By dividing the reinforcement zone and optimizing the reinforcement structure based on quantitative characteristic parameters and numerical simulation during tunnel construction in karst areas, the problems of poor reinforcement effect and high cost of karst tunnels have been solved, and efficient and economical tunnel reinforcement effect has been achieved.
Patent Information
- Application Number
- CN202211427054.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-11-15
- Publication Date
- 2026-11-17
- Estimated Expiration
- 2042-11-15
AI Technical Summary
When constructing tunnels in karst areas, existing reinforcement methods suffer from poor reinforcement effects and high costs. Furthermore, conventional methods rely on experience and qualitative analysis, making it difficult to guarantee the safety and economy of the tunnel structure.
By obtaining quantitative characteristic parameters of the tunnel structure and its surrounding soil layers and karst caves, a karst tunnel construction model is constructed, dividing the tunnel into a first reinforcement zone and a second reinforcement zone. Different reinforcement structures are adopted, and the reinforcement scheme is optimized through numerical simulation to ensure that the stress and deformation characteristics of the tunnel surrounding rock after reinforcement meet the requirements and achieve the target reinforcement scheme.
It improved the effectiveness of tunnel reinforcement in karst areas, reduced construction costs, avoided unnecessary over-reinforcement, and enhanced the reliability and applicability of the reinforcement scheme.
Smart Images

Figure CN115758524B_ABST
Abstract
Description
Technical Field
[0001] This invention belongs to the field of building construction technology, specifically relating to a method for reinforcing tunnels in karst areas. Background Technology
[0002] With the booming development of tunnel construction across the country, the complex working conditions encountered in tunnel construction are increasing, leading to a growing demand for tunnel reinforcement measures. Due to the influence of geological hydrological conditions, tunnel construction faces more stringent requirements, particularly in karst areas. Constructing tunnels in these regions may cause accidents such as cavern collapses. Sometimes, grouting is used for ground reinforcement; however, this method is costly and prone to leakage. Furthermore, methods like anchor bolts and grouting support may result in over-support over large areas, wasting resources. Additionally, current reinforcement methods rely solely on verifying whether the safety factor meets regulatory requirements to determine the safety of the reinforced tunnel structure. Achieving both effective reinforcement and low construction costs is often difficult. Summary of the Invention
[0003] In view of the problems in the prior art, the present invention proposes a method for tunnel reinforcement in karst areas, which, compared with existing reinforcement methods, not only ensures the reinforcement effect but also reduces construction costs.
[0004] This invention proposes a method for reinforcing tunnels in karst areas, comprising the following steps:
[0005] To obtain quantitative characteristic parameters of the tunnel structure and its surrounding soil layers and karst caves;
[0006] Based on the quantitative characteristic parameters, a karst tunnel construction model simulating the tunnel structure and its surrounding soil layers and karst caves is constructed; the stress and deformation characteristics of the surrounding rock of the karst tunnel construction model under construction load are obtained.
[0007] Based on the stress and deformation characteristics of the surrounding rock of the tunnel, the reinforcement area of the surrounding rock of the tunnel is divided into a first reinforcement area and a second reinforcement area; wherein, the first reinforcement area is located between the simulated karst cave and the tunnel structure, and the second reinforcement area is located around the simulated tunnel structure;
[0008] The karst tunnel construction model simulates a first reinforcement structure in the first reinforcement zone and a second reinforcement structure in the second reinforcement zone. The stress and deformation characteristics of the tunnel surrounding rock under construction loads are then obtained from the karst tunnel construction model to obtain the stress and deformation characteristics of the tunnel surrounding rock after reinforcement. Based on these reinforcement characteristics, the division between the first and second reinforcement zones is corrected, and the first and second reinforcement structures are simulated again until the stress and deformation characteristics of the tunnel surrounding rock after reinforcement meet the requirements, thus obtaining the target reinforcement scheme.
[0009] Based on the aforementioned target reinforcement scheme, tunnel reinforcement construction was carried out in karst areas.
[0010] Furthermore, the step of dividing the reinforced area of the tunnel surrounding rock into a first reinforced area includes:
[0011] A rectangular coordinate system is established with the center of the simulated tunnel structure as the origin and the radial section of the tunnel structure as the plane; the simulated karst cave is located in the plane of this rectangular coordinate system.
[0012] In a Cartesian coordinate system, the first sector-shaped region centered at the origin, located between the simulated cave and tunnel structures, is predefined as the first reinforcement area; the central angle of the first sector-shaped region is predefined as 'a', and the radius as 'd'.
[0013] The step of correcting the division of the first reinforced area includes: adjusting the values of the central angle α and the radius d.
[0014] Furthermore, the step of correcting the division of the first reinforced area also includes: adjusting the relative position of the first sector area and the simulated cave in the plane of the rectangular coordinate system, so that the center line of the first sector area passing through the center of the circle points to the simulated cave.
[0015] Furthermore, the first reinforced area includes a plurality of first sector-shaped regions disposed on the plane of the rectangular coordinate system.
[0016] Furthermore, the step of dividing the reinforced area of the tunnel surrounding rock into a first reinforced area also includes:
[0017] Multiple rectangular coordinate systems are established along the length of the simulated tunnel structure;
[0018] The first sector block region formed by merging the first sector regions of the multiple rectangular coordinate systems is preset as the first reinforcement area.
[0019] Furthermore, the step of dividing the reinforced area of the tunnel surrounding rock into a second reinforced area includes:
[0020] In the Cartesian coordinate system, a second sector-shaped region centered at the origin is pre-defined as the second reinforcement area. The second sector-shaped region and the first sector-shaped region are dispersed along the circumference of the simulated tunnel structure, and the radius of the second sector-shaped region is smaller than the radius of the first sector-shaped region.
[0021] Furthermore, the quantitative characteristic parameters include the number and burial depth of the tunnel structures, the number, shape, size, and position of the karst caves relative to the tunnel structures, and the soil properties of the surrounding soil layers.
[0022] Furthermore,
[0023] The karst tunnel construction model includes a tunnel lining model, a soil layer model, and a support model.
[0024] The steps for constructing a karst tunnel construction model simulating the tunnel structure and its surrounding soil layers and karst caves based on the quantitative characteristic parameters include:
[0025] Based on the quantitative characteristic parameters, the soil layer model is constructed. The soil in the embedded shell and the hollowed-out shell is used to simulate the karst cave. Based on the stress balance applied to the karst cave, the tunnel lining model and support model are constructed when the tunnel surrounding rock is subjected to construction load using the quantitative characteristic parameters.
[0026] The tunnel structure includes a tunnel body and a tunnel lining structure surrounding the tunnel body; the soil model adopts the Mohr-Coulomb constitutive model to simulate the tunnel body and its surrounding soil layers and karst caves; the tunnel lining model adopts the concrete damage plasticity model to simulate the tunnel lining structure; and the support model adopts the ideal elastic-plastic model to simulate the first and second reinforcement structures.
[0027] Furthermore, the first reinforcement structure includes a grouting layer and a plurality of first grouting pipes; the plurality of first grouting pipes are distributed circumferentially along the tunnel lining structure simulated by the tunnel lining model; the grouting layer is located at one end of the plurality of first grouting pipes away from the tunnel lining structure, and the end face of the grouting layer facing the karst cave simulated by the soil model is an arc surface.
[0028] Furthermore, the second reinforcement structure includes a plurality of second grouting pipes distributed circumferentially along the tunnel lining structure simulated by the tunnel lining model, wherein the length of the second grouting pipes is shorter than the length of the first grouting pipes.
[0029] The beneficial effects of this invention include: Based on hydrogeological information such as tunnel structure and geological survey reports, this invention obtains quantitative characteristic parameters of the tunnel structure and its surrounding soil layers and karst caves. Through numerical simulation, it quantitatively analyzes the stress and deformation characteristics of the tunnel surrounding rock during the construction process (the tunnel surrounding rock bears the construction load), initially determining the most unfavorable tunnel surrounding rock range (i.e., the first reinforcement zone). After initially determining the division between the first and second reinforcement zones, numerical simulation is used to compare the stress and deformation characteristics before and after applying the first and second reinforcement structures, so as to correct and optimize the division between the first and second reinforcement zones. This results in a more reliable and applicable target reinforcement scheme. Compared with commonly used tunnel surrounding rock reinforcement methods, this invention reduces the drawbacks of over-reliance on experience and qualitative analysis, thereby improving the reinforcement effect and having the advantage of being suitable for support in complex karst areas. In addition, by dividing the tunnel surrounding rock reinforcement area into a first reinforcement zone and a second reinforcement zone, and setting the first reinforcement zone as the most unfavorable tunnel surrounding rock range, and adopting a different reinforcement structure than the second reinforcement zone, the reinforcement effect of the tunnel surrounding rock is guaranteed, while avoiding over-reinforcement of unnecessary reinforcement ranges, thus reducing construction costs. Attached Figure Description
[0030] Figure 1 This is a flowchart of the tunnel reinforcement method for karst areas according to the present invention.
[0031] Figure 2 This is a schematic diagram of the rectangular coordinate system established with the radial section of the tunnel structure as the plane, and the simulated positional relationship between the karst cave and the tunnel structure on the plane, which is the method for tunnel reinforcement in karst areas according to the present invention.
[0032] Figure 3 for Figure 2 The rectangular coordinate system in the diagram divides the reinforced area of the tunnel surrounding rock into a first reinforcement zone and a second reinforcement zone, and corresponding schematic diagrams of the first and second reinforcement structures are provided.
[0033] Figure 4 for Figure 3 The simulated tunnel structure on the plane of the Cartesian coordinate system is a schematic diagram of a two-way tunnel.
[0034] In the diagram: 10-karst cave; 20-tunnel structure; 30-first reinforcement zone; 40-second reinforcement zone; 50-grouting layer; 60-first grouting pipe; 70-second grouting pipe. Detailed Implementation
[0035] The following is in conjunction with the appendix Figure 1 To be continued Figure 4 The present invention will be further described in detail with reference to specific embodiments.
[0036] The tunnel reinforcement method proposed in this invention is actually a tunnel surrounding rock reinforcement method based on construction load. Addressing the problem of karst caves in karst areas, it identifies specific quantitative characteristic parameters based on the region's geological and hydrological conditions. On this basis, it analyzes the stress and deformation characteristics of the tunnel surrounding rock during construction, determines the most unfavorable surrounding rock range, selects different degrees of further reinforcement, compares and analyzes the advantages and disadvantages of different reinforcement schemes, and evaluates the safety status of the reinforced tunnel structure using the tunnel reinforcement structure safety factor grading standard. This determines the optimal reinforcement scheme, and the tunnel reinforcement is achieved based on the determined optimal reinforcement scheme (i.e., the target reinforcement scheme).
[0037] The proposed method for tunnel reinforcement in karst areas involves first simulating the stress and deformation characteristics of the tunnel surrounding rock under construction loads using a karst tunnel construction model. Then, a preliminary reinforcement area is determined, divided into a first reinforcement zone and a second reinforcement zone. The first reinforcement zone is considered the most unfavorable area of the tunnel surrounding rock. Further reinforcement simulations are then performed, simulating a first reinforcement structure in the first reinforcement zone and a second reinforcement structure in the second reinforcement zone, resulting in different reinforcement levels for the two zones. Based on the stress and deformation characteristics of the reinforced tunnel surrounding rock, the division of the first and second reinforcement zones is corrected, and the first and second reinforcement structures are simulated again until the stress and deformation characteristics of the reinforced tunnel surrounding rock simulated by the karst tunnel construction model meet the requirements. This yields a target reinforcement scheme, which includes the division of the first and second reinforcement zones and the specific reinforcement schemes for the first and second reinforcement structures. After obtaining the target reinforcement scheme through the simulation of the karst tunnel construction model, this target reinforcement scheme is used as the specific construction scheme for the actual reinforcement construction of tunnels in karst areas.
[0038] like Figure 1 As shown, the tunnel reinforcement method for karst areas proposed in this invention includes the following steps:
[0039] Quantitative characteristic parameters of the tunnel structure 20 and its surrounding soil layers and karst caves 10 are obtained. These quantitative characteristic parameters include the number and depth of the tunnel structures 20, the number, shape, size, and position of the karst caves 10 relative to the tunnel structures 20, and the soil properties of the surrounding soil layers. Among these quantitative characteristic parameters, the number and depth of the tunnel structures 20 are determined by the design documents; the soil properties, size, and shape of the karst caves 10 are determined by geological survey reports and other documents; and the position (distance, angle) of the karst caves 10 relative to the tunnel structures 20 is jointly determined by the design documents and the geological survey report, etc.
[0040] Preliminary numerical simulations determine the stress and deformation characteristics of the tunnel surrounding rock. This includes: based on the quantitative characteristic parameters, using numerical simulation to construct a karst tunnel construction model simulating the tunnel structure 20 and its surrounding soil layers and karst caves 10; obtaining the stress and deformation characteristics of the tunnel surrounding rock under construction loads in the karst tunnel construction model. This allows for the classification of the deformation and stress of the tunnel surrounding rock at different locations.
[0041] The center of tunnel structure 20 is determined, and a rectangular coordinate system is established with the radial section of tunnel structure 20 as the plane to determine the reinforcement area of the surrounding rock and provide a preliminary reinforcement scheme. This includes: based on the stress and deformation characteristics of the surrounding rock, dividing the reinforcement area of the surrounding rock into a first reinforcement zone 30 and a second reinforcement zone 40; wherein, the first reinforcement zone 30 is located between the simulated karst cave 10 and tunnel structure 20, and the second reinforcement zone 40 is located around the simulated tunnel structure 20.
[0042] A preliminary reinforcement scheme is simulated, compared and analyzed, and the reinforcement scheme is optimized to obtain the target reinforcement scheme. This includes: simulating a first reinforcement structure in the first reinforcement zone 30 and a second reinforcement structure in the second reinforcement zone 40 using the karst tunnel construction model; obtaining the stress and deformation characteristics of the tunnel surrounding rock under construction loads using the karst tunnel construction model again to obtain the stress and deformation characteristics of the tunnel surrounding rock after reinforcement; based on the stress and deformation characteristics after reinforcement, correcting the division of the first reinforcement zone 30 and the second reinforcement zone 40, and simulating the first and second reinforcement structures again until the stress and deformation characteristics of the tunnel surrounding rock after reinforcement meet the requirements, thus obtaining the target reinforcement scheme.
[0043] Based on the aforementioned target reinforcement scheme, tunnel reinforcement construction was carried out in karst areas.
[0044] Specifically, the step of dividing the reinforced area of the tunnel surrounding rock into the first reinforced area 30 includes:
[0045] like Figure 2 As shown, a rectangular coordinate system is established with the center of the simulated tunnel structure 20 as the origin and the radial section of the tunnel structure 20 as the plane; wherein, the simulated karst cave 10 is located in the plane of this rectangular coordinate system;
[0046] In a rectangular coordinate system, the first sector-shaped region centered at the origin, located between the simulated cave 10 and tunnel structure 20, is preset as the first reinforcement area 30; the central angle of the first sector-shaped region is preset to be 'a', and the radius is preset to be 'd'.
[0047] The step of correcting the division of the first reinforced area 30 includes: adjusting the values of the central angle α and the radius d. For example, increasing or decreasing the value of the central angle α and the value of the radius d.
[0048] The step of dividing the reinforced area of the tunnel surrounding rock into a second reinforced area 40 includes:
[0049] In the Cartesian coordinate system, a second sector-shaped region centered at the origin is pre-defined as the second reinforcement area 40. The second sector-shaped region and the first sector-shaped region are dispersed along the circumference of the simulated tunnel structure 20, and the radius of the second sector-shaped region is smaller than the radius of the first sector-shaped region.
[0050] In some embodiments, the step of correcting the division of the first reinforced area 30 further includes: adjusting the relative position of the first sector area and the simulated cave 10 in the plane of the rectangular coordinate system, so that the center line of the first sector area passing through the center of the circle points to the simulated cave 10. In other words, although the division of the first reinforced area 30 is determined, its relative position with the simulated cave 10 and the origin of the rectangular coordinate system is not determined. The relative position of the first reinforced area 30 and the simulated cave 10 can be adjusted by adjusting the angle of rotation of the first reinforced area 30 around the origin. Of course, in a preferred embodiment, in such a case... Figure 2 In the plane of the Cartesian coordinate system shown, the centerline of the first sector region representing the first reinforced area 30 passes through both the center of the simulated cave 10 and the origin of the Cartesian coordinate system. In other words, the centerline of the first sector region divides the central angle α of the first sector region into two angles of α / 2.
[0051] In some embodiments, the first reinforced area 30 includes a plurality of first sector-shaped areas disposed on the plane of the Cartesian coordinate system. (See attached diagram) Figure 2 Although only one first reinforcement zone 30 is shown in the diagram, in practice, if multiple karst caves 10 exist around the same radial cross-section of the tunnel structure 20, multiple first sector-shaped regions are set on the radial cross-section (or the plane where the rectangular coordinate system is located), and these multiple first sector-shaped regions constitute the first reinforcement zone 30 on the plane where the rectangular coordinate system is located. Alternatively, in some embodiments, there are multiple first reinforcement zones 30, each including a first sector-shaped region. When multiple karst caves 10 exist around the same radial cross-section of the tunnel structure 20, multiple first reinforcement zones 30 are set on the radial cross-section (or the plane where the rectangular coordinate system is located). In addition, when multiple karst caves 10 exist around the same radial cross-section, the division areas of the multiple first reinforcement zones 30 or multiple first sector-shaped regions set on the radial cross-section can be different. This is because the multiple karst caves 10 on the same radial cross-section are not all at the same distance from the tunnel structure 20.
[0052] The step of dividing the reinforced area of the tunnel surrounding rock into the first reinforced area 30 further includes:
[0053] Multiple rectangular coordinate systems are established along the length of the simulated tunnel structure 20; the first sector block region formed by merging the first sector regions of the multiple rectangular coordinate systems is preset as the first reinforcement area 30.
[0054] For ease of demonstration and understanding, please refer to the attached document. Figure 3 The diagram only illustrates the division of the first reinforcement zone 30 and the second reinforcement zone 40 within a rectangular coordinate system. However, in actual construction, the tunnel structure 20 has a length; therefore, in reality, there are multiple auxiliary reinforcement zones along the length of the tunnel structure 20. Figure 3 The rectangular coordinate system shown in the image. After merging the first sector-shaped regions distributed along the length of the tunnel structure 20 in these rectangular coordinate systems, a first sector block region is formed, which is the first reinforcement zone 30 mentioned above. Since the shape of the karst cave 10 is not uniform in every rectangular coordinate system... Figure 3 The circles shown are not all at the same distance from the center of the tunnel structure 20. Therefore, the first sector regions in these rectangular coordinate systems, after being merged, do not necessarily form a sector block region. They can also be other irregular regions. This irregular region can be preset as the first reinforcement area 30.
[0055] The karst tunnel construction model includes a tunnel lining model, a soil layer model, and a support model.
[0056] The steps for constructing a karst tunnel construction model simulating the tunnel structure 20 and its surrounding soil layers and karst caves 10 based on the quantitative characteristic parameters include:
[0057] Based on the quantitative characteristic parameters, the soil layer model is constructed using numerical simulation. The karst cave 10 is simulated by the soil inside the embedded shell and the hollowed-out shell. Based on the stress balance applied to the karst cave 10, the tunnel lining model and support model are constructed using the quantitative characteristic parameters when the tunnel surrounding rock is subjected to construction loads.
[0058] The tunnel structure 20 includes a tunnel body and a tunnel lining structure disposed around the tunnel body.
[0059] The soil layer model adopts the Mohr-Coulomb constitutive model to simulate the tunnel body and its surrounding soil layers and karst cave 10. Among them, the karst cave 10 is simulated by a hollow shell, and the soil around the tunnel body is layered based on the geological survey report, and the parameters of each soil layer are set.
[0060] The tunnel lining model employs a concrete damage plasticity model to simulate the tunnel lining structure. The tunnel lining structure and the soil layer are in frictional hard contact.
[0061] The support model adopts an ideal elastic-plastic model to simulate the first and second reinforced structures. The first and second reinforced structures are reinforced in the soil layer using an embedded region approach.
[0062] The first reinforcement structure includes a grouting layer 50 and multiple first grouting pipes 60; the multiple first grouting pipes 60 are distributed circumferentially along the tunnel lining structure simulated by the tunnel lining model; the grouting layer 50 is located at the end of the multiple first grouting pipes 60 away from the tunnel lining structure, and the end face of the grouting layer 50 facing the karst cave 10 simulated by the soil model is an arc surface. The first reinforcement structure forms the grouting layer 50 through the multiple first grouting pipes 60. (See attached...) Figure 3 As shown, the arc angle of the grouting layer 50 on the arc surface is the central angle α of the first sector region. The grouting layer 50 is in hard friction contact with the soil.
[0063] The second reinforcement structure includes a plurality of second grouting pipes 70 distributed circumferentially along the tunnel lining structure simulated by the tunnel lining model, wherein the length of the second grouting pipe 70 is shorter than the length of the first grouting pipe 60.
[0064] Appendix Figure 3 It can be seen that the reinforcement effect of the first reinforcement structure is better than that of the second reinforcement structure. By modifying the division area of the first reinforcement area 30, the best possible reinforcement effect can be achieved by using the smallest possible first reinforcement area 30, thereby reducing construction costs.
[0065] The first and second reinforcement structures simulated in the karst tunnel construction model described above can also be applied to actual on-site construction. That is, after obtaining the target reinforcement scheme, it can be directly applied to the tunnel reinforcement construction in karst areas, so that the surrounding rock of the solid tunnel structure 20 in the karst area is provided with the first reinforcement zone 30, the second reinforcement zone 40, the first reinforcement structure set on the first reinforcement zone 30, and the second reinforcement structure set on the second reinforcement zone 40.
[0066] Appendix Figure 3 The diagram only shows a schematic representation of the reinforcement construction for a one-way tunnel. For example... Figure 4 As shown, the method of the present invention can also be applied to the reinforcement construction of bidirectional tunnels, and the construction method is the same as that for the reinforcement construction of unidirectional tunnels.
[0067] The above description is merely a preferred embodiment of the present invention. The scope of protection of the present invention is not limited to the above embodiments. All technical solutions falling within the scope of the present invention's concept are within the scope of protection of the present invention. It should be noted that for those skilled in the art, any improvements and modifications made without departing from the principle of the present invention should also be considered within the scope of protection of the present invention.
Claims
1. A method of reinforcing a tunnel in a karst region, characterized by, Includes the following steps: To obtain quantitative characteristic parameters of the tunnel structure and its surrounding soil layers and karst caves; Based on the quantitative characteristic parameters, a karst tunnel construction model simulating the tunnel structure and its surrounding soil layers and karst caves is constructed; the stress and deformation characteristics of the surrounding rock of the karst tunnel construction model under construction load are obtained. Based on the stress and deformation characteristics of the surrounding rock of the tunnel, the reinforcement area of the surrounding rock of the tunnel is divided into a first reinforcement area and a second reinforcement area; wherein, the first reinforcement area is located between the simulated karst cave and the tunnel structure, and the second reinforcement area is located around the simulated tunnel structure; The karst tunnel construction model simulates a first reinforcement structure in the first reinforcement zone and a second reinforcement structure in the second reinforcement zone. The stress and deformation characteristics of the tunnel surrounding rock under construction loads are then obtained from the karst tunnel construction model to obtain the stress and deformation characteristics of the tunnel surrounding rock after reinforcement. Based on these reinforcement characteristics, the division between the first and second reinforcement zones is corrected, and the first and second reinforcement structures are simulated again until the stress and deformation characteristics of the tunnel surrounding rock after reinforcement meet the requirements, thus obtaining the target reinforcement scheme. Based on the target reinforcement scheme, tunnel reinforcement construction is carried out in karst areas; the step of dividing the reinforcement area of the tunnel surrounding rock into the first reinforcement zone includes: A rectangular coordinate system is established with the center of the simulated tunnel structure as the origin and the radial section of the tunnel structure as the plane; the simulated karst cave is located in the plane of this rectangular coordinate system. In a Cartesian coordinate system, the first sector-shaped region centered at the origin, located between the simulated cave and tunnel structures, is predefined as the first reinforcement area; the central angle of the first sector-shaped region is predefined as 'a', and the radius as 'd'. The step of correcting the division of the first reinforced area includes: adjusting the values of the central angle α and the radius d; The step of dividing the reinforced area of the tunnel surrounding rock into a second reinforced area includes: In the Cartesian coordinate system, a second sector-shaped region centered at the origin is pre-defined as the second reinforcement area. The second sector-shaped region and the first sector-shaped region are dispersed along the circumference of the simulated tunnel structure, and the radius of the second sector-shaped region is smaller than the radius of the first sector-shaped region.
2. The method for reinforcing tunnels in karst areas according to claim 1, characterized in that, The step of correcting the division of the first reinforced area further includes: adjusting the relative position of the first sector area and the simulated cave in the plane of the rectangular coordinate system, so that the center line of the first sector area passing through the center of the circle points to the simulated cave.
3. The method for reinforcing tunnels in karst areas according to claim 1, characterized in that, The first reinforced area includes a plurality of first sector-shaped regions disposed on the plane of the rectangular coordinate system.
4. The method for reinforcing tunnels in karst areas according to claim 1, characterized in that, The step of dividing the reinforced area of the tunnel surrounding rock into the first reinforced area further includes: Multiple rectangular coordinate systems are established along the length of the simulated tunnel structure; The first sector block region formed by merging the first sector regions of the multiple rectangular coordinate systems is preset as the first reinforcement area.
5. The method for reinforcing tunnels in karst areas according to claim 1, characterized in that, The quantitative characteristic parameters include the number and depth of the tunnel structure, the number, shape, size and position of the karst caves relative to the tunnel structure, and the soil properties of the surrounding soil layers.
6. The method for reinforcing tunnels in karst areas according to claim 1, characterized in that, The karst tunnel construction model includes a tunnel lining model, a soil layer model, and a support model. The steps for constructing a karst tunnel construction model simulating the tunnel structure and its surrounding soil layers and karst caves based on the quantitative characteristic parameters include: Based on the quantitative characteristic parameters, the soil layer model is constructed. The soil in the embedded shell and the hollowed-out shell is used to simulate the karst cave. Based on the stress balance applied to the karst cave, the tunnel lining model and support model are constructed when the tunnel surrounding rock is subjected to construction load using the quantitative characteristic parameters. The tunnel structure includes a tunnel body and a tunnel lining structure surrounding the tunnel body; the soil model adopts the Mohr-Coulomb constitutive model to simulate the tunnel body and its surrounding soil layers and karst caves; the tunnel lining model adopts the concrete damage plasticity model to simulate the tunnel lining structure; and the support model adopts the ideal elastic-plastic model to simulate the first and second reinforcement structures.
7. The method for reinforcing tunnels in karst areas according to claim 6, characterized in that, The first reinforcement structure includes a grouting layer and multiple first grouting pipes; the multiple first grouting pipes are distributed circumferentially along the tunnel lining structure simulated by the tunnel lining model; the grouting layer is located at the end of the multiple first grouting pipes away from the tunnel lining structure, and the end face of the grouting layer facing the karst cave simulated by the soil model is an arc surface.
8. The method for reinforcing tunnels in karst areas according to claim 7, characterized in that, The second reinforcement structure includes a plurality of second grouting pipes distributed circumferentially along the tunnel lining structure simulated by the tunnel lining model, wherein the length of the second grouting pipe is shorter than the length of the first grouting pipe.
Citation Information
Patent Citations
Tunnel strengthening treatment method and support structure based on positions of dissolving cavities
CN106401600A
Tunnel bottom combined type reinforcement treatment method for crossing large-scale fully-filled karst cave
CN111794755A