A construction method for repairing the deformation of the shield tail of a tunnel boring machine under a river.

By using the combined method of steel casing and steel sheet piles when the shield machine passes through the river environment, the external slurry block of the shield body is removed and the deformation of the shield tail is repaired, which solves the problem of secondary deformation of the shield tail and achieves fast and safe construction. High, low cost effect.

CN115522939BActive Publication Date: 2024-10-22YSD RAIL TRANSIT CONSTR CO LTD +2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202210610998.1
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-05-31
Publication Date
2024-10-22
Estimated Expiration
2042-05-31

AI Technical Summary

Technical Problem

In complex environments such as when a shield machine passes through a river, existing technology cannot effectively clean up the large-scale mud outside the shield, leading to the risk of secondary deformation of the shield tail. Moreover, the ground shaft method is not feasible, affecting the construction schedule and safety.

Method used

Use steel casing and steel sheet piles to measure the deformation area, install a water stop ring, drill holes for inspection, use a piling boat and drilling rig to set the steel casing and steel sheet piles at the bottom of the river, and vibrate and sink the steel sheet piles to clear the outside of the shield tail. slurry block, and strengthen the shell through the support platform and curved steel plate to ensure the deformation repair of the shield tail.

Benefits of technology

Effectively removes slurry outside the shield to prevent secondary deformation. The construction speed is fast, the operation is simple, the safety is high, the cost is low, and the impact on the construction period is reduced.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN115522939B_ABST
    Figure CN115522939B_ABST
Patent Text Reader

Abstract

A construction method for repairing deformation of the shield tail of a shield machine under a river includes the steps of measuring deformation, applying a water stop ring, opening a hole for inspection, connecting and reinforcing pipe segments, positioning a pile-driving ship and measuring and positioning, arranging and sinking steel casings, drilling holes and vibrating and sinking steel sheet piles, correcting deformation of the shield tail, reinforcing the shell, advancing while vibrating, getting the shield out of trouble, and sealing and removing the steel casing. When the shield machine passes through a complex environment such as a river, this method can effectively remove the slurry blocks outside the shield body and prevent secondary deformation through the cooperation of simple steel casings and steel sheet piles, and at the same time complete the deformation repair of the shield tail through the top return in the hole. It has the characteristics of fast construction speed, simple operation, low construction difficulty, high safety, and low cost, and can effectively reduce the impact on the normal construction period.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of shield tunnel construction, is applicable to a method for repairing deformation of a shield tail of a shield machine, and particularly relates to a construction method for repairing deformation of a shield tail of a shield machine under a riverbed. Background Art

[0002] During the tunneling process, the shield tail of the shield machine will be deformed. When the shield tail is deformed, it will affect the assembly quality of the segments, and in severe cases, it will even make the segments unable to be assembled. At present, the deformation of the shield tail is usually treated in the tunnel. A hole is opened in the deformation area of ​​the shield tail shell for inspection, and foreign objects such as slurry blocks are crushed or manually cleaned with a high-pressure water gun, and then corrected with correction tools. However, this in-tunnel treatment measure cannot effectively clean the large area of ​​slurry outside the shield body, so there is a risk of secondary deformation of the shield tail. At this time, the ground shaft method can be used to solve this problem. However, in special environments such as when the shield passes through rivers, the ground shaft method cannot be used, and only in-tunnel treatment measures can be used, which leads to poor treatment effects and affects the construction period. At the same time, there are also major safety hazards. Summary of the invention

[0003] In order to solve the above technical problems, the present invention provides a construction method for repairing the deformation of the shield tail of a shield machine under a river. When the shield machine passes through a complex environment such as a river, the method can effectively remove the slurry blocks outside the shield body, prevent secondary deformation, and complete the deformation repair of the shield tail at the same time.

[0004] In order to achieve the above object, the technical solution adopted by the present invention is:

[0005] A construction method for repairing deformation of a shield tail of a shield machine under a riverbed is provided, comprising the following steps:

[0006] 1) Measure deformation: determine the deformation area and determine the size of the deformation area of ​​the shield tail by measurement;

[0007] 2) Construction of water stop ring: inject bentonite into the soil bin to fill the bin, and seal the water at the front and rear ends of the shield respectively;

[0008] 3) Hole inspection: Drill holes in the deformation area of ​​the shield tail to check the external slurry wrapping of the shield shell;

[0009] 4) Segment connection reinforcement: The segments in the deformation area of ​​the shield tail are supported and reinforced with support frames, and channel steel is used to longitudinally tie the segments on the upper part of the segments behind the shield tail;

[0010] 5) Positioning of pile-driving boat and measurement and positioning: The pile-driving boat is docked in the river channel to establish the plane control network of the section line measurement, and the position coordinates of the steel casing at the tail of the shield are measured and positioned;

[0011] 6) Arrangement and pile sinking of steel casing: vertically arrange vibration vertical points in the deformation area of ​​the shield tail and its vicinity, and use a pile driver to vibrate and sink the steel casing at the vibration vertical points, so that the steel casing enters the strongly weathered rock layer or is pressed down until it cannot move;

[0012] 7) Drilling and steel sheet pile vibration sinking: After the steel casing is sunk, a drilling rig is used to drill holes in the steel casing to the shield tail shell, and a pile driver is used to vibrate and sink the steel sheet pile along the drilled hole;

[0013] 8) Correction of deformation at the shield tail: a support platform is set inside the shield tail, and a jack is set on the support platform; first, a pile driver is used to vibrate the steel sheet piles in turn to crack the slurry blocks wrapped outside the shell, and then the jack is used to lift and correct the deformation area of ​​the shield tail;

[0014] 9) Shell reinforcement: After the deformation area of ​​the shield tail is corrected, the deformed guide ribs are replaced, and then arc-shaped steel plates are evenly distributed in the deformation area of ​​the shield tail through grid welding to strengthen the shell;

[0015] 10) Pushing forward while vibrating: The shield machine starts to push forward again. During the pushing forward, each steel sheet pile is vibrated in turn, and the shield shell is hit by vibration to break and vibrate off the wrapped slurry blocks;

[0016] 11) Shield body escapes from trouble: The shield tail passes through the vibration position of the steel sheet pile, the thrust parameters of the shield machine are normal, and the shield tail does not deform, the segment forming quality is good, there is no misalignment or water leakage, then it is judged that the slurry blocks wrapped in the shield tail shell have been effectively removed, and the shield machine has been successfully escaped from trouble;

[0017] 12) Sealing and removal of steel casing: Pour commercial concrete or mortar into the steel casing to seal the holes, and finally pull out the steel casing to complete the construction.

[0018] As a further improvement of the present invention, in step 1), the deformation area is judged by measuring the shield tail gap size and observing the tendency of the shield tail to deform inwardly concave, and the size of the shield tail deformation area is determined by measuring the axial length, annular width and maximum deformation amount of the shield tail deformation area.

[0019] As a further improvement of the present invention, in step 2), thick bentonite is used, and the specific gravity of bentonite is 1.2. The injection amount is determined by whether bentonite flows out of the soil bin ball valve. When ring sealing water is performed, polyurethane ring sealing water is injected into the radial holes of the middle shield and the 3 ring openings behind the shield tail. The radial holes at 2 and 10 o'clock in the clock direction at the support near the shield tail are used as observation holes, and the water-stopping effect is checked through the observation holes.

[0020] As a further improvement of the present invention, in step 3), a φ20mm hole is drilled at the maximum deformation point using a magnetic drill. After drilling, first check whether there is water outside the shield shell through the hole, and then use φ10mm steel bars to check the rock formation conditions; if it is found that there is no water and the formation has good self-stability, first weld a 3-inch thread joint on the shell, then expand the hole to φ50mm and install a ball valve; clean the mud residue at the drilling position, first use a core pulling device to check the formation rock properties and stability, and then use an endoscope to observe the slurry block wrapping condition outside the shield shell.

[0021] As a further improvement of the present invention, in step 4), the support frame is erected in combination with the connecting bridge; channel steels are used to longitudinally tie the segments at 2, 5, 7, and 10 o'clock on the upper part of the 5-ring segments behind the shield tail in the clockwise direction.

[0022] As a further improvement of the present invention, in step 5), steel pipes are installed around the piling ship to prevent the ship from moving due to the influence of water flow and tide; the measuring instrument uses a total station or GPS for measurement and positioning to ensure that the hole position deviation is less than 50 mm and the verticality is less than 1% to prevent vibration hammering on the hinged seal.

[0023] As a further improvement of the present invention, in step 6), 4 rows of vibration vertical points are arranged vertically along the axis direction of the shield machine, 1 point in the first row is located at the rear side of the shield tail deformation area, 2 points in the second row are located on the left and right sides of the shield tail deformation area, 2 points in the third row are located at the maximum position in the shield tail deformation area, and 7 points in the fourth row are located in the front side of the shield tail deformation area; 12 steel casings are vibrated and sunk, the total length of the steel pipes is 26m, the sinking depth of the pipes is 18m, and the distance from the river bottom to the pipe top is 8m.

[0024] As a further improvement of the present invention, in step 7), a positive circulation drilling rig is used for drilling, and during the drilling process, attention is paid to checking the specific gravity of the bentonite, and the scum at the pipe mouth is dug out in time, and the drilling speed is controlled after entering the rock formation; during the drilling process, a special person is arranged to be on duty at the tail of the tunnel shield to control the downward pressure of the drilling rig when drilling the last 0.5m, and when the drill bit hits the shield body and makes a sound, the ground is notified in time to stop drilling and lift the drill; the steel sheet piles are vibrated and sunk one by one along the borehole, and when the steel sheet piles are lowered, the opening direction of the steel sheet piles at the middle hole arrangement of the shield tail is toward the shield tail, and the opening directions of the steel sheet piles at the outermost holes of the shield tail are toward the left and right sides respectively.

[0025] As a further improvement of the present invention, in step 8), during the lifting and correction, the jacks are lifted in sequence in the middle first and then on both sides, and during the process, markings are made and the correction dimensions are measured in time to control the roundness of the shell.

[0026] As a further improvement of the present invention, in step 9), the arc-shaped steel plate is welded by slotting, and the welds on both sides of the arc-shaped steel plate are intermittently arranged. The temperature is controlled during welding to prevent thermal expansion and contraction stress from causing secondary deformation of the shield body.

[0027] As a further improvement of the present invention, in step 10), before the shield machine is pushed again, each steel sheet pile is vibrated for 1 to 2 minutes to check whether each vibration point is normal; during the push, all the steel sheet piles vibrate once for every 100 mm of advance of the shield machine; during the push, the thrust of the shield machine is controlled not to exceed 4100T, the speed is controlled at 10 to 20mm / min, the cutter head is adjusted after every 300 strokes of excavation, and the steel sheet pile should be lifted up 20 to 30mm when it vibrates and sinks to contact the shield body before vibrating; for the first 10 rings of the push of the shield machine, the synchronous grouting is filled with thick bentonite, and normal grouting is resumed after the slurry blocks are completely detached and the thrust drops to the normal value. At the same time, secondary grouting reinforcement should be carried out in this section area at a later stage.

[0028] As a further improvement of the present invention, in step 11), when the thrust of the shield machine advances one ring and drops significantly to 3000T, the shield machine continues to advance two rings and the shield tail passes through the vibration position of the steel sheet piles, the thrust drops to 2600T, and it is judged that the thrust parameters of the shield machine are normal.

[0029] The beneficial effects of the present invention are as follows: when the shield machine passes through a complex environment such as a river, the method can effectively remove the slurry blocks outside the shield body and prevent secondary deformation through the cooperation of simple steel casing and steel sheet piles, and at the same time complete the deformation repair of the shield tail by returning to the top in the hole. It has the characteristics of fast construction speed, simple operation, low construction difficulty, high safety and low cost, and can effectively reduce the impact on the normal construction period. BRIEF DESCRIPTION OF THE DRAWINGS

[0030] Figure 1 This is a schematic diagram of the deformation area of ​​the shield tail;

[0031] Figure 2 It is a schematic diagram of underwater steel casing setting;

[0032] Figure 3 This is a schematic diagram of the structure of the inner support platform of the shield tail;

[0033] Figure 4 This is a schematic diagram of the shell reinforcement structure;

[0034] Marking description: 1- shield tail deformation area, 2- vibration vertical point, 3- steel casing, 4- steel sheet pile, 5- assembly platform, 6- upper beam, 7- jack, 8- arc steel plate. DETAILED DESCRIPTION

[0035] The present invention will be further described below in conjunction with specific embodiments.

[0036] The left-line shield section of a subway project in Panyu District, Guangzhou City, Guangdong Province was constructed using a Mitsubishi 8780 shield machine. Due to severe deformation of the shield tail, the shield machine could not continue to excavate and was forced to stop (623 loops) below the riverbed of Dashi Waterway in Panyu District (the length of the underpass is about 480 meters). The shield was buried about 21.2m deep and the water depth was 6m.

[0037] After the shield tail was deformed, the shield excavation parameters were analyzed by checking the deformation of the shield tail and the misalignment of the segments. Measures such as opening holes to inspect the deformation area of ​​the shield tail were taken. It was found that the shield shell was wrapped in slurry blocks in the range of about 2 meters in the circumferential length and about 1.4 meters in the longitudinal length above the shield tail.

[0038] The first deformation of the shield tail was mainly caused by external extrusion stress during the excavation of rings 617 to 622. The upper part of the shield shell may be wrapped by slurry to form a hard block. The slurry block gradually wedged into the gap between the shield shell and the medium-weathered siltstone as the shield tail moved forward, causing the pressure on the upper part of the shield tail to increase, and eventually exceeded the limit pressure that the steel plate could withstand, causing the upper part of the shield tail to sag. After taking measures such as opening the shield tail shell in the tunnel, flushing the slurry block with a high-pressure cleaner, and jacking correction on site, deformation occurred again after re-pushing. The main reason was still that the slurry block wrapped on the top of the shield tail was not completely handled, resulting in local continuous extrusion.

[0039] In view of the above situation, the method of the present invention is used for construction, which can effectively remove the slurry blocks wrapped on the top of the shield tail and complete the deformation repair of the shield tail. No deformation will occur again, and the project proceeds smoothly.

[0040] A construction method for repairing deformation of a shield tail of a shield machine under a river comprises the following steps:

[0041] 1) Measure the deformation: Determine the deformation area by measuring the shield tail gap size and observing the trend of the shield tail deforming inward, and then determine the size of the shield tail deformation area 1 by measuring the shield tail deformation area 1, which is about 2000mm in axial length, about 1400mm in circumferential width, and the maximum deformation is about 86mm.

[0042] 2) Apply water stop ring: Inject thick bentonite into the soil bin to fill the bin. The specific gravity of bentonite is 1.2. The injection amount is determined by whether bentonite flows out of the soil bin ball valve. Ring sealing water is performed at the front and rear ends of the shield body respectively. Polyurethane ring sealing water can be injected into the radial hole of the middle shield and the 3 ring openings behind the shield tail. The radial holes at 2 and 10 o'clock in the clock direction near the support of the shield tail are used as observation holes to check the water stop effect through the observation holes.

[0043] 3) Hole inspection: Drill a hole in the deformation area 1 of the shield tail to check the external slurry block wrapping of the shield shell. Set up 3 holes with a hole spacing of 500mm. Use a magnetic drill to drill a φ20mm hole at the maximum deformation point. After the first hole is drilled, first check whether there is water outside the shield shell through the drill hole, and then use φ10mm steel bars to check the rock formation. If it is checked that there is no water and the formation has good self-stability, you can first weld a 3-inch thread joint on the shell, then expand the hole to φ50mm and install a ball valve. Clean the mud residue at the drilling position, first use a core pulling device to check the lithology and stability of the formation, and then use an endoscope to observe the slurry block wrapping outside the shield shell.

[0044] 4) Segment connection reinforcement: To prevent the deformation of the segment when the steel sheet pile 4 vibrates and hammers the shell, reinforcement measures are required for the segment at the deformation area of ​​the shield tail in the tunnel. 20H steel is used to reinforce the support frame of the 621-ring and 622-ring segments, and the support frame can be set up in combination with the connecting bridge. The 621-ring and 622-ring segments support a total of 4 support frames. After the support is completed, 10# channel steel is used to longitudinally tie the segments at 2, 5, 7, and 10 o'clock on the upper part of the 5-ring segments behind the shield tail.

[0045] 5) Positioning of pile-driving boat and measurement and positioning: The pile-driving boat is docked in the river channel to establish a plane control network for measuring the section line, and the coordinates of the steel casing 3 at the tail of the shield are measured and positioned. To prevent the movement of the ship due to the influence of water flow and tide, steel pipes can be set around the pile-driving boat for fixing in advance. Before vibrating and sinking the steel casing 3, its coordinate position and verticality are checked again. The measuring instrument uses a total station or GPS for measurement and positioning to ensure that the hole position deviation is less than 50mm and the verticality is less than 1%, and to prevent vibration hammering on the hinged seal.

[0046] 6) Arrangement and pile sinking of steel casing 3: Figure 1 , 2 As shown, four rows of vibration vertical points 2 are arranged vertically in the shield tail deformation area 1 and its vicinity along the shield machine axis. One point in the first row is located at the rear side of the shield tail deformation area 1, two points in the second row are located on the left and right sides of the shield tail deformation area 1, and two points in the third row are located at the maximum position in the shield tail deformation area 1. The purpose of the above three rows of holes is to enable the steel sheet piles 4 to directly vibrate and hammer to break the slurry blocks. The 7 points in the fourth row are located in the front position of the shield tail deformation area 1. The purpose is that the shield tail can be vibrated and hammered once when moving forward to ensure that the wrapped slurry blocks are completely broken. At the vibration vertical point 2, a pile driver is used to vibrate and sink 12 φ600mm steel casings 3, so that the steel casings 3 enter the strongly weathered rock layer for water and silt isolation, or the steel casings 3 are pressed down until they are immobile. The total length of the steel pipe is about 26m, the sinking depth of the pipe is about 18m, and the river bottom to the pipe top is about 8m to prevent tidal river water from backflow. Stopping vibration hammering is mainly controlled by penetration and design depth. Since the sunken steel pipe is long, attention should be paid to controlling the verticality when extending it.

[0047] 7) Drilling and vibration sinking of steel sheet piles 4: After the steel casing 3 is sunk, use a positive circulation drill and a φ500mm drill bit to drill holes in the steel casing 3 to the shield tail shell. During the drilling process, pay attention to check the specific gravity of the bentonite, and dig out the scum at the pipe mouth in time. After entering the rock formation, control the drilling speed. During the drilling process, arrange a dedicated person to be on duty at the tunnel shield tail to control the downward pressure of the drill rig when drilling the last 0.5m. When the drill bit touches the shield body and makes a sound, promptly notify the ground to stop drilling and lift the drill. After the drilling is completed, use a pile driver to vibrate and sink the steel sheet piles 4 one by one along the drill hole. The width of the steel sheet pile 4 is 400mm and the height is 100mm. When the steel sheet pile 4 is lowered, attention should be paid to the opening direction, such as Figure 1 As shown, the opening direction of the steel sheet pile 4 at the middle hole arrangement of the shield tail is toward the shield tail, and the opening directions of the steel sheet pile 4 at the outermost hole arrangement of the shield tail are toward the left and right sides respectively, which is more conducive to breaking the slurry blocks.

[0048] 8) Correction of deformation of shield tail: Figure 3 As shown, a support platform is set inside the shield tail. The support platform adopts an assembly platform 5. First, two 300H steels are welded at the shield tail to support the assembly platform 5. Then, 300H steels are welded on the left and right sides of the shield tail to support the upper crossbeam 6 of the portal frame. The upper crossbeam 6 adopts 450H steel and is placed on the splicing table, so that the assembly table and the 300H steel can support its force together. Two 450H steel supports are set on the upper part of the upper crossbeam 6, and a 600T jack 7 is placed on the top. Before the shield tail is returned to the top, the steel sheet piles 4 are vibrated in turn by a pile driver to crack the slurry blocks wrapped outside the shell, and then the jack 7 is used to lift and correct the deformation area 1 of the shield tail. The shield is lifted in the order of the middle first and then the two sides. During the process, make marks and measure the correction dimensions in time to control the roundness of the shell.

[0049] 9) Shell reinforcement: such as Figure 4 As shown, after the deformation area 1 of the shield tail is corrected, two deformed guide ribs are processed according to the original size and replaced, and five arc-shaped steel plates 8 are processed at the same time, with a length of 3000 mm, a width of 250 mm, and a thickness of 30 mm. The arc-shaped steel plates 8 are evenly distributed in the deformation area 1 of the shield tail through grid welding to strengthen the shell. The arc-shaped steel plates 8 are welded by cutting, and the welds on both sides of the arc-shaped steel plates 8 can be set intermittently. The temperature is controlled during welding to prevent the secondary deformation of the shield body caused by thermal expansion and contraction stress.

[0050] 10) Pushing while vibrating: Before re-pushing, the corresponding push ring number and cylinder stroke for stopping vibration should be formulated according to the position number of the steel sheet pile 4. Before the shield machine re-pushes, each steel sheet pile 4 is vibrated for 1 to 2 minutes to check whether each vibration point is normal, and then the shield machine starts to push again. During re-pushing, due to the control of the excavation speed, each steel sheet pile 4 is kept vibrating in turn. For every 100mm of advance of the shield machine, all steel sheet piles 4 vibrate once in a cycle, and the shield shell is vibrated and vibrated off by vibrating hammers to break and vibrate the wrapped slurry blocks. The condition of the shield tail shell should be checked during the process. During re-pushing, the thrust of the shield machine is controlled not to exceed 4100T. This embodiment adopts 3900T. The oil pressure distribution of each partition is as uniform as possible, the speed is controlled at 10 to 20mm / min, and the cutter head is adjusted after every 300 strokes of excavation. When the steel sheet pile 4 vibrates and sinks to contact the shield body, it should be lifted up 20 to 30mm before vibrating. During the first 10 rings of the shield machine re-pushing, thick bentonite or thick slurry shall be used for simultaneous grouting. After the slurry blocks are completely detached and the thrust drops to normal values, normal grouting will be resumed. Meanwhile, secondary grouting reinforcement shall be carried out in this section at a later stage.

[0051] 11) Shield body escapes from trouble: The shield tail passes through the vibration position of steel sheet pile 4. When the shield machine pushes forward 1 ring, the thrust drops significantly, from 3900T at the beginning to 3000T. The shield machine continues to push forward 2 rings, and the shield tail passes through the vibration position of steel sheet pile 4. The thrust drops to 2600T, and it is judged that the shield machine re-thrust parameters are normal. When the shield machine re-thrust parameters are normal, and the shield tail does not deform, the segment forming quality is good, and there is no misalignment or water leakage, it is judged that the slurry blocks wrapped in the shield tail shell have been effectively removed, and the shield machine has been successfully escaped from trouble;

[0052] 12) Sealing and removal of steel casing 3: When the shield tail is completely dragged through the 5th ring of the steel sheet pile 4, C15 commercial concrete or mortar is poured into the steel casing 3 to seal the hole, and finally the steel casing 3 is pulled out to complete the construction.

[0053] The above embodiments are only used to illustrate the present invention and are not intended to limit the present invention in any form. Any person with ordinary knowledge in the technical field may make partial changes or modifications to the technical contents disclosed in the present invention without departing from the scope of the technical features of the present invention, and the equivalent embodiments without departing from the technical features of the present invention are still within the scope of the technical features of the present invention.

Claims

1. A construction method for repairing the deformation of the shield tail of a shield machine under a river, characterized in that The following steps are involved: 1) Measure deformation: determine the deformation area and determine the size of the deformation area of ​​the shield tail through measurement; 2) Apply water stop ring: inject bentonite into the soil bin to fill the bin, and seal the water at the front and rear ends of the shield; 3) Hole inspection: Drill holes in the deformation area of ​​the shield tail to check the outer slurry wrapping of the shield shell; 4) Segment connection reinforcement: The segments in the deformation area of ​​the shield tail are supported and reinforced with support frames, and channel steel is used to longitudinally tie the segments on the upper part of the segments behind the shield tail; 5) Positioning of pile-driving boat and measurement and positioning: The pile-driving boat is docked in the river channel to establish the plane control network of the section line measurement, and the position coordinates of the steel casing at the tail of the shield are measured and positioned; 6) Arrangement and pile sinking of steel casing: vertically arrange vibration vertical points in the deformation area of ​​the shield tail and its vicinity, and use a pile driver to vibrate and sink the steel casing at the vibration vertical points, so that the steel casing enters the strongly weathered rock layer or is pressed down until it cannot move; 7) Drilling and steel sheet pile vibration sinking: After the steel casing is sunk, a drilling rig is used to drill holes in the steel casing to the shield tail shell, and a pile driver is used to vibrate and sink the steel sheet pile along the drilled hole; 8) Correction of deformation at the shield tail: a support platform is set inside the shield tail, and a jack is set on the support platform; first, a pile driver is used to vibrate the steel sheet piles in turn to crack the slurry blocks wrapped outside the shell, and then the jack is used to lift and correct the deformation area of ​​the shield tail; 9) Shell reinforcement: After the deformation area of ​​the shield tail is corrected, the deformed guide ribs are replaced, and then arc-shaped steel plates are evenly distributed in the deformation area of ​​the shield tail through grid welding to strengthen the shell; 10) Pushing forward while vibrating: The shield machine starts to push forward again. During the pushing forward, each steel sheet pile is vibrated in turn, and the shield shell is hit by vibration to break and vibrate off the wrapped slurry blocks; 11) Shield body escapes: If the tail of the shield passes through the vibration position of the steel sheet pile, the thrust parameters of the shield machine are normal, the tail of the shield does not deform, the segment forming quality is good, there is no misalignment or water leakage, then it is judged that the slurry blocks wrapped in the tail shell of the shield have been effectively removed and the shield machine has been successfully escaped; 12) Sealing and removal of steel casing: Pour commercial concrete or mortar into the steel casing to seal the holes, and finally pull out the steel casing to complete the construction.

2. The construction method for repairing the deformation of the shield tail of a shield machine under the river according to claim 1, characterized in that: In step 1), the deformation area is determined by measuring the shield tail gap size and observing the tendency of the shield tail to deform inwardly. The size of the shield tail deformation area is determined by measuring the axial length, circumferential width and maximum deformation of the shield tail deformation area.

3. The construction method for repairing the deformation of the shield tail of a shield machine under a river according to claim 1, characterized in that: In step 2), thick bentonite with a specific gravity of 1.2 is used, and the injection amount is determined by whether bentonite flows out of the soil bin ball valve. When performing ring sealing water, polyurethane ring sealing water is injected into the radial holes of the middle shield and the 3 ring openings behind the shield tail. The radial holes at 2 and 10 o'clock in the clock direction at the support near the shield tail are used as observation holes, and the water-stopping effect is checked through the observation holes.

4. The construction method for repairing the deformation of the shield tail of a shield machine under the riverbed according to claim 1 is characterized in that: In step 3), a φ20mm hole is drilled at the maximum deformation point using a magnetic drill. After drilling, first check whether there is water outside the shield through the hole, and then use φ10mm steel bars to check the rock formation. If there is no water and the formation is self-stable, first weld a 3-inch threaded joint on the shell, then expand the hole to φ50mm and install a ball valve. Clean the mud residue at the drilling position, first use a core pulling device to check the formation rock type and stability, and then use an endoscope to observe the slurry block wrapping condition outside the shield.

5. The construction method for repairing the deformation of the shield tail of a shield machine under the riverbed according to claim 1 is characterized in that: In step 4), the support frame is erected in combination with the connecting bridge; channel steel is used to longitudinally tie the segments at 2, 5, 7, and 10 o'clock on the upper part of the 5-ring segments behind the shield tail.

6. The construction method for repairing the deformation of the shield tail of a shield machine under the riverbed according to claim 1 is characterized by: In step 5), steel pipes are installed around the piling ship to prevent the ship from moving due to water flow and tides; the measuring instrument uses a total station or GPS for measurement and positioning to ensure that the hole position deviation is less than 50mm and the verticality is less than 1% to prevent vibration hammering on the hinged seal.

7. The construction method for repairing the deformation of the shield tail of a shield machine under the riverbed according to claim 1 is characterized by: In step 6), four rows of vibration vertical points are arranged vertically along the axis of the shield machine, with one point in the first row located at the rear side of the shield tail deformation area, two points in the second row located on the left and right sides of the shield tail deformation area, two points in the third row located at the maximum position in the shield tail deformation area, and seven points in the fourth row located in front of the shield tail deformation area; 12 steel casings are sunk by vibration, with a total length of 26m, a sinking depth of 18m, and a distance of 8m from the river bottom to the top of the pipe.

8. The construction method for repairing the deformation of the shield tail of a shield machine under a river according to claim 1, characterized in that: In step 7), a positive circulation drill is used for drilling. During the drilling process, attention should be paid to checking the specific gravity of the bentonite, and the scum at the pipe mouth should be dug out in time. After entering the rock formation, the drilling speed should be controlled. During the drilling process, a special person should be arranged to be on duty at the tail of the tunnel shield to control the downward pressure of the drill rig during the last 0.5m of drilling. When the drill bit hits the shield body and makes a sound, the ground should be notified in time to stop drilling and lift the drill. The steel sheet piles are vibrated and sunk one by one along the borehole. When the steel sheet piles are lowered, the opening direction of the steel sheet piles at the middle hole of the shield tail is toward the shield tail, and the opening direction of the steel sheet piles at the outermost hole of the shield tail is toward the left and right sides respectively.

9. The construction method for repairing the deformation of the shield tail of a shield machine under a river according to claim 1, characterized in that: In step 8), during the lifting and correction, the jacks are lifted in the order of the middle first and then the sides. During the process, good marks are made and the correction dimensions are measured in time to control the roundness of the shell.

10. The construction method for repairing the deformation of the shield tail of a shield machine under the riverbed according to claim 1, characterized in that: In step 9), the arc-shaped steel plate is welded by splitting, and the welds on both sides of the arc-shaped steel plate are intermittently arranged. The temperature is controlled during welding to prevent thermal expansion and contraction stress from causing secondary deformation of the shield body.

11. The construction method for repairing the deformation of the shield tail of a shield machine under a river according to claim 1, characterized in that: In step 11), when the thrust of the shield machine dropped significantly to 3000T after advancing 1 ring, the shield machine continued to advance 2 rings until the shield tail passed through the vibration position of the steel sheet piles, and the thrust dropped to 2600T. It was judged that the thrust parameters of the shield machine were normal.