Modular construction and installation system and method for high-temperature gas-cooled reactor nuclear power plant internal components
By first assembling the reactor internal component modules in a pre-assembly building outside the nuclear island plant and then using two cranes to lift them into the reactor pressure vessel cylinder, the problem of long installation period of reactor internal components in high-temperature gas-cooled reactor nuclear power plants was solved, and an efficient construction process was achieved.
Patent Information
- Application Number
- CN202211563530.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-12-07
- Publication Date
- 2025-09-26
- Estimated Expiration
- 2042-12-07
AI Technical Summary
The installation process of the internal components of a high-temperature gas-cooled reactor nuclear power plant takes up a long period of the main construction period, resulting in low construction efficiency.
A modular construction and installation system is adopted. While the civil construction of the reactor compartment and the installation of the reactor pressure vessel cylinder are in progress, the internal component modules are first assembled in a pre-assembly building outside the nuclear island plant, and then lifted into the reactor pressure vessel cylinder by two cranes.
It effectively shortened the main construction period of the high-temperature gas-cooled reactor, saved 5 months of construction time, and improved economic efficiency.
Smart Images

Figure CN115773023B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of nuclear power construction, and in particular to a modular construction and installation system and method for internal components of a high-temperature gas-cooled reactor nuclear power plant. Background Art
[0002] The original installation process for high-temperature gas-cooled reactor internal components (such as the core support structure) was: after the civil construction of the reactor compartment was completed, the reactor pressure vessel cylinder was installed first, and then the internal components were installed piece by piece inside it. This took a long time to complete the main line construction, which was 5 months. Summary of the Invention
[0003] In view of this, the present invention provides a modular construction and installation system for the internal components of a high-temperature gas-cooled reactor nuclear power plant. During the civil construction of the reactor compartment and the installation of the reactor pressure vessel cylinder, the internal components can be assembled into an internal component module by a first crane in a pre-assembly building outside the nuclear island building. After the installation of the reactor pressure vessel cylinder is completed, the internal component module can be lifted out of the pre-assembly building by a second crane and lifted into and installed in the reactor pressure vessel cylinder, thereby effectively shortening the main construction period of the high-temperature gas-cooled reactor, helping to save 5 months of the main construction period of the high-temperature gas-cooled reactor, and also helping to improve the economy of the high-temperature gas-cooled reactor.
[0004] To achieve the above object, the present invention provides the following technical solutions:
[0005] A modular construction and installation system for internal components of a high-temperature gas-cooled reactor nuclear power plant, comprising: a pre-assembly plant, a first crane, and a second crane;
[0006] The pre-assembly plant is used to be arranged outside the nuclear island plant, and a retractable roof is provided on the top of the plant. The pre-assembly plant is provided with an assembly area for the reactor internal component modules, and is aligned with the roof in the upper and lower positions.
[0007] The first crane is arranged in the preassembly plant and is capable of sequentially lifting a plurality of cylinders moved into the preassembly plant into the internals component module assembly area to assemble into internals component cylinders, and is capable of sequentially lifting a plurality of module components moved into the preassembly plant into the internals component cylinders to assemble into internals component modules;
[0008] The second crane is arranged outside the preassembly building and is used to lift the internals module out of the preassembly building and into the reactor pressure vessel cylinder of the reactor compartment installed in the nuclear island building for installation.
[0009] Preferably, the assembly area of the in-core component modules is provided with a plurality of assembly pits and a plurality of assembly platforms;
[0010] A plurality of the assembly platforms are arranged in one-to-one correspondence around a plurality of the assembly pits.
[0011] Preferably, the pre-assembled factory building comprises: an above-ground part of the pre-assembled factory building and an underground part of the pre-assembled factory building;
[0012] The above-ground part of the preassembly building is arranged on the ground; the underground part of the preassembly building is arranged underground and is connected with the above-ground part of the preassembly building; the assembly area of the in-core component module is distributed at the bottom of the underground part of the preassembly building and extends upward into the above-ground part of the preassembly building; the roof is distributed at the top of the above-ground part of the preassembly building; the first crane is arranged in the above-ground part of the preassembly building and spans above the underground part of the preassembly building.
[0013] Preferably, an openable and closable factory door is provided on the side of the above-ground part of the preassembly factory building.
[0014] Preferably, a parts storage and large parts cleaning area is provided in the above-ground part of the pre-assembly plant, and is located between the plant gate and the reactor internal component module assembly area.
[0015] Preferably, the above-ground part of the pre-assembly plant is provided with a small parts degreasing area, an air compressor room, a power distribution room, a tool room, a personnel preparation area and / or an office area, and is located on one side of the reactor internals module assembly area.
[0016] A method for modularizing and installing internal components of a high-temperature gas-cooled reactor nuclear power plant is provided, wherein the method employs the modularizing and installing system for internal components of a high-temperature gas-cooled reactor nuclear power plant as described above for construction and installation, and comprises the following steps:
[0017] S1. Use a transfer vehicle to move multiple cylinders and multiple module components into the pre-assembly workshop;
[0018] S2. Using a first crane, first hoist multiple cylinders into the in-core component module assembly area in sequence to assemble into an in-core component cylinder, and then hoist multiple module components into the in-core component cylinder in sequence to assemble into an in-core component module;
[0019] S3. Use a second crane to lift the reactor internals module out of the pre-assembly building and install it into the reactor pressure vessel cylinder of the reactor compartment installed in the nuclear island building.
[0020] Preferably, in step S2, sequentially hoisting multiple modular components into the in-core component cylinder to assemble into an in-core component module comprises:
[0021] Then, the module bottom component, module middle component and module top component are sequentially hoisted into the in-core component cylinder to be assembled into the in-core component module.
[0022] It can be seen from the above technical solutions that the modular construction and installation system for the internal components of a high-temperature gas-cooled reactor nuclear power plant provided by the present invention can, while the civil construction of the reactor compartment and the installation of the reactor pressure vessel cylinder are being carried out, first assemble the internal components into an internal component module by a first crane in a pre-assembly building outside the nuclear island building. Then, after the installation of the reactor pressure vessel cylinder is completed, the internal component module is lifted out of the pre-assembly building by a second crane and lifted into and installed in the reactor pressure vessel cylinder, thereby effectively shortening the main construction period of the high-temperature gas-cooled reactor, helping to save 5 months of the main construction period of the high-temperature gas-cooled reactor, and also helping to improve the economy of the high-temperature gas-cooled reactor.
[0023] The present invention also provides a modular construction and installation method for the internal components of a high-temperature gas-cooled reactor nuclear power plant. Since the above-mentioned modular construction and installation system for the internal components of a high-temperature gas-cooled reactor nuclear power plant is used for construction and installation, it also has corresponding beneficial effects. For details, please refer to the previous description and will not be repeated here. BRIEF DESCRIPTION OF THE DRAWINGS
[0024] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the following briefly introduces the drawings required for use in the embodiments or the description of the prior art. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying any creative work.
[0025] Figure 1 A schematic diagram of the pre-assembled plant structure provided by an embodiment of the present invention;
[0026] Figure 2 A plan layout of a pre-assembled plant provided in an embodiment of the present invention;
[0027] Figure 3 A elevation layout drawing of a pre-assembled factory building provided in an embodiment of the present invention;
[0028] Figure 4 A schematic diagram of the assembly of a cylinder of a reactor internals module according to an embodiment of the present invention;
[0029] Figure 5 A schematic diagram of the assembly of a reactor internal component module according to an embodiment of the present invention;
[0030] Figure 6 A schematic diagram of a pre-assembly plant for hoisting out the reactor internals modules according to an embodiment of the present invention;
[0031] Figure 7 A schematic diagram of a reactor internals module provided by an embodiment of the present invention being hoisted into a reactor pressure vessel cylinder;
[0032] Figure 8This is a diagram of the final placement of the in-pile component modules provided in an embodiment of the present invention.
[0033] Among them, 01 is the parts storage and large-part cleaning area, 02 is the in-core component module assembly area, 03 is the circular corridor, 04 is the small-part oil removal area, 05 is the air compressor room, 06 is the power distribution room, 07 is the tool room, 08 is the personnel preparation area, 09 is the office area, 10 is the first crane, 11 is the in-core component module assembly cleaning area, 12 is the assembly platform, 13 is the first cylinder, 14 is the second cylinder, 15 is the third cylinder, 16 is the fourth cylinder, 17 is the module bottom component, 18 is the module middle component, 19 is the module top component, 20 is the assembly pit, 100 is the underground part of the pre-assembly plant, 200 is the above-ground part of the pre-assembly plant, 300 is the roof, 400 is the in-core component module, 500 is the reactor pressure vessel cylinder, 600 is the second crane, and 700 is the reactor compartment. DETAILED DESCRIPTION
[0034] The following will clearly and completely describe the technical solutions in the embodiments of the present invention in conjunction with the accompanying drawings. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without making creative efforts are within the scope of protection of the present invention.
[0035] The embodiment of the present invention provides a modular construction and installation system for the internal components of a high-temperature gas-cooled reactor nuclear power plant, such as Figure 1 、 Figure 3 and Figure 6 As shown, it includes: a pre-assembly plant, a first crane 10 and a second crane 600;
[0036] The pre-assembled plant is used to be arranged outside the nuclear island plant, and a retractable roof 300 is provided on the top of the plant. Figure 2 As shown, the pre-assembly workshop is provided with an internal component module assembly area 02, which is aligned with the roof 300 in the vertical direction;
[0037] The first crane 10 is set in the pre-assembly workshop and can sequentially lift the multiple cylinders moved into the pre-assembly workshop into the internal component module assembly area 02 to assemble into the internal component cylinders (such as Figure 4 As shown), and multiple modular components moved into the pre-assembly workshop can be sequentially hoisted into the internal component cylinder to assemble into the internal component module 400 (as shown Figure 5 shown);
[0038] The second crane 600 is arranged outside the pre-assembly building and is used to lift the reactor internals module 400 out of the pre-assembly building and lift it into the reactor pressure vessel cylinder 500 installed in the reactor compartment 700 of the nuclear island building for installation (e.g. Figure 6 、 Figure 7 and Figure 8 shown).
[0039] It should be noted that if Figure 1 As shown, when the preassembled in-core component module 400 is ready to be lifted out of the preassembly plant, the roof 300 is in an open state, so as to serve as a passage for lifting the in-core component module 400 out of the preassembly plant. Of course, the roof 300 is in a closed state under normal circumstances to keep the preassembly plant closed. In addition, the in-core component module 400 is the core support structure, and the in-core component cylinder is the core shell cylinder. In addition, the first crane 10 is a small crane (80t crane) set in the preassembly plant, and is used to lift the cylinder and module components to assemble the in-core component module 400; the second crane 600 is a large crane set outside the preassembly plant, as shown in FIG. Figure 6 As shown, the large crane may be a large crawler crane, and is used to lift the reactor internals module 400 from the pre-assembly building and lift it into the installed reactor pressure vessel cylinder 500 for installation.
[0040] That is to say, in this solution, while the civil construction of the reactor compartment 700 is being carried out and the reactor pressure vessel cylinder 500 is being installed, the in-core components can be assembled into an in-core component module 400 by a first crane 10 in a pre-assembly building outside the nuclear island building. Then, after the installation of the reactor pressure vessel cylinder 500 is completed, the in-core component module 400 can be lifted out of the pre-assembly building by a second crane 600 and lifted into and installed in the reactor pressure vessel cylinder 500, thereby effectively shortening the main construction period of the high-temperature gas-cooled reactor, helping to save 5 months of the main construction period of the high-temperature gas-cooled reactor, and also helping to improve the economy of the high-temperature gas-cooled reactor.
[0041] In this solution, in order to better assemble the in-core component module in the in-core component module assembly area 02, as shown in FIG. Figure 2 and Figure 3 As shown, the internal component module assembly area 02 is provided with a plurality of assembly pits 20 and a plurality of assembly platforms 12;
[0042] A plurality of assembly platforms 12 are arranged in a one-to-one correspondence around a plurality of assembly pits 20. That is, the first crane 10 is used to first hoist the plurality of cylinders moved into the pre-assembly workshop into one assembly pit 20 in sequence to assemble into an internal component cylinder, and then hoist the plurality of module components moved into the pre-assembly workshop into the internal component cylinder in sequence to assemble into an internal component module 400; and in the internal component module assembly area 02, each assembly pit 20 is equipped with an assembly platform 12, such as Figure 3 As shown, the assembly platform 12 is a multi-layer structure from bottom to top, so as to facilitate the sequential assembly of multiple cylinders from bottom to top.
[0043] Furthermore, if Figure 2 As shown, multiple assembly pits 20 are arranged in two rows, with each row containing multiple, aligned pits 20. This design increases the assembly capacity of reactor internals modules, thereby further shortening the main construction period of the high-temperature gas-cooled reactor.
[0044] Specifically, if Figure 1 As shown, the pre-assembled factory building includes: a pre-assembled factory building above-ground part 200 and a pre-assembled factory building underground part 100;
[0045] The above-ground part 200 of the pre-assembly plant is arranged on the ground; the underground part 100 of the pre-assembly plant is arranged underground and is connected with the above-ground part 200 of the pre-assembly plant. Figure 3 As shown, the internal component module assembly area 02 is distributed at the bottom of the underground part 100 of the pre-assembly plant and extends upward to the above-ground part 200 of the pre-assembly plant; the roof 300 is distributed on the top of the above-ground part 200 of the pre-assembly plant; Figure 4 As shown, the first crane 10 is installed within the above-ground portion 200 of the preassembly plant and spans above the underground portion 100. In other words, this solution places the reactor internals module assembly area 02 underground, thereby lowering the assembly height of the preassembly plant and minimizing interference with the assembly of the reactor internals modules.
[0046] In this solution, a closable factory door is provided on the side of the above-ground part 200 of the preassembly plant, so that when the factory door is opened, a transfer vehicle can easily transfer multiple cylinders or multiple modular components to the preassembly plant.
[0047] Furthermore, in order to facilitate the arrangement of other functional areas or other supporting areas in the above-ground part 200 of the pre-assembly plant, such as Figure 1 As shown, the floor area of the above-ground part 200 of the pre-assembly factory building is larger than the floor area of the underground part 100 of the pre-assembly factory building.
[0048] Furthermore, if Figure 2 As shown, the above-ground portion 200 of the pre-assembly plant houses a parts storage and large component cleaning area 01, located between the plant entrance and the internal component module assembly area 02. This design facilitates the storage and cleaning of large components, such as multiple cylinders or modular components, after they are moved into the pre-assembly plant.
[0049] In order to further optimize the above technical solutions and enrich the supporting measures of pre-assembled workshops, such as Figure 2 As shown, the above-ground part 200 of the pre-assembly plant is provided with a small parts degreasing area 04, an air compressor room 05, a power distribution room 06, a tool room 07, a personnel preparation area 08 and / or an office area 09, and is located on one side of the reactor internal component module assembly area 02.
[0050] An embodiment of the present invention further provides a method for modularizing the construction and installation of internal components of a high-temperature gas-cooled reactor nuclear power plant, which uses the modularized construction and installation system for internal components of a high-temperature gas-cooled reactor nuclear power plant as described above for construction and installation, and includes the following steps:
[0051] S1. Use a transfer vehicle to move multiple cylinders and multiple modular components into the pre-assembly workshop; wherein, the transfer vehicle is used to move multiple cylinders and multiple modular components into the parts storage and large component cleaning area 01 for storage or cleaning; in addition, the first crane 10 is a beam crane and spans the parts storage and large component cleaning area 01 and the in-core component module assembly area 02;
[0052] S2, using the first crane 10 to first hoist multiple cylinders into the internal component module assembly area 02 in sequence and assemble them into the internal component cylinders (such as Figure 4 Then, multiple modular components are sequentially hoisted into the in-core component cylinder to assemble into an in-core component module 400 (as shown in FIG. Figure 5 shown);
[0053] S3, using the second crane 600 to lift the reactor internals module 400 out of the pre-assembly building and to lift it into the reactor pressure vessel cylinder 500 installed in the reactor compartment 700 of the nuclear island building for installation (e.g. Figure 6 and Figure 7 shown).
[0054] It should be noted that this solution uses a transfer vehicle to move multiple cylinders and multiple module components into the parts storage and large parts cleaning area 01 for storage or cleaning; in addition, if Figure 4 As shown, the first crane 10 is a beam crane, and spans the parts storage and large parts cleaning area 01 and the in-core component module assembly area 02, so that the first crane 10 can lift the cylinder or module component from the parts storage and large parts cleaning area 01 into the in-core component module assembly area 02 to assemble it into an in-core component module; Figure 4 As shown, in step S2, the four cylinders (fourth cylinder 16, third cylinder 15, second cylinder 14, and first cylinder 13) are sequentially hoisted into the internals module assembly area 02 using a first crane 10 for assembly into the internals cylinder. Of course, since this solution utilizes the aforementioned modular construction and installation system for high-temperature gas-cooled reactor nuclear power plants for construction and installation, it also has corresponding beneficial effects. For details, please refer to the previous description and will not be repeated here.
[0055] In this program, if Figure 5 As shown, in step S2, the plurality of modular components are sequentially hoisted into the internal component cylinder to be assembled into the internal component module 400, which includes:
[0056] Then, the module bottom component 17 , the module middle component 18 and the module top component 19 are sequentially hoisted into the in-core component cylinder to be assembled into the in-core component module 400 .
[0057] The present invention will be further described below with reference to specific embodiments:
[0058] The modular construction and installation method for in-core components adopted by the present invention is as follows: while the civil construction of the reactor compartment and the installation of the reactor pressure vessel cylinder are underway, the in-core components are assembled into a module in a pre-assembly building outside the nuclear island plant. After the installation of the reactor pressure vessel cylinder is completed, the in-core component module is hoisted into and installed within the reactor pressure vessel cylinder. At the same time, the present invention proposes a one-time installation method for the installation and adjustment of the in-core component module. The method mainly calculates the processing volume of the height adjustment pad through three-dimensional measurement means, completes the adjustment pad processing in advance, and while the in-core component module is in place, a self-designed guide device is installed to ensure that the in-core component module is precisely positioned at the installation position, thereby reducing its safety and quality risks during installation. The modular construction method for in-core components can save a total of 5 months of the main construction period of the high-temperature gas-cooled reactor.
[0059] The modular construction and installation method of the internal components of a high-temperature gas-cooled reactor nuclear power plant provided by the present invention comprises three parts: an internal component module assembly method, an internal component module hoisting method, and an internal component module installation method.
[0060] 1. A method for assembling a reactor internal component module includes the following steps:
[0061] (1) Constructing pre-assembled workshops;
[0062] (2) Environmental control in the assembly area: This is achieved by placing dehumidifiers, heaters, air conditioners, and continuously supplying clean, dry compressed air in the assembly area to control the temperature and humidity of the plant.
[0063] (3) Foundation preparation before module assembly: mainly by measuring the height difference of 15 sets of support platforms, installing adjustment pads of corresponding thickness on the support platforms to provide a good foundation for the placement of the cylinder of the internal components; among them, Figure 5 As shown, the support platform is distributed at the bottom of the assembly pit;
[0064] (4) First complete the core shell assembly cylinder assembly in the assembly area;
[0065] (5) Complete the assembly of the module bottom components in the assembly area;
[0066] (6) Complete the assembly of the module middle components in the assembly area;
[0067] (7) Assemble the module top components in the assembly area.
[0068] 2. A method for hoisting a reactor internals module includes the following steps:
[0069] (1) Preparation before connecting the sling;
[0070] (2) The connection between the large crane (i.e., the second crane) and the internal component module;
[0071] (3) Leveling and trial lifting;
[0072] (4) Use a large crane to lift the module into the reactor pressure vessel.
[0073] 3. The method for installing the in-pile component module includes the following steps:
[0074] (1) Installation of the guide device and intelligent adjustment device before module lifting;
[0075] (2) Adjust the module position using an intelligent adjustment device;
[0076] (3) Review of module installation parameters;
[0077] (4) Using the intelligent adjustment device to position the module on the adjustment pad;
[0078] (5) Final limit installation after the module is in place.
[0079] The various embodiments in this specification are described in a progressive manner, and each embodiment focuses on the differences from other embodiments. The same or similar parts between the various embodiments can be referenced to each other.
[0080] The above description of the disclosed embodiments is intended to enable one skilled in the art to implement or use the present invention. Various modifications to these embodiments will be readily apparent to one skilled in the art, and the general principles defined herein may be implemented in other embodiments without departing from the spirit or scope of the present invention. Therefore, the present invention is not limited to the embodiments shown herein but is intended to conform to the widest scope consistent with the principles and novel features disclosed herein.
Claims
1. A modular construction and installation system for internal components of a high-temperature gas-cooled reactor nuclear power plant, characterized in that: include: A pre-assembly plant, a first crane (10) and a second crane (600); The pre-assembly plant is arranged outside the nuclear island plant, and a closable roof (300) is provided on the top of the plant. An internal component module assembly area (02) is provided in the pre-assembly plant, and is aligned with the roof (300) in the upper and lower directions. The first crane (10) is arranged in the preassembly plant and is capable of sequentially hoisting a plurality of cylinders moved into the preassembly plant into the in-core component module assembly area (02) to assemble into in-core component cylinders, and is capable of sequentially hoisting a plurality of module components moved into the preassembly plant into the in-core component cylinders to assemble into in-core component modules (400); The second crane (600) is arranged outside the preassembly building and is used to lift the reactor internals module (400) out of the preassembly building and into the reactor pressure vessel cylinder (500) installed in the reactor compartment (700) of the nuclear island building for installation; The in-pile component module assembly area (02) is provided with a plurality of assembly pits (20) and a plurality of assembly platforms (12); A plurality of the assembly platforms (12) are arranged one by one around a plurality of the assembly pits (20); the assembly platforms (12) are multi-layer structures from bottom to top; The plurality of assembly pits (20) are divided into two rows, and the number of the assembly pits (20) in each row is multiple and distributed one by one; The pre-assembled factory building comprises: an above-ground pre-assembled factory building part (200) and an underground pre-assembled factory building part (100); The above-ground part (200) of the preassembly plant is arranged on the ground; the underground part (100) of the preassembly plant is arranged underground and is connected to the above-ground part (200) of the preassembly plant; the internal component module assembly area (02) is distributed at the bottom of the underground part (100) of the preassembly plant and extends upward into the above-ground part (200) of the preassembly plant; the roof (300) is distributed at the top of the above-ground part (200) of the preassembly plant; the first crane (10) is arranged in the above-ground part (200) of the preassembly plant and is distributed across the top of the underground part (100) of the preassembly plant.
2. The modular construction and installation system for internal components of a high-temperature gas-cooled reactor nuclear power plant according to claim 1 is characterized in that: The side of the above-ground part (200) of the pre-assembly plant is provided with an openable and closable plant door.
3. The modular construction and installation system for internal components of a high-temperature gas-cooled reactor nuclear power plant according to claim 2, characterized in that: A parts storage and large parts cleaning area (01) is provided in the above-ground part (200) of the pre-assembly plant, and is located between the plant gate and the in-core component module assembly area (02).
4. The modular construction and installation system for internal components of a high-temperature gas-cooled reactor nuclear power plant according to claim 1 is characterized in that: The above-ground portion (200) of the pre-assembly plant is provided with a small parts degreasing area (04), an air compressor room (05), a power distribution room (06), a tool room (07), a personnel preparation area (08) and / or an office area (09), and is located on one side of the reactor internal component module assembly area (02).
5. A modular construction and installation method for internal components of a high-temperature gas-cooled reactor nuclear power plant, characterized in that: The modular construction and installation system for the internal components of a high-temperature gas-cooled reactor nuclear power plant according to any one of claims 1 to 4 is used for construction and installation, and includes the following steps: S1. Use a transfer vehicle to move multiple cylinders and multiple module components into the pre-assembly workshop; S2, using a first crane (10) to sequentially hoist a plurality of cylinders into the in-core component module assembly area (02) to assemble into an in-core component cylinder, and then sequentially hoist a plurality of module components into the in-core component cylinder to assemble into an in-core component module (400); S3. Using a second crane (600), the reactor internals module (400) is lifted out of the pre-assembly building and lifted into the reactor pressure vessel cylinder (500) already installed in the reactor compartment (700) of the nuclear island building for installation.
6. The modular construction and installation method for internal components of a high-temperature gas-cooled reactor nuclear power plant according to claim 5, characterized in that: In the step S2, the plurality of module components are sequentially hoisted into the in-core component cylinder to be assembled into an in-core component module (400), which includes: Then, the module bottom component (17), the module middle component (18), and the module top component (19) are sequentially hoisted into the in-pile component cylinder to assemble into an in-pile component module (400).
Citation Information
Patent Citations
Modularization construction method for nuclear power station nuclear island
CN101748915A