A method for arranging routes of LKJ trains on high-speed railway lines for CTC

Through the CTC system's self-discipline machine and operation diagram software, the signal light operation is automatically judged and executed, which solves the problem of manual judgment errors in the operation of the C3 line, improves operation efficiency and safety, and reduces the burden on staff.

CN115535043BActive Publication Date: 2024-11-01CASCO SIGNAL LTD
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
CN202211386153.5
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-11-07
Publication Date
2024-11-01
Estimated Expiration
2042-11-07

AI Technical Summary

Technical Problem

When the LKJ train is running on line C3, it is necessary to manually determine the train number and signal status, which can easily lead to misjudgment and affect driving efficiency and safety.

Method used

Through the CTC system's self-discipline machine and operation diagram software, train plans are prepared, route sequences are generated, train numbers and signal status are automatically judged, and necessary signal lights are performed or alarms are performed to ensure the execution of route triggering steps.

Benefits of technology

It improves the safety and efficiency of LKJ trains operating on C3 line, reduces the work intensity of staff, realizes automated signal operation, reduces manual errors, is highly applicable and has low cost.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN115535043B_ABST
    Figure CN115535043B_ABST
Patent Text Reader

Abstract

The present invention provides a method for arranging routes of LKJ trains applied to CTC on high-speed railway lines, including the steps of: S1, preparing a train plan; S2, receiving and parsing the train plan, and generating a corresponding route sequence; S3, continuously patrolling the route sequence, checking the triggering timing of each train in the route sequence, and entering step S4 when there is a train that meets the triggering timing; S4, judging whether the train that meets the triggering timing needs to execute a signal lighting operation, and then executing a route triggering step or a signal lighting operation; S5, checking whether the signal has been lit, and then executing a route triggering step or an alarm. The present invention solves the technical problems existing in the operation of LKJ trains on the C3 line in the prior art, meets the requirements of the operation of power-concentrated EMUs on the C3 line, ensures the safe operation of the train, improves the operation efficiency, and reduces the work intensity of the staff.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of rail transit signals, and in particular to a method for arranging routes of LKJ (train operation control recording device) trains on high-speed railway lines applied to CTC (centralized traffic control, centralized dispatching system). Background Art

[0002] Fuxing CR200J centralized power EMU is a centralized power EMU based on the mature 25T passenger car and HXD1G / HXD3G locomotive, which aims to improve the quality of existing railway transportation services, meet people's increasingly high travel requirements, and realize the replacement of conventional speed trains in existing electrified railways. It subverts the concept of traditional passenger cars. While retaining the large capacity, it uses new structures and new materials to innovate passenger interfaces such as train interiors, such as improving sound insulation, heat insulation and shock absorption performance, and adding humanized design according to high-speed EMU standards to improve the travel comfort of the majority of passengers. Fuxing CR200J centralized power EMU is a type of LKJ train.

[0003] For China, the railway network is huge, and the centralized power EMU is not only to improve the efficiency of the hub, but more importantly, it is to promote the unification and standardization of our country's locomotives and vehicles. However, the operation of LKJ trains still requires locomotive drivers to observe the status of outdoor signal lights to drive the train, and the C3 (CTCS-3, China's train control system level 3, CTCS includes 0 to 4, a total of 5 levels, of which C2 and above are suitable for high-speed railways, and C4 is still in the research and development stage and has not been actually applied) line signal lights are normally off. Therefore, when LKJ trains run on the C3 line, the station must light up the corresponding signal lights when receiving or sending trains in order to receive and send trains normally. At present, it is necessary to manually judge whether the current train is an LKJ train and whether the current route needs to be lit, which is easy to cause misjudgment and affect driving efficiency. Summary of the invention

[0004] The purpose of the present invention is to provide a method for arranging the route of LKJ trains applied to CTC on high-speed railway lines, solve the technical problems existing in the operation of LKJ trains on C3 lines in the prior art, meet the needs of power-centralized EMUs running on C3 lines, ensure the safe operation of trains, improve operation efficiency, and reduce the work intensity of staff.

[0005] To achieve the above object, the present invention is implemented through the following technical solutions:

[0006] A method for arranging routes of LKJ trains on high-speed railway lines, applied to CTC, comprises the steps of:

[0007] S1. Prepare train plan;

[0008] S2, receiving and parsing the train plan, generating the corresponding route sequence;

[0009] S3, continuously patrol the route sequence, check the triggering timing of each train in the route sequence, and enter step S4 when there is a train that meets the triggering timing;

[0010] S4, determining whether the train number that meets the triggering opportunity needs to execute the signal lighting operation, and then executing the route triggering step or the signal lighting operation;

[0011] S5. Check whether the signal light is on, and then execute the route triggering steps or alarm.

[0012] Preferably, the high-speed railway line includes a first line and a second line, and the LKJ train does not need to perform a signal lighting operation when on the first line, but needs to perform a signal lighting operation when on the second line; step S4 includes:

[0013] S41, determine whether the train number is LKJ train:

[0014] If no, the train does not need to perform the signal lighting operation and executes the route triggering step;

[0015] If yes, go to step S42;

[0016] S42, determining whether the current line is the second line:

[0017] If no, the current line is the first line, and there is no need to perform the signal lighting operation, and the route triggering step is performed;

[0018] If yes, the train needs to execute the signal lighting operation. Execute the signal lighting operation.

[0019] Preferably, step S5 comprises:

[0020] Check whether the starting signals of all routes required by the current train are lit:

[0021] If yes, execute the route triggering step and automatically trigger the corresponding route;

[0022] If no, an alarm is sounded to remind the staff to light up the lights. Repeat this step until it is confirmed that the signal has been lit and then execute the route triggering step.

[0023] Preferably, in the signal lighting operation in step S4 and the step of checking whether the signal has been lit in step S5, the signal includes the starting signals of all routes that the current train needs to handle.

[0024] Preferably, the route triggering step in steps S4 and S5 includes:

[0025] J1. Automatically trigger the route of the current train and send the route trigger message to the interlocking execution;

[0026] J2. The route is completely locked, the signal is open, and the route triggering is completed.

[0027] Preferably, in step S42,

[0028] Whether the current line is the second line is determined based on whether the signal at the station has a light-off code position. If there is a light-off code position, it means that the line is the second line, otherwise it is not.

[0029] Preferably, the train plan includes LKJ train attributes, and the preparation of the train plan in step S1 includes setting the LKJ train attribute to be an LKJ train according to the actual type of the train.

[0030] Preferably, in step S41, determining whether the train number is an LKJ train is achieved by reading the LKJ train attributes in the train plan.

[0031] Preferably, step S1 is implemented by CTC's operation chart software.

[0032] Preferably, steps S2 and S3 are implemented by an autonomous machine of CTC.

[0033] Preferably, the second line is a line whose signal is normally off.

[0034] In summary, compared with the prior art, the method for arranging the route of LKJ trains on high-speed railway lines applied to CTC provided by the present invention has the following beneficial effects:

[0035] 1. Provides a solution for LKJ trains to run on the C3 line, meeting the needs of centralized power EMUs to run on the C3 line, ensuring safe train operation, improving operating efficiency, and reducing the workload of staff;

[0036] 2. Utilize the existing CTC system and modify the autonomous machine and operation diagram software to achieve simple implementation, low cost and easy promotion and application;

[0037] 3. The autonomous machine can perform different route handling logics according to whether it is an LKJ train or a C2 / C3 line, and has strong applicability;

[0038] 4. When the LKJ train runs on the C3 line, if the approach signal is not lit, an alarm will be sounded to remind the staff to light it. If the signal is not lit, the train cannot approach the route, which is safe and reliable. BRIEF DESCRIPTION OF THE DRAWINGS

[0039] Figure 1 It is a flow chart of the method for arranging routes of LKJ trains on high-speed railway lines applied to CTC of the present invention;

[0040] Figure 2 The present invention is a flow chart of the steps for judging whether a train number that meets the triggering opportunity needs to execute the signal lighting operation step. DETAILED DESCRIPTION

[0041] The following is a further detailed description of a method for arranging routes of LKJ trains applied to CTC on high-speed railway lines proposed by the present invention in combination with the accompanying drawings and specific embodiments. According to the following description, the advantages and features of the present invention will be clearer. It should be noted that the accompanying drawings are in a very simplified form and use non-precise proportions. They are only used to conveniently and clearly assist in explaining the purpose of the embodiments of the present invention, and are not used to limit the limiting conditions for the implementation of the present invention. Therefore, they have no technical substantive significance. Any structural modification, change in proportional relationship or adjustment of size should still fall within the scope of the technical content disclosed by the present invention without affecting the effects and purposes that can be achieved by the present invention.

[0042] It should be noted that, in the present invention, relational terms such as and are used only to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only the elements explicitly listed, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device.

[0043] Combined with Figures 1-2 The present invention provides a method for arranging routes of LKJ trains applied to CTC on high-speed railway lines, wherein in this embodiment, the high-speed railway line refers to the C2 or C3 line; the principle is: utilizing the existing CTC system, by modifying the CTC's autonomous machine and operation diagram software, compiling a train plan in the operation diagram software, and then receiving and parsing the train plan through the CTC's autonomous machine software, judging whether it is necessary to execute the signal lighting operation for the train number that meets the triggering timing based on the train plan and the current line, and executing the signal lighting operation only when the train is an LKJ train and the current line is a C3 line, and triggering the route for those that do not need to light up or have already lit up. As shown in the attached Figure 1 As shown, the method of the present invention comprises the steps of:

[0044] S1. Prepare train plans through CTC's operation diagram software;

[0045] Preferably, in some embodiments, the train plan includes LKJ train attributes, that is, when compiling the train plan, it can be set whether it is an LKJ train according to the actual type of the train, so that the subsequent step of determining whether it is an LKJ train is simple and accurate;

[0046] S2, receive and analyze the train plan through the CTC autonomous machine software, and generate the corresponding route sequence;

[0047] S3, the CTC autonomous machine continuously patrols the route sequence, checks the triggering timing of each train in the route sequence, and enters step S4 when there is a train that meets the triggering timing;

[0048] S4, judging whether the train number that meets the triggering opportunity needs to execute the signal lighting operation, and then executing the route triggering step or the signal lighting operation; Figure 2 As shown, this step includes:

[0049] S41, determine whether the train number is LKJ train:

[0050] If no, the train does not need to perform the signal lighting operation and executes the route triggering step;

[0051] If yes, go to step S42;

[0052] Preferably, in an embodiment where the train plan includes LKJ train attributes, determining whether the train number is an LKJ train is achieved by reading the LKJ train attributes in the train plan;

[0053] S42, determine whether the current line is a C3 line:

[0054] If no, the current line is C2 line, and there is no need to perform the signal lighting operation. Perform the route triggering step;

[0055] If yes, the train needs to execute the signal lighting operation, and execute the signal lighting operation; wherein the signal includes the starting signal of all routes that the current train needs to handle;

[0056] Preferably, in some embodiments, whether the current line is a C3 line is determined based on whether the signal at the station has a light-off code position. If there is a light-off code position, it means that the line is a C3 line, otherwise it is not. This judgment method is simpler and more accurate.

[0057] S5. Check whether the signal light is on, and then execute the route triggering step or alarm; including:

[0058] Check whether the starting signals of all routes required by the current train are lit:

[0059] If yes, execute the route triggering step and automatically trigger the corresponding route;

[0060] If no, an alarm is sounded to remind the staff to light up the lights. Repeat this step until it is confirmed that the signal has been lit and then execute the route triggering step.

[0061] Wherein, the route triggering step includes:

[0062] J1. Automatically trigger the route of the current train and send the route trigger message to the interlocking execution;

[0063] J2. The route is completely locked, the signal is open, and the route triggering is completed.

[0064] In summary, the present invention provides a method for arranging routes for LKJ trains applied to CTC on high-speed railway lines, provides a solution for LKJ trains to run on the C3 line, meets the needs of centralized power EMUs to run on the C3 line, ensures safe operation of trains, improves operation efficiency, and reduces the workload of staff; utilizes the existing system of CTC, and by modifying the autonomous machine and the operation diagram software, the implementation is simple, low-cost, and easy to promote and apply; the autonomous machine can perform different route processing logics according to whether it is an LKJ train and the C2 / C3 line, and has strong applicability; when the LKJ train runs on the C3 line, if the route signal is not lit, an alarm will be issued to remind the staff to light it, and the route cannot be processed when the signal is not lit, which is safe and reliable.

[0065] Although the content of the present invention has been described in detail through the above preferred embodiments, it should be appreciated that the above description should not be considered as a limitation of the present invention. After reading the above content, it will be apparent to those skilled in the art that various modifications and substitutions of the present invention will occur. Therefore, the protection scope of the present invention should be limited by the appended claims.

Claims

1. A method for arranging routes of LKJ trains on high-speed railway lines, applied to CTC, characterized in that: Includes steps: S1. Prepare train plan; S2, receiving and parsing the train plan, generating the corresponding route sequence; S3, continuously patrol the route sequence, check the triggering timing of each train in the route sequence, and enter step S4 when there is a train that meets the triggering timing; S4, determining whether the train number that meets the triggering opportunity needs to execute the signal lighting operation, and then executing the route triggering step or the signal lighting operation; The high-speed railway line includes a first line and a second line, the LKJ train does not need to perform a signal lighting operation when on the first line, and needs to perform a signal lighting operation when on the second line; step S4 includes: S41, determine whether the train number is LKJ train: If no, the train does not need to perform the signal lighting operation and executes the route triggering step; If yes, go to step S42; S42, determining whether the current line is the second line: If no, the current line is the first line, and there is no need to perform the signal lighting operation, and the route triggering step is performed; If yes, the train needs to execute the signal lighting operation. S5. Check whether the signal light is on, and then execute the route triggering steps or alarm.

2. The method for arranging the route of LKJ trains on a high-speed railway line as claimed in claim 1, characterized in that: Step S5 includes: Check whether the starting signals of all routes required by the current train are lit: If yes, execute the route triggering step and automatically trigger the corresponding route; If no, an alarm is sounded to remind the staff to light up the lights. Repeat this step until it is confirmed that the signal has been lit and then execute the route triggering step.

3. The method for arranging the route of LKJ trains on a high-speed railway line as claimed in claim 1, characterized in that: In the signal lighting operation in step S4 and the step of checking whether the signal has been lit in step S5, the signal includes the starting signals of all routes that the current train needs to handle.

4. The method for arranging the route of LKJ trains on a high-speed railway line as claimed in claim 1, characterized in that: The route triggering step in steps S4 and S5 includes: J1. Automatically trigger the route of the current train and send the route trigger message to the interlocking execution; J2. The route is completely locked, the signal is open, and the route triggering is completed.

5. The method for arranging the route of LKJ trains on a high-speed railway line as claimed in claim 1, characterized in that: In step S42, Whether the current line is the second line is determined based on whether the signal at the station has a light-off code position. If there is a light-off code position, it means that the line is the second line, otherwise it is not.

6. The method for arranging the route of LKJ trains on a high-speed railway line as claimed in claim 1, characterized in that: The train plan includes LKJ train attributes, and the preparation of the train plan in step S1 includes setting the LKJ train attribute to be an LKJ train according to the actual type of the train.

7. The method for arranging the route of LKJ trains on a high-speed railway line as claimed in claim 6, characterized in that: In step S41, whether the train number is an LKJ train is determined by reading the LKJ train attributes in the train plan.

8. The method for arranging the route of LKJ trains on a high-speed railway line as claimed in claim 1, characterized in that: Step S1 is implemented by the operation chart software of CTC.

9. The method for arranging the route of LKJ trains on a high-speed railway line as claimed in claim 1, characterized in that: Steps S2 and S3 are implemented by the autonomous machine of CTC.

10. The method for arranging the route of LKJ trains on a high-speed railway line according to claim 1 or 5, characterized in that: The second line is a line where the signal light is normally off.

Citation Information

Patent Citations

  • Automatic access management method and control device for high-speed train

    CN102616251A

  • Centralized traffic control (CTC) automatic approaching trigger method applicable to inter-city railways

    CN110104029A

  • CTC route control method for automatic inter-city railway reentry operation

    CN110203259A

  • Method and device for displaying route advance notice and handling condition of train control system

    CN113335345A

  • Train routing method and total traffic control device

    JP1999048974A