Laboratory air duct installation structure and installation method
By adopting a combined structure of brackets and beams in the laboratory, and using a combination of guide tubes and hanging tubes to achieve stable hoisting of air ducts, the problems of high labor intensity and high construction risks of air duct installation in high-rise laboratories are solved, and the efficiency is improved Installation efficiency and reduced risk.
Patent Information
- Application Number
- CN202210848607.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-07-19
- Publication Date
- 2024-10-18
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
In high-rise laboratories, existing air duct installation methods suffer from high labor intensity, low installation efficiency, and high construction risks, especially due to the increased size of scissor lifts and the presence of high-altitude operations.
A laboratory air duct installation structure is adopted, including two sets of brackets and cross beams set between the brackets. Through the combination of guide pipes and hanging pipes, the lifting components and support members are used to achieve stable hoisting of the air duct, reducing high-altitude operations. Improve installation efficiency and solve assembly difficulties caused by uneven floors by adjusting components.
It significantly reduces the time and intensity of working at heights, improves the installation efficiency of air ducts, reduces construction risks, and enables flexible adjustment of the height of the air ducts by adjusting components, simplifying the splicing process.
Smart Images

Figure CN115164396B_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of pipeline installation, and in particular to a laboratory air duct installation structure and an installation method thereof. Background Art
[0002] An air duct is a pipe used to transport air. Existing air ducts can be divided into circular air ducts, rectangular air ducts, oblate air ducts and other types according to their cross-sectional shapes. Among them, rectangular air ducts are widely used because they are easier to install.
[0003] At present, there are two commonly used methods for installing air ducts: the first is to use a scissor lift for auxiliary installation, and the second is to build a scaffolding on site, and then manually place the air duct on the scaffolding for assembly.
[0004] However, since the floor heights of office spaces such as laboratories are generally high, if the first method is used for installation, as the installation height increases, the risk of the air duct falling from the scissor lift during the lifting process will also increase. In addition, the volume of the required scissor lift also increases accordingly, resulting in an increase in the height of the scissor lift. Therefore, the air duct needs to be manually moved to the lifting platform of the scissor lift, which has the defects of high labor intensity and low installation efficiency. If the second method is used for installation, it will take a lot of time to disassemble and assemble the scaffolding, and the air duct needs to be manually placed on the scaffolding, during which a lot of high-intensity high-altitude operations are required, which is not only inefficient, but also has high construction risks. Summary of the invention
[0005] In order to improve the installation efficiency of air ducts and reduce construction risks, the present application provides a laboratory air duct installation structure and an installation method thereof.
[0006] The present application provides a laboratory air duct installation structure and an installation method thereof using the following technical solutions:
[0007] First aspect:
[0008] A laboratory air duct installation structure includes two groups of brackets and a beam arranged between the two groups of brackets, the bracket includes an anchoring part and a hanging pipe, the anchoring part is used to connect to a floor slab, one end of the hanging pipe is fixedly connected to the anchoring part, and the other end of the hanging pipe is detachably connected to a guide pipe, the beam is slidably sleeved with the hanging pipe, the beam is slidably sleeved with the guide pipe, the anchoring part is connected to a lifting assembly for lifting the beam, and the hanging pipe is provided with a supporting member for supporting the beam.
[0009] By adopting the above technical solution, when installing the air duct, by selecting a guide tube of appropriate length, after the guide tube is connected to the hanging pipe, the end of the guide tube away from the hanging pipe is close to the ground, and then the crossbeam is sleeved on the lower ends of the two guide tubes and the lifting assembly is connected to the crossbeam, and then the air duct is placed between the two crossbeams, and then the crossbeam is lifted by the lifting assembly. During the rising of the crossbeam, the guide tube guides the crossbeam, so that the crossbeam moves upward stably. At the same time, the guide tube limits the air duct, so that the air duct will not fall from the crossbeam. When the air duct rises to the installation height, the supporting member supports the crossbeam, so that the crossbeam is stably sleeved on the hanging pipe, and then only the air duct needs to be spliced. In summary, the air duct is installed by hoisting. During the entire installation process, the relatively labor-intensive work steps are completed on the ground, which significantly reduces the time and intensity of high-altitude work, not only improves the installation efficiency of the air duct, but also significantly reduces the construction risk.
[0010] Preferably, the lifting assembly includes a fixed pulley detachably arranged on the anchoring portion, a pull rope is wound around the fixed pulley, one end of the pull rope is connected to the cross beam, and the other end of the pull rope is a force-applying end.
[0011] By adopting the above technical solution, after placing the air duct on the beam, one end of the pull rope is tied to the beam, and then the beam can be moved upward by pulling the force-applying end of the pull rope. It can be seen that the staff can complete the hoisting of the air duct on the ground, which is conducive to improving the installation efficiency of the air duct.
[0012] Preferably, the supporting member includes a accommodating box arranged in the hanging tube, one side of the accommodating box is opened, a wedge block is inserted into the open side of the accommodating box, a side wall of the hanging tube is provided with a through groove for the wedge block to pass through, an elastic member is fixedly connected between one end of the wedge block inserted into the accommodating box and the bottom of the accommodating box, the inclined surface of the wedge block is arranged downward, and when the elastic member is not subjected to external force, the segment of the wedge block provided with the inclined surface extends out of the hanging tube.
[0013] By adopting the above technical solution, when the cross beam moves to abut against the wedge block, the cross beam is continuously pulled, and the wedge block is squeezed and slides into the receiving box, and the elastic member is compressed. When the cross beam and the wedge block are completely separated, the wedge block pops out of the receiving box under the action of the elastic member, thereby providing stable support for the cross beam and realizing self-locking of the cross beam, eliminating the operation steps of fixing the cross beam, and significantly improving the installation efficiency of the air duct.
[0014] Preferably, a limit plate is provided on the side of the hanging pipe facing away from the wedge block, the limit plate is located above the wedge block, and the shortest distance between the limit plate and the wedge block matches the sum of the height of the air duct and the thickness of the beam.
[0015] By adopting the above technical solution, when the crossbeam moves to the position above the wedge block, the air duct abuts against the limit plate, the limit plate cooperates with the wedge block to limit the vertical displacement of the air duct, and the two hanging pipes limit the horizontal displacement of the air duct, so that the air duct can be stably hung under the floor.
[0016] Preferably, a movable groove is opened along the length direction of the hanging tube on the side wall away from the wedge block, one end of the limit plate is inserted into the movable groove and fixedly connected with a connecting rod, the connecting rod is perpendicular to the limit plate, and one end of the connecting rod away from the limit plate is fixedly connected to the accommodating box, the through groove is opened along the length direction of the hanging tube, the wedge block is slidably connected to the hanging tube along the length direction of the through groove, and an adjustment component for adjusting the height of the accommodating box is provided on the hanging tube.
[0017] By adopting the above technical solution, since it is difficult to keep the floor surface completely flat, it may be difficult to align the air duct after the air duct is hoisted, which makes it difficult to splice the air duct. Therefore, the limit plate is fixedly connected to the receiving box through a connecting rod, and the height of the limit plate can be changed synchronously by adjusting the height of the receiving box by using the adjustment component, thereby changing the height of the air duct, so as to assemble the air duct.
[0018] Preferably, the adjustment assembly includes an adjustment screw, a bearing is embedded in the lower end of the hanging tube, the adjustment screw is rotatably connected to the hanging tube via the bearing, a screw tube is fixedly connected to the side of the accommodating box away from the connecting rod, and the adjustment screw is threadedly connected to the screw tube.
[0019] By adopting the above technical solution, the height of the container box can be adjusted by rotating the adjusting screw rod, thereby realizing the adjustment of the height of the air duct. Various tests are carried out in the laboratory, which inevitably generates large vibrations. Therefore, the screw rod is connected to the hanging pipe through the bearing rotation, so that the screw rod will not loosen and fall off, which not only makes the air duct installation more stable, but also significantly reduces the possibility of subsequent instruments in the laboratory being damaged by the falling adjusting screw rod.
[0020] Second aspect:
[0021] A method for installing a laboratory air duct installation structure comprises the following steps:
[0022] S1. Anchor several brackets on the lower surface of the floor slab according to the designed air duct layout line;
[0023] S2. Install the fixed pulley on the anchoring part, and wind the pull rope around the fixed pulley, and adjust the position of the pull rope so that both ends of the pull rope naturally fall to the ground;
[0024] S3, connecting the guide tube to the hanging tube, then sleeve the crossbeam between the two guide tubes and tie one end of the pull rope to the crossbeam;
[0025] S4. Place the air duct on two adjacent beams, and then lift the beams by pulling the force-applying end of the pull rope until the air duct abuts against the limit plate;
[0026] S5. Repeat step S4 until all the air ducts are hoisted;
[0027] S6. Remove the fixed pulley and guide tube, and then splice the air duct.
[0028] By adopting the above technical solution, the air duct can be installed by hoisting, which can be completed on the ground, saving time and effort, and no high-intensity work is required at high altitude, which significantly reduces the construction risk. After the air duct is installed, the fixed pulley and guide rod can be recycled, which not only helps to reduce construction costs, but also meets the requirements of green and environmentally friendly construction.
[0029] Preferably, in step S6, when splicing the air ducts, if the interfaces of the air ducts are not aligned, the height of the air ducts can be changed by rotating the adjusting screw, thereby facilitating the splicing of the air ducts.
[0030] By adopting the above technical solution, the problem of difficulty in assembling the air duct due to uneven floor slabs is solved, thereby effectively improving the installation efficiency of the air duct.
[0031] In summary, the present application includes at least one of the following beneficial technical effects:
[0032] 1. By using the hoisting method to install the air duct, there is no need to perform high-intensity work at high altitude, which is not only conducive to improving the installation efficiency of the air duct, but also significantly reducing the construction risk;
[0033] 2. By setting the adjustment component to adjust the height of the air duct, the problem of difficulty in assembling the air duct due to uneven floor slabs can be effectively solved, thereby effectively improving the installation efficiency of the air duct. BRIEF DESCRIPTION OF THE DRAWINGS
[0034] Figure 1 It is a schematic diagram of the overall structure of this application;
[0035] Figure 2 is a schematic diagram of the installation structure in this application;
[0036] Figure 3 It is a schematic diagram of the internal structure of the hanging pipe and the guide pipe in this application.
[0037] Description of reference numerals:
[0038] 1. Bracket; 11. Anchoring part; 111. Fixed frame; 112. Anchor rod; 113. Fixed plate; 12. Hanging pipe; 13. Connecting pipe; 2. Crossbeam; 3. Air duct; 4. Guide pipe; 5. Lifting assembly; 51. Fixed pulley; 52. Pull rope; 53. Hook; 6. Support member; 61. Accommodating box; 62. Wedge block; 63. Elastic member; 64. Adjusting assembly; 641. Adjusting screw; 642. Bearing; 643. Screw; 7. Through slot; 8. Limiting plate; 9. Movable slot; 10. Connecting rod. DETAILED DESCRIPTION
[0039] The following is combined with Figure 1-3 This application is described in further detail.
[0040] The embodiments of the present application disclose a laboratory air duct installation structure and an installation method thereof.
[0041] Reference Figure 1 A laboratory air duct installation structure includes two groups of brackets 1 and a beam 2 arranged between the two groups of brackets 1. The two groups of brackets 1 and the beam 2 form a U-shaped frame for placing the air duct 3.
[0042] Reference Figure 2 and Figure 3 The bracket 1 includes an anchoring portion 11 for connecting with the floor slab and a hanging pipe 12 connected with the anchoring portion 11. The anchoring portion 11 includes a fixing frame 111, which is rectangular in shape. An anchor rod 112 is provided on the top of the fixing frame 111. The anchor rod 112 is used to anchor in the upper floor slab. A nut is threadedly connected to the anchor rod 112. The hanging pipe 12 is provided on the opposite side of the fixing frame 111 where the anchor rod 112 is provided. The hanging pipe 12 is parallel to the anchor rod 112. The hanging pipe 12 is welded and fixed to the fixing frame 111. The hanging pipe 12 has a square cross section. The end of the hanging pipe 12 away from the fixing frame 111 is fixedly connected with a connecting pipe 13. The connecting pipe 13 is provided with an external thread. The connecting pipe 13 is threadedly connected with a guide pipe 4. The cross section of the guide pipe 4 is consistent with the cross section of the hanging pipe 12. The cross beam 2 is provided with a through hole for the guide pipe 4 and the hanging pipe 12 to pass through. The cross beam 2 is slidably connected with the guide pipe 4 and the hanging pipe 12. The hanging pipe 12 is provided with a lifting assembly 5 for lifting the cross beam 2 and a supporting member 6 for supporting the cross beam 2 .
[0043] Reference Figure 1 and Figure 2When installing the air duct 3, several groups of brackets 1 are anchored on the lower surface of the floor slab through anchor rods 112 according to the designed layout of the air duct 3. During the anchoring period, pay attention to adjusting the positions of the two brackets 1 in the same group so that the spacing between the two hanging pipes 12 matches the width of the air duct 3. Then, according to the floor height, select a guide tube 4 of appropriate length and connect the guide tube 4 with the hanging pipe 12, then sleeve the crossbeam 2 on the lower ends of the two guide tubes 4 and connect the lifting assembly 5 with the crossbeam 2, then place the air duct 3 between the two crossbeams 2, and then use the lifting assembly 5 to lift the crossbeam 2. When the air duct 3 moves up to the installation height, use the supporting member 6 to support the crossbeam 2 to complete the hoisting of the air duct 3, and then splice the air duct 3.
[0044] Reference Figure 2 The lifting assembly 5 includes a fixed pulley 51 and a pull rope 52. A fixed plate 113 is welded and fixed to one end of the fixed frame 111 facing away from the air duct 3. The fixed pulley 51 is hung on the fixed plate 113 through a hook 53. The fixed plate 113 has a hole for the hook 53 to pass through. One end of the pull rope 52 passes over the top of the fixed pulley 51 and is tied to the crossbeam 2. The other end of the pull rope 52 serves as a force-applying end, which can be pulled manually or connected to an external winch or other equipment.
[0045] Reference Figure 3 The supporting member 6 includes a receiving box 61 and an adjusting assembly 64 for adjusting the height of the receiving box 61. The receiving box 61 is arranged in the hanging tube 12, and the receiving box 61 is slidably connected to the hanging tube 12. The receiving box 61 is arranged at an end away from the air duct 3, and a wedge block 62 is inserted into the open end of the receiving box 61. An elastic member 63 is fixedly connected between one end of the wedge block 62 inserted into the receiving groove and the bottom of the receiving box 61, and the elastic member 63 is a spring. The side wall of the hanging tube 12 is provided with a through groove 7 for the wedge block 62 to pass through. The through groove 7 is provided along the length direction of the hanging tube 12. The slot width of the through groove 7 matches the width of the wedge block 62, and the slot length of the through groove 7 is greater than the thickness of the wedge block 62. When the elastic member 63 is not subjected to external force, the segment of the wedge block 62 provided with the inclined surface extends out of the hanging tube 12 and the inclined surface of the wedge block 62 is arranged downward. And at the beginning, the wedge block 62 abuts against the lower groove wall of the through groove 7.
[0046] Reference Figure 3 The adjustment component 64 includes an adjustment screw 641, a bearing 642 is embedded in the connecting tube 13, the adjustment screw 641 is rotatably connected to the connecting tube 13 through the bearing 642, a screw tube 643 is fixedly connected to the lower surface of the fixed frame 111, the screw tube 643 is provided with an internal thread, and the adjustment screw 641 is threadedly connected to the screw tube 643.
[0047] In the process of lifting the cross beam 2 by the lifting assembly 5, the cross beam 2 abuts against the inclined surface of the wedge block 62, and the cross beam 2 squeezes the wedge block 62 so that the wedge block 62 is squeezed into the receiving box 61, and the spring is compressed at this time. When the cross beam 2 continues to move up and completely separates from the wedge block 62, the spring rebounds to reset the wedge block 62, and the wedge block 62 supports the cross beam 2. The construction workers stop lifting the cross beam 2 after hearing the sound, and the lifting of the air duct 3 is completed. After that, the air duct 3 is assembled. If the interface of the air duct 3 is found to be uneven during the assembly process of the air duct 3, the height of the air duct 3 can be changed by adjusting the height of the cross beam 2 by adjusting the screw 641, so as to facilitate the assembly of the air duct 3.
[0048] Reference Figure 2 and Figure 3 The hanging tube 12 is also provided with a limit plate 8 on the side away from the wedge block 62. The hanging tube 12 is provided with a movable groove 9 on the side provided with the limit plate 8. The movable groove 9 is provided along the length direction of the hanging tube 12. The movable groove 9 is located above the through groove 7. The slot length of the movable groove 9 is consistent with the slot length of the through groove 7. One end of the limit plate 8 is inserted into the hanging tube 12 through the movable groove 9 and is fixedly connected with a connecting rod 10. The end of the connecting rod 10 away from the limit plate 8 is fixedly connected to the upper surface of the receiving box 61. The shortest distance between the lower surface of the limit plate 8 and the upper surface of the wedge block 62 matches the sum of the height of the air duct 3 and the thickness of the crossbeam 2. The limit plate 8 cooperates with the wedge block 62 to clamp the air duct 3, so that the air duct 3 will not vibrate in the vertical direction, which is conducive to improving the stability of the air duct 3 after installation.
[0049] The implementation principle of a laboratory air duct installation structure is as follows: the present application installs the air duct 3 by hoisting, and when the air duct 3 is hoisted to the installation height, the air duct 3 is self-locked, and the subsequent assembly of the air duct 3 is only required. Compared with the prior art, there is no need to build a scaffold or use a scissor lift for auxiliary installation, the installation efficiency is significantly improved, and the time and intensity of high-altitude operations are significantly reduced, which significantly improves construction safety.
[0050] A method for installing a laboratory air duct installation structure:
[0051] S1. Anchor several groups of brackets 1 on the lower surface of the floor according to the designed arrangement of the air duct 3. During the anchoring of the brackets 1, pay attention to adjusting the distance between two brackets 1 in the same group so that the distance between two hanging pipes 12 in the same group matches the width of the air duct 3.
[0052] S2. After the bracket 1 is anchored, the fixed pulley 51 is hung on the fixing plate 113, and then the pull rope 52 is wound around the fixed pulley 51 and the two ends of the pull rope 52 are allowed to naturally hang down to the ground.
[0053] S3. Select a guide tube 4 of appropriate length according to the floor height, so that after the guide tube 4 is connected to the hanging tube 12, the lower end of the guide tube 4 is close to the ground, then connect and tighten the guide tube 4 to the hanging tube 12, and then put the beam 2 between the lower ends of the two guide tubes 4 and tie one end of the pull rope 52 to the beam 2.
[0054] S4, placing the air duct 3 between two adjacent beams 2, and then lifting the beam 2 by manually pulling the force-applying end of the pull rope 52 or by using a winch to reel in the force-applying end of the pull rope 52 until the air duct 3 abuts against the limit plate 8;
[0055] S5. Repeat step S4 until all the air ducts 3 are hoisted. It should be noted that when hoisting the next section of air duct 3, the position of the air duct 3 on the beam 2 needs to be adjusted so that the hoisted air duct 3 will not collide with the hoisted air duct 3. At the same time, it is necessary to ensure that the distance between the hoisted air duct 3 and the hoisted air duct 3 does not exceed 2 cm, so as to facilitate the subsequent splicing of the air duct 3. Specifically:
[0056] Before hoisting the next section of the air duct 3, a vertical positioning bar is set on the ground and placed against the splicing end of the already hoisted air duct 3, and then the splicing end of the air duct 3 to be hoisted is pressed against the positioning bar, and then the air duct 3 is hoisted. By selecting a positioning bar of appropriate thickness, the spacing between two adjacent sections of the air duct 3 can be controlled to facilitate the subsequent splicing of the air duct 3.
[0057] S6. After the air duct 3 is hoisted, the fixed pulley 51 and the guide tube 4 are removed, and then the air duct 3 is spliced. When splicing the air duct 3, if the heights of two adjacent air ducts 3 are not aligned, the height of the next section of the air duct 3 is adjusted by rotating the adjusting screw 641 until the interfaces of the two air ducts 3 are aligned, and then the air duct 3 can be spliced.
[0058] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.
Claims
1. A laboratory air duct installation structure, Features: The invention comprises two groups of brackets (1) and a crossbeam (2) arranged between the two groups of brackets (1); the bracket (1) comprises an anchoring portion (11) and a hanging pipe (12); the anchoring portion (11) is used to be connected to a floor slab; one end of the hanging pipe (12) is fixedly connected to the anchoring portion (11); the other end of the hanging pipe (12) is detachably connected to a guide pipe (4); the crossbeam (2) is slidably sleeved with the hanging pipe (12); the crossbeam (2) is slidably sleeved with the guide pipe (4); the anchoring portion (11) is connected to a lifting assembly for lifting the crossbeam (2); The hanging tube (12) is provided with a supporting member (6) for supporting the cross beam (2), the supporting member (6) comprising a receiving box (61) arranged in the hanging tube (12), one side of the receiving box (61) is open, a wedge block (62) is inserted into the open side of the receiving box (61), a through groove (7) for the wedge block (62) to pass through is formed on the side wall of the hanging tube (12), an elastic member (63) is fixedly connected between one end of the wedge block (62) inserted into the receiving box (61) and the bottom of the receiving box (61) The inclined surface of the wedge block (62) is arranged downwards, and when the elastic member (63) is not subjected to external force, the segment of the wedge block (62) provided with the inclined surface extends out of the hanging pipe (12), and a limiting plate (8) is arranged on the side of the hanging pipe (12) facing away from the wedge block (62), and the limiting plate (8) is located above the wedge block (62), and the shortest distance between the limiting plate (8) and the wedge block (62) matches the sum of the height of the air duct (3) and the thickness of the crossbeam (2), and the side wall of the hanging pipe (12) facing away from the wedge block (62) is arranged along the length direction. A movable groove (9) is provided, one end of the limit plate (8) is inserted into the movable groove (9) and fixedly connected with a connecting rod (10), the connecting rod (10) is perpendicular to the limit plate (8), one end of the connecting rod (10) away from the limit plate (8) is fixedly connected to the accommodating box (61), the through groove (7) is provided along the length direction of the hanging tube (12), the wedge block (62) is slidably connected to the hanging tube (12) along the length direction of the through groove (7), and the hanging tube (12) is provided with an adjusting component (64) for adjusting the height of the accommodating box (61).
2. A laboratory air duct installation structure according to claim 1, Features: The lifting assembly (5) comprises a fixed pulley (51) detachably arranged on the anchoring portion (11), a pull rope (52) is wound around the fixed pulley (51), one end of the pull rope (52) is connected to the crossbeam (2), and the other end of the pull rope (52) is a force-applying end.
3. A laboratory air duct installation structure according to claim 2, Features: The adjustment assembly (64) comprises an adjustment screw (641), a bearing (642) is embedded in the lower end of the hanging tube (12), the adjustment screw (641) is rotatably connected to the hanging tube (12) via the bearing (642), a screw tube (643) is fixedly connected to the side of the accommodating box (61) away from the connecting rod (10), and the adjustment screw (641) is threadedly connected to the screw tube (643).
4. A method for installing a laboratory air duct installation structure according to any one of claims 1 to 3, Features: The following steps are involved: S1. Anchoring a plurality of brackets (1) on the lower surface of the floor slab according to the designed air duct (3) layout; S2, installing the fixed pulley (51) on the anchoring portion (11), winding the pull rope (52) around the fixed pulley (51), and adjusting the position of the pull rope (52) so that both ends of the pull rope (52) naturally hang to the ground; S3, connecting the guide tube (4) to the hanging tube (12), then sleeve the crossbeam (2) between the two guide tubes (4) and tie one end of the pull rope (52) to the crossbeam (2); S4, placing the air duct (3) on two adjacent beams (2), and then lifting the beams (2) by pulling the force-applying end of the pull rope (52) until the air duct (3) abuts against the limit plate (8); S5, repeat step S4 until all the air ducts (3) are hoisted; S6, remove the fixed pulley (51) and the guide tube (4), and then splice the air duct (3).
5. The installation method according to claim 4, Features: In step S5, when splicing the air duct (3), if the interfaces of the air duct (3) are not aligned, the height of the air duct (3) can be changed by rotating the adjusting screw (641), thereby facilitating the splicing of the air duct (3).
Citation Information
Patent Citations
Mounting rack and fresh air system
CN108870717A
Prop up top formula pipeline hoist device and system
CN206336964U
Air conditioner standard air duct patio type installation structure
CN216814560U
Hoisting system of air pipe for purification engineering
CN216952211U
Cited By
A duct installation auxiliary device for medical building purification decoration
CN122981723A