A method, device, equipment and medium for supervising an engineering project

By establishing a relationship in the project decomposition structure and obtaining the construction code and settlement amount, the problem of difficulty in project progress acceptance and settlement in project management is solved, and comprehensive supervision of engineering projects is achieved.

CN115222369BActive Publication Date: 2025-08-12CHINA THREE GORGES CORPORATION +1
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202210939908.3
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-08-05
Publication Date
2025-08-12
Estimated Expiration
2042-08-05

AI Technical Summary

Technical Problem

In the existing technology, project managers are unable to understand the actual progress of the project from all aspects at any time, which leads to the inability to promptly advance the project progress acceptance and difficulty in completing the project settlement.

Method used

By establishing the correlation between the project decomposition structure, unit decomposition structure and work decomposition structure, obtain the construction code and settlement amount, and use the measurement visa form, bill of quantity and budget details for monitoring and management.

Benefits of technology

It realizes a timely correlation between project progress, quality and settlement, solves the problems of project progress acceptance and settlement, and realizes comprehensive supervision of project projects.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN115222369B_ABST
    Figure CN115222369B_ABST
Patent Text Reader

Abstract

The present invention discloses a method, device, equipment and medium for supervising an engineering project, comprising: receiving identification information transmitted by a first project decomposition item; determining, based on the identification information, a second project decomposition item corresponding to the information from a pre-built unit decomposition structure; establishing a first association relationship between the two; establishing a second association relationship between the second project decomposition item and the third project decomposition item based on the first association relationship and a third project decomposition item corresponding to the first project decomposition item in a work breakdown structure; obtaining status information of the second project decomposition item; when the status information of the second project decomposition item is qualified, obtaining a construction code of a construction item corresponding thereto; determining an actual settlement amount based on the construction code, a measurement visa, a bill of quantities and a budget detail sheet; monitoring and managing the project decomposition items in the work breakdown structure and the unit decomposition structure, as well as the actual settlement amount, based on the second association relationship and the bill of quantities.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of construction engineering, and in particular to a method, device, equipment and medium for supervising an engineering project. Background Art

[0002] During the construction process, the management of large and complex group projects is highly complex and inefficient. In the current project management process, there are problems such as the inability to make reasonable arrangements after project decomposition, the inability to promptly advance the project progress through project quality acceptance, and the inability to settle payments for completed projects. As a result, project managers or other staff are unable to understand the actual progress of the project from all aspects at any time.

[0003] Therefore, how to enable project managers to understand the current progress of the project in terms of project progress, quality and project settlement at any time is a problem that needs to be solved. Summary of the Invention

[0004] Therefore, the technical problem to be solved by the present invention is to overcome the defect in the prior art that project managers or other staff cannot understand the actual progress of the project from all aspects at any time, thereby providing a project supervision method, device, equipment and medium.

[0005] In a first aspect, the present invention provides a method for supervising an engineering project, comprising: receiving identification information transmitted by a first project decomposition item in a pre-constructed project decomposition structure, wherein the first project decomposition item is any decomposition item in the project decomposition structure; determining, based on the identification information, a second project decomposition item corresponding to the identification information from a pre-constructed unit decomposition structure, the second project decomposition item being a project decomposition item in the unit decomposition structure to be associated with the first project decomposition item; establishing a first association relationship between the first project decomposition item and the second project decomposition item; establishing a second association relationship between the second project decomposition item and the third project decomposition item based on the first association relationship and a third project decomposition item corresponding to the first project decomposition item in a pre-constructed work breakdown structure; obtaining status information of the second project decomposition item; when the status information of the second project decomposition item is qualified, obtaining a construction code of a construction item corresponding to the second project decomposition item; determining an actual settlement amount of the second project decomposition item based on the construction code, a pre-acquired measurement certification sheet, a pre-acquired bill of quantities, and a pre-acquired budget detail sheet; monitoring and managing the project decomposition items in the work breakdown structure and the unit decomposition structure, and the actual settlement amount based on the second association relationship and the bill of quantities.

[0006] The present invention associates the identification information transmitted by the first project decomposition item of the project decomposition structure with the second project decomposition item in the unit decomposition structure, thereby forming a first association relationship between the project decomposition structure and the unit decomposition structure; associates the third project decomposition item in the work breakdown structure with the first project decomposition item in the project decomposition structure, and combines the work breakdown structure and the unit decomposition structure with the project decomposition structure in combination with the first association relationship, thereby forming a second association relationship between the work breakdown structure and the unit decomposition structure, namely, work breakdown structure-project breakdown structure-unit decomposition structure, thereby completing the association between project progress and project quality; after the second association relationship is established, when the project is completed to a certain stage, the progress from the unit decomposition structure is completed. The status of the second project decomposition item is obtained from the unit decomposition structure. When the status of the second project decomposition item is qualified, the construction code of the construction item corresponding to the second project decomposition item is obtained. According to the construction code of each construction item, the pre-acquired measurement certification form, the pre-acquired bill of quantities and the pre-acquired budget details, the actual settlement amount of the second project decomposition item is determined. In this way, the second project decomposition item in the unit decomposition structure is associated with the actual settlement amount, and the association between quality and settlement amount is completed. Therefore, this method solves the problems in the prior art that the acceptance of project progress cannot advance the project progress in time and cannot settle the completed project, and enables project personnel to supervise the project from the aspects of project progress, project quality and project settlement.

[0007] In combination with the first aspect, in a first embodiment of the first aspect, the actual settlement amount of the second project decomposition item is determined based on the construction code, the pre-acquired measurement certificate, the pre-acquired bill of quantities and the pre-acquired budget details, including: determining the usage of the construction item corresponding to the construction code based on the construction code and the pre-acquired measurement certificate; based on the construction code, obtaining the unit price of the construction item corresponding to the construction code and the contract amount of the construction item corresponding to the construction code from the pre-acquired bill of quantities; based on the construction code, obtaining the budget amount of the construction item corresponding to the construction code from the pre-acquired budget details; determining the actual settlement amount of the construction item corresponding to the construction code based on the usage, unit price, contract amount and budget amount; determining the actual settlement amount of the second project decomposition item based on the actual settlement amount of the construction item corresponding to the construction code.

[0008] By obtaining the construction code of the construction item corresponding to the second project decomposition item with a qualified status, the usage, unit price, contract amount and budget amount of the construction item corresponding to the construction code are determined from the pre-acquired measurement certification form, the pre-acquired bill of quantities and the pre-acquired budget details form through the construction code, and finally the actual settlement amount of the second project decomposition item is determined through the usage, unit price, contract amount and budget amount of the construction item corresponding to the construction code. This solves the problem in the existing technology that completed engineering projects cannot be settled, realizes the association between quality and amount settlement, and facilitates settlement management of projects that have passed acceptance.

[0009] In combination with the first aspect, in the second embodiment of the first aspect, the usage quantity of the construction item corresponding to the construction code is determined based on the construction code and the pre-acquired measurement visa form, including: obtaining the audit quantity of the construction item corresponding to the construction code from the measurement visa form based on the construction code; and determining the audit quantity as the usage quantity.

[0010] In combination with the first aspect, in the third embodiment of the first aspect, the actual settlement amount of the construction item corresponding to the construction code is determined based on the usage, unit price, contract amount and budget amount, including: determining the amount to be settled of the construction item corresponding to the construction code based on the usage and unit price; determining the actual settlement amount of the construction item corresponding to the construction code based on the amount to be settled, the contract amount and the budget amount.

[0011] In combination with the first aspect, in the fourth embodiment of the first aspect, the actual settlement amount of the construction item corresponding to the construction code is determined based on the amount to be settled, the contract amount and the budget amount, including: determining the conversion ratio based on the amount to be settled and the budget amount; determining the actual settlement amount of the construction item corresponding to the construction code based on the conversion ratio and the contract amount.

[0012] In a second aspect, the present invention provides an engineering project supervision device, comprising: a receiving module for receiving identification information transmitted by a first project decomposition item in a pre-constructed project decomposition structure, wherein the first project decomposition item is any decomposition item in the project decomposition structure; a first determining module for determining, based on the identification information, a second project decomposition item corresponding to the identification information from a pre-constructed unit decomposition structure, wherein the second project decomposition item is a project decomposition item in the unit decomposition structure to be associated with the first project decomposition item; a first establishing module for establishing a first association relationship between the first project decomposition item and the second project decomposition item; and a second establishing module for determining, based on the first association relationship and the first association relationship in the pre-constructed work breakdown structure. a third project decomposition item corresponding to the project decomposition item, establishing a second association relationship between the second project decomposition item and the third project decomposition item; a first acquisition module, used to obtain status information of the second project decomposition item; a second acquisition module, used to obtain the construction code of the construction item corresponding to the second project decomposition item when the status information of the second project decomposition item is qualified; a second determination module, used to determine the actual settlement amount of the second project decomposition item based on the construction code, the pre-acquired measurement certification sheet, the pre-acquired bill of quantities and the pre-acquired budget details sheet; a supervision module, used to monitor and manage the project decomposition items in the work breakdown structure and unit decomposition structure, as well as the actual settlement amount, based on the second association relationship and the bill of quantities.

[0013] In combination with the second aspect, in the first embodiment of the second aspect, the second determination module includes: a first determination sub-module, used to determine the usage of the construction item corresponding to the construction code based on the construction code and the pre-acquired measurement certification sheet; a first acquisition sub-module, used to obtain the unit price of the construction item corresponding to the construction code and the contract amount of the construction item corresponding to the construction code from the pre-acquired bill of quantities based on the construction code; a second acquisition sub-module, used to obtain the budget amount of the construction item corresponding to the construction code from the pre-acquired budget details sheet based on the construction code; the second determination sub-module, used to determine the actual settlement amount of the construction item corresponding to the construction code based on the usage, unit price, contract amount and budget amount.

[0014] In combination with the second aspect, in the second embodiment of the second aspect, the first determination submodule includes: an acquisition unit for obtaining the audit quantity of the construction item corresponding to the construction code from the measurement visa form based on the construction code; and a determination unit for determining the audit quantity as the usage quantity.

[0015] In a third aspect, the present invention provides a computer device comprising: a memory and a processor, the memory and the processor being communicatively connected to each other, the memory being used to store a computer program, and when the computer program is executed by the processor, the processor executes an engineering project supervision method as described in any one of the invention contents.

[0016] In a fourth aspect, the present invention provides a computer-readable storage medium for storing computer instructions, which, when executed by a processor, implements an engineering project supervision method as described in any one of the invention contents. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] In order to more clearly illustrate the specific embodiments of the present invention or the technical solutions in the prior art, the following briefly introduces the drawings required for use in the specific embodiments or the description of the prior art. Obviously, the drawings described below are some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying any creative work.

[0018] Figure 1 A flowchart of a method for supervising an engineering project provided by an embodiment of the present invention.

[0019] Figure 2 A connection diagram of the engineering project monitoring device provided in an embodiment of the present invention.

[0020] Figure 3 A diagram showing the connection of computer devices according to an embodiment of the present invention. DETAILED DESCRIPTION

[0021] The technical solution of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the embodiments described are only some embodiments of the present invention, not all embodiments. All other embodiments obtained by ordinary technicians in this field based on the embodiments of the present invention without making any creative efforts shall fall within the scope of protection of the present invention.

[0022] The present invention discloses a method for supervising an engineering project. Figure 1 As shown, the following steps are included:

[0023] Step S1: receiving identification information transmitted by a first project decomposition item in a pre-built project decomposition structure, wherein the first project decomposition item is any decomposition item in the project decomposition structure.

[0024] Specifically, before step S1, the pre-built project breakdown structure, pre-built unit breakdown structure, pre-built work breakdown structure, pre-acquired measurement engineering bill, pre-acquired bill of quantities and pre-acquired budget details are first imported into the system. Among them, the project breakdown structure (PBS) is a structure formed by the project management personnel through the decomposition of project entity objects. PBS decomposes project outputs, and the decomposed objects are deliverables; the unit breakdown structure is a decomposition structure obtained by dividing the target project according to the work specifications required to be achieved in the contract or in accordance with the national industry standards; the work breakdown structure (PBS) is a structure formed by the project management personnel through the decomposition of project entity objects. WBS (Work Schema Structure) is a work process decomposition oriented towards project output. The object of decomposition is work. WBS decomposes the project plan into different tasks according to the project progress based on the specific project objects sorted out by PBS, and then decomposes the tasks into individual works. Among them, when constructing the actual project decomposition structure, the project decomposition structure can adopt the same structure as the unit decomposition structure, or a different structure. As shown in Table 1, it is the unit decomposition structure of a certain engineering project, which is divided by level. The smallest unit in the unit decomposition structure is the inspection lot, which is also the smallest unit in the quality inspection process.

[0025]

[0026] Table 1

[0027] Specifically, in the project breakdown structure, unit breakdown structure, and work breakdown structure, each structure has several decomposition items corresponding to each structure with identification information that uniquely identifies the decomposition item. The identification information can be a code composed of numbers, a string of characters, etc.

[0028] Step S2: according to the identification information, determine a second project decomposition item corresponding to the identification information from the pre-built unit decomposition structure, where the second project decomposition item is a project decomposition item in the unit decomposition structure to be associated with the first project decomposition item.

[0029] Specifically, after receiving the identification information input by the user at the association interface corresponding to the first project decomposition item of the project decomposition structure, the system will search for the second project decomposition item corresponding to the identification information from the unit decomposition structure based on the identification information, wherein the project decomposition structure has been bound to the unit decomposition structure when it was imported, so the second project decomposition item to be associated can be directly determined from the unit decomposition structure based on the identification information; for example, in the PBS of a certain engineering project, there is a first project decomposition item "A", and the system receives the identification information 01010101 input by the user from this decomposition item interface at the corresponding association interface of "", and according to this identification information, obtains the second project decomposition item "B" corresponding to 01010101 from the unit decomposition structure associated with the project decomposition structure.

[0030] Step S3: establishing a first association relationship between the first project decomposition item and the second project decomposition item.

[0031] Specifically, after the system determines the second project decomposition item corresponding to the identification information transmitted by the first project decomposition item, the system binds the first project decomposition item with the second project decomposition item, thereby establishing a first association relationship between the first project decomposition item and the second project decomposition item. As described in the above embodiment, the first project decomposition item in the project decomposition structure is bound to the second project decomposition item in the unit decomposition structure, and the first association relationship between the first project decomposition item and the second project decomposition item is established.

[0032] Step S4: establishing a second association relationship between the second project decomposition item and the third project decomposition item according to the first association relationship and the third project decomposition item corresponding to the first project decomposition item in the pre-built work breakdown structure.

[0033] Specifically, in the work breakdown structure, there is a third project decomposition item corresponding to the first project decomposition item. In this embodiment, by receiving the identification information transmitted by the third project decomposition item, the first project decomposition item corresponding to the identification information is searched from the project decomposition structure according to the identification information, so as to establish a connection between the first project decomposition item and the third project decomposition item. After the connection relationship between the first project decomposition item and the third project decomposition item is established, the first association relationship between the first project decomposition item and the second project decomposition item is combined to form a connection relationship with the first project decomposition item as the intermediate item, and the second project decomposition item and the third project decomposition item are both connected to it, thereby establishing the second project decomposition item. The second association relationship between the decomposition item and the third project decomposition item; for example, in the WBS, there is a third project decomposition item "X", and the system receives the identification information 01010102 transmitted from this decomposition item. According to this identification information, the system obtains the first project decomposition item "Y" corresponding to 01010102 from the PBS associated with the WBS, and connects the third project decomposition item with the first project decomposition item through the identification information 01010102. Prior to this, a first association relationship has been established between the first project decomposition item and the second project decomposition item, thereby establishing a second association relationship between the second project decomposition item and the third project decomposition item through the first project decomposition item.

[0034] Step S5: Obtain status information of the second project decomposition item.

[0035] Specifically, after establishing the second association relationship between the second project decomposition item and the third project decomposition item, when the project progresses to a certain stage, the status information of the second project decomposition item can be viewed from the unit decomposition structure. The status information may include under construction, under inspection or qualified, etc.; under construction means that the current second project decomposition item is still in an unfinished state, under inspection means that the current second project decomposition item has been completed and is in the supervision or owner inspection and evaluation period, qualified means that the current second project decomposition item has been completed, the inspection and evaluation has been completed and the inspection and evaluation result is qualified. In addition, when the inspection and evaluation result is unqualified, the second project decomposition item needs to be re-constructed, so when the inspection and evaluation result is unqualified, its status is under construction.

[0036] Step S6: When the status information of the second project decomposition item is qualified, the construction code of the construction item corresponding to the second project decomposition item is obtained.

[0037] Specifically, when the status information of the second project decomposition item obtained is qualified, it means that the second project decomposition item can enter the project payment settlement link. At this time, the construction code of the construction item corresponding to the current second project decomposition item is obtained. The construction item can be the materials or other aspects that require capital investment during the construction process of the second project decomposition item; the construction code is a unique code used to identify the construction item, and the construction code can be in the form of a numeric string, a character string, etc.

[0038] Specifically, when the status of the second project decomposition item "Data Center Earthwork Excavation" is qualified, obtain the construction items corresponding to the second project decomposition item. The construction items corresponding to the "Data Center Earthwork Excavation" are "Leveling the Site", "Digging Trench Earthwork", "Digging Foundation Pit Earthwork", and "Abandonment of Remaining Volume". Obtain the construction codes of the four construction items corresponding to the "Data Center Earthwork Excavation" respectively, namely the construction code of "Leveling the Site", the construction code of "Digging Trench Earthwork", the construction code of "Digging Foundation Pit Earthwork", and the construction code of "Abandonment of Remaining Volume".

[0039] Step S7: Based on the construction code, the pre-acquired measurement certification form, the pre-acquired bill of quantities, and the pre-acquired budget details, determine the actual settlement amount of the second project breakdown item.

[0040] Specifically, based on the construction code, the measurement information of the construction item corresponding to the construction code is obtained from the pre-acquired measurement certificate, based on the construction code, the amount information of the construction item corresponding to the construction code is obtained from the pre-acquired engineering quantity certificate, based on the construction code, the budget information of the construction item corresponding to the construction code is obtained from the pre-acquired budget details sheet, and the actual settlement amount of the construction item corresponding to the construction code is determined according to the measurement information of the construction item corresponding to the construction code, the amount information of the construction item corresponding to the construction code, and the budget information of the construction item corresponding to the construction code; based on the actual settlement amount of the construction item corresponding to the construction code, the actual settlement amount of the second project decomposition item is determined.

[0041] Specifically, based on the measurement information of the construction item corresponding to the construction code in the measurement certificate and the first amount information of the construction quantity corresponding to the construction code in the bill of quantities, the payable settlement information of the construction item corresponding to the construction code is determined; based on the payable settlement amount of the construction item corresponding to the construction code, the payable settlement information of the second project breakdown item is determined; based on the identification information of the second project breakdown item, the second amount information of the second project breakdown item corresponding to the identification information is obtained from the bill of quantities; based on the identification information of the second project breakdown item, the budget information of the second project breakdown item corresponding to the identification information is obtained from the budget breakdown sheet; and based on the payable settlement amount of the second project breakdown item, the budget information of the second project breakdown item, and the amount information of the second project breakdown item, the actual settlement amount of the second project breakdown item is determined.

[0042] Step S8: Based on the second association relationship and the bill of quantities, monitor and manage the project breakdown items in the work breakdown structure and the unit breakdown structure, as well as the actual settlement amount.

[0043] Specifically, based on the second correlation between the third project decomposition item and the second project decomposition item, the correlation between the project progress and the project quality is realized. Through the bill of quantities, the construction code corresponding to the construction item in the second project decomposition item is used to associate the second project decomposition item that has passed the inspection and evaluation with the settlement amount of the second project decomposition item, thereby realizing the correlation between the project quality and the project settlement. Therefore, this method realizes the connection between the three aspects of project progress, project quality and project settlement by taking project quality as the intermediate bridge, so that when the project progresses to a certain stage, it is convenient to understand the inspection and evaluation progress of the currently completed project and the settlement degree of the engineering projects that have passed the inspection and evaluation, thereby realizing the supervision of the project.

[0044] Specifically, a second association relationship is established between the second project decomposition item and the third project decomposition item based on the project decomposition structure, unit decomposition structure and work breakdown structure of the engineering project. For example, the third project decomposition item "pile foundation detection subunit" is associated with the "dry operation bored cast-in-place pile inspection batch" in the second project decomposition item through the first project decomposition item. When it is checked from the work breakdown structure that the current third project decomposition item "pile foundation detection subunit" has been completed, the second project decomposition item "dry operation bored cast-in-place pile inspection batch" associated with the "pile foundation detection subunit" can be quality inspected. When the dry operation bored cast-in-place pile inspection batch passes the inspection, the construction codes of each construction item corresponding to the "dry operation bored cast-in-place pile inspection batch" can be obtained, such as the construction items and codes corresponding to the "dry operation bored cast-in-place pile inspection batch". For "mud wall bored cast-in-place piles D800 (0101010202)", "post-grouting of bored cast-in-place piles (0101010208)", "rebar cage (0101010209)", and "cut (chisel) pile heads (0101010210)", the corresponding measurement information, amount information, and budget information are obtained from the pre-acquired measurement certification form, the pre-acquired bill of quantities, and the pre-acquired budget details based on the construction code to determine the actual settlement amount of the "dry operation bored cast-in-place pile inspection batch". Therefore, according to the second association relationship between the second project decomposition item "dry operation bored cast-in-place pile inspection batch" and the third project decomposition item "pile foundation detection subunit" and the information in the bill of quantities, the project progress, quality inspection, and project payment settlement are monitored and managed.

[0045] The present invention associates the identification information transmitted by the first project decomposition item of the project decomposition structure with the second project decomposition item in the unit decomposition structure, thereby forming a first association relationship between the project decomposition structure and the unit decomposition structure; associates the third project decomposition item in the work breakdown structure with the first project decomposition item in the project decomposition structure, and combines the work breakdown structure and the unit decomposition structure with the project decomposition structure in combination with the first association relationship, thereby forming a second association relationship between the work breakdown structure and the unit decomposition structure, namely, work breakdown structure-project breakdown structure-unit decomposition structure, thereby completing the association between project progress and project quality; after the second association relationship is established, when the project is completed to a certain stage, the progress from the unit decomposition structure is completed. The status of the second project decomposition item is obtained from the unit decomposition structure. When the status of the second project decomposition item is qualified, the construction code of the construction item corresponding to the second project decomposition item is obtained. According to the construction code of each construction item, the pre-acquired measurement certification form, the pre-acquired bill of quantities and the pre-acquired budget details, the actual settlement amount of the second project decomposition item is determined. In this way, the second project decomposition item in the unit decomposition structure is associated with the actual settlement amount, and the association between quality and settlement amount is completed. Therefore, this method solves the problems in the prior art that the acceptance of project progress cannot advance the project progress in time and cannot settle the completed project, and enables project personnel to supervise the project from the aspects of project progress, project quality and project settlement.

[0046] In an optional embodiment, the actual settlement amount of the second project decomposition item is determined based on the construction code, the pre-acquired measurement certificate, the pre-acquired bill of quantities and the pre-acquired budget statement, including: determining the usage of the construction item corresponding to the construction code based on the construction code and the pre-acquired measurement certificate; based on the construction code, obtaining the unit price of the construction item corresponding to the construction code and the contract amount of the construction item corresponding to the construction code from the pre-acquired bill of quantities; based on the construction code, obtaining the budget amount of the construction item corresponding to the construction code from the pre-acquired budget statement; determining the actual settlement amount of the construction item corresponding to the construction code based on the usage, unit price, contract amount and budget amount; and determining the actual settlement amount of the second project decomposition item based on the actual settlement amount of the construction item corresponding to the construction code.

[0047] Exemplarily, when the status information of the second project decomposition item is obtained as qualified, the construction code of the construction item corresponding to the second project decomposition item is obtained, and the usage of the construction item corresponding to the construction code is determined based on the construction code and the pre-acquired measurement certificate. For example, the second project decomposition item "Data Center 1# Dry Operation Bored Pile Inspection Batch" corresponds to four construction items, one of which is the cutting (chiseling) of pile heads with the construction code "0101010210". Based on the construction code "at 101010210" and the measurement certificate, the usage of the cutting (chiseling) of pile heads for the construction item corresponding to the construction code is determined; similarly, based on the construction code 0101010210, the unit price and contract amount of the cutting (chiseling) of pile heads for the construction item corresponding to the construction code are obtained from the bill of quantities, and the budget amount of the (chiseling) of pile heads for the construction item corresponding to the construction code is obtained from the budget details sheet. The actual settlement amount is determined based on the usage, unit price, budget amount and contract amount of the construction item corresponding to the obtained construction code.

[0048] By obtaining the construction code of the construction item corresponding to the second project decomposition item with a qualified status, the usage, unit price, contract amount and budget amount of the construction item corresponding to the construction code are determined from the pre-acquired measurement certification form, the pre-acquired bill of quantities and the pre-acquired budget details form through the construction code, and finally the actual settlement amount of the second project decomposition item is determined through the usage, unit price, contract amount and budget amount of the construction item corresponding to the construction code. This solves the problem in the existing technology that completed engineering projects cannot be settled, realizes the association between quality and amount settlement, and facilitates settlement management of projects that have passed acceptance.

[0049] In an optional embodiment, the usage quantity of the construction item corresponding to the construction code is determined based on the construction code and the pre-acquired measurement certificate, including: obtaining the audit quantity of the construction item corresponding to the construction code from the measurement certificate based on the construction code; and determining the audit quantity as the usage quantity.

[0050] Exemplarily, the audited quantity of the construction item corresponding to the construction code is obtained from the measurement certification form. The audited quantity is the usage quantity of the construction item finally determined through the review during the inspection and evaluation, so the audited quantity is determined as the usage quantity of the construction item.

[0051] In an optional embodiment, the actual settlement amount of the construction item corresponding to the construction code is determined based on the usage, unit price, contract amount and budget amount, including: determining the amount to be settled of the construction item corresponding to the construction code based on the usage and unit price; determining the actual settlement amount of the construction item corresponding to the construction code based on the amount to be settled, the contract amount and the budget amount.

[0052] For example, after obtaining the usage and unit price corresponding to the construction item based on the construction code, the actual amount to be settled for the construction item is determined based on the actual usage and unit price of the construction item, that is, the amount to be settled is the product of the unit price and the usage, thereby determining the amount to be settled for the construction item corresponding to the construction code.

[0053] For example, since the contract amount has been determined before the project construction, the contract amount is the total amount of the final actual settlement of the project. Therefore, after determining the amount to be settled for the construction item, the final actual settlement amount must be determined based on the contract amount and budget amount of the construction item.

[0054] In an optional embodiment, the actual settlement amount of the construction item corresponding to the construction code is determined based on the amount to be settled, the contract amount and the budget amount, including: determining the conversion ratio based on the amount to be settled and the budget amount; determining the actual settlement amount of the construction item corresponding to the construction code based on the conversion ratio and the contract amount.

[0055] For example, the conversion ratio The conversion process is:

[0056]

[0057] in, Indicates the amount to be settled. It represents the budget amount, which is the amount estimated based on the actual situation when the project starts.

[0058] For example, the actual settlement amount The determination process is:

[0059]

[0060] in, Indicates the conversion ratio. Indicates the contract amount.

[0061] In another optional embodiment, the construction code of the first construction item in the second project decomposition item is obtained, wherein the first construction item is any construction item in the second project decomposition item; based on the construction code of the first construction item, the usage of the first construction item corresponding to the construction code is obtained from the measurement certificate; based on the construction code of the first construction item, the unit price of the first construction item corresponding to the construction code is obtained from the bill of quantities; the settleable amount of the first construction item is determined based on the usage of the first construction item and the unit price of the first construction item; the settleable amount of the second project decomposition item is determined based on the settleable amounts of all the first construction items corresponding to the second project decomposition item; based on the identification information of the second project decomposition item, the contract amount of the second project decomposition item corresponding to the identification information is determined from the bill of quantities; based on the second project decomposition item, the budget amount of the second project decomposition item corresponding to the identification information is determined from the budget details sheet; the conversion ratio is determined based on the settleable amount of the second project decomposition item and the budget amount of the second project decomposition item; the actual settlement amount of the second project decomposition item is determined based on the conversion ratio of the second project decomposition item and the contract amount of the second project decomposition item.

[0062] The present invention discloses a project supervision device, such as Figure 2 As shown, specifically including:

[0063] The receiving module 21 is configured to receive identification information transmitted by a first project decomposition item in a pre-built project decomposition structure, wherein the first project decomposition item is any decomposition item in the project decomposition structure;

[0064] A first determining module 22 is configured to determine, based on the identification information, a second project decomposition item corresponding to the identification information from the pre-built unit decomposition structure, where the second project decomposition item is a project decomposition item in the unit decomposition structure to be associated with the first project decomposition item;

[0065] A first establishing module 23 is configured to establish a first association relationship between the first project decomposition item and the second project decomposition item;

[0066] A second establishing module 24 is configured to establish a second association relationship between the second project decomposition item and the third project decomposition item based on the first association relationship and the third project decomposition item corresponding to the first project decomposition item in the pre-built work breakdown structure;

[0067] A first acquisition module 25 is used to obtain status information of the second project decomposition item;

[0068] The second acquisition module 26 is configured to acquire the construction code of the construction item corresponding to the second project decomposition item when the status information of the second project decomposition item is qualified;

[0069] A second determining module 27 is configured to determine the actual settlement amount of the second project breakdown item based on the construction code, the pre-acquired measurement certification sheet, the pre-acquired bill of quantities, and the pre-acquired budget breakdown sheet;

[0070] The supervision module 28 is used to monitor and manage the project breakdown items in the work breakdown structure and the unit breakdown structure, as well as the actual settlement amount based on the second association relationship and the bill of quantities.

[0071] In an optional embodiment, the second determination module includes: a first determination submodule, which is used to determine the usage of the construction item corresponding to the construction code based on the construction code and the pre-acquired measurement certification form; a first acquisition submodule, which is used to obtain the unit price of the construction item corresponding to the construction code and the contract amount of the construction item corresponding to the construction code from the pre-acquired bill of quantities based on the construction code; a second acquisition submodule, which is used to obtain the budget amount of the construction item corresponding to the construction code from the pre-acquired budget details based on the construction code; a second determination submodule, which is used to determine the actual settlement amount of the construction item corresponding to the construction code based on the usage, unit price, contract amount and budget amount; and a third determination submodule, which is used to determine the actual settlement amount of the second project decomposition item based on the actual settlement amount of the construction item corresponding to the construction code.

[0072] In an optional embodiment, the first determination submodule includes: an acquisition unit for acquiring the audit quantity of the construction item corresponding to the construction code from the measurement certification form based on the construction code; and a determination unit for determining the audit quantity as the usage quantity.

[0073] In an optional embodiment, the second determination submodule includes: a first determination unit, used to determine the settlement amount of the construction item corresponding to the construction code based on the usage and unit price; a second determination unit, used to determine the actual settlement amount of the construction item corresponding to the construction code based on the settlement amount, the contract amount and the budget amount.

[0074] In an optional embodiment, the second determination unit includes: a first determination subunit, used to determine the conversion ratio based on the amount to be settled and the budget amount; and a second determination subunit, used to determine the actual settlement amount of the construction item corresponding to the construction code based on the conversion ratio and the contract amount.

[0075] This embodiment provides a computer device, such as Figure 3As shown, the computer device may include at least one processor 31, at least one communication interface 32, at least one communication bus 33 and at least one memory 34, wherein the communication interface 32 may include a display screen (Display), a keyboard (Keyboard), and optionally the communication interface 32 may also include a standard wired interface, a wireless interface. The memory 34 may be a high-speed RAM memory (Random Access Memory, volatile random access memory) or a non-volatile memory (non-volatile memory), such as at least one disk storage. The memory 34 may also be at least one storage device located away from the aforementioned processor 31. The processor 31 may be combined with Figure 3 In the described device, the memory 34 stores an application program, and the processor 31 calls the program code stored in the memory 34 to execute the engineering project supervision method of any of the above method embodiments.

[0076] The communication bus 33 may be a peripheral component interconnect (PCI) bus or an extended industry standard architecture (EISA) bus. The communication bus 33 may be divided into an address bus, a data bus, a control bus, etc. For ease of representation, Figure 3 Only one thick line is used in the diagram, but this does not mean that there is only one bus or one type of bus.

[0077] The memory 34 may include volatile memory, such as random-access memory (RAM); the memory may also include non-volatile memory, such as flash memory, a hard disk drive (HDD), or a solid-state drive (SSD); the memory 34 may also include a combination of the above-mentioned types of memory.

[0078] The processor 31 may be a central processing unit (CPU), a network processor (NP), or a combination of a CPU and a NP.

[0079] The processor 31 may further include a hardware chip. The hardware chip may be an application-specific integrated circuit (ASIC), a programmable logic device (PLD), or a combination thereof. The PLD may be a complex programmable logic device (CPLD), a field-programmable gate array (FPGA), a generic array logic (GAL), or any combination thereof. Optionally, the memory 34 is also used to store program instructions. The processor 31 may invoke the program instructions to implement the engineering project supervision method of any embodiment of the present invention.

[0080] This embodiment provides a computer-readable storage medium storing computer-executable instructions capable of executing the project supervision method described in any of the above method embodiments. The storage medium may be a magnetic disk, an optical disk, a read-only memory (ROM), a random access memory (RAM), a flash memory, a hard disk drive (HDD), or a solid-state drive (SSD); the storage medium may also include a combination of the aforementioned types of memory.

[0081] Obviously, the above embodiments are merely examples for clarity of explanation and are not intended to limit the implementation methods. Those skilled in the art will readily appreciate that other variations or modifications based on the above descriptions are possible. It is not necessary and impossible to enumerate all implementation methods here. Obvious variations or modifications arising therefrom remain within the scope of protection of the present invention.

Claims

1. A method for supervising an engineering project, characterized in that: include: receiving identification information transmitted by a first project decomposition item in a pre-built project decomposition structure, wherein the first project decomposition item is any decomposition item in the project decomposition structure; determining, based on the identification information, a second project decomposition item corresponding to the identification information from a pre-built unit decomposition structure, where the second project decomposition item is a project decomposition item in the unit decomposition structure to be associated with the first project decomposition item; Establishing a first association relationship between the first project decomposition item and the second project decomposition item; Establishing a second association relationship between the first project decomposition item and the third project decomposition item according to the first association relationship and a third project decomposition item corresponding to the first project decomposition item in the pre-built work breakdown structure; Obtaining status information of the second project decomposition item; When the status information of the second project decomposition item is qualified, obtaining the construction code of the construction item corresponding to the second project decomposition item; Determine the actual settlement amount of the second project breakdown item based on the construction code, the pre-acquired measurement certification form, the pre-acquired bill of quantities, and the pre-acquired budget breakdown; Based on the second association relationship and the bill of quantities, the work breakdown structure, the project breakdown items in the unit breakdown structure, and the actual settlement amount are monitored and managed.

2. The engineering project supervision method according to claim 1, characterized in that: The determining the actual settlement amount of the second project breakdown item based on the construction code, the pre-acquired measurement certification sheet, the pre-acquired bill of quantities, and the pre-acquired budget details sheet includes: Determining the usage of the construction item corresponding to the construction code based on the construction code and the pre-acquired measurement certificate; Based on the construction code, obtaining the unit price of the construction item corresponding to the construction code and the contract amount of the construction item corresponding to the construction code from the pre-acquired bill of quantities; Based on the construction code, obtaining the budget amount of the construction item corresponding to the construction code from the pre-obtained budget details sheet; Determine the actual settlement amount of the construction item corresponding to the construction code based on the usage, the unit price, the contract amount and the budget amount; The actual settlement amount of the second project decomposition item is determined based on the actual settlement amount of the construction item corresponding to the construction code.

3. The engineering project supervision method according to claim 2, characterized in that: The determining the usage of the construction item corresponding to the construction code based on the construction code and the pre-acquired measurement certificate includes: Based on the construction code, obtain the audit quantity of the construction item corresponding to the construction code from the measurement certification sheet; The audit amount is determined as the usage amount.

4. The engineering project supervision method according to claim 2, characterized in that: The determining the actual settlement amount of the construction item corresponding to the construction code based on the usage, the unit price, the contract amount, and the budget amount includes: Determine the amount to be settled for the construction item corresponding to the construction code based on the usage amount and the unit price; The actual settlement amount of the construction item corresponding to the construction code is determined based on the amount to be settled, the contract amount and the budget amount.

5. The engineering project supervision method according to claim 4, characterized in that: The determining the actual settlement amount of the construction item corresponding to the construction code based on the settlement amount, the contract amount, and the budget amount includes: Determine a conversion ratio based on the amount to be settled and the budget amount; The actual settlement amount of the construction item corresponding to the construction code is determined based on the conversion ratio and the contract amount.

6. A project supervision device, characterized in that: include: a receiving module, configured to receive identification information transmitted by a first project decomposition item in a pre-built project decomposition structure, wherein the first project decomposition item is any decomposition item in the project decomposition structure; a first determining module configured to determine, based on the identification information, a second project decomposition item corresponding to the identification information from a pre-built unit decomposition structure, where the second project decomposition item is a project decomposition item in the unit decomposition structure to be associated with the first project decomposition item; A first establishing module, configured to establish a first association relationship between the first project decomposition item and the second project decomposition item; a second establishing module, configured to establish a second association relationship between the second project decomposition item and the third project decomposition item based on the first association relationship and a third project decomposition item corresponding to the first project decomposition item in a pre-built work breakdown structure; A first acquisition module is used to obtain status information of the second project decomposition item; A second acquisition module is configured to acquire a construction code of a construction item corresponding to the second project decomposition item when the status information of the second project decomposition item is qualified; A second determining module is configured to determine the actual settlement amount of the second project breakdown item based on the construction code, the pre-acquired measurement certification form, the pre-acquired bill of quantities, and the pre-acquired budget breakdown form; A supervision module is used to monitor and manage the project decomposition items in the work breakdown structure and the unit breakdown structure, and the actual settlement amount based on the second association relationship and the bill of quantities.

7. The engineering project supervision device according to claim 6, characterized in that: The second determining module includes: A first determining submodule is configured to determine the usage of the construction item corresponding to the construction code based on the construction code and the pre-acquired measurement certificate; A first acquisition submodule is configured to acquire, based on the construction code, from the pre-acquired bill of quantities the unit price of the construction item corresponding to the construction code and the contract amount of the construction item corresponding to the construction code; A second acquisition submodule is configured to acquire, based on the construction code, the budget amount of the construction item corresponding to the construction code from the pre-acquired budget details sheet; The second determining submodule is configured to determine an actual settlement amount of the construction item corresponding to the construction code based on the usage, the unit price, the contract amount, and the budget amount.

8. The engineering project supervision device according to claim 7, characterized in that: The first determining submodule includes: An acquiring unit, configured to acquire, based on the construction code, from the measurement certification sheet the audited quantity of the construction item corresponding to the construction code; A determining unit is configured to determine the audit amount as the usage amount.

9. A computer device, characterized in that: include: A memory and a processor, wherein the memory and the processor are communicatively connected to each other, the memory is used to store a computer program, and when the computer program is executed by the processor, the processor executes the engineering project supervision method according to any one of claims 1 to 5.

10. A computer-readable storage medium, characterized in that The computer-readable storage medium is used to store computer instructions. When the computer instructions are executed by a processor, the engineering project supervision method according to any one of claims 1 to 5 is implemented.

Citation Information

Patent Citations

  • Engineering settlement method, system and device based on Revit and storage medium

    CN111369279A

  • Data processing method for engineering project progress and output value linkage

    CN112258075A