A risk dispatching method considering dynamic frequency security in multiple regions

Through the two-stage risk scheduling method, combined with robust optimization and conditional risk value theory, the problem of inconsistent frequency changes after wind power access in multi-region power grids is solved, and the uncertainty of wind power output and frequency safety is taken into account, which improves the power grid Dynamic frequency security.

CN114925540BInactive Publication Date: 2024-11-05NORTH CHINA ELECTRIC POWER UNIV
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202210619602.X
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-06-02
Publication Date
2024-11-05
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

After large-scale wind power is connected to the power system, the frequency changes in multiple regions are inconsistent due to uneven inertia distribution, making it difficult to effectively defend against frequency instability accidents.

Method used

A two-stage risk scheduling method is proposed. By constructing a multi-region frequency dynamic security constraint set, combining robust optimization and conditional risk value theory, the risk scheduling model is dismantled into two parts: pre-scheduling and rescheduling, and the uncertainty of wind power output is handled separately. and frequency security defense, using column and constraint generation algorithms for solving.

Benefits of technology

In the wind power access scenario, it realizes scheduling that takes into account the uncertainty of wind power output and dynamic safety of multi-region frequency, improves the economic and safety of the system, and clearly defines the responsibilities of backup capacity and optimizes the allowable consumption range of wind power, effectively Defense against frequency instability accidents.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114925540B_ABST
    Figure CN114925540B_ABST
Patent Text Reader

Abstract

The large-scale wind power grid connection has aggravated the problem of uneven inertia distribution among different regions, bringing challenges to the frequency security defense of multi-regional systems. The present invention proposes a two-stage risk scheduling model that takes into account the uncertainty of wind power output and the dynamic safety of multi-regional frequencies. The first stage is based on the conditional risk value theory to collaboratively optimize the operating costs and operating risks of the multi-regional system, and obtain the acceptable safety boundary of wind power. In the second stage, a dynamic safety check of multi-regional frequencies is performed under severe wind power scenarios. The reserve capacity is decoupled into non-accident reserve and accident reserve, which are nested in the two-stage model respectively to clarify the solution ideas. Finally, the two-stage optimization problem is solved by the column and constraint generation algorithm. The simulation verification of the example shows that the model and method proposed in the present invention can effectively improve the frequency response capability of the multi-regional system and ensure safe and economical operation.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of power system risk dispatching and frequency security defense, and specifically refers to a risk dispatching method that takes into account the dynamic security of multi-regional frequencies. Background Art

[0002] By the end of 2020, my country's wind power installed capacity has reached 281 million kilowatts. By 2030, my country's wind power installed capacity will be further increased. Since wind turbines themselves do not have synchronous inertia and frequency regulation capabilities, a large number of replacement synchronous units will lead to poor system frequency response characteristics, reduced power disturbance resistance, and prominent frequency safety issues, such as the Jinsu DC bipolar blocking in East my country Power Grid on September 9, 2015, the "9.28" blackout in South Australia in 2016, and the "8.9" blackout in the UK in 2019. The occurrence of these frequency instability accidents is mainly attributed to the insufficient inertia support capacity of the power system caused by the large-scale grid connection of new energy units. The multi-regional interconnected system can achieve mutual assistance of frequency regulation resources between different regions through power interaction through interconnection lines. Therefore, it is of great significance to study the consideration of frequency safety defense in the multi-regional power grid dispatching plan under the background of large-scale wind power access for the proactive prevention of frequency instability accidents. Summary of the invention

[0003] The technical problem to be solved by the present invention is to provide a risk scheduling method that takes into account the dynamic safety of multi-regional frequencies.

[0004] In order to solve the above technical problems, the technical solution provided by the present invention is: a risk scheduling method considering dynamic safety of multi-regional frequencies, comprising the following methods:

[0005] S1, starting from the three indicators of frequency drop rate at the initial moment, the lowest point frequency deviation and the quasi-steady-state frequency deviation, a multi-region frequency dynamic safety constraint set is constructed.

[0006] S2, introduces the multi-regional frequency dynamic security constraint set into the day-ahead risk dispatch model, and decomposes it into the day-ahead risk dispatch based on the wind power forecast value and the anticipated disturbance verification considering the wind power uncertainty and multi-regional frequency security. It can also be simplified as a two-layer optimization of pre-dispatch-reschedule. The former focuses on economy and the latter focuses on safety, which can achieve a balance between the two.

[0007] In order to solve the problem of uncertainty in wind power output and inconsistent frequency changes in multiple regions after disturbance, the reserve capacity is decoupled into non-accident reserve and accident reserve. The former is used to cope with the fluctuation of wind power output during normal operation, and the latter is used for emergency frequency regulation in the scenario of large power shortage in the system. Among them, the non-accident reserve is solved in the first stage unit combination part to deal with the fluctuation of wind power based on the predicted value. The design of the accident reserve capacity is mainly reflected in the primary frequency regulation reserve, which is solved in the second stage expected disturbance verification part. The two responsibilities are clear. The two-stage problems are coupled with each other and solved alternately. The inertia mutual assistance between different regions is achieved through scheduling, and the economy and safety of the multi-regional system are coordinated.

[0008] S3, the pre-dispatch stage dispatches thermal power output and non-accident reserve and the transmission power of regional interconnection lines according to the wind power forecast value, with the goal of minimizing the total operating cost, non-accident reserve cost and operating risk of each regional subsystem. A piecewise linearization function is used to characterize the operating cost and startup cost of thermal power units.

[0009] S4, the constraints in the pre-dispatch phase include the upper and lower limits of the active output of thermal power units, the minimum start and stop time constraints of thermal power units, the climbing constraints of thermal power units, the positive and negative standby constraints, the wind power output limit constraints, the active power balance constraints, the DC power flow constraints of the sending and receiving end power grids, and the regional interconnection line constraints. Based on the flexible and controllable characteristics of DC interconnection lines, the regional interconnection line type considered in the constructed model is a DC interconnection line.

[0010] S5, based on the idea of ​​robust optimization, in the worst wind power scenario within the allowable absorption range of wind power generators, a multi-regional frequency dynamic safety check is performed in the form of expected power shortage. The max-min double-layer optimization problem of the second-stage scheduling is converted into a max single-layer problem using the strong duality theory. In order to make the dual problem solvable, slack variables representing wind abandonment and load loss are introduced into the constraints, and the objective function is to minimize the slack variables and the primary frequency regulation reserve capacity. When the two introduced slack variables are iterated to zero, it means that wind abandonment and load shedding will not occur in the worst scenario within the allowable absorption range of wind power generators obtained in the first stage, and the purpose of optimizing the allowable absorption range of wind power generators is indirectly achieved. The convergence of slack variables to zero is a sign of stopping the two-stage scheduling iteration.

[0011] S6, the constraints in the rescheduling phase include two parts: basic power adjustment constraints and frequency safety verification constraints.

[0012] In the frequency security verification problem of the second stage, it is assumed that the power shortage has the same effect as the sudden increase in load. The expected disturbance is set to 10% of the total regional load in each time period for verification. Combined with the start and stop conditions of the units obtained in the first stage, the dynamic frequency security of the regional power system is guaranteed by arranging a frequency regulation reserve capacity.

[0013] Since it is necessary to solve the problems of uncertainty in wind power output and frequency security defense in multi-regional systems, in order to have a clear division of labor, it is necessary to split the reserve capacity into non-accident reserve and accident reserve. Among them, non-accident reserve is intended to deal with the uncertainty of wind power output, and accident reserve is intended to deal with frequency security issues under large power shortage events. Among them, accident reserve is mainly reflected in primary frequency regulation reserve. The primary frequency regulation reserve variable mainly exists in the multi-regional frequency dynamic security constraint set, and also includes the upper and lower limit constraints of the primary frequency regulation reserve.

[0014] S7, two-stage dispatch model optimization solution, considering the uncertainty of wind power output and dynamic frequency safety, split it into the main problem of unit combination under wind power forecast scenario and the sub-problem of safety feasibility verification under wind power forecast error scenario, and construct a two-stage robust optimization model to take into account both economy and safety. The column and constraint generation algorithm is used for solution.

[0015] After adopting the above structure, the present invention has the following advantages: In view of the problem that the frequency changes between different regions of the multi-region system are inconsistent after being disturbed due to the uneven distribution of inertia in the scenario of large-scale wind power access, the present invention proposes a two-stage risk scheduling model that takes into account the uncertainty of wind power output and the dynamic safety of multi-regional frequencies. Its characteristics are: (1) Combining the risk scheduling of multi-regional power grids with frequency safety defense, based on the idea of ​​robust optimization and the conditional risk value theory, a two-stage risk scheduling model of day-ahead scheduling and frequency dynamic safety verification is constructed; (2) The idea of ​​decoupling spare capacity is proposed, and the spare capacity is decoupled into non-accident spare and accident spare, which are nested in the two-stage scheduling model respectively, so that the responsibilities of the two are clear and the solution ideas are clear. Finally, the column and constraint generation algorithm is used to solve the scheduling model, and the modified two-region 12-node interconnected system and the two-region RTS-79 system are used as examples to test the effectiveness of the constructed model. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] Figure 1 It is a schematic diagram of the wind power output probability density curve of the present invention.

[0017] Figure 2 It is a schematic diagram of the dynamic frequency characteristics of the power system of the present invention.

[0018] Figure 3 It is a schematic diagram of the dynamic spatiotemporal distribution characteristics of the power system frequency of the present invention.

[0019] Figure 4 It is a schematic diagram of the inconsistent frequency oscillation in different regions of the present invention.

[0020] Figure 5 It is a schematic diagram of the solution obtained by the C&CG algorithm of the present invention.

[0021] Figure 6 It is a schematic diagram of a two-region 12-node interconnection system of Example 1 of the present invention.

[0022] Figure 7 It is a schematic diagram of the economic cost comparison of different scheduling modes in Example 1 of the present invention.

[0023] Figure 8 It is a schematic diagram of the economic cost comparison of different wind power proportions in the sending-end system in Example 1 of the present invention.

[0024] Fig. 9 It is a schematic diagram of the lowest point frequencies of different scheduling modes in Example 1 of the present invention.

[0025] Fig.10 It is a schematic diagram of the positive and negative standby configurations of different scheduling modes in Example 1 of the present invention.

[0026] Fig.11 It is a schematic diagram of the allowable consumption range of the wind farm in Example 1 of the present invention.

[0027] Fig.12 Schematic diagram of the two-region RTS-79 system of Example 2 of the present invention.

[0028] Fig.13 It is a schematic diagram of the economic cost comparison of different scheduling modes in Example 2 of the present invention.

[0029] Fig.14 It is a schematic diagram of the inertia distribution of the two-region system under different scheduling modes in Example 2 of the present invention.

[0030] Fig.15 It is a schematic diagram of the lowest point frequencies of different scheduling modes in Example 2 of the present invention.

[0031] Fig.16 It is a schematic diagram of interconnection line power transmission under different scheduling modes in Example 2 of the present invention.

[0032] Fig.17 Schematic diagram of economic cost comparison of different optimization methods in Example 2 of the present invention.

[0033] Fig.18 It is a schematic diagram of the impact of the risk cost coefficient on the model in Example 2 of the present invention. DETAILED DESCRIPTION

[0034] The present invention is further described in detail below in conjunction with all the accompanying drawings.

[0035] The present invention constructs a wind power output uncertainty set from three aspects: output interval, time smoothing effect, and spatial clustering effect. The wind power output probability density curve is as follows: Figure 1 shown.

[0036]

[0037] Where: P w,t Wind power output value for dispatching decision; is the predicted value of wind power output; They are respectively the upward and downward adjustment margins of wind power output; are the upward and downward adjustment factors of wind power output, which are 0 / 1 variables; Γ S is the space uncertainty budget, Γ T Unsure budget for time.

[0038] The calculation of the spatiotemporal uncertainty budget parameters is as follows:

[0039]

[0040] Where: Φ is the cumulative probability distribution function of the normal distribution; α is the pre-set significance level (α∈(0,1)); W is the number of wind farms; T is the number of scheduling time periods.

[0041] The grid frequency essentially reflects the balance between power generation and load, and is an important indicator of the quality and safety of power system operation. Frequency dynamic response refers to the transition process from the initial normal state to the new stable state after the active power disturbance. Figure 2 As shown in the figure, it can be roughly divided into three stages: 1. Δt1 is the system inertia response time, which is the frequency regulation dead zone, takes 0 to 5 seconds and only plays a buffering role; 2. Δt2 is the primary frequency response (PFR) stage. When the system frequency deviation exceeds the frequency regulation dead zone and after a short delay, PFR intervenes, which takes 5 to 25 seconds; 3. Δt3 is the stage where the secondary frequency response (SFR) and spare capacity take effect until the frequency returns to the initial value, which takes 30 seconds to 30 minutes.

[0042] First, the frequency-time-space characteristics are qualitatively analyzed, and an IEEE 39-node system model is built in the PSD-BPA software, where the reference frequency is 60Hz and the reference voltage is 100kV. A disturbance is applied at the 29-node load node, causing the load active power to increase from 283.5MW to 500MW, resulting in a large power shortage. The simulation step size is 0.01s. The frequency changes of each generator node after the disturbance are observed, such as Figure 3 As shown in the figure, it can be seen that due to the sudden increase in load, the frequency of each generator node generally shows a downward trend. Among them, the speed and response amplitude of the No. 38 generator set, which is closest to the 29 load node in electrical distance, to perceive the frequency change are the most obvious, and the frequency changes at each generator node are differentiated.

[0043] In a power system with a high proportion of renewable energy access, the system inertia is lower and the power structure in different regions is significantly different, which makes the frequency fluctuation after the disturbance more intense. The frequency spatiotemporal distribution characteristics are more obvious in multi-regional systems. The frequency evolution after a fault in any given region is equal to the frequency evolution of the inertial center plus some inter-regional oscillations, as shown in Figure 4.

[0044] The conditional risk value theory is an effective tool for assessing risk. The present invention assumes that the wind power output at each moment follows a normal distribution with the current moment prediction value as the expected value, and sets the wind power safe operation range as Defined as the allowable consumption interval of wind power, when the wind power output is higher than the upper limit of the allowable consumption interval, there is a risk of wind abandonment, and when the wind power output is lower than the lower limit of the allowable consumption interval, there is a risk of load loss, which can be measured by the conditional risk value:

[0045]

[0046]

[0047] Where: Respectively represent the risk of wind abandonment and the risk of load loss; Pr(P w,t ) represents the probability density function of wind power output distribution; represents the capacity of the wind farm; P w,t They respectively represent the wind power output forecast value, upper and lower fluctuation range, and output dispatch value.

[0048] The total cost of system operation risk in day-ahead dispatch is:

[0049]

[0050] Where: RISK is the total cost of system operation risk in day-ahead scheduling; They are the unit wind curtailment penalty cost and the unit load loss penalty cost respectively.

[0051] For an N-area interconnected system suffering from power shortage disturbance, the frequency variation of each area i can be expressed as:

[0052]

[0053] On this basis, the three indicators of initial frequency drop rate, lowest frequency deviation and quasi-steady-state frequency deviation are rewritten as scenarios that can be applied to multi-region interconnected systems. The universal expressions of the relevant indicators are given below:

[0054] (1) Frequency drop rate at the initial moment

[0055]

[0056] Where: ΔP L is the total power shortage suffered by the multi-regional interconnected system; H is the total inertia of the multi-regional interconnected system; A i With ω i The value of depends on the operating conditions of the system and its value is related to the H i ,ΔP L ,D i P D,i ,PFR i There is a linear relationship.

[0057] The universal expression of the frequency drop rate at the initial moment after linearization is given below:

[0058]

[0059] Where: m is the linearization coefficient obtained using linear regression analysis.

[0060] (2) Minimum frequency deviation

[0061] Disturbed area:

[0062]

[0063] Undisturbed areas:

[0064]

[0065] in:

[0066]

[0067] Where: t nadir is the moment corresponding to the lowest frequency point; I Loss is the set of all disturbed areas; J i is the set of non-disturbed areas connected to the disturbed area i; J Nonloss is the set of all non-disturbed areas; I j is the set of disturbed areas interconnected with the non-disturbed area j; T ij is the electrical stiffness of the tie line between area i and area j; V i ,V j Respectively represent the voltage amplitude at both ends of the tie line; X ij is the transmission reactance between regional tie lines; They respectively represent the steady-state phase angle values ​​at both ends of the tie line before the fault.

[0068] For Δf i (t) The linearization of the single integral and double integral is as follows:

[0069]

[0070]

[0071] The linear regression method is still used to estimate the corresponding correlation coefficients m′ and m″.

[0072] (3) Quasi-steady-state frequency deviation

[0073] There is no obvious relationship between the quasi-steady-state frequency and the regional inertia, which can be expressed as:

[0074]

[0075] Where: Δf ss is the quasi-steady-state frequency; is the maximum limit of the quasi-steady-state frequency; D i is the load damping coefficient of area i; P D,i is the load-side power demand in area i.

[0076] Equations (8), (9), (10), and (14) together constitute the multi-region frequency dynamic security constraint set.

[0077] In the pre-dispatch phase, thermal power output and non-accident reserve as well as the transmission power of regional interconnection lines are dispatched according to the wind power forecast value. Its goal is to minimize the total operating cost, non-accident reserve cost and operating risk of each regional subsystem.

[0078]

[0079] Where: K, W is the collection of multiple sub-regions; They represent the operating cost and startup cost of thermal power units, respectively, and the shutdown cost is negligible; They represent the non-accident standby up and down capacity of thermal power units respectively; They are The corresponding cost coefficient; ε is the system risk cost coefficient; RISK is the system risk cost.

[0080] The present invention adopts a piecewise linearization function to characterize the operating cost of a thermal power unit, as shown in equations (16) to (18). The startup cost of a thermal power unit is shown in equations (19) and (20).

[0081] (i) Operating costs of thermal power units

[0082]

[0083] f k ( P k )=a k +b k Pk +c k ( P k ) 2 (17)

[0084] ρ k,t,l =c k (P k,t,l +P k,t,l-1 )+b k (18)

[0085] Where: u k,t is the start-stop decision variable of the thermal power unit; L is the number of segmented linearization segments of the thermal power unit; ρ k,t,l is the slope of each segment after piecewise linearization; P k,t,l is the output value of each section of the unit; P k is the lower limit of thermal power unit output; a k 、b k and c k Represents the cost coefficient of the output of thermal power units.

[0086] (ii) Start-up costs of thermal power units

[0087]

[0088]

[0089] Where: They represent the hot start cost and cold start cost of thermal power units respectively; They represent the cold start time and minimum shutdown time of the thermal power unit respectively; T is the number of scheduling time periods.

[0090] (iii) Constraints on upper and lower limits of active power output of thermal power units

[0091]

[0092] Where: is the thermal power output value in the pre-dispatch stage; P k They are the upper and lower limits of thermal power unit output respectively.

[0093] (iv) Minimum start and stop time constraints for thermal power units

[0094] The minimum running time constraint is:

[0095]

[0096]

[0097]

[0098] Minimum downtime constraints:

[0099]

[0100]

[0101]

[0102] Where: G k L is the number of time periods that the unit still needs to run continuously at the initial moment; k The number of time periods during which the unit still needs to be shut down continuously at the initial moment; The minimum startup time of the unit; They represent the startup time and shutdown time at the initial scheduling moment respectively; is the operating status of the unit at the initial moment.

[0103] (v) Thermal power unit climbing constraints

[0104]

[0105] Where: DR k , UR k They represent the ramp rate and climbing rate of the thermal power unit respectively; Δt is the scheduling time interval, which is 1.

[0106] (vi) Positive and negative reserve constraints

[0107]

[0108] (ⅶ) Wind power output limitation constraints

[0109]

[0110] Where: It is the wind power output value in the pre-dispatch stage.

[0111] (ⅷ) Active power balance constraints

[0112]

[0113]

[0114] Where: K se , K re Respectively represent the thermal power generation units of the sending and receiving systems; W se , W re They represent the wind turbine sets of the sending and receiving systems respectively; C represents the regional interconnection line set; D se , D re Respectively represent the load node sets of the sending and receiving end systems; P d,t They respectively represent the transmission power of the tie line in the pre-dispatching stage and the power absorbed by the load node.

[0115] (ⅸ) DC power flow constraints of the power grids at the transmitting and receiving ends

[0116]

[0117]

[0118] Where: is the upper limit of branch current; k , Υ w , Υ c , Υ d They represent the power flow transfer factors of thermal power, wind power, tie lines and load nodes respectively.

[0119] (ⅹ) Regional connection line constraints:

[0120] The regional tie line type considered in the model constructed by the present invention is a DC tie line. Based on the flexible and controllable characteristics of the DC tie line, the following regional tie line constraints are set:

[0121]

[0122] Where: They represent the transmission power of the tie lines of the sending and receiving end systems in the pre-scheduling stage respectively; They represent the upper and lower adjustment margins of power transmission of the transmission and receiving end interconnection lines respectively; The upper limit of the power transmission of the tie line; is the upper limit of the tie line power regulation margin; + ,δ - They are respectively the rate limits for upward and downward adjustment of the interconnection line transmission power.

[0123] Based on the idea of ​​robust optimization, in the worst wind power scenario within the allowable absorption range of wind power generators, the multi-regional frequency dynamic safety verification is carried out in the form of expected power shortage. The max-min double-layer optimization problem of the second-stage scheduling is converted into a max single-layer problem using the strong duality theory. In order to make the dual problem solvable, slack variables representing wind abandonment and load loss are introduced into the constraints, and the objective function is to minimize the slack variables and the primary frequency regulation reserve capacity. When the two introduced slack variables are iterated to zero, it means that there will be no wind abandonment and load shedding in the worst scenario within the allowable absorption range of wind power generators obtained in the first stage, and the purpose of optimizing the allowable absorption range of wind power generators is indirectly achieved. The convergence of slack variables to zero is a sign of stopping the two-stage scheduling iteration.

[0124]

[0125] Where: are the relaxation variables for wind curtailment and load loss, respectively; PFR k,t It is the primary frequency regulation reserve capacity.

[0126] (1) Basic power adjustment constraints

[0127]

[0128]

[0129]

[0130]

[0131]

[0132]

[0133]

[0134]

[0135] Formulas (37) and (38) represent the active power balance constraints of the transmission and receiving systems, Formulas (39) and (40) represent the DC power flow constraints in the redispatch stage, Formulas (41) and (42) represent the dispatch output adjustment constraints of thermal power units and regional tie lines, and Formulas (43) and (44) represent the upper and lower limit constraints of wind abandonment and load loss. The superscript u in the formula is the power adjustment symbol in the redispatch stage.

[0136] In the second stage of dispatch, the wind power output needs to be adjusted according to the wind power output obtained in the first stage of dispatch. At this time, the adjustable range of wind power is Based on this, the uncertainty set of wind power in the second phase is constructed:

[0137]

[0138] Where: is the wind power output value obtained in the pre-dispatch stage; is the wind power output value to be requested in the redispatch phase; is the wind power forecast value; is the corresponding value obtained in the first stage.

[0139] (2) Frequency safety verification constraints

[0140] In the frequency security verification problem of the second stage, it is assumed that the power shortage has the same effect as the sudden increase in load. The expected disturbance is set to 10% of the total regional load in each time period for verification. Combined with the start and stop conditions of the units obtained in the first stage, the dynamic frequency security of the regional power system is guaranteed by arranging a frequency regulation reserve capacity.

[0141] The inertia that the regional system can provide in each period of day-ahead scheduling can be expressed by equation (46).

[0142]

[0143] The present invention needs to solve the problems of uncertainty in wind power output and frequency safety defense in multi-regional systems. In order to have a clear division of labor, the reserve capacity needs to be split into non-accident reserve and accident reserve. Among them, the non-accident reserve is intended to deal with the uncertainty of wind power output, and the accident reserve is intended to deal with frequency safety issues under large power shortage events. Among them, the accident reserve is mainly reflected in the primary frequency regulation reserve.

[0144] The primary frequency regulation reserve variables mainly exist in the multi-region frequency dynamic safety constraint set. In addition, the upper and lower limit constraints of the primary frequency regulation reserve are as follows:

[0145]

[0146] Equations (46), (47) and (8), (9), (10), and (14) together constitute the frequency security verification constraints in the rescheduling phase.

[0147] Taking into account the uncertainty of wind power output and the dynamic safety of frequency, it is divided into the main problem of unit combination under the wind power forecast scenario and the sub-problem of safety feasibility verification under the wind power forecast error scenario, and a two-stage robust optimization model is constructed to take into account both economy and safety. The column and constraint generation algorithm is used to solve it, and it is written into a compact mathematical expression as follows:

[0148]

[0149] Where: I is the start and stop variable of the thermal power unit; x 0 is the unit output decision variable of the first stage; pw is the wind power output value; x u is the unit output decision variable in the second stage; s is the relaxation variable introduced in the second stage to test the safety feasibility; zw is the upward and downward adjustment factor of wind power based on the output forecast value, which is a 0 / 1 variable; o " is the matrix product; a,b,c, d,e,f,g,A,B,C,D,E,F are the corresponding coefficient matrices.

[0150] Since the security check sub-problem is a max-min two-level optimization problem and is difficult to solve, the strong duality theory is used to transform it into a max single-level optimization problem as follows:

[0151]

[0152] The solution process of the two-stage risk scheduling model is as follows: Figure 5 shown.

[0153] 1. Initialize the number of iterations n = 1.

[0154] 2. Find the main problem MP and find the optimal solution of the first stage decision variables

[0155] 3. The child-seeking problem SP, Substitute it into the sub-problem to verify the frequency dynamic safety and stable operation of the system. If f T s≠0, return to the infeasible cut to the main problem, update n=n+1, and continue to optimize the solution; if f T s=0, which means that for any wind power output, certain control measures can be used to ensure safe operation and thus obtain the optimal solution. n as follows:

[0156]

[0157] Where: N is the total number of iterations.

[0158] The present invention is specifically implemented:

[0159] First, a two-area 12-node system was used for testing. Figure 6 As shown, the left side is the sending end system and the right side is the receiving end system. Assuming that the power shortage disturbance is applied to the receiving end system, the disturbance is 10% of the total load in the area at the current moment, the maximum limit of the frequency drop rate at the initial moment is 1Hz / s, the minimum frequency limit is 49.2Hz, and the quasi-steady-state frequency is required to be maintained above 49.5Hz within 60s. The sending end area contains two wind farms with a capacity of 100MW and a thermal power unit with a capacity of 200MW. The wind power in this area accounts for 50%. The receiving end area contains two thermal power units with capacities of 200MW and 300MW, respectively, and a wind farm with a capacity of 100MW. The wind power in this area accounts for 16.7%. The total load of the receiving end system is about twice the total load of the sending end system. The transmission power limit of the tie line is 200MW, and the upward and downward adjustment rate limits of the tie line transmission power are set to 15% of the maximum transmission capacity. The penalty costs for unit wind curtailment and load loss are set to $50 / MWh and $500 / MWh respectively, and the risk cost coefficient ε is taken as 1.

[0160] In order to analyze the impact of frequency security constraint sets on multi-regional power grid dispatch, the following three dispatch modes are compared: Mode 1: frequency security constraint sets are not added to the two-region system dispatch model; Mode 2: dynamic security constraint sets of uniform frequency of the whole system are added on the basis of Mode 1; Mode 3: frequency security constraint sets that take into account the inconsistency of dynamic frequency changes in multiple regions are added on the basis of Mode 1.

[0161] Figure 7 The results of three different dispatching modes are analyzed from the perspective of economic cost. From the perspective of total cost, the cost of considering frequency safety verification is higher than the cost of not considering frequency safety verification, and the cost increment is mainly reflected in the accident reserve cost. In order to ensure frequency safety, the system reserves more accident reserves for some thermal power units. Dispatching modes 2 and 3 both consider the frequency safety verification link. The difference between the two is that mode 2 considers the uniform frequency safety constraint of the entire region, and mode 3 considers the multi-region frequency safety constraint. From the perspective of economic cost, the cost difference between the two is not much, but mode 3 provides more flexible accident reserve capacity allocation than mode 2. Mode 2 allocates primary frequency regulation reserve to the two-region system according to the pre-set allocation ratio, assuming that the disturbed end bears no less than 80% of the total primary frequency regulation. The multi-region frequency safety constraint of mode 3 is solved by itself in the resource configuration in each region to determine the inertia and primary frequency regulation reserve in the current region, making the allocation of primary frequency regulation reserve more reasonable and more in line with the actual situation.

[0162] In order to further illustrate the impact of wind power proportion on multi-region system dispatch mode 2 and mode 3, based on the calculation example of 12-node system in two regions, four different wind power proportions of 33.3%, 42.8%, 50% and 60% are applied to the sending end system respectively, and the economic cost difference between mode 2 and mode 3 under these four different wind power proportions is compared. The results are shown in Figure 8. As can be seen from the table, under the premise of unchanged load level and interconnection line transmission channel capacity, increasing the wind power proportion of the sending end system can reduce the cost difference between modes 2 and 3. In other words, considering the multi-regional frequency dynamic safety constraint in mode 3 is more suitable for scenarios with large differences in wind power resource distribution in the sending and receiving end systems. It should be specially noted that when the wind power proportion of the sending end is 33%, the wind farm capacity in the two regions is equal, both 100MW. At this time, there is no obvious sending end and receiving end for the consumption of wind power, that is, the power generation resources and loads in various places tend to be consumed locally, so the economic cost difference between modes 2 and 3 is not obvious.

[0163] Take the case of a 50% wind power system at the sending end as an example. Based on the optimized inertia results of each region and the standby allocation of thermal power units, the SIMULINK software is used to perform simulation analysis to solve the lowest frequency of each region under different dispatching modes. The results are as follows: Fig. 9As shown. As can be seen from the figure, when the sending and receiving systems face a large power shortage at one end, the frequency changes at the lowest points in the two areas are basically consistent. When frequency safety constraints are not considered, it is difficult to ensure the frequency safety of the system by relying solely on non-accident standby as emergency adjustment, and it is very easy to trigger low-frequency load shedding. In the dispatch period of 1h to 16h, the lowest point frequency of mode 3 is significantly higher than that of mode 2. Among them, in the period of 4h to 16h, the lowest point frequency of mode 2 wanders around the minimum limit of 49.2, and its risk of withstanding low-frequency load shedding is higher than that of mode 3. This shows that dispatch mode 3 can better ensure system frequency safety than dispatch modes 1 and 2.

[0164] Fig.10 The figure shows the reserve capacity of dispatching modes 1, 2, and 3 respectively. The blue represents the reserve capacity of the receiving area, and the yellow represents the reserve capacity of the sending area. The increased reserve capacity is the sum of the increased reserve capacity for non-accident reserves and the accident reserve capacity. As can be seen from the figure, the total amount of increased reserve in modes 2 and 3 is significantly larger than that in mode 1, mainly because the latter two have opened more accident reserves to cope with frequency safety verification. The total amount of positive and negative reserves optimized in modes 2 and 3 is equivalent, but the distribution of reserve capacity in the two regional systems is very different. Mode 3 is more inclined to allocate the increased reserve in the disturbed receiving system.

[0165] Taking wind farm 3 in the receiving system as an example, its acceptable safety margin is obtained as follows: Fig.11 The blue line represents the wind power dispatch value obtained after solving the two-stage risk dispatch model. The upper and lower black lines represent the upper and lower boundaries of the wind power permissible consumption range. The upper and lower boundaries are obtained through iterative solution as optimization variables, and are not based on the upper and lower adjustment margins directly given by the predicted values. When the actual wind power output value is higher than the upper limit of the acceptable wind power, there is a risk of wind abandonment, and when it is lower than the lower limit of the acceptable wind power, there is a risk of load loss.

[0166] To further verify the effectiveness of the method proposed in the present invention, the improved two-area RTS-79 system is taken as an example. Fig.12 As shown. There are 48 busbar nodes and 38 thermal power units in the two-region system. The sending-end system contains 10 thermal power units and 3 wind farms with a capacity of 800MW. The wind farms are located at nodes 25, 31 and 42. The proportion of wind power in the sending-end area is as high as 65.2%. The receiving-end system contains 28 thermal power units and no wind power, that is, the proportion of wind power in the receiving-end area is 0. The load level of the receiving-end system is set to 1.7 times the load level of the sending-end system, the transmission power limit of the regional interconnection line is 300MW, and the upward and downward adjustment rate limits of the interconnection line transmission power are set to 30% of the maximum transmission capacity. The penalty costs for unit wind abandonment and load loss are set to $50 / MWh and $500 / MWh respectively, and the risk cost coefficient ε is taken as 1.

[0167] A comparative experiment was conducted on the three dispatching modes in Example 1 in the two-region RTS-79 system to obtain the economic costs under the three different dispatching modes. Fig.13 As shown. Among the three different dispatching modes, Mode 1 does not consider frequency safety and does not allocate a certain amount of reserve capacity to the system. Although the economic cost is low, the safety of the system is sacrificed. Mode 3 is more detailed than Mode 2 in describing the frequency response. Although it increases a part of the accident reserve capacity, it greatly reduces the investment in non-accident reserve, so that the reserve capacity can be allocated on demand. The total cost is only $676 different from Mode 2, and the risk of load loss is reduced to a certain extent. It can be seen that the dispatching mode designed in this paper that considers multi-regional frequency dynamic safety constraints is more suitable for multi-regional systems with obvious differences in wind power resources.

[0168] The following is a comparative analysis of the inertia of the sending and receiving end systems at each moment in the three modes. Fig.14 As shown in the figure, when the receiving system suffers from a large power shortage disturbance, the inertia required by the receiving system remains consistent in dispatching modes 2 and 3. The inertia required by the receiving system in the 2h~5h period is slightly lower than that in mode 1. For the 2h~5h period of the sending system, mode 3 requires more inertia than modes 1 and 2. This shows that in order to ensure frequency safety between regions, mode 3 does not require more units to be turned on in each region to provide more inertia support, but makes full use of the inertia mutual assistance function provided by the interconnection line to achieve flexible allocation of inertia between different regions.

[0169] In order to focus on comparing the frequency dynamic safety of scheduling modes 2 and 3, simulation is used to obtain the lowest point frequency comparison diagram of the large system example under the two modes, as shown in the figure. Fig.15 As shown. It can be seen that in the two-region RTS-79 example, although mode 2 can meet the frequency security of the receiving system at all scheduling times, the lowest frequency in the 8h~24h period in the sending system is significantly lower than 49.2Hz, which is easy to trigger low-frequency load reduction. Mode 3 can maintain the lowest frequency of the system above the limit at most times in both the receiving and sending systems. Therefore, mode 3 is better than mode 2 in terms of frequency security. Since the obtained scheduling scheme is based on the expected disturbance imposed on the receiving system, the optimization result tends to guard the frequency security of the receiving system. Therefore, Fig.15 It can be seen that in the large system example, the frequency security of the receiving system is higher than that of the sending system.

[0170] The total transmission volume of the tie line under different dispatching modes is compared. The results are as follows: Fig.16As shown. In the 24 time periods of day-ahead scheduling, there are 18 time periods in which the total power transmission of modes 2 and 3 is higher than that of mode 1, indicating that considering frequency security constraints can promote energy exchange between regions better than not considering frequency security constraints. Comparing modes 2 and 3 alone, the total power transmission of the interconnection line of mode 3 is basically higher than that of mode 2 in each time period, which can better illustrate the adaptability of mode 3 to the mutual assistance of consumption between different regions by considering multi-regional frequency security constraints.

[0171] In order to illustrate the advantages of the two-stage risk scheduling model proposed in this paper, the model of the present invention is compared with the multi-scenario stochastic optimization method. The economic costs of different optimization methods are shown in Figure 2. Fig.17 As shown. Assuming that the output forecast error of each wind farm in the multi-scenario random optimization method obeys a normal distribution with a mean of 0 and a standard deviation of 4% of the predicted value, 5 typical output scenarios are obtained through Monte Carlo simulation and scenario reduction, and a 95% confidence level is set. The conditional risk value is used to quantify the risk loss faced by the system under different scenarios. From the cost comparison of the two optimization methods in Tables 2-5, it can be seen that the optimization method proposed in the present invention reduces the cost of the multi-scenario random optimization method by 2.2%, which is mainly reflected in the reduction of the cost of load loss risk. The reason is that the model constructed by the present invention considers the acceptable boundary of wind power as the decision variable to be optimized. Due to the high cost of load loss, the acceptable output boundary of wind power will be expanded downward during the optimization process, which can actively avoid the risk of load loss. However, there must be load loss in the typical scenarios simulated and generated by the random optimization method, and the risk of load loss cannot be actively avoided.

[0172] By changing the risk cost coefficient, its impact on the optimization results and model convergence speed is analyzed, and the simulation results are shown in Figure 18. It can be seen that the higher the risk cost coefficient, the higher the cost of non-accident standby, and the total amount of operating risk cost is not lower. The reason is that the setting of non-accident standby itself is to cope with the fluctuation of wind power output under normal operating conditions. The higher the value of the risk cost coefficient, the more the dispatching decision tends to avoid risks, and the risk of wind abandonment and load loss is reduced by setting more non-accident stands, which leads to an increase in non-accident standby costs. However, although the risk of wind abandonment and load loss decreases with the increase of the risk cost coefficient, the unit risk cost is increasing, so the total operating risk cost does not decrease with the increase of the risk coefficient. Summary Fig.18 From the results in , it can be concluded that when the risk cost coefficient is 3, the scheduling results and model convergence effect of the constructed model are the best.

[0173] This paper first analyzes and explains the multi-region frequency dynamic safety constraint set. On this basis, a risk scheduling method considering the dynamic safety of multi-region frequency is proposed, and the solution process of the two-stage scheduling model is described in detail. Finally, the model characteristics are introduced through examples and the advantages of the scheduling method proposed in this invention are explained. The following conclusions can be drawn:

[0174] 1. The combination of frequency dynamic security constraint set based on inconsistent frequency oscillation changes in multiple regions and day-ahead risk scheduling is a refined modeling of the multi-region interconnected system, which has a good guiding role in resource mutual assistance and frequency security defense between regions with different inertia.

[0175] 2. Decoupling the reserve capacity into non-accident reserve and accident reserve can better accommodate it into the scheduling framework, making it easier to balance the handling of wind power uncertainty and the dynamic safety of multi-regional frequency.

[0176] 3. Compared with single-region dynamic frequency security constraints, multi-region dynamic frequency security constraints are more suitable for multi-region systems with a high proportion of wind power and large differences in wind power resource distribution.

[0177] The present invention and its implementation methods are described above, and such description is not restrictive, and the actual structure is not limited thereto. In general, if ordinary technicians in the field are inspired by it, without departing from the purpose of the invention, they can design a structure and implementation method similar to the technical solution without creativity, which should fall within the protection scope of the present invention.

Claims

1. A risk scheduling method considering dynamic safety of multi-regional frequencies, characterized in that: Including the following methods, S1, starting from the three indicators of frequency drop rate at the initial moment, the lowest frequency deviation and the quasi-steady-state frequency deviation, constructs a multi-region frequency dynamic safety constraint set. Where: ΔP L is the total power shortage suffered by the multi-regional interconnected system; H is the total inertia of the multi-regional interconnected system; m is the linearization coefficient obtained by linear regression analysis; t nadir is the moment corresponding to the lowest frequency point; I Loss is the set of all disturbed areas; J i is the set of non-disturbed areas connected to the disturbed area i; J Nonloss is the set of all non-disturbed areas; I j is the set of disturbed areas interconnected with the non-disturbed area j; T ij is the electrical stiffness of the tie line between area i and area j; Δf ss is the quasi-steady-state frequency; is the maximum limit of the quasi-steady-state frequency; D i is the load damping coefficient of area i; P D,i is the load-side power demand of area i; S2, introduces the multi-regional frequency dynamic security constraint set into the day-ahead risk dispatch model, decomposing it into the day-ahead risk dispatch based on wind power forecast value and the expected disturbance check considering wind power uncertainty and multi-regional frequency security, or simply expressing it as a two-layer optimization of pre-dispatch-re-dispatch. The former focuses on economy, while the latter focuses on safety, which can achieve a balance between the two. In order to solve the problem of uncertainty in wind power output and inconsistent frequency changes in multiple regions after disturbance, the reserve capacity is decoupled into non-accident reserve and accident reserve. The former is used to cope with the fluctuation of wind power output in normal operation, and the latter is used for emergency frequency regulation in the scenario of large power shortage in the system. The non-accident reserve is solved in the first stage unit combination part to deal with the fluctuation of wind power based on the predicted value. The design of the accident reserve capacity is reflected in the primary frequency regulation reserve, which is solved in the second stage expected disturbance verification part. The two have clear responsibilities, and the two-stage problems are coupled with each other and solved alternately. Through scheduling, the inertia mutual assistance between different regions is achieved, and the economy and safety of the multi-regional system are coordinated. S3, the pre-dispatch stage dispatches thermal power output and non-accident reserve as well as the transmission power of regional interconnection lines according to the wind power forecast value. Its goal is to minimize the total operating cost, non-accident reserve cost and operating risk of each regional subsystem. The piecewise linearization function is used to characterize the operating cost and startup cost of thermal power units. S4, the constraints in the pre-dispatch stage include the upper and lower limits of the active output of thermal power units, the minimum start and stop time of thermal power units, the climbing constraints of thermal power units, the positive and negative standby constraints, the wind power output limit constraints, the active power balance constraints, the DC power flow constraints of the sending and receiving end power grids, and the regional interconnection line constraints. The method is based on the flexible and controllable characteristics of DC interconnection lines. The type of regional interconnection line considered in the constructed model is DC interconnection line. Where: They represent the transmission power of the tie lines of the sending and receiving end systems in the pre-scheduling stage respectively; They represent the upper and lower adjustment margins of power transmission of the transmission and receiving end interconnection lines respectively; The upper limit of the power transmission of the tie line; is the upper limit of the tie line power regulation margin; + ,δ - They are the upward and downward adjustment rate limits for the transmission power of the tie line respectively; represents the transmission power of the tie line in the pre-scheduling stage; Δt is the scheduling time interval, which is 1; S5, based on the idea of ​​robust optimization, in the worst wind power scenario within the permissible absorption range of wind power, the multi-regional frequency dynamic safety check is carried out in the form of expected power shortage, and the max-min double-layer optimization problem of the second-stage scheduling is converted into a max single-layer problem using strong duality theory. In order to make the dual problem solvable, slack variables representing wind abandonment and load loss are introduced into the constraints, and the objective function is to minimize the slack variables and the primary frequency regulation reserve capacity. When the two slack variables introduced are iteratively zero, it means that no wind abandonment and load shedding will occur in the worst scenario within the permissible absorption range of wind power obtained in the first stage, and the purpose of optimizing the permissible absorption range of wind power is indirectly achieved. The convergence of slack variables to zero is a sign of stopping the two-stage scheduling iteration. S6, the constraints in the rescheduling phase include two parts: basic power adjustment constraints and frequency safety verification constraints. In the second phase of frequency security verification, it is assumed that the power shortage has the same effect as the sudden increase in load, and the expected disturbance is set to 10% of the total regional load in each period for verification. Combined with the start and stop conditions of the units obtained in the first phase, the dynamic frequency security of the regional power system is guaranteed by arranging a frequency regulation reserve capacity. Since it is necessary to solve the problems of uncertainty in wind power output and frequency safety defense in multi-regional systems, in order to make the division of labor clear, the reserve capacity is divided into non-accident reserve and accident reserve. Among them, the non-accident reserve is intended to deal with the uncertainty of wind power output, and the accident reserve is intended to deal with the frequency safety problem under large power shortage events. Among them, the accident reserve is mainly reflected in the primary frequency regulation reserve. The primary frequency regulation reserve variable mainly exists in the multi-regional frequency dynamic safety constraint set. In addition, it also includes the upper and lower limit constraints of the primary frequency regulation reserve. S7, considering the uncertainty of wind power output and dynamic frequency safety, is divided into the main problem of unit combination under the wind power prediction scenario and the sub-problem of safety feasibility verification under the wind power prediction error scenario. A two-stage robust optimization model is constructed, taking into account both economy and safety. The column and constraint generation algorithm is used to solve the problem. The optimization solution of the two-stage scheduling model is as follows: Where: I is the start and stop variable of the thermal power unit; x 0 is the unit output decision variable in the first stage; p w is the wind power output value; x u is the unit output decision variable in the second stage; s is the relaxation variable introduced in the second stage to test the safety feasibility; z w is the upward and downward adjustment factor of wind power based on the output forecast value, which is a 0 / 1 variable; "o" is the matrix product; a, b, c, d, e, f, g, A, B, C, D, E, F are the corresponding coefficient matrices.

2. The risk scheduling method considering dynamic safety of multi-regional frequencies according to claim 1, characterized in that: The dispatch strategy takes into account both the uncertainty of wind power output and the frequency security of multiple regions to prevent the occurrence of frequency instability problems in the scenario of reverse distribution of wind power load.

3. The risk scheduling method considering dynamic safety of multi-regional frequencies according to claim 1, characterized in that: The multi-regional frequency dynamic safety constraint set is introduced into the day-ahead risk scheduling model, and the impact of wind power access uncertainty on the frequency safety of the multi-regional system is analyzed. Based on the conditional risk value theory and robust optimization ideas, a two-stage risk scheduling model is constructed, which includes unit combination based on wind power forecast values ​​and dynamic safety verification of multi-regional frequencies under severe wind power scenarios.

4. The risk scheduling method considering dynamic safety of multi-regional frequencies according to claim 1, characterized in that: The reserve capacity is decoupled into non-accident reserve and accident reserve. The non-accident reserve is designed to cope with the uncertainty of wind power output, and the accident reserve is designed to cope with the frequency safety problem under large power shortage events. The two forms of reserve capacity are integrated into the two-stage model to clarify the modeling ideas and solution process.