention provides a factory load scheduling method based on a high proportion of distributed power sources, which has the advantage of comprehensively considering the factory load, high-access distributed power sources and energy storage equipment, and proposing a method for obtaining the maximum participation in demand response benefits in the presence of a high proportion of distributed power sources, thereby realizing factory resource integration and optimal configuration and enhancing the reliability of the power grid.

[0004] The technical solution of the present invention is as follows:

[0005] A factory load dispatching method based on a high proportion of distributed power sources comprises the following steps:

[0006] 1) Connect photovoltaic and energy storage equipment to the factory load dispatching system to collect output information of photovoltaic and energy storage equipment;

[0007] 2) Predict the load curve within the factory;

[0008] 3) Calculate the regulation capacity of each process in the factory at each time and form a load regulation plan;

[0009] 4) Formulate an overall load regulation plan based on the maximum benefit target;

[0010] 5) Adjust photovoltaic, energy storage output and factory load according to the overall load regulation plan.

[0011] In the step 1), the collected energy storage output information includes the charge and discharge current, charge and discharge voltage, charge and discharge capacity, and charge and discharge times of the energy storage device; the collected photovoltaic device output information includes the photovoltaic output power and output voltage.

[0012] In the step 2), predicting the load curve in the factory includes:

[0013] (2.1) Select the historical energy consumption data of the 10 days before the current day as the data window and calculate the average power load within the data window;

[0014] (2.2) Eliminate weekends, holidays, and dates with an average power load of less than 75% within the data window;

[0015] (2.3) Calculate the total daily electricity consumption and select the five days with the largest total electricity load in the data window as typical days;

[0016] (2.4) Divide a day into T time periods, and calculate the average power load in each T time period of each typical day as the basic predicted power load curve for the day.

[0017] In step 3), calculating the regulating capacity of each process of the factory at each moment includes:

[0018] (3.1) Collect the operating status of each time sequence of the factory;

[0019] (3.2) Determine the regulation potential of a single time sequence based on the start-up time, adjustable time, and maximum load reduction, and form a regulation plan for a single time sequence;

[0020] (3.3) Combine various time-series load regulation plans to form multiple dispatch plans.

[0021] In step 4), formulating a load dispatch plan with the maximum benefit target includes:

[0022] (4.1) Calculate the unit cost of photovoltaic power generation;

[0023] (4.2) Calculate the unit charging and discharging cost of energy storage;

[0024] (4.3) Calculate the cost of each timing control;

[0025] (4.4) Obtain the amount of demand response subsidy;

[0026] (4.5) Formulate load dispatch plans with the maximum profit target in mind.

[0027] The photovoltaic unit power generation cost can be expressed as:

[0028]

[0029] In formula (1), Bde is the photovoltaic power generation cost, I0 is the photovoltaic investment cost, A n is the operation and maintenance cost in year n, D n is the depreciation in year n, B e is the environmental cost per unit of electricity generated, Y n is the electricity generation in year n.

[0030] The unit charging and discharging cost of energy storage can be expressed as:

[0031]

[0032] In formula (2), B sc is the unit charging and discharging cost of the energy storage device, I1 is the investment cost of the energy storage device, A m is the operation and maintenance cost in the mth year, D m is the depreciation in the mth year, a is the number of charge and discharge cycles of the energy storage device, P sc is the capacity of the energy storage device, and θ is the charging and discharging efficiency of the energy storage device.

[0033] The control cost of each time sequence can be calculated according to the unit output of each time sequence.

[0034] The demand response subsidy amount is obtained by connecting with an external demand response issuing agency and receiving a demand response instruction sent by the external demand response issuing agency to obtain the subsidy amount corresponding to the demand response event.

[0035] In step 4), the overall load regulation plan includes comprehensive consideration of the unit power generation cost of photovoltaics, the unit charging and discharging cost of energy storage, the cost of each timing regulation and the amount of demand response subsidy, and calculates the optimal scheduling plan with maximum profit as the constraint condition.

[0036] In the step 5), before executing the overall load regulation plan, it is necessary to receive a demand response instruction sent by an external demand response issuing agency.

[0037] In summary, the beneficial effects of the present invention are as follows: by providing a factory load scheduling method based on a high proportion of distributed power sources, user power and load resources are decomposed, factory resources are integrated, and demand response plans are formulated with the goal of maximum benefit, so as to adapt to different demand response scenarios. The present invention comprehensively considers factory loads, high-access distributed power sources and energy storage equipment, and proposes a method for obtaining the maximum benefit of participating in demand response in the presence of a high proportion of distributed power sources, thereby realizing factory resource integration and optimal configuration, and enhancing the reliability of the power grid. BRIEF DESCRIPTION OF THE DRAWINGS

[0038] Figure 1 It is a flow chart of a factory load scheduling method based on a high-proportion distributed power source provided by the present invention. DETAILED DESCRIPTION

[0039] The specific implementation of the present invention will be described in detail below with reference to the accompanying drawings.

[0040] Example: Reference Figure 1 , a factory load scheduling method based on a high proportion of distributed power sources, comprising the following steps:

[0041] S101, connect photovoltaic and energy storage equipment to the factory load dispatching system to collect photovoltaic and energy storage output information;

[0042] The collected energy storage output information includes the charge and discharge current, charge and discharge voltage, charge and discharge capacity, and charge and discharge times of the energy storage device; the collected photovoltaic output information includes the photovoltaic output power and output voltage.

[0043] S102, predicting the load curve in the factory;

[0044] In this step, the prediction of the load profile within the plant includes the following steps:

[0045] (2.1) Select the historical energy consumption data of the 10 days before the current day as the data window and calculate the average power load within the data window;

[0046] (2.2) Eliminate weekends, holidays, and dates with an average power load of less than 75% within the data window;

[0047] (2.3) Calculate the total daily electricity consumption and select the five days with the largest total electricity load in the data window as typical days;

[0048] (2.4) Divide a day into T time periods, and calculate the average power load in each T time period of each typical day as the basic predicted power load curve for the day.

[0049] S103, calculating the regulation capacity of each process of the factory at each time, and forming a load regulation plan;

[0050] Under this step, the factory's process adjustment capabilities include the following steps:

[0051] (3.1) Collect the operating status of each time sequence of the factory;

[0052] (3.2) Determine the regulation potential of a single time sequence based on the start-up time, adjustable time, and maximum load reduction, and form a regulation plan for a single time sequence;

[0053] (3.3) Combine various time-series load regulation plans to form multiple dispatch plans.

[0054] S104. Formulate an overall load regulation plan based on the maximum benefit target;

[0055] Under this step, the formulation of the overall load regulation plan includes the following steps:

[0056] (4.1) Calculate the unit cost of photovoltaic power generation;

[0057] (4.2) Calculate the unit charging and discharging cost of energy storage;

[0058] (4.3) Calculate the cost of each timing control;

[0059] (4.4) Obtain the amount of demand response subsidy;

[0060] (4.5) Formulate an overall load dispatch plan with the maximum profit target in mind.

[0061] The unit cost of photovoltaic power generation can be expressed as:

[0062]

[0063] In formula (1), B de is the photovoltaic power generation cost, I0 is the photovoltaic investment cost, A n is the operation and maintenance cost in year n, D n is the depreciation in year n, B e is the environmental cost per unit of electricity generated, Y n is the electricity generation in year n.

[0064] The unit charging and discharging cost of energy storage can be expressed as:

[0065]

[0066] In formula (2), B sc is the unit charging and discharging cost of the energy storage device, I1 is the investment cost of the energy storage device, A m is the operation and maintenance cost in the mth year, D m is the depreciation in the mth year, a is the number of charge and discharge cycles of the energy storage device, P sc is the capacity of the energy storage device, and θ is the charging and discharging efficiency of the energy storage device.

[0067] The control cost of each time series can be calculated based on the unit output of each time series.

[0068] To obtain the demand response subsidy amount, you can connect with an external demand response issuing agency and receive the demand response instructions sent by the external demand response issuing agency to obtain the subsidy amount for the corresponding demand response event.

[0069] The overall load regulation plan includes comprehensive consideration of the unit power generation cost of photovoltaics, the unit charging and discharging cost of energy storage, the cost of each timing control, and the amount of demand response subsidies, and calculates the optimal scheduling plan with the maximum profit as the constraint condition.

[0070] S105. Adjust the photovoltaic, energy storage output and factory load according to the overall load adjustment plan.

[0071] Before executing the overall load regulation plan, it is necessary to receive a demand response instruction sent by an external demand response issuing agency and adjust the photovoltaic, energy storage output and factory load according to the overall load regulation plan.

[0072] The above is only a preferred embodiment of the present invention. It should be pointed out that a person skilled in the art can make several modifications and improvements without departing from the inventive concept of the present invention, which all fall within the protection scope of the present invention.

Claims

1. A factory load dispatching method based on a high proportion of distributed power sources, characterized in that: The following steps are involved: 1) Connect photovoltaic and energy storage equipment to the factory load dispatching system to collect photovoltaic and energy storage output information; 2) Predict the load curve within the factory; 3) Calculate the regulation capacity of each process in the factory at each time and form a load regulation plan; 4) Formulate an overall load regulation plan based on the maximum benefit target; 5) Adjust the photovoltaic, energy storage output and factory load according to the overall load adjustment plan; In the step 2), predicting the load curve in the factory includes: (2.1) Select the historical energy consumption data of the 10 days before the current day as the data window and calculate the average power load within the data window; (2.2) Eliminate weekends, holidays, and dates with an average power load of less than 75% within the data window; (2.3) Calculate the total daily electricity consumption and select the five days with the largest total electricity load in the data window as typical days; (2.4) Divide a day into T time periods, calculate the average power load in each T time period of each typical day, and use it as the basic forecast power load curve for that day; In step 3), calculating the adjustment capacity of each process of the factory at each moment includes: (3.1) Collect the operating status of each time sequence of the factory; (3.2) Determine the regulation potential of a single time sequence based on the start-up time, adjustable time, and maximum load reduction, and form a regulation plan for a single time sequence; (3.3) Combining various time-series load regulation plans to form multiple dispatch plans; In step 4), formulating a load dispatch plan with the maximum benefit target includes: (4.1) Calculate the unit cost of photovoltaic power generation; (4.2) Calculate the unit charging and discharging cost of energy storage; (4.3) Calculate the cost of each timing control; (4.4) Obtain the amount of demand response subsidy; (4.5) Formulate load dispatch plans with the maximum profit target in mind.

2. The factory load scheduling method based on high-proportion distributed power sources according to claim 1 is characterized in that: In the step 1), the collecting of energy storage output information includes collecting the charge and discharge current, charge and discharge voltage, charge and discharge capacity, and charge and discharge times of the energy storage device; the collecting of photovoltaic output information includes collecting the output power and output voltage of the photovoltaic device.

3. The factory load dispatching method based on high-proportion distributed power sources according to claim 1 is characterized in that: The photovoltaic unit power generation cost can be expressed as: In formula (1), B de is the photovoltaic power generation cost, I0 is the photovoltaic investment cost, A n is the operation and maintenance cost in year n, D n is the depreciation in year n, B e is the environmental cost per unit of electricity generated, Y n is the electricity generation in year n.

4. The factory load dispatching method based on high-proportion distributed power sources according to claim 1 is characterized in that: The unit charging and discharging cost of energy storage can be expressed as: In formula (2), B sc is the unit charging and discharging cost of the energy storage device, I1 is the investment cost of the energy storage device, A m is the operation and maintenance cost in the mth year, D m is the depreciation in the mth year, a is the number of charge and discharge cycles of the energy storage device, P sc is the capacity of the energy storage device, and θ is the charging and discharging efficiency of the energy storage device.

5. The factory load dispatching method based on high-proportion distributed power sources according to claim 1 is characterized in that: The control cost of each time sequence can be calculated based on the unit output of each time sequence; The demand response subsidy amount is obtained by connecting with an external demand response issuing agency and receiving a demand response instruction sent by the external demand response issuing agency to obtain the subsidy amount corresponding to the demand response event.

6. The factory load dispatching method based on high-proportion distributed power sources according to claim 1 is characterized in that: The overall load regulation plan includes comprehensive consideration of the unit power generation cost of photovoltaics, the unit charging and discharging cost of energy storage, the cost of each timing regulation and the amount of demand response subsidy, and calculates the optimal scheduling plan with maximum profit as the constraint condition.

7. The factory load dispatching method based on high-proportion distributed power sources according to claim 1 is characterized in that: In the step 5), before executing the overall load regulation plan, it is necessary to receive a demand response instruction sent by an external demand response issuing agency.

Citation Information

Patent Citations

  • Source-load-storage coordinated low-carbon economic dispatching method and device

    CN112821397A

  • Load curve adjustment-oriented active power distribution network simulation optimization operation method

    CN113013929A

  • Virtual aggregation system and method for regional energy source complex

    WO2021244000A1