A joint optimization scheduling system and method for agricultural product production and cold chain transportation
Through the joint optimization of the scheduling system of agricultural product production and cold chain transportation, the problem of incomplete scheduling of agricultural product production is solved, efficient cold chain transportation of agricultural products and rational utilization of resources is achieved, the shelf life is extended, and the circulation rate and quality are improved.
Patent Information
- Application Number
- CN202210637132.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-06-07
- Publication Date
- 2024-12-03
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
The existing agricultural product production scheduling arrangements are incomplete, resulting in waste of resources and inefficiency. Especially during cold chain transportation, it is difficult to reasonably formulate production time and pre-cooling equipment distribution unevenly, affecting the quality and circulation rate of agricultural products.
Design a joint optimization scheduling system and method for agricultural product production and cold chain transportation, send order information through the user side, upload information through the communication module, and generate production plans and vehicle scheduling plans based on freshness, transportation distance and pre-cooling needs. Scheduling to ensure the optimization of the cold chain transportation path and production plan of agricultural products.
It realizes efficient cold chain transportation of agricultural products, extends shelf life, reduces losses caused by heat, improves the circulation rate and quality of agricultural products, reduces transportation costs, and rationally utilizes resources.
Smart Images

Figure CN114926081B_ABST
Abstract
Description
Technical Field
[0001] The present invention belongs to the technical field of agricultural information engineering, and in particular relates to a system and method for joint optimization scheduling of agricultural product production and cold chain transportation. Background Art
[0002] With the continuous improvement of living standards, people's requirements for the quality of fresh products are also rising. The quality of fresh agricultural products in my country is prominent. The quality of agricultural products is related to the life safety of the people, and it also seriously affects the development of agricultural product production and logistics. For fresh agricultural products that are highly seasonal and perishable, reasonable optimization of scheduling from picking, cold chain transportation to warehousing, the "first kilometer" stage of the agricultural product cold chain, can significantly extend the shelf life.
[0003] As the first step in agricultural product production, the picking production plan can not only effectively reduce the opportunity loss of the planting farm, but also affect the subsequent cold chain transportation. Pre-cooling technology can significantly reduce the loss of products caused by field heat after harvesting, storage and transportation. Studies have shown that the cold chain circulation rate of fresh agricultural products in my country is only 19%, while the loss rate of fruit and vegetable videos in the circulation link reaches 0% to 30%. On the one hand, as the country vigorously promotes the development and construction of modern agriculture, cold storage and cold chain transportation conditions have improved the quality of fruits and reduced losses to a certain extent; but on the other hand, due to the differences in the characteristics of fresh agricultural products and considering the impact on subsequent transportation and pre-cooling, its production time is difficult to reasonably formulate. At the same time, considering the uneven distribution of pre-cooling equipment and the limited capacity of transportation, accurate and efficient production-cold chain transportation scheduling has become a major challenge for the "first kilometer" of the agricultural product cold chain. Summary of the invention
[0004] In order to solve the problem that the existing crop production scheduling is incomplete, resulting in a large amount of resource waste and low efficiency, the present invention proposes a joint optimization scheduling system and method for agricultural product production and cold chain transportation.
[0005] A method for joint optimization and scheduling of agricultural product production and cold chain transportation of the present invention comprises the following steps:
[0006] Step 1: The user terminal sends the order information to the communication module;
[0007] Step 2: The communication module uploads the required agricultural product delivery information to the control module;
[0008] Step 3: The information storage module uploads the collected information to the control module;
[0009] Step 4: After receiving various types of information, the control module executes the agricultural product production and cold chain transportation scheduling method to generate a farm production plan and a vehicle scheduling plan;
[0010] Step 5: The control module uploads the production plan and the vehicle dispatching plan to the communication module and the information storage module respectively. The communication module sends the production plan to each farm, and the communication module sends the vehicle dispatching instruction to the cold chain vehicle. The information storage module updates the farm and vehicle information according to the received production plan and vehicle dispatching plan.
[0011] Step 6: The communication module sends the process information to the user end.
[0012] Furthermore, in step 2, the demanded agricultural product information includes delivery time and location information, freshness information, real-time road traffic information, weather information, cold chain vehicle information and warehouse inventory information.
[0013] Furthermore, in step three, the information collected by the information storage module includes farm product variety information, yield information, farm production capacity hash table data, each node location information and designated node distance information.
[0014] Furthermore, in step 4, the agricultural product production and cold chain transportation scheduling method includes the following steps:
[0015] S41: adding the batch order information of the user end to the task total list;
[0016] S42: For the obtained batch order information, if the customer demand for each product i is D i No more than the excess production capacity D i ≤Q i , where Q i is the total production of all farms producing the commodity, then the order can be produced and S43 will be continued. Otherwise, the order production fails and the task ends. The demand for each commodity is lower than the maximum production capacity, so it can be produced.
[0017] S43: For the production orders that can be produced, a production plan for each farm is generated according to the farm production task allocation rules;
[0018] S44: For each product in the demand order, if the product has a production farm whose distance from the warehouse node is greater than the transportation distance threshold I required by the freshness, the product is added to the set of products that require precooling; otherwise, the product is added to the set of products that do not require precooling;
[0019] S45: For the products in all demand orders, a vehicle dispatching plan is generated according to the pre-cooling product vehicle dispatching rule, and the product is removed from the list;
[0020] S46: Send the farm production plan and vehicle dispatch plan to relevant users for confirmation, then delete the order and return the order completed.
[0021] Further, in step S45, the pre-cooling product vehicle dispatching rule includes the following steps:
[0022] S451: Product i is produced according to the demand coefficient C i Add to the task list in non-reverse order, and execute S452 for all farms in turn; where demand production coefficient = demand / production
[0023] S452: Traverse the farms that meet the conditions and select Prioritize the transportation of the largest j1. If the production and demand meet the judgment condition 1, update the remaining capacity restC of the transport vehicle and execute S453; otherwise, execute S455;
[0024] The formula for judgment condition 1 is: The formula for updating the remaining volume of the transport vehicle is:
[0025] The production plan for farm j1 to produce commodity i, C is the vehicle volume threshold II;
[0026] S453: For the remaining farms that can produce the product, i.e. Select a farm whose output is less than the remaining volume restC of the transport vehicle. If it exists, execute S454, otherwise execute S455;
[0027] S454: add these farms to the transport node in sequence. If the time from the start of loading the product to the pre-cooling node along the route meets the pre-cooling condition, then add the node to the transport node, update the production plan of the farm commodity i to zero, update the remaining capacity of the transport vehicle, and execute S452. Otherwise, execute S455.
[0028] The formula for updating the remaining volume of the transport vehicle is:
[0029] If the nodes added to the transport route are j1, j2, ...j n , the transportation time calculation formula is: The cold condition is: T≤T0, T0 is the time threshold I of the freshness requirement, where For node j i to i+1 The distance, v is the speed of the transport vehicle;
[0030] S455: If the goods need to be pre-cooled, the cold chain transport vehicle will fill the products at the production node and transport them to the pre-cooling equipment node. After pre-cooling, the products will be transported to the nearest warehouse where they can be stored. Otherwise, the cold chain transport vehicle will transport the products to the nearest warehouse where they can be stored. If there are still products that have not been transported, S451 will be executed, otherwise the vehicle scheduling is completed.
[0031] Furthermore, the farm production task allocation rule in S43 includes the following steps:
[0032] S431 adds the commodities in the customer demand order to the task list according to the non-ascending order of demand inventory coefficients, and executes S432 for each commodity type in turn according to the order;
[0033] Demand-inventory coefficient = demand / inventory
[0034] Where S i is the inventory of commodity i; S432 selects the farm that produces the commodity. If farm j with the largest output can produce the quantity of commodities that meet the demand, the farm will produce the product and update the farm production capacity. The commodity is produced and removed, and the production quantity of the commodity is Determined by the following formula: Execute S433, otherwise the farm produces the maximum output of the commodity, the farm production capacity is set to zero, the commodity demand is updated, and the production plan is added Repeat S432;
[0035] Farm production capacity update formula: Product demand update formula:
[0036] S433: Remove the tasks of the products that have been produced. If there are still products that have not been planned for production, execute S431, otherwise the production plan is completed.
[0037] The present invention also relates to a system for implementing a method for jointly optimizing and scheduling agricultural product production and cold chain transportation, the system comprising a communication module, an information storage module and a control module.
[0038] Furthermore, the system also includes a user terminal, a cold chain vehicle and a farm control terminal that exchange information with the communication module.
[0039] Furthermore, the information storage module stores information on farm product categories, farm product output information, node location information, distance between any two nodes, user basic information data, and transportation vehicle basic data information; the information transmitted by the communication module includes: real-time road traffic information and weather information, required agricultural product delivery time and location and freshness information, vehicle real-time location, cargo status, agricultural product freshness, farm production information, cold equipment information, and warehouse information. The user client collects order information, the cold chain vehicle and farm control terminal receive transportation instructions and pre-cooling instructions from the communication module, and the user client can display transportation status and order logistics information for the user.
[0040] Beneficial Effects
[0041] The present invention takes into account the freshness constraints under the requirements of fruit information and order demand information, and scientifically formulates production plans for different fruits in each farm. Under indicators such as transportation distance and fruit freshness that affects the fruit, pre-cooling demand decisions are made before transportation route planning, and then cold chain transportation scheduling is achieved based on the obtained production plan, existing vehicle information and route information, ensuring freshness while minimizing transportation costs. BRIEF DESCRIPTION OF THE DRAWINGS
[0042] Figure 1 It is a schematic diagram of the scheduling method of the present invention;
[0043] Figure 2 The figure is a flow chart of the system of the present invention. DETAILED DESCRIPTION
[0044] The following combination Figures 1 to 2 This embodiment will be described in detail.
[0045] A method for joint optimization and scheduling of agricultural product production and cold chain transportation of the present invention comprises the following steps:
[0046] Step 1: The user terminal sends the order information to the communication module;
[0047] Step 2: The communication module uploads the required agricultural product delivery information to the control module; the required agricultural product information includes delivery time and location information, freshness information, real-time road traffic information, weather information, cold chain vehicle information and warehouse inventory information.
[0048] Step 3, the information storage module uploads the collected information to the control module; the information collected by the information storage module includes farm product variety information, yield information, farm production capacity hash table data, each node location information and distance information between designated nodes.
[0049] Step 4: After receiving various types of information, the control module executes the agricultural product production and cold chain transportation scheduling method to generate a farm production plan and a vehicle scheduling plan; the agricultural product production and cold chain transportation scheduling method includes the following steps:
[0050] S41: adding the batch order information of the user end to the task total list;
[0051] S42: For the obtained batch order information, if the customer demand for each product i is D i No more than the excess production capacity D i ≤Q i , where Q iis the total production of all farms producing the commodity, then the order can be produced and S43 will be continued. Otherwise, the order production fails and the task ends. The demand for each commodity is lower than the maximum production capacity, so it can be produced.
[0052] S43: For the production orders that can be produced, a production plan for each farm is generated according to the farm production task allocation rules;
[0053] S44: For each product in the demand order, if the product has a production farm whose distance from the warehouse node is greater than the transportation distance threshold I required by the freshness, the product is added to the set of products that require precooling; otherwise, the product is added to the set of products that do not require precooling;
[0054] S45: For the products in all demand orders, a vehicle dispatching plan is generated according to the pre-cooling product vehicle dispatching rule, and the product is removed from the list;
[0055] S46: Send the farm production plan and vehicle dispatch plan to relevant users for confirmation, then delete the order and return the order completed.
[0056] In step S45, the pre-cooling product vehicle dispatching rules include the following steps:
[0057] S451: Product i is produced according to the demand coefficient C i Add to the task list in non-reverse order, and execute S452 for all farms in turn; where demand production coefficient = demand / production
[0058] S452: Traverse the farms that meet the conditions and select Prioritize the transportation of the largest j1. If the production and demand meet the judgment condition 1, update the remaining capacity restC of the transport vehicle and execute S453; otherwise, execute S455;
[0059] The formula for judgment condition 1 is: The formula for updating the remaining volume of the transport vehicle is: The production plan for farm j1 to produce commodity i, C is the vehicle volume threshold II;
[0060] S453: For the remaining farms that can produce the product, i.e. Select a farm whose output is less than the remaining volume restC of the transport vehicle. If it exists, execute S454, otherwise execute S455;
[0061] S454: add these farms to the transport node in sequence. If the time from the start of loading the product to the pre-cooling node along the route meets the pre-cooling condition, then add the node to the transport node, update the production plan of the farm commodity i to zero, update the remaining capacity of the transport vehicle, and execute S452. Otherwise, execute S455.
[0062] The formula for updating the remaining volume of the transport vehicle is:
[0063] If the nodes added to the transport route are j1, j2, ...j n , the transportation time calculation formula is: The cold condition is: T≤T0, T0 is the time threshold I of the freshness requirement, where For node j i to i+1 The distance, v is the speed of the transport vehicle;
[0064] S455: If the goods need to be pre-cooled, the cold chain transport vehicle will fill the products at the production node and transport them to the pre-cooling equipment node. After pre-cooling, the products will be transported to the nearest warehouse where they can be stored. Otherwise, the cold chain transport vehicle will transport the products to the nearest warehouse where they can be stored. If there are still products that have not been transported, S451 will be executed, otherwise the vehicle scheduling is completed.
[0065] The farm production task allocation rules in S43 include the following steps:
[0066] S431 adds the commodities in the customer demand order to the task list according to the non-ascending order of demand inventory coefficients, and executes S432 for each commodity type in turn according to the order;
[0067] Demand-inventory coefficient = demand / inventory Where S i is the inventory of commodity i;
[0068] S432 selects the farms that produce the product. If the farm j with the largest output can produce the quantity of the product that meets the demand, the farm will produce the product and update the farm production capacity. The product is completed and removed. The production quantity of the product Determined by the following formula: Execute S433, otherwise the farm produces the maximum output of the commodity, the farm production capacity is set to zero, the commodity demand is updated, and the production plan is added Repeat S432;
[0069] Farm production capacity update formula: Product demand update formula:
[0070] S433: Remove the tasks of the products that have been produced. If there are still products that have not been planned for production, execute S431, otherwise the production plan is completed.
[0071] Step 5: The control module uploads the production plan and the vehicle dispatching plan to the communication module and the information storage module respectively. The communication module sends the production plan to each farm, and the communication module sends the vehicle dispatching instruction to the cold chain vehicle. The information storage module updates the farm and vehicle information according to the received production plan and vehicle dispatching plan.
[0072] Step 6: The communication module sends the process information to the user end.
[0073] The present invention also relates to a system for implementing a method for jointly optimizing and scheduling agricultural product production and cold chain transportation, comprising a communication module, an information storage module and a control module.
[0074] The system also includes a user terminal, a cold chain vehicle and a farm control terminal that exchange information with the communication module.
[0075] The information storage module stores information on farm product categories, output information on various farm products, location information on each node, distance information between any two nodes, basic user information, and basic transport vehicle data.
[0076] The information transmitted by the communication module includes: real-time road traffic information and weather information, required agricultural product delivery time, location and freshness information, real-time vehicle location, cargo status, agricultural product freshness, farm production information, cold equipment information, and warehouse information.
[0077] The user client collects order information, the cold chain vehicle and farm control terminal receive transportation instructions and pre-cooling instructions from the communication module, and the user client can display transportation status and order logistics information to the user.
[0078] The following is a detailed description of the embodiments:
[0079] Embodiment 1
[0080] The hash table data of fruit varieties and farm production capacity includes information on the types and quantities of produced products, information on the types of produced products, the production capacity of each farm under each product, and the corresponding yield information of each farm production type;
[0081] The steps to generate the hash table data of fruit variety and farm production capacity are:
[0082] S31: Based on the product types and yield information of each farm stored in the information storage module, obtain dictionary data of the types of products that can be produced and the corresponding yields; the following example takes the agricultural product production information of each farm in a certain area and describes it, for example: (unit: ton t)
[0083] {Farm 1: blueberries, peaches, pears; Farm 2: pears, blueberries, apples; Farm 3: apples, apricots;}
[0084] S32: For each product that can be produced and the total production capacity, the dictionary data stores the key-value pair information of product type-product production capacity; corresponding to the above example, the production capacity of each farm for each product is described as follows (unit: ton t)
[0085] Blueberries: {Farm 1: 70; Farm 2: 10;}
[0086] Pear: {Farm 1: 120; Farm 2: 240;}
[0087] Apple: {Farm 2: 220; Farm 3: 40;}
[0088] peach: {farm1:100;}
[0089] Apricot: {Farm 3: 120;}
[0090] All categories: {Blueberry: 80; Pear: 360; Apple: 260; Peach: 100; Apricot: 120;}
[0091] S33: For each farm, a key-value pair of product type-remaining output is generated according to the information storage module data and the farm data; corresponding to the above example, before the transportation starts, the remaining output of all farms is the total output, for example: (unit: ton t)
[0092] Farm 1: {Blueberries: 70; Peaches: 100; Pears: 120;}
[0093] Farm 2: {Pears: 240; Blueberries: 10; Apples: 220;}
[0094] Farm 3: {Apples: 40; Apricots: 120;}
[0095] Embodiment 2
[0096] The agricultural product production and cold chain transportation scheduling method includes the following steps:
[0097] S41: Add the batch order information of the user end to the task list; for example, the order content is: (unit: ton t)
[0098] {Blueberries: 10; Peaches: 20; Apples: 20}
[0099] S42: For the obtained batch order information, if the customer demand for each product does not exceed the remaining production capacity, the order can be produced and S43 is continued to be executed. Otherwise, the order production failure is returned and the task ends. In this example, the demand for each product is lower than the maximum production capacity, so it can be produced.
[0100] S43: For the production orders that can be produced, a production plan for each farm is generated according to the farm production task allocation rules;
[0101] S44: For each product in the demand order, if the product has a production farm whose distance from the warehouse node is greater than the transportation distance threshold I required by the freshness, the product is added to the set of products that require precooling; otherwise, the product is added to the set of products that do not require precooling;
[0102] S45: For the products in all demand orders, a vehicle dispatching plan is generated according to the pre-cooling product vehicle dispatching rule, and the product is removed from the list;
[0103] S46: Send the farm production plan and vehicle dispatch plan to relevant users for confirmation, then delete the order and return the order completed;
[0104] Embodiment 3
[0105] The farm production task allocation rules in S43 include the following steps:
[0106] S431 adds the commodities in the customer demand order to the task list according to the non-ascending order of demand inventory coefficients, and executes S432 for each commodity type in turn according to the order;
[0107] Demand-inventory coefficient = demand / inventory
[0108] Where S i is the inventory of commodity i,
[0109] For example, in the above example, the sorting rules are: peaches (1 / 5), blueberries (1 / 8), apples (1 / 13), where the values in brackets are the demand / inventory values;
[0110] S432 selects the farms that produce the product. If the farm j with the largest output can produce the quantity of the product that meets the demand, the farm will produce the product and update the farm production capacity. The product is completed and removed. The production quantity of the product Determined by the following formula: Execute S433, otherwise the farm produces the maximum output of the commodity, the farm production capacity is set to zero, the commodity demand is updated, and the production plan is added Repeat S432;
[0111] Farm production capacity update formula:
[0112] Product demand update formula:
[0113] S433: Remove the tasks of the products that have been produced. If there are still products that have not been planned for production, execute S431, otherwise the production plan is completed.
[0114] Embodiment 4
[0115] The pre-cooling product vehicle dispatching rules in S45 include the following steps:
[0116] S451: Product i is produced according to the demand coefficient C i Add to the task list in non-reverse order, and execute S452 for all farms in turn; where demand production coefficient = demand / production
[0117] S452: Traverse the farms that meet the conditions and select Prioritize the transportation of the largest j1. If the production and demand meet the judgment condition 1, update the remaining capacity restC of the transport vehicle and execute S453; otherwise, execute S455;
[0118] The formula for judgment condition 1 is:
[0119] The formula for updating the remaining volume of the transport vehicle is:
[0120] The production plan for farm j1 to produce commodity i,
[0121] C is the vehicle volume threshold II;
[0122] S453: For the remaining farms that can produce the product, i.e. Select a farm whose output is less than the remaining volume restC of the transport vehicle. If it exists, execute S454, otherwise execute S455;
[0123] S454: add these farms to the transport node in sequence. If the time from the start of loading the product to the pre-cooling node along the route meets the pre-cooling condition, then add the node to the transport node, update the production plan of the farm commodity i to zero, update the remaining capacity of the transport vehicle, and execute S452. Otherwise, execute S455.
[0124] The formula for updating the remaining volume of the transport vehicle is:
[0125] If the nodes added to the transport route are j1, j2, ...j n , the transportation time calculation formula is:
[0126] The cold condition is: T≤T0,
[0127] T0 is the time threshold I of freshness requirement,
[0128] in For node j i to i+1 The distance
[0129] v is the speed of the transport vehicle;
[0130] S455: If the goods need to be pre-cooled, the cold chain transport vehicle will fill the products at the production node and transport them to the pre-cooling equipment node. After pre-cooling, the products will be transported to the nearest warehouse where they can be stored. Otherwise, the cold chain transport vehicle will transport the products to the nearest warehouse where they can be stored. If there are still products that have not been transported, S451 will be executed, otherwise the vehicle scheduling is completed.
[0131] The above contents are only preferred embodiments of the present invention and are not intended to limit the implementation scheme of the present invention. A person skilled in the art can easily make corresponding changes or modifications based on the main concept and spirit of the present invention. Therefore, the protection scope of the present invention shall be based on the protection scope required by the claims.
Claims
1. A method for joint optimization and scheduling of agricultural product production and cold chain transportation, characterized in that: The steps include: Step 1: The user terminal sends the order information to the communication module; Step 2: The communication module uploads the required agricultural product delivery information to the control module; Step 3: The information storage module uploads the collected information to the control module; Step 4: After receiving various types of information, the control module executes the agricultural product production and cold chain transportation scheduling method to generate a farm production plan and a vehicle scheduling plan; Step 5: The control module uploads the production plan and the vehicle dispatching plan to the communication module and the information storage module respectively. The communication module sends the production plan to each farm, and the communication module sends the vehicle dispatching instruction to the cold chain vehicle. The information storage module updates the farm and vehicle information according to the received production plan and vehicle dispatching plan. Step 6: The communication module sends the process information to the user end; In step 4, the agricultural product production and cold chain transportation scheduling method includes the following steps: S41: adding the batch order information of the user end to the task total list; S42: For the obtained batch order information, if the customer demand for each product i is D i No more than the excess production capacity D i ≤Q i , where Q i is the total production of all farms producing the commodity, then the order can be produced and S43 will be continued. Otherwise, the order production fails and the task ends. The demand for each commodity is lower than the maximum production capacity, so it can be produced. S43: For the production orders that can be produced, a production plan for each farm is generated according to the farm production task allocation rules; S44: For each product in the demand order, if the product has a production farm whose distance from the warehouse node is greater than the transportation distance threshold I required by the freshness, the product is added to the set of products that require precooling; otherwise, the product is added to the set of products that do not require precooling; S45: For the products in all demand orders, a vehicle dispatching plan is generated according to the pre-cooling product vehicle dispatching rule, and the product is removed from the list; S46: Send the farm production plan and vehicle dispatch plan to relevant users for confirmation, then delete the order and return the order completed; In step S45, the pre-cooling product vehicle dispatching rules include the following steps: S451: Product i is produced according to the demand coefficient C i Add to the task list in non-reverse order, and execute S452 for all farms in turn; where demand production coefficient = demand / production S452: Traverse the farms that meet the conditions and select Prioritize the transportation of the largest j1. If the production and demand meet the judgment condition 1, update the remaining capacity restC of the transport vehicle and execute S453; otherwise, execute S455; The formula for judgment condition 1 is: The formula for updating the remaining volume of the transport vehicle is: The production plan for farm j1 to produce commodity i, C is the vehicle volume threshold II; S453: For the remaining farms that can produce the product, i.e. Select a farm whose output is less than the remaining volume restC of the transport vehicle. If it exists, execute S454, otherwise execute S455; S454: add these farms to the transport node in sequence. If the time from the start of loading the product to the pre-cooling node along the transport route meets the pre-cooling condition, then add the node to the transport node, update the production plan of the farm commodity i to zero, update the remaining capacity of the transport vehicle, and execute S452. Otherwise, execute S455. The formula for updating the remaining volume of the transport vehicle is: If the nodes added to the transport route are j1, j2, ...j n , the transportation time calculation formula is: The cold condition is: T≤T0, T0 is the time threshold I of the freshness requirement, where For node j i to i+1 The distance, v is the speed of the transport vehicle; S455: If the product needs to be pre-cooled, the cold chain transport vehicle will be filled with products at the production node and transported to the pre-cooling equipment node. After pre-cooling, the product will be transported to the nearest warehouse where it can be stored. Otherwise, the cold chain transport vehicle will transport the product to the nearest warehouse where it can be stored. If there are still products that have not been transported, S451 will be executed. Otherwise, the vehicle scheduling is completed. The farm production task allocation rules in S43 include the following steps: S431 adds the commodities in the customer demand order to the task list according to the non-ascending order of demand inventory coefficients, and executes S432 for each commodity type in turn according to the order; Demand-inventory coefficient = demand / inventory Where S i is the inventory of commodity i; S432 selects the farms that produce the product. If the farm j with the largest output can produce the quantity of the product that meets the demand, the farm will produce the product and update the farm production capacity. The product is completed and removed. The production quantity of the product Determined by the following formula: Execute S433, otherwise the farm produces the maximum output of the commodity, the farm production capacity is set to zero, the commodity demand is updated, and the production plan is added Repeat S432; Farm production capacity update formula: Product demand update formula: S433: Remove the tasks of the products that have been produced. If there are still products that have not been planned for production, execute S431, otherwise the production plan is completed.
2. The method for joint optimization and scheduling of agricultural product production and cold chain transportation according to claim 1 is characterized in that: In step 2, the demanded agricultural product delivery information includes delivery time and location information, freshness information, real-time road traffic information, weather information, cold chain vehicle information and warehouse inventory information.
3. The method for joint optimization and scheduling of agricultural product production and cold chain transportation according to claim 1 is characterized in that: In step three, the information collected by the information storage module includes farm product variety information, yield information, farm production capacity hash table data, each node location information and designated node distance information.
4. A system for implementing the method for joint optimization and scheduling of agricultural product production and cold chain transportation according to any one of claims 1 to 3, characterized in that: The system includes a communication module, an information storage module and a control module.
5. The agricultural product production and cold chain transportation joint optimization scheduling system according to claim 4 is characterized in that: The system also includes a user terminal, a cold chain vehicle and a farm control terminal that exchange information with the communication module.
6. The agricultural product production and cold chain transportation joint optimization scheduling system according to claim 4 is characterized in that: The information storage module stores information on farm product categories, information on the output of various farm products, location information of each node, distance information between any two nodes, basic user information, and basic transport vehicle data; The information transmitted by the communication module includes: real-time road traffic information and weather information, required agricultural product delivery time, location and freshness information, real-time vehicle location, cargo status, agricultural product freshness, farm production information, cold equipment information, and warehouse information.
7. The agricultural product production and cold chain transportation joint optimization scheduling system according to claim 4 is characterized in that: The user client collects order information, the cold chain vehicle and farm control terminal receive transportation instructions and pre-cooling instructions from the communication module, and the user client can display transportation status and order logistics information to the user.