A plunger type orifice plate performance test system and test method
By designing a plunger orifice plate performance test system and using open loops and parallel flow meters, we have solved the problem of domestic plunger orifice plate performance verification, achieved efficient flow-pressure drop performance measurement, supported localization and reduced costs. cost, breaking the foreign technology monopoly.
Patent Information
- Application Number
- CN202110180930.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2021-02-08
- Publication Date
- 2024-10-18
- Estimated Expiration
- 2041-02-08
AI Technical Summary
At present, the performance verification conditions of plunger-type orifice plates in domestic third-generation nuclear power plants are harsh and costly, and imported products cannot fully meet domestic needs, especially in terms of pressure drop accuracy, vibration and noise, resulting in limited development of localization.
Design a plunger orifice plate performance test system, including an open loop, using a deionized water tank, a plunger pump, a spiral tube heater, a plunger orifice plate test section and a pressure relief water tank. Through a parallel flow meter and DC power heater enables measurement and optimization of flow-pressure drop performance curve.
It achieves a wide flow measurement range and high precision, improves test efficiency, reduces operating costs, provides performance testing support for the domestically produced CAP1400 plunger orifice plate, breaks the foreign technology monopoly, and achieves independent intellectual property rights.
Smart Images

Figure CN114910255B_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of orifice plate performance experimental devices, and in particular relates to a plunger type orifice plate performance test system and a test method. Background Art
[0002] There are currently three types of plunger-type orifice plates with different parameters in the AP and CAP series of third-generation nuclear power: nuclear-grade SGS hydrophobic orifice plates, non-nuclear-grade PORV hydrophobic orifice plates, and non-nuclear-grade MSSV hydrophobic orifice plates. Due to the limited engineering applications of such orifice plates in China, harsh performance verification conditions, and high costs, the manufacturing and development of such orifice plates in China are restricted, and currently all rely on imports from the United States. A survey of imported orifice plates revealed that their procurement costs are high, their delivery cycles are long, and they cannot fully meet domestic demand in terms of pressure drop accuracy, vibration, and noise. Therefore, achieving the localization of such orifice plates, solving their key design, manufacturing, and testing technology bottlenecks, and breaking the situation of being restricted by American manufacturers are one of the key tasks in the process of achieving the localization of third-generation nuclear power.
[0003] Focus on the pressure drop accuracy, vibration and noise of the orifice plate, realize independent design, and support the application needs of this type of orifice plate in nuclear power. According to the performance and structural requirements of the CAP1400 plunger orifice plate, CFD technology is used to analyze the flow mechanism and resistance characteristics and perform preliminary structural optimization. The optimized structure is designed and manufactured, and then performance tests are carried out. Build an orifice plate performance test bench to carry out cold and hot tests on the structure after preliminary optimization. Continuously improve and improve the orifice plate structure based on the test results, laying the foundation for the subsequent localization, standardization and productization of this type of plunger orifice plate. Summary of the invention
[0004] The purpose of the present invention is to propose a plunger type orifice plate performance test system, which can reveal the flow-pressure drop relationship characteristics of the plunger type orifice plate under cold, high temperature, low pressure and high pressure states, and provide experimental support for the localization of the plunger type orifice plate used in the third-generation nuclear power CAP1400.
[0005] In order to achieve the above purpose, a plunger type orifice plate performance test system is designed, which is characterized by:
[0006] It includes an open circuit, which includes: a deionized water tank, a plunger pump, a spiral tube heater, a plunger orifice plate test section, and a pressure relief water tank connected by a plurality of pipelines;
[0007] The outlet of the deionized water tank is connected to the inlet of the plunger pump, the inlet and outlet ends of the plunger pump are connected in parallel with a first bypass, and the outlet of the plunger pump outside the first bypass is divided into a main route and a branch route:
[0008] The main line is connected in sequence to the first venturi flowmeter, the spiral tube heater, the plunger-type orifice plate test section, and the pressure relief water tank; the pipelines at the inlet and outlet ends of the plunger-type orifice plate test section are respectively connected in sequence to the first temperature measuring device and the first differential pressure transmitter;
[0009] After the branch is connected to the second Venturi flowmeter, it is merged into the main road between the first Venturi flowmeter and the spiral tube heater; the pipelines at the inlet and outlet ends of the second Venturi flowmeter are respectively connected to the second differential pressure transmitter by using pressure pipes, and the pipeline on the inlet side of the second Venturi flowmeter is also provided with a second temperature measuring device;
[0010] The first venturi flowmeter has a larger measuring range than the second venturi flowmeter;
[0011] The spiral tube heater uses a direct current power supply to heat the deionized water flowing therethrough.
[0012] Furthermore, a first valve is provided on the pipeline between the deionized water tank and the plunger pump; an electric regulating valve is provided on the first bypass; a second valve is provided on the main road on the inlet side of the second bypass; third valves are provided at both ends of the first venturi flowmeter between the inlet and outlet of the second bypass; a fourth valve is provided on the main road on the outlet side of the spiral tube heater; a fifth valve is provided on the pipeline between the first differential pressure transmitter and the pressure relief water tank; and a sixth valve is provided on the inlet side of the branch.
[0013] Furthermore, the spiral tube heater is made of DN50 304 stainless steel tube and is wound in 20 layers with a radius of 500 mm.
[0014] Furthermore, the inlet and outlet of the spiral tube heater are respectively connected to the positive electrode and the negative electrode of the DC power supply.
[0015] Furthermore, the spiral tube heater is heated by loading direct current, with a power of 6MW.
[0016] Furthermore, the first temperature measuring device and the second temperature measuring device respectively use armored K-type thermocouples.
[0017] Furthermore, the deionized water tank and the plunger pump are connected by a stainless steel 304 pipe.
[0018] Furthermore, the fourth valve is another electric regulating valve.
[0019] A test method for a plunger type orifice plate performance test system, characterized in that the following method is adopted:
[0020] Before the experiment begins, open the first valve at the outlet of the deionized water tank and the electric regulating valve on the first bypass. If the measured operating flow rate is less than 100kg / h, open the third valve on the inlet and outlet sides of the first Venturi flowmeter. If the measured operating flow rate is greater than 100kg / h, open the inlet valve of the second Venturi flowmeter, open the fourth valve at the inlet of the plunger-type orifice plate test section and the fifth valve at the outlet. After that, perform the following operations according to different tests:
[0021] If the cold test is conducted with a flow rate less than 100kg / h, start the plunger pump, slowly adjust the opening of the electric control valve to increase the pressure of the open circuit as a whole, measure the flow rate on the main circuit through the first Venturi flowmeter on the main circuit, and record the data of the first differential pressure transmitter at the same time; continuously adjust the opening of the electric control valve to form a pressure increase curve of the open circuit, and record the flow curve of the first Venturi flowmeter and the pressure drop curve of the first differential pressure transmitter at the same time, and finally form the flow-pressure drop performance curve of the plunger-type orifice plate;
[0022] If a cold test is conducted with a flow rate greater than 100kg / h, the plunger pump is turned on again, and the opening of the electric control valve is slowly adjusted to increase the pressure of the open circuit as a whole. The flow rate on the main circuit is measured by the second Venturi flowmeter on the branch circuit, and the data of the second differential pressure transmitter is recorded at the same time. The opening of the electric control valve is continuously adjusted to form a pressure increase curve of the open circuit, and the flow curve of the first Venturi flowmeter and the pressure drop curve of the second differential pressure transmitter are recorded at the same time, and finally the flow-pressure drop performance curve of the plunger-type orifice plate is formed.
[0023] If a hot test is conducted with a flow rate less than 100kg / h, start the plunger pump, slowly adjust the opening of the electric control valve to increase the pressure of the open circuit as a whole, turn on the DC power supply, adjust the heating power of the spiral tube heater, monitor the temperature measured by the first temperature measuring device at the outlet of the entire spiral tube heater and the pressure at the inlet of the plunger orifice plate test section, and when the test conditions are met, record the main flow measured by the first venturi flowmeter of the main road, and read the differential pressure value of the first differential pressure transmitter at the same time, continuously adjust the opening of the electric control valve to form a pressure increase curve for the open circuit, and record the flow curve of the first venturi flowmeter and the differential pressure curve of the first differential pressure transmitter at the same time, and finally form the flow-pressure drop performance curve of the orifice plate;
[0024] If a hot test with a flow rate greater than 100kg / h is conducted, the plunger pump is turned on, and the opening of the electric control valve is slowly adjusted to increase the pressure of the open circuit as a whole. The DC power supply is turned on, and the heating power of the spiral tube heater is adjusted. The temperature measured by the first temperature measuring device at the outlet of the entire spiral tube heater and the pressure at the inlet of the plunger orifice test section are monitored. When the test conditions are met, the main flow measured by the second venturi flowmeter of the branch is recorded, and the differential pressure value of the second differential pressure transmitter is read at the same time. The opening of the electric control valve is continuously adjusted to form a pressure increase curve for the open circuit. At the same time, the flow curve of the second venturi flowmeter and the differential pressure curve of the second differential pressure transmitter are recorded to finally form the flow-pressure drop performance curve of the orifice.
[0025] Furthermore, the pressure range of the open loop is 0.1-20 MPa, and the spiral tube heater is used for heating, so that the maximum operating temperature of the open loop can reach 350°C.
[0026] The beneficial effects of the present invention are as follows: the parallel flowmeter is adopted, which has a wide flow measurement range and high precision, and can meet the measurement requirements of nuclear-grade and non-nuclear-grade orifice plates; the DC power heater is adopted, and the heating rate is greatly improved, which greatly improves the test efficiency; the power load can be accurately adjusted according to the flow requirements, and the test bench operation cost is greatly reduced; the CAP1400 plunger-type orifice plate with independent intellectual property rights developed for my country solves the performance test problem, breaks the foreign monopoly on this technology, and realizes the localization of this type of plunger-type orifice plate. BRIEF DESCRIPTION OF THE DRAWINGS
[0027] Figure 1 It is a schematic diagram of the process of the present invention. DETAILED DESCRIPTION
[0028] The present invention will now be further described with reference to the accompanying drawings.
[0029] Example 1
[0030] See also Figure 1 The present invention provides a plunger type orifice plate performance test system, characterized in that:
[0031] The open circuit includes: a deionized water tank 1, a plunger pump 2, a spiral tube heater 3, a plunger orifice plate test section 4, and a pressure relief water tank 5 connected by a plurality of pipelines; in this example, the spiral tube heater 3 is made of DN50 304 stainless steel pipe with a radius of 500 mm and wound in 20 layers;
[0032] The outlet of the deionized water tank 1 is connected to the first valve 81 and the plunger pump 2 in sequence. The inlet and outlet ends of the plunger pump 2 are connected in parallel to the first bypass. The first bypass is provided with an electric regulating valve 82. The outlet of the plunger pump 2 outside the first bypass is connected by a three-way pipe to form a main route and a branch route:
[0033] The main path is connected in sequence to the second valve 83, the first venturi flowmeter 6, the spiral tube heater 3, the fourth valve 86, the first temperature measuring device 41 on the inlet side, the first differential pressure transmitter 42 on the inlet side, the plunger-type orifice plate test section 4, the first temperature measuring device 41 on the outlet side, the first differential pressure transmitter 42 on the outlet side, the fifth valve 87, and the pressure relief water tank 5;
[0034] After the branch is connected to the second Venturi flowmeter 7, it is merged into the main road between the first Venturi flowmeter 6 and the spiral tube heater 3; the pipelines at the inlet and outlet ends of the second Venturi flowmeter 7 are respectively connected to the second differential pressure transmitter 72 by pressure pipes, and the pipeline on the inlet side of the second Venturi flowmeter 7 is also provided with a second temperature measuring device 71; the inlet side of the branch is provided with a sixth valve 88;
[0035] The measuring range of the first venturi flowmeter 6 is greater than that of the second venturi flowmeter 7;
[0036] The spiral tube heater 3 uses a DC power supply to heat the deionized water flowing through it, that is, the positive and negative electrodes of the DC power supply are connected to the inlet and outlet of the spiral tube heater 3 respectively, and the spiral tube heater 3 is heated by loading DC power, with a power of 6MW.
[0037] Furthermore, the first temperature measuring device 41 and the second temperature measuring device 71 respectively adopt armored K-type thermocouples.
[0038] Furthermore, the deionized water tank 1 and the plunger pump 2 are connected by a stainless steel 304 pipe.
[0039] Furthermore, the fourth valve 86 is another electric regulating valve.
[0040] Example 2
[0041] A test method for a plunger type orifice plate performance test system, characterized in that the following method is adopted:
[0042] Before the experiment begins, open the first valve 81 at the outlet of the deionized water tank 1 and the electric regulating valve 82 on the first bypass. If the measured operating flow rate is less than 100 kg / h, open the third valve 84 on the inlet and outlet sides of the first venturi flowmeter 6; if the measured operating flow rate is greater than 100 kg / h, open the inlet side valve 88 of the second venturi flowmeter 7, open the fourth valve 86 at the inlet of the plunger-type orifice plate test section 4 and the fifth valve 87 at the outlet; then, perform the following operations according to different tests:
[0043] If a cold test is conducted with a flow rate less than 100 kg / h, the plunger pump 2 is turned on, and the opening of the electric regulating valve 82 is slowly adjusted to increase the pressure of the open circuit as a whole. The flow rate on the main circuit is measured by the first venturi flowmeter 6 on the main circuit, and the data of the first differential pressure transmitter 42 is recorded at the same time; the opening of the electric regulating valve 82 is continuously adjusted to form a pressure increase curve of the open circuit, and the flow curve of the first venturi flowmeter 6 and the pressure drop curve of the first differential pressure transmitter 42 are recorded at the same time, and finally the flow-pressure drop performance curve of the plunger-type orifice plate is formed;
[0044] If a cold test is conducted with a flow rate greater than 100 kg / h, the plunger pump 2 is turned on again, and the opening of the electric regulating valve 82 is slowly adjusted to increase the pressure of the open circuit as a whole. The flow rate on the main circuit is measured by the second venturi flowmeter 7 on the branch circuit, and the data of the second differential pressure transmitter 72 is recorded at the same time; the opening of the electric regulating valve 82 is continuously adjusted to form a pressure increase curve of the open circuit, and the flow curve of the first venturi flowmeter 6 and the pressure drop curve of the second differential pressure transmitter 72 are recorded at the same time, and finally the flow-pressure drop performance curve of the plunger-type orifice plate is formed;
[0045] If a hot test with a flow rate less than 100kg / h is conducted, the plunger pump 2 is turned on, and the opening of the electric regulating valve 82 is slowly adjusted to increase the pressure of the open circuit as a whole. The DC power supply is turned on, and the heating power of the spiral tube heater 3 is adjusted. The temperature measured by the first temperature measuring device 41 at the outlet of the entire spiral tube heater 3 and the pressure at the inlet of the plunger orifice plate test section 4 are monitored. When the test conditions are met, the main road flow measured by the first venturi flowmeter 6 of the main road is recorded, and the differential pressure value of the first differential pressure transmitter 42 is read at the same time. The opening of the electric regulating valve 82 is continuously adjusted to form a pressure increase curve of the open circuit. At the same time, the flow curve of the first venturi flowmeter 6 and the differential pressure curve of the first differential pressure transmitter 42 are recorded, and finally the flow-pressure drop performance curve of the orifice plate is formed;
[0046] If a hot test with a flow rate greater than 100kg / h is conducted, the plunger pump 2 is turned on, and the opening of the electric control valve 82 is slowly adjusted to increase the pressure of the open circuit as a whole. The DC power supply is turned on, the heating power of the spiral tube heater 3 is adjusted, and the temperature measured by the first temperature measuring device 41 at the outlet of the entire spiral tube heater 3 and the pressure at the inlet of the plunger orifice test section 4 are monitored. When the test conditions are met, the main flow measured by the second venturi flowmeter 7 of the branch is recorded, and the differential pressure value of the second differential pressure transmitter 72 is read at the same time. The opening of the electric control valve 82 is continuously adjusted to form a pressure increase curve for the open circuit. At the same time, the flow curve of the second venturi flowmeter 7 and the differential pressure curve of the second differential pressure transmitter 72 are recorded to finally form the flow-pressure drop performance curve of the orifice.
[0047] The plunger type orifice plate performance test system can use the plunger pump 2 to increase the pressure, and the open circuit pressure range is 0.1-20MPa. The spiral tube heater 3 is used for heating, so that the maximum operating temperature of the open circuit can reach 350°C.
Claims
1. A plunger type orifice plate performance test system, characterized in that: The open circuit comprises: a deionized water tank (1), a plunger pump (2), a spiral tube heater (3), a plunger orifice plate test section (4), and a pressure relief water tank (5) connected by a plurality of pipelines; The outlet of the deionized water tank (1) is connected to the inlet of the plunger pump (2), the inlet and outlet ends of the plunger pump (2) are connected in parallel to a first bypass, and the outlet of the plunger pump (2) outside the first bypass is divided into a main route and a branch route: The main line is connected in sequence to a first venturi flowmeter (6), a spiral tube heater (3), a plunger-type orifice plate test section (4), and a pressure relief water tank (5); the pipelines at the inlet and outlet ends of the plunger-type orifice plate test section (4) are respectively connected in sequence to a first temperature measuring device (41) and a first differential pressure transmitter (42); After the branch is connected to the second Venturi flowmeter (7), it is merged into the main road between the first Venturi flowmeter (6) and the spiral tube heater (3); the pipelines at the inlet and outlet ends of the second Venturi flowmeter (7) are respectively connected to a second differential pressure transmitter (72) by means of a pressure lead pipe, and the pipeline on the inlet side of the second Venturi flowmeter (7) is also provided with a second temperature measuring device (71); The measuring range of the first Venturi flowmeter (6) is greater than that of the second Venturi flowmeter (7); The spiral tube heater (3) uses a direct current power supply to heat the deionized water flowing through it.
2. A plunger type orifice plate performance test system as claimed in claim 1, characterized in that: A first valve (81) is provided on the pipeline between the deionized water tank (1) and the plunger pump (2); an electric regulating valve (82) is provided on the first bypass; a second valve (83) is provided on the main road on the inlet side of the second bypass; third valves (84) are provided at both ends of the first venturi flowmeter (6) between the inlet and outlet of the second bypass; a fourth valve (86) is provided on the main road on the outlet side of the spiral tube heater (3); a fifth valve (87) is provided on the pipeline between the first differential pressure transmitter (42) and the pressure relief water tank (5); and a sixth valve (88) is provided on the inlet side of the branch road.
3. A plunger type orifice plate performance test system as claimed in claim 1, characterized in that: The spiral tube heater (3) is made of DN50 304 stainless steel tube and is wound in 20 layers with a radius of 500 mm.
4. A plunger type orifice plate performance test system as claimed in claim 1, characterized in that: The inlet and outlet of the spiral tube heater (3) are respectively connected to the positive electrode and the negative electrode of a DC power supply.
5. A plunger type orifice plate performance test system as claimed in claim 1, characterized in that: The spiral tube heater (3) is heated by loading direct current, with a power of 6 MW.
6. A plunger type orifice plate performance test system as claimed in claim 1, characterized in that: The first temperature measuring device (41) and the second temperature measuring device (71) respectively use armored K-type thermocouples.
7. A plunger type orifice plate performance test system as claimed in claim 1, characterized in that: The deionized water tank (1) and the plunger pump (2) are connected by a stainless steel 304 pipe.
8. A plunger type orifice plate performance test system as claimed in claim 2, characterized in that: The fourth valve (86) is another electric regulating valve.
9. A method for testing a plunger type orifice plate performance test system as claimed in claim 2, characterized in that: Use the following method: Before the experiment begins, the first valve (81) at the outlet of the deionized water tank (1) and the electric regulating valve (82) on the first bypass are opened. If the measured operating flow rate is less than 100 kg / h, the third valve (84) at the inlet and outlet sides of the first venturi flowmeter (6) is opened; if the measured operating flow rate is greater than 100 kg / h, the inlet side valve (88) of the second venturi flowmeter (7) is opened, and the fourth valve (86) at the inlet and the fifth valve (87) at the outlet of the plunger-type orifice plate test section (4) are opened; thereafter, the following operations are performed according to different tests: If a cold test is conducted with a flow rate less than 100 kg / h, the plunger pump (2) is turned on, and the opening of the electric control valve (82) is slowly adjusted to increase the pressure of the open circuit as a whole. The flow rate on the main circuit is measured by the first venturi flowmeter (6) on the main circuit, and the data of the first differential pressure transmitter (42) is recorded at the same time. The opening of the electric control valve (82) is continuously adjusted to form a pressure increase curve of the open circuit, and the flow curve of the first venturi flowmeter (6) and the pressure drop curve of the first differential pressure transmitter (42) are recorded at the same time, and finally a flow-pressure drop performance curve of the plunger-type orifice plate is formed. If a cold test is conducted with a flow rate greater than 100 kg / h, the plunger pump (2) is turned on again, and the opening of the electric control valve (82) is slowly adjusted to increase the pressure of the open circuit as a whole. The flow rate on the main circuit is measured by the second venturi flowmeter (7) on the branch circuit, and the data of the second differential pressure transmitter (72) is recorded at the same time. The opening of the electric control valve (82) is continuously adjusted to form a pressure increase curve of the open circuit, and the flow curve of the first venturi flowmeter (6) and the pressure drop curve of the second differential pressure transmitter (72) are recorded at the same time, and finally a flow-pressure drop performance curve of the plunger-type orifice plate is formed. If a hot test is conducted with a flow rate less than 100 kg / h, the plunger pump (2) is turned on, the opening of the electric control valve (82) is slowly adjusted to increase the pressure of the open circuit as a whole, the DC power supply is turned on, the heating power of the spiral tube heater (3) is adjusted, the temperature measured by the first temperature measuring device (41) at the outlet of the entire spiral tube heater (3) and the pressure at the inlet of the plunger orifice plate test section (4) are monitored, and when the test conditions are met, the main flow measured by the first venturi flowmeter (6) of the main road is recorded, and the differential pressure value of the first differential pressure transmitter (42) is read at the same time, and the opening of the electric control valve (82) is continuously adjusted to form a pressure increase curve of the open circuit, and the flow curve of the first venturi flowmeter (6) and the differential pressure curve of the first differential pressure transmitter (42) are recorded at the same time, and finally the flow-pressure drop performance curve of the orifice plate is formed; If a hot test with a flow rate greater than 100 kg / h is conducted, the plunger pump (2) is turned on, the opening of the electric control valve (82) is slowly adjusted to increase the pressure of the open circuit as a whole, the DC power supply is turned on, the heating power of the spiral tube heater (3) is adjusted, the temperature measured by the first temperature measuring device (41) at the outlet of the entire spiral tube heater (3) and the pressure at the inlet of the plunger orifice plate test section (4) are monitored, and when the test conditions are met, the main flow measured by the second venturi flowmeter (7) of the branch is recorded, and the differential pressure value of the second differential pressure transmitter (72) is read at the same time, and the opening of the electric control valve (82) is continuously adjusted to form a pressure increase curve of the open circuit, and the flow curve of the second venturi flowmeter (7) and the differential pressure curve of the second differential pressure transmitter (72) are recorded at the same time, and finally the flow-pressure drop performance curve of the orifice plate is formed.
10. A method for testing a plunger type orifice plate performance test system as claimed in claim 2, characterized in that: The pressure range of the open circuit is 0.1-20 MPa. The spiral tube heater (3) is used for heating, so that the maximum operating temperature of the open circuit can reach 350°C.
Citation Information
Patent Citations
Plunger type pore plate performance test system
CN215448418U