A static pressure construction method for ultra-deep hollow concrete pipe piles
By not carrying out foundation pit excavation and using pile feeders during the construction of ultra-deep hollow piles, the static pressure construction of ultra-deep hollow piles was realized by using site leveling and pile driver operation, solving the difficulty and high cost of construction. problems, met the design and specification requirements, and improved construction efficiency.
Patent Information
- Application Number
- CN202210710871.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-06-22
- Publication Date
- 2024-10-18
- Estimated Expiration
- 2042-06-22
AI Technical Summary
The existing technology requires excavation of foundation pits and the use of pile feeders during the construction of ultra-deep hollow piles, which results in high construction difficulty and cost, and cannot meet design and specification requirements.
The static pressure construction method of ultra-deep hollow concrete pipe piles without foundation pit excavation is adopted, and the steps are followed by leveling the site, positioning the pile driver, inserting the piles and observing the verticality, sinking the piles, and using the second pipe pile to deliver the piles. The first pipe pile reaches the preset elevation to avoid using the pile feeder.
The construction of ultra-deep hollow piles does not require foundation pit excavation, which reduces construction costs, meets the design and specification requirements for pile top elevation and pile position, and improves construction efficiency.
Smart Images

Figure CN114960646B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of prestressed concrete pipe piles for water conservancy, municipal administration and building construction, and in particular to a static pressure construction method for ultra-deep hollow concrete pipe piles. Background Art
[0002] At present, in the case of empty piles, the existing technology uses a pile driver to deliver the prestressed pipe piles to the designed elevation. Generally, the construction limit of empty piles is 8m. In the case of ultra-deep empty piles, site excavation is required. After excavation, the site needs to be backfilled with dry soil of more than 2m, or backfilled with sand, or backfilled with stones in places where there are no piles, and backfilled with clay in places where there are piles, so as to meet the construction conditions for static pressure equipment. However, the assembly of equipment on site after most foundation pit excavation brings great difficulties. Summary of the invention
[0003] The technical problem to be solved by the present invention is to provide a static pressure construction method for ultra-deep hollow concrete pipe piles without excavating a foundation pit and using a pile driver.
[0004] The technical solution adopted by the present invention to solve the technical problem is: the static pressure construction method of the ultra-deep hollow pile concrete pipe pile comprises the following steps:
[0005] S1. Site leveling and surveying and laying out; site leveling includes clearing obstacles at the construction site or draining water from low-lying areas;
[0006] S2, the pile driver is in place and the pile is hoisted and fed; the pile hoisting and feeding includes setting a size mark on the pile body of the first pipe pile and smoothly sending the first pipe pile to the pile clamp;
[0007] S3, insert the pile and observe the verticality, and correct the deviation when the verticality is greater than the preset value;
[0008] S4, after the pile is sunk and the top of the first pipe pile is lower than the preset height, the second pipe pile is lifted and the second pipe pile is used to push the first pipe pile until the first pipe pile reaches the preset elevation;
[0009] S5. Pull out the second pipe pile and move the machine to the next pile position.
[0010] Furthermore, the S4 step further includes:
[0011] Before the second pipe pile is hoisted and used to transport the first pipe pile, an iron sheet is laid at the bottom of the second pipe pile.
[0012] Furthermore, in the step S3, after the verticality is greater than a preset value, the deviation correction includes:
[0013] Observe whether the verticality of the first pipe pile insertion is greater than 0.5%. If so, make corrections.
[0014] Furthermore, the first pipe pile is a Φ500PHC prestressed pipe pile.
[0015] Furthermore, the first pipe pile has a concrete strength grade of not less than C80, a wall thickness of not less than 125 mm, and a minimum prestressed steel bar area of not less than 1080 mm. 2 , the anti-cracking bending moment is not less than 136kN*m, the ultimate bending moment is not less than 226kN*m, and the characteristic value Ra of the vertical bearing capacity of a single pile is as high as 1000kN.
[0016] Furthermore, in the step S4, until the first pipe pile reaches the preset elevation, it includes:
[0017] Control the height from the top of the first pipe pile to the construction plane to 10-15m.
[0018] The static pressure construction method of ultra-deep hollow pile concrete pipe pile of the present invention does not use pile delivery equipment after the existing site is basically leveled without excavating the foundation pit, and starts equipment assembly and prestressed concrete pipe piles for ultra-deep hollow pile construction, ensuring that the pile top elevation meets the design and specification requirements, and solves the problems of site replacement, waiting of mechanical equipment in a semi-excavated state, and difficulty in assembling equipment on the working surface brought by the prior art. At the same time, the construction method of the present invention has high efficacy, avoids excavation and backfilling of the construction platform to reduce costs, and the pile foundation elevation and pile position meet the design and specification requirements after the construction is completed. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] The present invention will be further described below with reference to the accompanying drawings and embodiments, in which:
[0020] Figure 1 It is a flowchart of a static pressure construction method for ultra-deep hollow pile concrete pipe piles according to an embodiment of the present invention;
[0021] Figure 2 It is a schematic diagram of static pressure construction of ultra-deep hollow concrete pipe piles according to an embodiment of the present invention. DETAILED DESCRIPTION
[0022] In order to have a clearer understanding of the technical features, purposes and effects of the present invention, specific embodiments of the present invention are now described in detail with reference to the accompanying drawings.
[0023] like Figure 1-2 As shown, the static pressure construction method of the ultra-deep hollow pile concrete pipe pile comprises the following steps:
[0024] S1. Site leveling and surveying and setting out; site leveling includes clearing obstacles at the construction site or draining water from low-lying waterlogged areas. At the specific construction site, surface attachments and ground obstacles in the construction site are generally cleared. In areas with frequent rainfall, temporary drainage ditches are set up and drainage is kept unobstructed to prevent rainwater from affecting construction. For low-lying waterlogged areas, drainage ditches should be dug to divert water or centralized water pumping should be used. For surveying and setting out, after the site is leveled, control setting out is carried out, and white lime is sprinkled around the pile positions or other markings are made to make the pile position ground markings obvious.
[0025] S2, the pile driver is in place and the pile is hoisted and fed; the hoisting and feeding of piles include setting size marks on the body of the first pipe pile and smoothly sending the first pipe pile to the pile clamp. After the equipment is assembled and debugged, the pile driver moves and walks in place, and sets size marks on the body of the first pipe pile in advance or on site, such as setting a mark every 0.5-1.5, so as to observe and record during construction. After the pile is hoisted, the first pipe pile is smoothly sent to the pile clamp, and the center of the first pipe pile is aligned with the pile position. The pile driver holds the pile and waits for the downward pressure operation.
[0026] S3. Insert the pile and observe the verticality. Correct the deviation when the verticality is greater than the preset value. Observe whether the verticality of the first pile is greater than 0.5%. If so, correct the deviation. When inserting the pile, slowly press it down into the soil. After the pile is inserted to the preset length, such as 40-60cm deep, observe the verticality of the pile to see if it is greater than 0.5%. If the verticality is less than 0.5%, proceed normally and observe in real time. If deviation is found, adjust it in time. After the verticality is greater than 0.5%, adjust it and start pressing the pile after it meets the requirements.
[0027] S4, after the pile is sunk and the top of the first pipe pile is lower than the preset height, the second pipe pile is lifted and the first pipe pile is pushed by the second pipe pile until the top of the first pipe pile reaches the preset elevation. In this embodiment, the control of the top of the pile to the preset elevation is to control the top of the first pipe pile to the height of 10-15m from the construction plane. In addition, the pile sinking speed needs to be observed during the pile sinking process, and the speed is adjusted after encountering a hard interlayer or entering the bearing layer.
[0028] In this embodiment, the second pipe pile is hoisted again, and the pile is driven by aligning the end of the second pipe pile with the end of the first pipe pile. The strength of the pile body is utilized to reduce the time for replacing the driving device. If site conditions permit, one pile driver can drive about 400m of pipe piles a day.
[0029] S5, pull out the second pipe pile and move the machine to the next pile position. After the pile reaches the elevation, the pile driver moves to the next pile position for construction.
[0030] The static pressure construction method of ultra-deep hollow pile concrete pipe pile of the present invention does not use pile delivery equipment after the existing site is basically leveled without excavating the foundation pit, and starts equipment assembly and prestressed concrete pipe piles for ultra-deep hollow pile construction, ensuring that the pile top elevation meets the design and specification requirements, and solves the problems of site replacement, waiting of mechanical equipment in a semi-excavated state, and difficulty in assembling equipment on the working surface brought by the prior art. At the same time, the construction method of the present invention has high efficacy, avoids excavation and backfilling of the construction platform to reduce costs, and the pile foundation elevation and pile position meet the design and specification requirements after the construction is completed.
[0031] In this embodiment, the first pipe pile is a Φ500PHC prestressed pipe pile. The first pipe pile has a concrete strength grade of not less than C80, a wall thickness of not less than 125mm, and a minimum prestressed steel bar area of not less than 1080mm 2 , the anti-cracking bending moment is not less than 136kN*m, the ultimate bending moment is not less than 226kN*m, and the characteristic value Ra of the vertical bearing capacity of a single pile is as high as 1000kN. For PHC piles, the pile sections of PHC piles are 5~15m, which can be freely matched, convenient for transportation and hoisting, and the pile length is not limited. Rapid connection can be achieved by two-way welding.
[0032] The present invention does not require a pile driver during the static pressure construction process of prestressed pipe piles, and the ultra-deep empty pile reaches more than 10m during construction. The construction effect meets the specifications and design requirements, and the construction method is highly effective, avoids excavation and backfilling of the construction platform, and reduces costs.
[0033] like Figure 2 The static pressure construction site of ultra-deep hollow concrete pipe piles is shown in the figure, where e is the pile driver (static pressure equipment), a is the pipe pile that has been constructed to the design elevation, and its distance from the construction plane is b, and b is the ultra-deep hollow pile range, which is 10-15m. c is the pipe pile being delivered, and d is the pipe pile that replaces the delivery device. Iron sheets are also laid between c and d. Iron sheets are laid at the bottom of the pile before delivery to ensure that the soil does not fall into the pile after the pile is pulled out, avoiding difficulties in cleaning later.
Claims
1. A method for static pressure construction of ultra-deep hollow concrete pipe piles, characterized in that: The steps include: S1. Site leveling and surveying and laying out; site leveling includes clearing obstacles at the construction site or draining water from low-lying areas; S2, the pile driver is in place and the pile is hoisted and fed; Pile hanging and pile feeding include setting size marks on the first pipe pile, with a mark set every 0.5-1.5, so as to observe and record during construction, and smoothly send the first pipe pile to the pile clamp; S3, inserting piles and observing verticality, and correcting the deviation after the verticality is greater than a preset value; in the step S3, correcting the deviation after the verticality is greater than the preset value includes observing whether the verticality of the first pile inserted is greater than 0.5%, and if so, correcting the deviation; S4, after the pile is sunk and the top of the first pipe pile is lower than the preset height, the second pipe pile is lifted and the first pipe pile is pushed by the second pipe pile until the top of the first pipe pile reaches the preset elevation, specifically controlling the height of the top of the first pipe pile to the construction plane to be 10-15m; including laying iron sheets at the bottom of the second pipe pile before lifting the second pipe pile and pushing the first pipe pile by the second pipe pile, and laying iron sheets at the bottom of the pile before pushing the pile to ensure that soil does not fall into the pile after the pile is pulled out, so as to avoid difficulties in cleaning later; S5, pull out the second pipe pile and move the machine to the next pile position; The first pipe pile is a Φ500PHC prestressed pipe pile; The first pile concrete strength grade is not less than C80, the wall thickness is not less than 125mm, and the minimum prestressed steel bar area is not less than 1080mm 2 , the anti-cracking bending moment is not less than 136kN*m, the ultimate bending moment is not less than 226kN*m, and the characteristic value Ra of the vertical bearing capacity of a single pile is as high as 1000kN.