Deformation Monitoring System Based on 3D GIS

Through the deformation monitoring system based on 3D GIS, real-time and standard tunnel models are established to compare lines and angles, which solves the problem of accuracy and efficiency of tunnel deformation monitoring, achieves more accurate deformation detection and early warning, and extends the service life of the tunnel.

CN115451904BActive Publication Date: 2024-10-11BEIJING HUANAN ENG TESTING CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202211289668.3
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-10-20
Publication Date
2024-10-11
Estimated Expiration
2042-10-20

AI Technical Summary

Technical Problem

Existing tunnel deformation monitoring technology is difficult to detect tunnel deformation accurately and efficiently, resulting in inaccurate monitoring results and affecting safety.

Method used

A deformation monitoring system based on three-dimensional GIS is used to obtain real-time and historical monitoring data to establish a real-time tunnel model and a standard tunnel model, compare the two to analyze the deformation degree of the tunnel, and use line and angle dimensions to perform calculations to improve the accuracy of monitoring. and efficiency.

Benefits of technology

It significantly improves the accuracy and efficiency of tunnel deformation monitoring, enables timely identification of abnormal data and issues alarms, and extends the service life of the tunnel.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN115451904B_ABST
    Figure CN115451904B_ABST
Patent Text Reader

Abstract

The present application relates to a deformation monitoring system based on three-dimensional GIS, which belongs to the field of tunnel safety, and includes a server, in which the following method is executed: obtaining real-time monitoring data and historical monitoring data; establishing a real-time tunnel model and a standard tunnel model according to the real-time monitoring data and the historical monitoring data; processing the real-time tunnel model and the standard tunnel model to obtain the lines and angles of the real-time tunnel model and the lines and angles of the standard tunnel model, and the lines and angles of the real-time tunnel model correspond to the lines and angles of the standard tunnel model; comparing the lines of the real-time tunnel model with the corresponding lines of the standard tunnel model, and comparing the angles of the real-time tunnel model with the corresponding angles of the standard tunnel model to obtain the deformation degree of the tunnel. The present application has the effect of improving the accuracy of tunnel deformation monitoring.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of tunnel safety, and in particular to a deformation monitoring system based on three-dimensional GIS. Background Art

[0002] Three-dimensional GIS generally refers to a three-dimensional geographic information system; three-dimensional means the expression and display of data after collection and calculation and analysis; three-dimensional data can better reflect the objective reality than two-dimensional data; geographic information system is a specific spatial information system, which can collect, store, manage, calculate, analyze and display data related to geographical distribution in space with the support of computer hardware and software systems.

[0003] The application field of 3D GIS is relatively wide, including the field of tunnel deformation monitoring; tunnel deformation refers to the deformation of deep buried tunnels under surrounding rock conditions; generally, tunnel deformation includes arch foot deformation and side wall deformation; tunnel deformation may be caused by factors such as initial geostress field, mechanical properties of surrounding rock, tunnel shape and tunnel cross-sectional dimensions.

[0004] With respect to the above-mentioned related technologies, the inventors found that tunnel deformation may lead to more serious consequences, so it is necessary to monitor tunnel deformation. Summary of the invention

[0005] In order to improve the accuracy of tunnel deformation monitoring, the present application provides a deformation monitoring system based on three-dimensional GIS.

[0006] The deformation monitoring system based on 3D GIS provided in this application adopts the following technical solutions:

[0007] A deformation monitoring system based on three-dimensional GIS includes a server, and the following method is executed in the server:

[0008] Obtain real-time monitoring data and historical monitoring data;

[0009] A real-time tunnel model and a standard tunnel model are established according to the real-time monitoring data and the historical monitoring data respectively;

[0010] After processing the real-time tunnel model and the standard tunnel model, lines and angles of the real-time tunnel model and lines and angles of the standard tunnel model are obtained, wherein the lines and angles of the real-time tunnel model and the lines and angles of the standard tunnel model correspond to each other;

[0011] The deformation degree of the tunnel is obtained by comparing the lines of the real-time tunnel model with the lines of the corresponding standard tunnel model, and by comparing the angles of the real-time tunnel model with the angles of the corresponding standard tunnel model.

[0012] By adopting the above technical solution, a real-time tunnel model and a standard tunnel model are established respectively, and then the two models are compared. The maximum deformation and displacement of the real-time tunnel model compared with the standard tunnel model are analyzed and calculated from the two dimensions of line and angle. In this way, the accuracy and efficiency of tunnel deformation monitoring are improved.

[0013] In a preferred example, the present application can be further configured as follows: the step of obtaining real-time monitoring data includes obtaining real-time monitoring data based on information output by sensors pre-installed in the tunnel; multiple sensors are pre-installed in the tunnel, and each sensor is a detection point for sending the detected tunnel data to the server. In a preferred example, the present application can be further configured as follows: the step of obtaining historical monitoring data includes obtaining historical monitoring data based on crawling by a crawler.

[0014] In a preferred example, the present application may be further configured as follows: the step of establishing a real-time tunnel model and a standard tunnel model according to the real-time monitoring data and the historical monitoring data respectively comprises:

[0015] Establish a real-time tunnel model based on 3D GIS technology and real-time monitoring data;

[0016] Obtain original tunnel data based on historical monitoring data;

[0017] Establish the original model of the tunnel based on 3D GIS technology and original tunnel data;

[0018] The original tunnel model is the standard tunnel model

[0019] In a preferred example, the present application may be further configured as follows: the step of comparing the lines of the real-time tunnel model with the lines of the corresponding standard tunnel model, and comparing the angles of the real-time tunnel model with the angles of the corresponding standard tunnel model to obtain the deformation degree of the tunnel comprises:

[0020] According to the line of the real-time tunnel model, each point on the line is obtained;

[0021] According to the line of the standard tunnel model, each point on the line is obtained;

[0022] Among them, the points on the standard tunnel model correspond to the points on the real-time tunnel model;

[0023] Calculating distances between corresponding points on the real-time tunnel model and the standard tunnel model to obtain multiple distance values;

[0024] After comparing multiple distance values, the maximum distance value is obtained;

[0025] The maximum distance value at this time represents the maximum displacement of the line on the real-time tunnel model compared to the line on the corresponding standard tunnel model.

[0026] In a preferred example, the present application may be further configured as follows: the step of comparing the lines of the real-time tunnel model with the lines of the corresponding standard tunnel model, and comparing the angles of the real-time tunnel model with the angles of the corresponding standard tunnel model to obtain the deformation degree of the tunnel comprises:

[0027] Calculate mean square error based on multiple distance values;

[0028] The mean square error at this time indicates the degree of deformation of the line on the real-time tunnel model compared with the line on the corresponding standard tunnel model.

[0029] In a preferred example, the present application can be further configured to include:

[0030] Deformation monitoring range data is obtained based on historical monitoring data;

[0031] Abnormal data is obtained by calculating based on real-time monitoring data and deformation monitoring range data;

[0032] Obtaining tunnel location information to which the abnormal data belongs according to the abnormal data;

[0033] Obtaining historical data of the tunnel location corresponding to the tunnel location information according to the tunnel location information and historical monitoring data;

[0034] Based on the preset data analysis rules, historical data and abnormal data are analyzed to obtain analysis results;

[0035] Determine the alarm result based on the analysis results.

[0036] In summary, the present application includes at least one of the following beneficial technical effects:

[0037] A real-time tunnel model and a standard tunnel model can be established through real-time monitoring data and historical monitoring data respectively, one representing the current tunnel and the other representing the tunnel without deformation. Then, the real-time tunnel model is compared with the standard tunnel model to determine the degree of deformation of the real-time tunnel model compared with the standard tunnel model, thereby improving the accuracy and efficiency of tunnel deformation monitoring. BRIEF DESCRIPTION OF THE DRAWINGS

[0038] Figure 1 It is a flow chart of a deformation monitoring system based on three-dimensional GIS in an embodiment of the present application. DETAILED DESCRIPTION

[0039] In order to make the purpose, technical solution and advantages of the embodiments of the present application clearer, the technical solution in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of this application.

[0040] The embodiments of the present application are further described in detail below in conjunction with the drawings in the specification.

[0041] The present application embodiment discloses a deformation monitoring system based on three-dimensional GIS. Figure 1 The deformation monitoring system based on three-dimensional GIS includes a server and sensors; the sensors are set at the connection nodes and support nodes in the tunnel, among which the connection nodes and load-bearing nodes are important nodes that can reflect the main structure of the tunnel; each sensor is a detection point; the server is connected to the sensor, receives the data sent by each detection point, and generates a tunnel model based on these data; through the coordinated use of the server and the sensor, the tunnel model at the current moment can be generated.

[0042] The connection nodes and support nodes in the embodiments of the present application can be understood as the connection positions of the lining in the tunnel and the bearing points in the tunnel, and the locations of these bearing points are the installation positions of the sensors; in the field of tunnel deformation monitoring, tunnel deformation monitoring can be achieved through a variety of sensors. The types of sensors are not limited in the embodiments of the present application, as long as the structural monitoring of the tunnel can be achieved.

[0043] The main scheme of the present application is to compare the tunnel model generated according to the real-time data with the preset tunnel model, and then analyze the deformation degree of the tunnel; wherein, the preset tunnel model is a standard tunnel model, that is, a tunnel model established according to a tunnel that has not undergone deformation, which is referred to as the standard tunnel model in this scheme; and the tunnel model generated according to the real-time data is a tunnel model established according to a tunnel that has undergone deformation, which is referred to as the real-time tunnel model in this scheme; by comparing the tunnel models before and after deformation, that is, comparing the real-time tunnel model with the standard tunnel model, and after analysis, the deformation degree of the tunnel can be obtained, and this method can be used to improve the accuracy of tunnel deformation monitoring.

[0044] It can be understood that the methods and steps executed in the embodiments of the present application are all run in the server. The scheme of the present application is described in detail below.

[0045] First, the crawler is used to crawl the historical data of the tunnel, and then a preset tunnel model is established based on the historical data; it can be understood that when modeling the tunnel, the data sent by each detection point is combined with the three-dimensional GIS technology to model, so as to obtain a tunnel model; and the preset tunnel model, that is, the standard tunnel model, is a model established based on the original data of the tunnel; the original data of the tunnel can be understood as the data pre-set before the construction of the tunnel. Before the start of the tunnel project, the tunnel data must be pre-set according to factors such as terrain, landform and geology, for example, the length, width and height of the tunnel, the thickness of the tunnel lining, the connection nodes of the tunnel, the support nodes of the tunnel and other data; the standard tunnel model can be understood as the model of the tunnel when no deformation occurs, so the standard tunnel model is used as a comparison benchmark, and the real-time tunnel model is compared with the standard tunnel model to obtain the deformation of the tunnel at the current moment.

[0046] In an embodiment of the present application, the method of constructing a model is based on various detection points, and then the various detection points are connected according to the actual context of the tunnel, and finally a tunnel model is constructed; the above process can be achieved through three-dimensional GIS technology and related three-dimensional modeling software, which will not be repeated here.

[0047] The server receives the data sent by the sensor and generates a real-time tunnel model based on the data; then compares the real-time tunnel model with a preset standard tunnel model, and determines the degree of deformation of the tunnel based on the comparison result. In the embodiment of the present application, both the comparison process and the judgment process are executed in the server.

[0048] When comparing the real-time tunnel model with the standard tunnel model, the models are compared from two perspectives: line and angle. First, from the perspective of line, the real-time tunnel model is generated based on the data output by the sensor, and the standard tunnel model is generated based on preset data. Both the real-time tunnel model and the standard tunnel model are models that represent the tunnel. It can be understood that when the sensor is just installed at the specified position, the tunnel at this time can be regarded as a tunnel that has not been deformed. The tunnel model at this time is called the initial tunnel model. The initial tunnel model can be understood as a tunnel model that is the same as the standard tunnel model. The specific position of the sensor in the initial tunnel model at this time represents the specific position of the same sensor in the standard tunnel model. That is, the initial tunnel model is equivalent to the standard tunnel model.

[0049] Then each sensor is regarded as a detection point, and the detection point can be understood as a point in the model. Connecting the points in sequence forms a line. Then, by comparing the line of the real-time tunnel model with the line of the corresponding position of the standard tunnel model, the degree of deformation of the line of the real-time tunnel model compared with the line of the standard tunnel model can be obtained.

[0050] In the above description, it should be noted that although the standard tunnel model is generated based on the original data of the tunnel and there are no detection points in the standard tunnel model, the initial tunnel model and the standard tunnel model are regarded as equivalent models. Then, the detection points in the initial tunnel model can also be copied to the standard tunnel model, so that the detection points are marked at the same positions in the standard tunnel model. Then, in the process of comparing the real-time tunnel model with the standard tunnel model, the above-mentioned comparison line method can be used to compare the real-time tunnel model and the standard tunnel model. In this way, the convenience and efficiency of comparing the real-time tunnel model and the standard tunnel model are improved.

[0051] In the embodiment of the present application, the method for comparing the lines of the real-time tunnel model with the lines of the corresponding positions of the standard tunnel model is as follows.

[0052] After obtaining the real-time tunnel model and the standard tunnel model, the model can be decomposed into multiple lines, and each line can be decomposed into multiple points; since each line is composed of multiple points, calculating the maximum distance between corresponding lines can be converted into calculating the maximum distance between two corresponding points in the corresponding line; after decomposing the real-time tunnel model and the standard tunnel model, multiple points can be obtained, and then the distance between two corresponding points on the corresponding line can be calculated, so as to obtain the maximum distance between the corresponding lines of the real-time tunnel model and the standard tunnel model.

[0053] For example, extract line A in the real-time tunnel model, and then extract line A' corresponding to line A in the standard tunnel model; then extract points a, b, c and d in line A, and then extract points a', b', c' and d' in A'; calculate the distance values ​​between point a and point a', point b and point b', point c and point c', point d and point d' respectively, and then compare the above distance values ​​to obtain the maximum distance; the distance between point a and point a' is 2.3, the distance between point b and point b' is 3.5, the distance between point c and point c' is 1.6, and the distance between point d and point d' is 4.9; then after comparing the above distances, it is obtained that the distance between point d and point d' is the largest, that is, the maximum distance between the two corresponding points is 4.9, which means that the maximum distance between line A and line A' is 4.9; this maximum distance indicates the maximum displacement generated by the real-time tunnel model compared with the standard tunnel model.

[0054] The maximum distance between the corresponding lines between the real-time tunnel model and the standard tunnel model is obtained by calculation, and then the calculated maximum distance value is compared with the preset distance threshold. If the maximum distance value is greater than the preset distance threshold, it means that the position of the point corresponding to the maximum distance value, that is, the specific position in the tunnel where the detection point corresponding to this point is located, has undergone a relatively serious displacement, and then it is necessary to maintain the surrounding area of ​​the detection point; when the maximum distance value is greater than the preset distance threshold, the server will mark and alarm the position of the point corresponding to the maximum distance value on the real-time tunnel model to serve as a warning; since each detection point corresponds to a sensor, this method can realize the detection and maintenance of the specific sensor location and surrounding area in the tunnel.

[0055] It can be understood that the extraction of lines and points in the model mentioned in the above example is the process of disassembling the model. Since the model is based on various detection points in the modeling process, the tunnel model is constructed after connecting various detection points according to the actual context of the tunnel. The above example is to disassemble the model, that is, the reverse process of modeling. The above operations are commonly used technical means in related fields and will not be repeated here.

[0056] In the process of calculating the maximum distance between the corresponding lines of the real-time tunnel model and the standard tunnel model, it is necessary to calculate the distance between every two corresponding points, and then compare the distance values ​​to obtain the maximum distance; although the calculated maximum distance represents the maximum displacement of the real-time tunnel model compared with the standard tunnel model, this maximum displacement is for the same line, and it is rather one-sided to judge the deformation of the real-time tunnel model by calculating the maximum distance, and it is impossible to accurately analyze the deformation degree of the real-time tunnel model, so it is necessary to further compare the real-time tunnel model with the standard tunnel model.

[0057] In the above process, the displacement of each line on the real-time tunnel model compared with the standard line on the standard tunnel model can be calculated. This displacement refers to the displacement of a certain point on each line and cannot represent the displacement or deformation degree of the entire line. Therefore, it is necessary to perform a comprehensive analysis and calculation of each point on the entire line. The following method is used in the embodiment of the present application to analyze and calculate the entire line.

[0058] When comparing the corresponding lines of the real-time tunnel model and the standard tunnel model, it is necessary to calculate the distance value between the corresponding points on the two corresponding lines, and then compare multiple distance values ​​to calculate the displacement of the line; then, if you want to analyze the entire line, you only need to calculate the mean square error of multiple distance values ​​to get the deformation degree of the entire line.

[0059] The mean square error generally refers to the standard deviation, which is the square root of the arithmetic mean of the square of the mean error. The standard deviation is also called the standard deviation, or experimental standard deviation, and is most commonly used in probability statistics as a measurement of the degree of statistical distribution. The standard deviation is the square root of the variance, and the standard deviation can reflect the degree of discreteness of a data set. In the embodiment of the present application, by calculating the mean square error, the degree of deformation of the line of the real-time tunnel model compared to the line of the standard tunnel model can be obtained.

[0060] In the above example, the mean square error S can be obtained after calculation using the formula.

[0061] First calculate the average x of the four distance values.

[0062]

[0063] The calculated value of x is 3.075.

[0064]

[0065] The calculated S is 1.57.

[0066] According to the meaning of the mean square error itself, 1.57 is slightly greater than 1. Although the difference is relatively small, it still shows that the real-time tunnel model has undergone a certain degree of overall deformation compared with the standard tunnel model, that is, it shows that the real tunnel has undergone a certain degree of deformation.

[0067] By calculating the maximum distance and mean square error of the corresponding lines between the real-time tunnel model and the standard tunnel model, the displacement and deformation of the real-time tunnel model compared with the standard tunnel model can be preliminarily obtained. In order to further improve the judgment of the degree of deformation of the real-time tunnel model, the embodiment of the present application further judges the angle of the tunnel model based on the center line of the tunnel model.

[0068] It can be understood that the angle in the tunnel model refers to the angle between two lines. By judging the angle of the tunnel model, the overall deformation degree of the two lines that form the angle can be judged. Compared with the above analysis and calculation for lines, the comparison of angles is more holistic; because the angle is based on lines and the line is based on points, after comparing the deformation degree of each line, the deformation degree of the angle formed by the two lines is compared, which improves the detection accuracy of the deformation degree of the tunnel model.

[0069] In the embodiment of the present application, the comparison of the corresponding angles in the two tunnel models is achieved through image recognition technology; that is, the corresponding angles in the two tunnel models are superimposed. Since the angle is formed by lines and the line is formed by points, the points at corresponding positions are superimposed, and then the image recognition technology is used to compare the degree of deformation of the angle of the real-time tunnel model compared with the angle of the standard tunnel model.

[0070] It should be noted that, during the comparison process, one of the lines of the corners of the standard tunnel model is used as a reference to ensure that the positions of the corresponding points on the line overlap, and then the corresponding corners in the two tunnel models are overlapped.

[0071] The image recognition technology can be used to determine the difference between the angle of the real-time tunnel model and the angle of the standard tunnel model, and the degree of deformation of the angle of the real-time tunnel model can be obtained based on the difference; for example, line C and line D are lines of the real-time tunnel model, and line C' and line D' are lines of the standard tunnel model; compared with angle 2 formed by line C' and line D', angle 1 formed by line C and line D is 5° larger than angle 2, that is, angle 1 has undergone a certain degree of deformation; it can be understood that the above example is only an illustrative description; in the actual comparison process, more accurate data can be obtained through image recognition technology, which will not be repeated here.

[0072] In the embodiment of the present application, with the assistance of equipment such as a total station, a level, and a three-dimensional laser scanner on site, the tunnel is detected by the above equipment and related sensors, and a detection signal is output; the server receives the detection signal and analyzes and processes the detection signal; among them, in the embodiment of the present application, GIS technology adopts a GIS engine, and through the use of the GIS engine, the deformation of the tunnel is monitored, thereby improving the accuracy and efficiency of the tunnel deformation monitoring.

[0073] In an embodiment of the present application, when performing deformation analysis on a tunnel, as the monitoring time increases, the monitoring data will also increase day by day. Therefore, if the initial standard tunnel model is used to perform deformation analysis on the real-time tunnel each time, inaccurate results will occur. Therefore, the following method is proposed in this application for processing.

[0074] Specifically, deformation monitoring range data is obtained based on historical monitoring data; abnormal data is obtained by calculation based on real-time monitoring data and deformation monitoring range data; tunnel location information to which the abnormal data belongs is obtained based on the abnormal data; historical data of the tunnel location corresponding to the tunnel location information is obtained based on the tunnel location information and historical monitoring data; based on preset data analysis rules, historical data and abnormal data are analyzed to obtain analysis results; and an alarm result is determined based on the analysis results.

[0075] The historical monitoring data here includes relevant data of the tunnel corresponding to multiple time points. Therefore, the standard data of the initial tunnel can be determined through the historical monitoring data, that is, the relevant data when the tunnel has not been deformed; it can be understood that in the embodiment of the present application, the relevant data of the tunnel, that is, the node data, is obtained by sensors at each node of the tunnel, and the relevant data when the tunnel has not been deformed is the initial node data.

[0076] Through historical monitoring data, multiple node data of the tunnel corresponding to each time point can be obtained.

[0077] In an embodiment of the present application, deformation monitoring range data can be obtained by combining historical monitoring data and a preset deformation deviation value. The preset deformation deviation value here means that the node data in the tunnel is allowed to fluctuate within a certain range. As long as it is within the range, the fluctuation of the data can be ignored; for example, the initial node data is 8, and the preset deformation deviation value is ±0.5, then the deformation monitoring range data is 7.5-8.5, then the node data at the same position monitored subsequently will not trigger an alarm as long as it is within this range, and an alarm will be triggered if it exceeds the range.

[0078] After determining the deformation monitoring range data, abnormal data can be obtained based on the real-time monitoring data. This abnormal data refers to data that exceeds the deformation monitoring range. It can be understood that the node data at different positions in the tunnel are all set with their own deformation monitoring range data. After analyzing the real-time monitoring data to obtain the abnormal data, it can be determined to which position in the tunnel the abnormal data belongs, that is, the tunnel location information to which the abnormal data belongs can be obtained based on the abnormal data.

[0079] After obtaining the tunnel location information to which the abnormal data belongs, the historical data of the tunnel location corresponding to the tunnel location information can be obtained based on the tunnel location information and the historical monitoring data; for example, if abnormal data appears at tunnel location point A, then all historical data corresponding to point A can be found from the historical monitoring data.

[0080] After finding the historical data corresponding to the abnormal data, the preset data analysis rules are used to analyze the historical data and abnormal data to obtain the analysis results, and then the alarm results are determined based on the analysis results; that is, the analysis results of the abnormal data are determined by the data analysis rules. If the analysis results are safe, there is no need to alarm. If the analysis results are dangerous, there is a need to alarm.

[0081] In an embodiment of the present application, the data analysis rules include calculating the difference between the abnormal data and the deformation monitoring range data, comparing the difference with a first preset threshold value, if the difference is greater than the first preset threshold value, it indicates that the tunnel has undergone severe deformation at the position corresponding to the abnormal data, if the difference is less than the first preset threshold value, it indicates that the tunnel has undergone slight deformation at the position corresponding to the abnormal data.

[0082] If the tunnel has undergone severe deformation, it means that the analysis result is that the tunnel has undergone severe deformation. Then the alarm result determined based on this analysis result is to sound an alarm and mark the location where the tunnel has undergone severe deformation.

[0083] If the tunnel has a slight deformation, the historical data of the location where the slight deformation occurred is analyzed using data analysis rules.

[0084] In an embodiment of the present application, the data analysis rules also include analyzing historical data corresponding to positions where slight deformations occur in the tunnel, calculating the difference between the last historical data and the next historical data according to time, comparing these differences with a second preset threshold value, if the difference is greater than the second preset threshold value, it means that the next historical data corresponding to the difference in the historical data has undergone a mutation, calculating the time difference between the mutated historical data and the original data, and marking the time difference as a periodic interval value, which means that the data may mutate every periodic interval value; calculating multiple periodic values ​​according to the initial time and the periodic interval value; finding the periodic value closest to the current time according to the current time, calculating the difference between the two, and comparing the difference with a third preset threshold value, if the difference is not greater than the third preset threshold value, the analysis result is that an alarm is required, and if the difference is greater than the third preset threshold value, the analysis result is that no alarm is required.

[0085] To explain the above process in detail, an example is given below. When it is determined that the tunnel has a slight deformation, it is necessary to analyze the historical data of the corresponding position. In the historical data, it is assumed that the data is recorded once every week, the initial value is 3, the data of the second record is 5, the data of the third record is 4.6, and the data of the fourth record is 8. Then calculate the difference between the second record and the initial value, the difference between the third record and the second record, etc. After calculating the difference, compare the difference with the second preset threshold. For example, the difference between the third record and the fourth record is 3.4, which is greater than the second preset threshold of 3. This means that the data has a mutation during the fourth recording, which also means that the deformation amplitude of the tunnel is large. Then calculate the time difference between the time of this recording and the initial time as one month, and mark one month as The cycle interval value means that the data may be deformed every month. This means that starting from the initial time, every month is a date that may be deformed, thus obtaining multiple cycle values. For example, if the initial time is January 1, then the first cycle value is February 1, and the third cycle value is March 1, etc.; then find the cycle value closest to the current time. The current time is February 19, so the closest one is the third cycle value. Calculate the difference between the two, which is 9 days. Compare this difference with the third preset threshold of 15 days. If it is less than 15 days, it means that although the tunnel at the current time has a slight deformation, the time to the next data mutation is short, so an alarm is needed to process the location where the tunnel has a slight deformation to prevent the tunnel from being severely deformed when the data mutates next time, thereby causing serious impact on the tunnel.

[0086] By analyzing tunnel deformation in the above manner, early warning, analysis, processing and prediction of tunnel deformation can be effectively and quickly achieved, thereby extending the service life of the tunnel and improving the accuracy of tunnel deformation monitoring.

[0087] The above description is only a preferred embodiment of the present application and an explanation of the technical principles used. Those skilled in the art should understand that the scope of disclosure involved in the present application is not limited to the technical solution formed by a specific combination of the above technical features, but should also cover other technical solutions formed by any combination of the above technical features or their equivalent features without departing from the aforementioned disclosed concept. For example, the above features are replaced with the technical features with similar functions disclosed in this application (but not limited to) by each other to form a technical solution.

Claims

1. A deformation monitoring system based on three-dimensional GIS, characterized in that: The method comprises a server, wherein the server executes the following method: Obtain real-time monitoring data and historical monitoring data; A real-time tunnel model and a standard tunnel model are established according to the real-time monitoring data and the historical monitoring data respectively; After processing the real-time tunnel model and the standard tunnel model, lines and angles of the real-time tunnel model and lines and angles of the standard tunnel model are obtained, wherein the lines and angles of the real-time tunnel model and the lines and angles of the standard tunnel model correspond to each other; The deformation degree of the tunnel is obtained by comparing the lines of the real-time tunnel model with the lines of the corresponding standard tunnel model, and comparing the angles of the real-time tunnel model with the angles of the corresponding standard tunnel model; The step of comparing the lines of the real-time tunnel model with the lines of the corresponding standard tunnel model, and comparing the angles of the real-time tunnel model with the angles of the corresponding standard tunnel model to obtain the deformation degree of the tunnel comprises: According to the line of the real-time tunnel model, each point on the line is obtained; According to the line of the standard tunnel model, each point on the line is obtained; Among them, the points on the standard tunnel model correspond to the points on the real-time tunnel model; Calculating distances between corresponding points on the real-time tunnel model and the standard tunnel model to obtain multiple distance values; After comparing multiple distance values, the maximum distance value is obtained; The maximum distance value at this time represents the maximum displacement of the line on the real-time tunnel model compared to the line on the corresponding standard tunnel model; The step of comparing the lines of the real-time tunnel model with the lines of the corresponding standard tunnel model, and comparing the angles of the real-time tunnel model with the angles of the corresponding standard tunnel model to obtain the deformation degree of the tunnel comprises: Calculate mean square error based on multiple distance values; The mean square error at this time indicates the degree of deformation of the line on the real-time tunnel model compared with the line on the corresponding standard tunnel model.

2. The deformation monitoring system based on three-dimensional GIS according to claim 1, characterized in that: The step of obtaining real-time monitoring data includes obtaining real-time monitoring data according to information output by sensors pre-installed in the tunnel; a plurality of sensors are pre-installed in the tunnel, each sensor being a detection point for sending detected tunnel data to a server.

3. The deformation monitoring system based on three-dimensional GIS according to claim 1, characterized in that: The step of obtaining historical monitoring data includes obtaining the historical monitoring data by crawling with a crawler.

4. The deformation monitoring system based on three-dimensional GIS according to claim 1, characterized in that: The steps of establishing a real-time tunnel model and a standard tunnel model respectively according to the real-time monitoring data and the historical monitoring data include: Establish a real-time tunnel model based on 3D GIS technology and real-time monitoring data; Obtain original tunnel data based on historical monitoring data; Establish the original model of the tunnel based on 3D GIS technology and original tunnel data; The original tunnel model is the standard tunnel model.

5. The deformation monitoring system based on three-dimensional GIS according to claim 1 is characterized in that: Also includes: Deformation monitoring range data is obtained based on historical monitoring data; Abnormal data is obtained by calculating based on real-time monitoring data and deformation monitoring range data; Obtaining tunnel location information to which the abnormal data belongs according to the abnormal data; Obtaining historical data of the tunnel location corresponding to the tunnel location information according to the tunnel location information and historical monitoring data; Based on the preset data analysis rules, historical data and abnormal data are analyzed to obtain analysis results; Determine the alarm result based on the analysis results.