A construction method for flange-connected pipelines under trenchless conditions
Through the combination of the wire connection flange and large-diameter protective sleeve, the problem of flange connection easily breaking when the pipe is topped or pulled under non-excavation conditions is solved, and the stability and sealing of flange connection are achieved, ensuring that the The integrity of the pipeline and the normality of medium transportation.
Patent Information
- Application Number
- CN202210251241.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-03-15
- Publication Date
- 2024-11-01
- Estimated Expiration
- 2042-03-15
AI Technical Summary
Under non-excavation conditions, the flange-connected pipes are more flange-connected because the flange diameter is larger than the diameter of the pipe body, which is easy to be damaged during the pipe top or pipe pulling process, resulting in poor sealing or breaking, affecting the medium transportation.
The flange is connected by wire and combined with a large-diameter protective sleeve. Through the design of the guide curve and the traction drilling rig, the flange is subjected to uniform force during the traction process and avoid direct tension. The protective sleeve and pull head are used. Perform traction to ensure the stability of flange connection.
It effectively solves the problem that flange connections are easily damaged due to large resistance under non-excavation conditions, realizes the stability and sealing of flange connections, and ensures the integrity of the pipeline and the normality of medium transportation.
Smart Images

Figure CN115217415B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a construction method for a flange-connected pipeline, and in particular to a construction method for a flange-connected pipeline under a trenchless condition. Background Art
[0002] Trenchless technology refers to the use of rock drilling technology to lay, repair and replace pipelines without excavation or only excavating a small number of working pits. It is efficient, high-quality, moderately cost-effective, environmentally friendly, and has the advantages of not affecting traffic and not polluting the environment. In many cases, it has a shorter construction period, lower overall cost and better safety than the excavation method. It has now become the main means of urban municipal construction and is widely used in the laying of gas, electricity, telecommunications, cable TV lines, oil, natural gas, heat, drainage and other pipelines across roads, railways, buildings, rivers, and in downtown areas, monuments and protection areas, crop and vegetation protection areas, etc., where excavation is not allowed or cannot be carried out.
[0003] Previous researchers have studied many methods of pipeline construction under trenchless conditions. Xu Haixu studied the application of trenchless drilling technology in water supply pipeline construction, and used directional drilling to cross the water surface of Jiajiang River with an outer diameter of Φ842mm for more than 300 meters. Pan Jianjun studied the splicing technology of PE pipes under trenchless conditions, but most of these technical solutions are for steel pipes, polyethylene pipes, and concrete pipes, and their connection methods are usually welding, hot melt connection, etc., which are characterized by the same diameter of the interface between pipes and the pipe body. When constructing under trenchless conditions, jacking and pulling can be used, and the construction resistance is small, and it is not easy to damage the interface.
[0004] However, when the pre-laid pipeline has pressure requirements, the pipeline interface is often connected by flanges. If trenchless construction is carried out, since the diameter of the interface flange is usually larger than the diameter of the pipe body, the flange will be embedded in the soil or rock during jacking or pulling, and will be subject to great resistance. Therefore, the flange will often be damaged during the pulling process, resulting in poor sealing or even fracture at the flange connection of the pipeline, thus affecting the medium transportation of the entire pipeline. Therefore, how to realize the construction of flange-connected pipelines under trenchless conditions has become an urgent problem to be solved. Summary of the invention
[0005] Purpose of the invention: The present invention aims to improve the problems existing in the above-mentioned prior art, that is, the present invention discloses a construction method for flange-connected pipelines under trenchless conditions.
[0006] Technical solution: A construction method for flange-connected pipelines under trenchless conditions, comprising the following steps:
[0007] Step (1), determining the positions of the operation pit and the traction drilling rig on both sides of the obstacle to be crossed, then measuring and laying out the lines, and designing the guide curve so that the direction of the connection between the operation pit and the traction drilling rig is consistent with the direction of the main pipeline design;
[0008] Step (2), respectively carrying out construction work of the operation pit and installation of the traction drilling rig;
[0009] Step (3), according to the maximum outer diameter D of the flange of the through pipe 1 , determine the inner diameter D of the protective sleeve 2 , where D 2 =(1.5-2)D 1 ; Then select multiple roots with inner diameter D 2 The spiral steel pipes are connected end to end and welded to form a protective casing pipeline;
[0010] Step (4), constructing the guide hole from the operation pit to the installation location of the traction drilling rig along the guide curve:
[0011] When the guide drill reaches the expected position and the drilling trajectory matches the guide curve, stop drilling and perform 2-4 levels of pre-expansion to finally expand the hole to a diameter of D. 3 =1.5D 2 ;
[0012] Step (5), constructing the protective casing pipeline from the operation pit to the installation location of the traction drilling rig along the guide curve:
[0013] Connect one end of the traction head to one end of the protective casing pipeline, and the other end of the traction head to the drill rod and the traction drilling rig in sequence, and pull back the protective casing pipeline to form a protective casing pipeline from the operation pit to the installation location of the traction drilling rig;
[0014] Step (6), construction of the crossing pipeline:
[0015] Flanges are provided at both ends of the crossing pipe, and the flanges of adjacent crossing pipes are connected by bolts to form a crossing pipeline, wherein:
[0016] A tight steel wire for axial stress is arranged along the axial direction of the penetration tube;
[0017] Step (7), connect one end of the traction head to one end of the crossing pipeline, and connect the other end of the traction head to the drill rod and the traction drilling rig in sequence, and pull the crossing pipeline back to cross the protective casing pipeline.
[0018] Furthermore, the designing of the guide curve in step (1) includes:
[0019] (11) Select the best traversal layer based on the survey data and design the guide path based on the distance between the operating pit and the traction drill rig;
[0020] (12) Taking into account the entry angle, exit angle and curvature radius, the entry angle shall not exceed 15° and the exit angle shall not exceed 20°.
[0021] Furthermore, in step (2), the size of the operation pit is 2m×1.5m×1.5m.
[0022] Furthermore, the guide hole construction in step (4) includes:
[0023] The drilling section must be straight, and the depth must be detected every 6m. The deviation between the hole position and the guide curve must be determined based on the detection parameters and adjusted in time to ensure that the hole is drilled in the direction of the guide curve.
[0024] Furthermore, the wiring method of the steel wire in step (6) is:
[0025] One end of the steel wire is wrapped around and fixed with the bolt head of the crossing pipe, and then the other end of the steel wire is extended along the axial direction of the crossing pipe to the adjacent flange, and then the other end of the steel wire is wrapped around and fixed with the screw position at that location to lock the steel wire.
[0026] Beneficial effects: The construction method of flange-connected pipelines under trenchless conditions disclosed by the present invention has the following beneficial effects:
[0027] By combining the two technical means of using steel wire to connect the flange and adding a large-diameter protective sleeve, the problem of poor sealing or even fracture at the flange connection of the pipeline due to large resistance and easy damage of the flange during jacking or pulling of the pipe is solved, thus realizing the construction of flange-connected pipelines under non-excavation conditions. BRIEF DESCRIPTION OF THE DRAWINGS
[0028] Figure 1 A schematic diagram of a construction method for flange-connected pipelines under trenchless conditions disclosed in the present invention
[0029] Figure 2 Schematic diagram of steel wire connection.
[0030] in:
[0031] 1- Operation pit 2- Crossing pipe
[0032] 3-Protective sleeve 4-Traction head
[0033] 5-flange 6-drill rod
[0034] 7-Traction Drill 8-Bolt Head
[0035] 9-screw 10-wire DETAILED DESCRIPTION
[0036] The specific embodiments of the present invention are described in detail below.
[0037] like Figure 1-2 As shown, a construction method for flange-connected pipelines under trenchless conditions includes the following steps:
[0038] Step (1), determining the positions of the operation pit 1 and the traction drilling rig 7 on both sides of the obstacle to be crossed, then measuring and laying out the lines, and designing the guide curve so that the direction of the line connecting the operation pit 1 and the traction drilling rig 7 is consistent with the direction of the main pipeline design;
[0039] Step (2), respectively carrying out the construction work of the operation pit 1 and the installation of the traction drilling rig 7;
[0040] Step (3), according to the maximum outer diameter D of the flange 5 of the through pipe 2 1 , determine the inner diameter D of the protective sleeve 3 2 , where D 2 =1.8D 1 Then select multiple roots with inner diameter D 2 The spiral steel pipes are welded end to end to form a protective casing pipeline; in another embodiment, D 2 =1.5-D 1 In yet another embodiment, D 2 =2D 1 ;
[0041] Step (4), constructing a guide hole from the operation pit 1 to the installation location of the traction drilling rig 7 along the guide curve:
[0042] When the guide drill bit reaches the expected position and the drilling trajectory is consistent with the guide curve, the drilling is stopped and a 3-stage pre-expansion is performed (in another embodiment, a 2-stage pre-expansion is performed, and in another embodiment, a 4-stage pre-expansion is performed) to finally expand the hole to a hole diameter D 3 =1.5D 2 ;
[0043] Step (5), construction of the protective casing pipeline from the operation pit 1 to the installation location of the traction drilling rig 7 along the guide curve:
[0044] Connect one end of the traction head 4 to one end of the protective casing pipeline, and the other end of the traction head 4 is connected to the drill rod 6 and the traction drilling rig 7 in sequence, and the protective casing pipeline is pulled back to form a protective casing pipeline from the operation pit 1 to the installation location of the traction drilling rig 7;
[0045] Step (6), construction of the crossing pipeline:
[0046] Flanges 5 are provided at both ends of the crossing pipe 2, and the flanges 5 of adjacent crossing pipes 2 are connected by bolts to form a crossing pipeline, wherein:
[0047] A tight steel wire 10 for axial force is provided along the axial direction of the through pipe 2;
[0048] Step (7), connect one end of the traction head 4 to one end of the crossing pipeline, and connect the other end of the traction head 4 to the drill rod 6 and the traction drilling rig 7 in sequence, and pull the crossing pipeline back to pass through the protective casing pipeline.
[0049] Furthermore, the designing of the guide curve in step (1) includes:
[0050] (11) According to the survey data, the best traversing layer is selected, and the guiding path is designed according to the distance between the operating pit 1 and the traction drilling rig 7;
[0051] (12) Taking into account the entry angle, exit angle and curvature radius, the entry angle shall not exceed 15° and the exit angle shall not exceed 20°.
[0052] Furthermore, in step (2), the size of the operation pit 1 is 2m×1.5m×1.5m.
[0053] Furthermore, the guide hole construction in step (4) includes:
[0054] The drilling section must be straight, and the depth must be detected every 6m. The deviation between the hole position and the guide curve must be determined based on the detection parameters and adjusted in time to ensure that the hole is drilled in the direction of the guide curve.
[0055] Furthermore, the wiring method of the steel wire 10 in step (6) is:
[0056] One end of the steel wire 10 is wound and fixed with the bolt head 8 of the crossing pipe 2, and then the other end of the steel wire 10 is extended along the axial direction of the crossing pipe to the adjacent flange 5, and then the other end of the steel wire 10 is wound and fixed with the screw 9 at that location and the steel wire 10 is locked. The purpose of setting the steel wire 10 is to make the steel wire bear force first during the traction process, so as to prevent the flange 5 from being directly subjected to the tensile force in the traction direction, thereby protecting the flange 5.
[0057] The above describes the embodiments of the present invention in detail. However, the present invention is not limited to the above embodiments, and various changes can be made within the knowledge of ordinary technicians in the relevant technical field without departing from the purpose of the present invention.
Claims
1. A construction method for flange-connected pipelines under trenchless conditions, characterized in that: The following steps are involved: Step (1), determining the positions of the operation pit and the traction drilling rig on both sides of the obstacle to be crossed, then measuring and laying out the lines, and designing the guide curve so that the direction of the connection between the operation pit and the traction drilling rig is consistent with the direction of the main pipeline design; Step (2), respectively carrying out construction work of the operation pit and installation of the traction drilling rig; Step (3), according to the maximum outer diameter D1 of the flange of the through pipe, determine the inner diameter D2 of the protective sleeve, wherein D2 = (1.5-2) D1; then select a plurality of spiral steel pipes with an inner diameter of D2 and weld them end to end to form a protective sleeve pipeline; Step (4), constructing the guide hole from the operation pit to the installation location of the traction drilling rig along the guide curve: When the guide drill bit reaches the expected position and the drilling trajectory matches the guide curve, the drilling is stopped and 2-4 levels of pre-expansion are performed, and the hole is finally expanded to a hole diameter of D3 = 1.5D2; Step (5), constructing the protective casing pipeline from the operation pit to the installation location of the traction drilling rig along the guide curve: Connect one end of the traction head to one end of the protective casing pipeline, and the other end of the traction head to the drill rod and the traction drilling rig in sequence, and pull back the protective casing pipeline to form a protective casing pipeline from the operation pit to the installation location of the traction drilling rig; Step (6), construction of the crossing pipeline: Flanges are provided at both ends of the crossing pipe, and the flanges of adjacent crossing pipes are connected by bolts to form a crossing pipeline, wherein: A tight steel wire for axial stress is arranged along the axial direction of the penetration tube; Step (7), connecting one end of the traction head to one end of the crossing pipeline, and connecting the other end of the traction head to the drill rod and the traction drilling rig in sequence, towing the crossing pipeline back, and towing the crossing pipeline to cross the protective casing pipeline, wherein: The guide hole construction in step (4) includes: The drilling section must be straight, and the depth should be detected every 6m. The deviation between the hole position and the guide curve should be determined based on the detection parameters and adjusted in time to ensure that the borehole is drilled in the direction of the guide curve; The design of the guide curve in step (1) includes: (11) Select the best traversal layer based on the survey data and design the guide path based on the distance between the operating pit and the traction drill rig; (12) Taking into account the entry angle, exit angle and curvature radius, the entry angle shall not exceed 15° and the exit angle shall not exceed 20°; The wiring method of the steel wire in step (6) is: One end of the steel wire is wrapped around and fixed with the bolt head of the crossing pipe, and then the other end of the steel wire is extended along the axial direction of the crossing pipe to the adjacent flange, and then the other end of the steel wire is wrapped around and fixed with the screw position at that location to lock the steel wire.
2. A construction method for flange-connected pipelines under trenchless conditions as claimed in claim 1, characterized in that: In step (2), the size of the operation pit is 2m×1.5m×1.5m.