High-rise building demolition equipment and high-rise building demolition method

By using high-rise building demolition equipment and enclosed operation methods, the problems of low construction efficiency and high noise pollution in high-rise building demolition have been solved, achieving a safe and efficient demolition process, which is suitable for the overall demolition of high-rise buildings.

CN115807562BActive Publication Date: 2025-12-05CHINA CONSTR THIRD ENG BUREAU GRP CO LTD
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
CN202211426818.0
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-11-15
Publication Date
2025-12-05
Estimated Expiration
2042-11-15

AI Technical Summary

Technical Problem

Existing methods for demolishing high-rise buildings suffer from low construction efficiency, significant noise pollution, and numerous safety hazards. In particular, blasting demolition requires strict spatial constraints, while mechanical demolition has a long construction period and causes continuous disturbance to residents.

Method used

High-rise building demolition equipment, including support mechanisms, hoisting mechanisms, transportation mechanisms, frame platforms, and soundproof enclosures, is used to achieve the overall demolition of high-rise buildings through liftable support columns and hoisting systems. Combined with a closed working environment and multi-layer construction lines, the structure, electromechanical equipment, and decoration materials are demolished layer by layer.

Benefits of technology

It achieved efficient and safe demolition of high-rise buildings, reduced noise pollution, improved construction efficiency and working environment quality, avoided the impact of external weather, and ensured construction safety and environmental protection.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN115807562B_ABST
    Figure CN115807562B_ABST
Patent Text Reader

Abstract

The application provides a high-rise building demolition equipment and a high-rise building demolition method, which comprises at least two groups of supporting mechanisms, at least one hoisting mechanism, a transportation mechanism, a frame platform, four groups of operation hangers and a soundproof cover; the two groups of supporting mechanisms are respectively installed in opposite sides of a building structure to be demolished in a liftable manner, are used for lifting the high-rise building demolition equipment, and make the high-rise building demolition equipment demolish building structures at different heights; the hoisting mechanism is transversely movably installed between the two groups of supporting mechanisms, and is used for demolishing building structures at different positions; the four groups of operation hangers are respectively detachably installed on outer walls of opposite sides of the building structure; the frame platform is installed on top of the supporting mechanisms and the operation hangers; the transportation mechanism is installed on the building structure; and the soundproof cover is arranged on the outside of the operation hangers and the top of the frame platform. The device and the method can improve the construction efficiency of building demolition, guarantee construction safety, and avoid dust and noise during construction.
Need to check novelty before this filing date? Find Prior Art

Description

TECHNICAL FIELD

[0001] The present application relates to the field of building construction, in particular to a high-rise building demolition equipment and a high-rise building demolition method. BACKGROUND

[0002] Currently, the traditional high-rise building demolition generally has two types of construction methods, namely blasting demolition and mechanical demolition. The blasting demolition has high construction efficiency, but requires sufficient space around the building to be demolished to meet the safety of the area where the debris is accumulated and scattered after blasting. In addition, the huge noise, dust and vibration impact of blasting also have a greater impact on the surrounding area, so the application scenarios of blasting demolition are limited. The mechanical demolition usually uses a large hydraulic excavator, cooperates with accessories such as hydraulic breaking head, breaking tongs, and breaking shears, reaches the top of the building, and works from top to bottom to break the reinforced concrete structure. Another way of mechanical demolition is to use a specially designed super-long arm excavator to stand on the ground and gradually break and demolish the building from the side. The mechanical demolition has certain requirements on the building height and bearing capacity, and has low efficiency, long construction period, and continuous noise, vibration, and dust during construction, which disturbs the public, causes chaos at the construction site, and frequent safety accidents. SUMMARY

[0003] One of the purposes of the present application is to provide a high-rise building demolition equipment and a high-rise building demolition method to solve the problem of time-consuming and labor-intensive demolition of existing high-rise buildings.

[0004] The technical solution of the present application is:

[0005] A high-rise building demolition equipment, comprising at least two groups of supporting mechanisms, at least one hoisting mechanism, a transportation mechanism, a frame platform, four groups of operation hangers, and at least one layer of soundproof cover; two groups of the supporting mechanisms are respectively and vertically movably installed in opposite sides of a building structure to be demolished, for driving the high-rise building demolition equipment to move up and down, so that the high-rise building demolition equipment demolishes the building structure at different heights; the hoisting mechanism is horizontally movably installed between the two groups of supporting mechanisms, for demolishing the building structure at different positions; four groups of the operation hangers are respectively and detachably installed on the outer walls of the opposite sides of the building structure; the frame platform is installed on the top of the supporting mechanisms and the operation hangers; the transportation mechanism is installed on the building structure, for transporting the demolished building structure; and the soundproof cover is arranged on the outside of the operation hangers and the top of the frame platform.

[0006] As a technical scheme of the present application, the support mechanism comprises at least one support column, a screw jack, an upper support beam, a lower support beam and an electric push cylinder; the support column is installed on the building structure in a liftable manner and can drive the lower support beam to pass through the hole on the building structure downward; the lower support beam is hingedly connected between the lower parts of the two opposite inner walls of the support column in an openable and closable manner, for fixing the support column on the building structure or passing through the hole on the building structure by the support column; the electric push cylinder is fixedly installed on the support column, for driving the lower support beam to open or close, so that the lower support beam is fixed on the building structure or passes through the hole on the building structure; the screw jack is fixedly installed on the inner walls of the support column at the top and bottom ends, for driving the upper support beam to rise and fall on the screw jack; the upper support beam is installed on the sliding block of the screw jack; when the screw jack is rotated in a normal direction, the upper support beam moves downward relative to the screw jack until the upper support beam moves to the upper layer, so that the upper support beam bears all the loads on the support mechanism; when the lower support beam is driven to turn and close by the electric push cylinder, the screw jack is reversed, and the upper support beam is fixed on the upper layer, so that the support column and the screw jack move downward and drive the closed lower support beam to pass through the hole on the middle layer and then open until the lower support beam is clamped in the hole on the lower layer, so that the lower support beam bears all the loads on the support mechanism.

[0007] As a technical scheme of the present application, the support column comprises two profiles and a plurality of connecting plates, the two profiles are arranged in parallel and spaced apart and connected by the plurality of connecting plates arranged in the height direction at intervals, and the symmetric axis between the two profiles is arranged at an angle of 45° with the column grid axis on the building structure.

[0008] As a technical scheme of the present application, the lower support beam comprises a wedge block, a first support part and a second support part; the first support part and the second support part are respectively hingedly connected to the gaps between the two profiles, and can be flipped towards the direction of mutual contraction or mutual expansion; the wedge block can move into or out of the gap between the first support part and the second support part, and is used for clamping in the gap between the first support part and the second support part to make the lower support beam clamp on the opening, or moving out of the gap between the first support part and the second support part to make the lower support beam pass through the opening; the driving end of the electric push cylinder is in transmission connection with the wedge block, and is used for driving the wedge block to lift relative to the support column, so that the wedge block moves into or out of the gap between the first support part and the second support part, and the first support part and the second support part are flipped towards the direction of mutual contraction or mutual expansion, so that the two lower support beams can pass through the opening or clamp on the opening.

[0009] As a technical scheme of the present application, the hoisting mechanism comprises a track beam, a steel rail and a trolley; the top of each set of support mechanisms is provided with a top supporting plate; the track beam is installed between two top supporting plates, and the steel rail is installed on the track beam; the trolley is transversely movably installed on the steel rail.

[0010] As a technical scheme of the present application, the transportation mechanism comprises a first construction elevator and a second construction elevator; the first construction elevator is attached to the outer wall of the building structure; the second construction elevator is vertically installed in the elevator shaft inside the building structure, and comprises a cage with an open top, a frame door which is openable and closable is arranged on one side of the cage, and a detachable tray is arranged on the inner wall of the bottom.

[0011] As a technical scheme of the present application, the frame platform is a frame structure formed by a plurality of bailey beams and a plurality of connecting nodes.

[0012] As a technical scheme of the present application, the operation hanger comprises a plurality of operation platforms connected in sequence from top to bottom, the operation platforms are arranged between the outer walls of the middle layer and the lower layer, and each operation platform is hingedly connected with a flap platform on the side close to the building structure.

[0013] As a technical scheme of the present application, the soundproof cover is openably and closably arranged on the outside of the operation hanger and the top of the frame platform.

[0014] A high-rise building demolition method, which is demolished by using the high-rise building demolition equipment described above; comprising the following steps:

[0015] Step one, installing a first construction elevator outside the building structure, transporting roofing to the top of the building by the first construction elevator for installation, and demolishing part of the structure at the top of the building;

[0016] Step two, installing the high-rise building demolition equipment on the top of the building by the roofing crane, transporting various equipment and tools required for the work to the top of the building, and then demolishing the roofing crane;

[0017] Step three, simultaneously performing structural demolition, secondary structural demolition, decoration and mechanical and electrical demolition on the three upper, middle and lower buildings on the top of the building in a parallel flow operation manner;

[0018] Performing structural demolition on the upper building on the building structure: first placing the position of the cutting joint on the upper layer, then cutting the upper layer into blocks by cutting mechanical equipment, then hoisting the cut floor slabs into the second construction elevator by the travelling crane, and then transporting the floor slabs to the ground floor by the second construction elevator and then transporting them outside, and then cutting and hoisting the beams, walls and columns in the upper building;

[0019] Performing secondary structural demolition on the middle building on the building structure: first crushing the masonry infill walls in the secondary structure by a crusher, then collecting and loading the crushed debris into a transport bucket by a forklift, then transporting the transport bucket to the first construction elevator and down to the ground;

[0020] Performing demolition of mechanical and electrical equipment and internal decoration materials on the lower building on the building structure: first removing the decoration materials on the building by an operation platform, then horizontally transporting the removed decoration materials to the second construction elevator by a forklift, and then transporting them down to the ground;

[0021] Step four, when the demolition work of the upper, middle and lower buildings on the three working layers is completed simultaneously, opening a hole in the building floor slab of the next floor; moving each working equipment on each working layer to the corresponding next working layer by the second construction elevator, folding up the flip platform on the operation hanger, and simultaneously lowering the support mechanism, so that the entire high-rise building demolition equipment is lowered to the next working layer, and the construction operation in step three is repeated to realize the demolition of mechanical and electrical equipment and internal decoration materials, the demolition of secondary structures, and the demolition of structures on the next floor.

[0022] The beneficial effects of the present application are:

[0023] The high-rise building demolition equipment and the high-rise building demolition method of the present application realize the factory-like operation of the demolition construction, improve the work efficiency, guarantee the construction safety, and reduce the noise. Moreover, the construction operation is not affected by the external weather, and the available operation time is increased. Meanwhile, the operation environment is improved, the work efficiency of the workers is improved, the dust and the noise are avoided by creating a closed environment, and the demolition noise pollution of the whole building is small, and the environmental protection is safe. BRIEF DESCRIPTION OF DRAWINGS

[0024] In order to more clearly illustrate the technical solutions of the embodiments of the present application, the drawings needed to be used in the embodiments will be briefly introduced below. It should be understood that the following drawings only show some embodiments of the present application, and therefore should not be regarded as a limitation on the scope. For those skilled in the art, other related drawings can also be obtained without creative labor on the basis of these drawings.

[0025] Figure 1 The high-rise building demolition equipment provided by the embodiments of the present application is shown in the schematic diagram.

[0026] Figure 2 The support mechanism and the hoisting mechanism provided by the embodiments of the present application are shown in the schematic diagram of the single-span arrangement in the plane.

[0027] Figure 3 The support mechanism and the hoisting mechanism provided by the embodiments of the present application are shown in the schematic diagram of the double-span arrangement in the plane.

[0028] Figure 4 The support column, the frame platform, and the track beam provided by the embodiments of the present application are shown in the connection schematic diagram.

[0029] Figure 5 The support column provided by the embodiments of the present application is shown in the schematic diagram.

[0030] Figure 6 The first angle of the support column provided by the embodiments of the present application is shown in the schematic diagram.

[0031] Figure 7 The partial structure of the support column provided by the embodiments of the present application is shown in the schematic diagram.

[0032] Figure 8 The support column provided by the embodiments of the present application is shown in the sectional view.

[0033] Figure 9 The openable lower support beam on the support column provided by the embodiments of the present application is shown in the schematic diagram of the state when passing through the hole opening.

[0034] Figure 10A schematic diagram of a support column provided in this application embodiment when the lower support beam is under stress and the upper support beam is in a suspended state;

[0035] Figure 11 A schematic diagram of a support column provided in this application embodiment when the upper support beam is in a state of descent to replace the lower support beam under stress;

[0036] Figure 12 A schematic diagram of a support column provided in this application embodiment when the upper support beam is under stress and the lower support beam is in a closed state and passes downward through the opening;

[0037] Figure 13 A schematic diagram of the support column provided in this application embodiment when the lower support beam is in the state of being opened and descended to the lower floor slab, replacing the upper support beam in bearing the force.

[0038] Figure 14 A schematic diagram illustrating the vertical and then horizontal transportation of building structure components after cutting, as provided in an embodiment of this application.

[0039] Figure 15 A schematic diagram showing the components of a building structure after being cut and transported vertically along a diagonal line inside a hoisting cage, as provided in an embodiment of this application.

[0040] Figure 16 A schematic diagram of the hoisting cage provided in an embodiment of this application;

[0041] Figure 17 This is a schematic diagram showing the horizontal dragging of a cut building structure component using a pallet inside a cage, as provided in an embodiment of this application.

[0042] Icons: 1-Supporting mechanism; 2-Lifting mechanism; 3-Transporting mechanism; 4-Frame platform; 5-Operating hanger; 6-Soundproof enclosure; 7-Building structure; 8-Supporting column; 9-Screw jack; 10-Upper support beam; 11-Lower support beam; 12-Rail wheel; 13-Electric pusher cylinder; 14-Wedge block; 15-Rail beam; 16-Rail; 17-Overhead crane; 18-First construction elevator; 19-Second construction elevator; 20-Cage; 21-Platform; 22-Upper layer; 23-Middle layer; 24-Lower layer; 25-Opening; 26-First support section; 27-Second support section. Detailed Implementation

[0043] To make the objectives, technical solutions, and advantages of the embodiments of this application clearer, the technical solutions of the embodiments of this application will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of this application, and not all embodiments. The components of the embodiments of this application described and shown in the accompanying drawings can typically be arranged and designed in various different configurations.

[0044] Therefore, the following detailed description of the embodiments of this application provided in the accompanying drawings is not intended to limit the scope of the claimed application, but merely to illustrate selected embodiments of the application. All other embodiments obtained by those skilled in the art based on the embodiments of this application without inventive effort are within the scope of protection of this application.

[0045] It should be noted that similar labels and letters in the following figures indicate similar items. Therefore, once an item is defined in one figure, it does not need to be further defined and explained in subsequent figures.

[0046] In the description of this application, it should be noted that the terms "upper" and "lower" indicate the orientation or positional relationship based on the orientation or positional relationship shown in the accompanying drawings, or the orientation or positional relationship in which the product of the invention is usually placed when in use. They are only used to facilitate the description of this application and to simplify the description, and do not indicate or imply that the device or element referred to must have a specific orientation, or be constructed and operated in a specific orientation. Therefore, they should not be construed as limitations on this application.

[0047] Furthermore, in this application, unless otherwise expressly specified and limited, "above or below" the first feature may include direct contact between the first and second features, or contact between the first and second features through another feature between them. Moreover, "above," "over," and "on" the first feature includes the first feature directly above or diagonally above the second feature, or simply indicates that the first feature is at a higher horizontal level than the second feature. "Below," "below," and "under" the first feature includes the first feature directly below or diagonally below the second feature, or simply indicates that the first feature is at a lower horizontal level than the second feature.

[0048] Furthermore, terms such as "horizontal" and "vertical" do not imply that components must be absolutely horizontal or suspended, but rather that they can be slightly tilted. For example, "horizontal" simply means that its direction is more horizontal than "vertical," and does not mean that the structure must be completely horizontal, but can be slightly tilted.

[0049] In the description of this application, it should also be noted that, unless otherwise expressly specified and limited, the terms "set up," "connected," and "linked" should be interpreted broadly. For example, they can refer to a fixed connection, a detachable connection, or an integral connection; they can refer to a mechanical connection or an electrical connection; they can refer to a direct connection or an indirect connection through an intermediate medium; and they can refer to the internal connection of two components. Those skilled in the art can understand the specific meaning of the above terms in this application based on the specific circumstances.

[0050] Example:

[0051] Please refer to Figure 1 (Refer to)Figures 2 to 17 This application provides a high-rise building demolition equipment, including at least two sets of support mechanisms 1, at least one hoisting mechanism 2, a transport mechanism 3, a frame platform 4, four sets of operating hangers 5, and at least one layer of soundproof enclosure 6; wherein, the two sets of support mechanisms 1 are respectively and vertically installed on opposite sides of the building structure 7 to be demolished, for driving the hoisting mechanism 2 to rise and fall, so that the hoisting mechanism 2 can demolish the building structure 7 at different heights; at the same time, the hoisting mechanism 2 is horizontally movable between the two sets of support mechanisms 1, for demolishing the building structure 7 at different locations; and the four sets of operating hangers 5 are respectively and detachably installed on the outer walls of opposite sides of the building structure 7; in addition, the frame platform 4 is installed on the top of the support mechanisms 1 and the operating hangers 5; the transport mechanism 3 is installed on the building structure 7 for transporting the demolished building structure 7; the soundproof enclosure 6 is openably and closably installed on the outside of the operating hangers 5 and on the top of the frame platform 4.

[0052] Furthermore, the support mechanism 1 includes at least one support column 8, a screw jack 9, an upper support beam 10, a lower support beam 11, and an electric pusher cylinder 13; wherein, the support column 8 is vertically and flexibly installed on the building structure 7, and can drive the lower support beam 11 downward through the opening 25 on the building structure 7; at the same time, the lower support beam 11 is hinged to the two opposite inner walls at the lower part of the support column 8, for fixing the support column 8 to the building structure 7 or passing through the building structure via the support column 8. The support column 7 has an opening 25; and the electric push cylinder 13 is fixedly installed on the support column 8 to drive the lower support beam 11 to open or close, so that the lower support beam 11 is fixed to the building structure 7 or passes through the opening 25 in the building structure 7; in addition, the top and bottom ends of the screw jack 9 are respectively fixedly installed on the inner wall of the support column 8 to drive the upper support beam 10 to rise and fall on the screw jack 9; the upper support beam 10 is installed on the slider of the screw jack 9, and it can move up and down relative to the support column 8. The planar arrangement of the support column 8 is determined according to the beam and column arrangement of the building structure 7 and the rigidity of the frame platform 4. The support column 8 has a lifting function, and the distance between the fulcrum of the upper support beam 10 supporting the building structure 7 and the top of the support column 8 can vary within a range exceeding one building height. Adjacent support columns 8 can be connected by pipelines. The support columns 8 can pass through openings 25 at the corners of the building floor slab. A horizontal limiting structure is installed at the openings in the building floor slab to constrain the horizontal movement of the support columns 8 during descent. Specifically, the horizontal limiting structure includes two horizontally arranged limiting plates and four track wheels 12. The two limiting plates are installed at intervals on the openings 25 near the two corners. Two vertically arranged track wheels 12 are installed at intervals on each limiting plate. The opposite sides of the support columns 8 are movably connected to the four track wheels 12, thereby achieving the effect of constraining the horizontal movement of the support columns 8 during descent.

[0053] It should be noted that, depending on the actual dimensions of the building plan, the hoisting mechanism 2 can be arranged in various ways. The arrangement mainly depends on the width of the building: if the building width is less than 24m, a single-span arrangement is preferred, that is, two rows of supporting columns 8 are set on the plane, and a track beam 15 is set on the top of the supporting columns 8 to install a single-span overhead crane 17. The number of overhead cranes 17 depends on the requirements. If the building length is greater than 40m, it is recommended to arrange 2 or more cranes. When the building width is greater than 24m, which exceeds the economic span of conventional Bailey beams and overhead cranes 17, a double-span arrangement can be considered, that is, three rows of supporting columns 8 are arranged on the plane, one track beam 15 is set on the top of the outer supporting columns 8, and two track beams 15 are set on the top of the middle row of supporting columns 8 to install two spans of overhead cranes 17. In addition, a top support plate is installed on the top of each support column 8, and the track beam 15 of the overhead crane 17 is installed on the top support plate. A short column extends out from one corner of the top support plate, and the top of the short column supports the frame platform 4.

[0054] The height of the supporting column 8 must ensure that the clear distance between the bottom of the frame platform 4 and the top floor is not less than 9m, in order to meet the operational requirements of structural demolition. The bottom end of the supporting column 8 must penetrate the lower floor by at least 1m.

[0055] It should be noted that the upper support beam 10 and the lower support beam 11 can be alternately stressed, allowing the support column 8 to drive the entire high-rise building demolition equipment to descend. The specific working principle is as follows: After the building structure 7 on the top floor slab is demolished, the upper support beam 10 is in the air. At this time, the support column 8 relies on the lower support beam 11 located on the middle layer 23 to transmit force and bear all the load. Then, the screw jack is activated, rotating clockwise, which drives the upper support beam 10 to move downwards relative to the screw jack until it contacts the upper layer 22, allowing the upper support beam 10 to bear all the load on the support mechanism 1. This allows the upper support beam 10 to replace the lower support beam 11 and become the new path for load transfer to the building structure 7. Then… Start the electric push cylinder 13, which drives the lower support beam 11 to flip and close, shortening its projected length to be able to pass through the opening 25 on the middle layer 23. Start the screw jack and reverse it. At this time, fix the upper support beam 10 on the upper layer 22 and keep it stationary, so that the support column 8, the screw jack, and the upper structure connected to the support column 8 (frame platform 4, operating bracket 5, and soundproof cover 6, etc.) move downward together, and drive the closed lower support beam 11 to open after passing through the opening 25 on the middle layer 23, until the lower support beam 11 is engaged in the opening 25 on the lower layer 24, so that the lower support beam 11 bears all the load on the support mechanism 1, thereby replacing the upper support beam 10 to transfer the load.

[0056] Therefore, the device, through the synchronously lifting support mechanism 1, allows the entire high-rise building demolition equipment to be conveniently lowered as a whole. After being lowered into place, no much adjustment or preparation work is required before proceeding with the demolition work on the next floor. Furthermore, the support mechanism 1 only requires opening holes in the building floor slab so that the support columns 8 can pass through smoothly. It is supported by the lower support beam at the corner where the longitudinal and transverse beams intersect at the beam-column node. The main support point is located on the middle floor 23, which will not affect the demolition work of the structure above the upper floor 22. The operation of the entire support mechanism 1 is relatively simple.

[0057] Specifically, the supporting column 8 includes two profiles and multiple connecting plates. The two profiles are arranged in parallel and spaced apart, and connected by multiple connecting plates spaced apart along the height direction. The axis of symmetry between the two profiles is set at a 45° angle to the column grid axis on the building structure 7, so that the supporting beam 11 below can be supported on the longitudinal and transverse beams at the corner. In this embodiment, the profiles can be I-beams, channel steel, and H-beams, etc.

[0058] Furthermore, the lower support beam 11 includes a wedge block 14, a first support portion 26, and a second support portion 27; the first support portion 26 and the second support portion 27 are respectively hinged at intervals between the gaps of the two profiles, and can be rotated in the direction of mutual contraction and closing or mutual extension and opening; the wedge block 14 can move into or out of the gap between the first support portion 26 and the second support portion 27, and is used to engage with the gap between the first support portion 26 and the second support portion 27 so that the lower support beam 11 is engaged with the opening 25 or moved out of the first support portion 26. The lower support beam 11 passes through the opening 25 between the first support part 26 and the second support part 27; the drive end of the electric push cylinder 13 is connected to the wedge block 14 for driving the wedge block 14 to rise and fall relative to the support column 8, so that the wedge block 14 moves into or out of the gap between the first support part 26 and the second support part 27, and causes the first support part 26 and the second support part 27 to flip in the direction of mutual contraction and closing or mutual extension and opening, so that the two lower support beams 11 can pass through the opening 25 or be engaged with the opening 25.

[0059] When the electric actuator 13 pulls the wedge block 14 to a height range away from the lower support beam 11, the first support portion 26 and the second support portion 27 of the lower support beam 11 can freely flip upwards. When the support column 8 moves downwards, the first support portion 26 and the second support portion 27 of the lower support beam 11 are pushed upwards by the opening 25 and automatically flip upwards after passing through the opening 25. Under their own weight, the first support portion 26 and the second support portion 27 of the lower support beam 11 automatically flip to a horizontal state. When the electric actuator 13 pushes the wedge block 14 to its uppermost position, the wedge block 14 constrains the first support portion 26 and the second support portion 27 of the lower support beam 11 to flip upwards, thereby enabling the lower support beam 11 to support the building floor slab and bear the load.

[0060] In addition, the hoisting mechanism 2 includes a track beam 15, steel rails 16, and a gantry crane 17. Each set of support mechanisms 1 has a top support plate on its top. The track beam 15 is installed between two top support plates, and the steel rails 16 are installed on the track beam 15. The gantry crane 17 is laterally movable and installed on the steel rails 16. The gantry crane 17 can move along the steel rails 16, essentially covering the entire building plan. Blind spots at both ends and sides that are difficult for the gantry crane 17 to cover can be avoided by adjusting the floor slab segmentation scheme.

[0061] Furthermore, the transportation mechanism 3 includes a first construction elevator 18 and a second construction elevator 19. The first construction elevator 18 is attached to the lower part of the outer wall of the building structure 7. The second construction elevator 19 is vertically installed in the elevator shaft inside the building structure 7. The second construction elevator 19 includes a cage 20 with an open top. One side of the cage 20 is equipped with an openable frame door, and the bottom inner wall is equipped with a detachable tray 21. The second construction elevator 19 adopts a cage 20 design with an open top. The object to be hoisted can be directly hoisted into the cage 20 after being moved horizontally by the overhead crane 17, and then transported downwards to the ground. The second construction elevator 19 adopts a beamless design. Its hanging steel wire ropes are wrapped around both sides of the cage 20 from below. One end is anchored to the side wall of the shaft, and the other end turns downwards after turning at the top of the side wall on the other side of the shaft and enters its drive structure. In addition, the second construction elevator 19 can also use electromagnetic resistance to control the descent speed of the cage 20, converting the gravitational potential energy of the building components during the descent into electrical energy.

[0062] After being cut, the building components are first transported horizontally by the overhead crane 17. Horizontal components such as walls and columns can be directly hoisted into the hoisting cage 20. Horizontal components such as floor slabs and beams are turned over before being hoisted into the hoisting cage 20 of the second construction elevator 19. The components are placed diagonally inside the hoisting cage 20 to make full use of its size. After the components are placed into the hoisting cage 20, they are temporarily reinforced with diagonal braces at the bottom of the cage 20. After the components are transported to the ground using the second construction elevator 19, they can be dragged out of the building by horizontal towing and then loaded onto trucks for transport.

[0063] Therefore, this device integrates a horizontal transport system (gantry crane 17), a vertical transport system (second construction elevator 19), and an external first construction elevator 18, eliminating the need for external tower cranes and enabling 24 / 7 operation, thus avoiding the limitations of tower crane hoisting. Separating horizontal and vertical transport avoids prolonged equipment occupation and time consumption, improving overall construction efficiency. The second construction elevator 19 features a top-opening design, facilitating the direct hoisting of components into its cage 20 by the gantry crane 17. Using the second construction elevator 19 also significantly increases vertical transport speed, thereby improving overall transport efficiency.

[0064] It should be noted that the frame platform 4 is a frame structure composed of multiple longitudinally and transversely arranged 321 Bailey beams connected by multiple connecting nodes. The lower part of the connecting nodes is connected to the top of the supporting column 8; the bottom of the outer Bailey beams is connected to the longitudinally and transverse steel sections through the first connecting seat, and the longitudinally and transverse steel sections are connected to the top of the suspension rod of the operating bracket 5 through the second connecting seat. The frame platform 4 is composed of 321 Bailey beams and connecting nodes, which improves the adaptability of the frame platform 4, reduces the manufacturing cost of the platform, and provides sufficient rigidity and strength to provide enough hanging points, facilitating equipment integration and construction auxiliary hanging. At the same time, the operating bracket 5 includes multiple operating platforms connected sequentially from bottom to top. The operating platforms are arranged within the range between the outer walls of the middle layer 23 and the lower layer 24, and each operating platform has a hinged flip platform on the side closest to the building structure 7. The width of the flip platform is slightly larger than the gap between the building structure 7 and the operating bracket 5. Furthermore, the soundproof enclosure 6 can be made of multi-layer sound insulation and sound absorption materials. Furthermore, various integrated devices are attached to the frame platform 4 or the supporting columns 8. These can include existing technologies such as dust suppression spraying equipment, laser projection layout equipment, and retractable roofs. The specific arrangement is the same as in existing structures and will not be elaborated here. A dust suppression spraying system is integrated under the frame platform 4, improving the internal working environment. In addition, the device also integrates laser projection layout equipment, simplifying the layout work of cutting seams and improving efficiency. Moreover, the cutting of the building structure 7 can be achieved using wire saw cutting machines, coil saw cutting machines, etc. There is no need to erect scaffolds below before cutting horizontal components such as floor slabs and beams. For floor slabs, steel spreader beams can be used for temporary support. For beams, oblique cuts can be made on both sides to ensure that the final beam side elevation is an inverted trapezoidal shape that is wider at the top and narrower at the bottom, thereby ensuring that the beam will not fall.

[0065] Specifically, the soundproof enclosure 6 covers the three working floors at the top in terms of height, and it covers the perimeter of the operating rack 5 and the frame platform 4, providing safety conditions for external operations.

[0066] Furthermore, this embodiment also provides a method for demolishing high-rise buildings, which mainly uses the above-mentioned high-rise building demolition equipment for demolition; the method includes the following steps:

[0067] Step 1: Install the first construction elevator 18 on the outside of the building structure 7. Use the first construction elevator 18 to transport the small roof hoist to the roof of the building for installation. At the same time, dismantle part of the structure on the top of the building to create conditions for the installation of the high-rise building demolition equipment.

[0068] Step 2: Use the roof crane to install high-rise building demolition equipment on the top of the building, and transport all kinds of equipment and tools required for the operation to the top of the building, and then dismantle the roof crane;

[0069] Step 3: Simultaneously carry out structural demolition, secondary structure demolition, decoration and mechanical / electrical system demolition on the three interconnected upper, middle and lower floors at the top of the building using a parallel, sequential operation method.

[0070] The superstructure on building structure 7 is demolished as follows: First, the cutting seam is marked on the upper floor 22 using laser projection equipment. Then, the upper floor 22 is cut into sections using cutting machinery. During this process, the upper floor 22 is supported and suspended. The cut floor slabs are then hoisted to the second construction elevator 19 using a crane 17 and transported to the ground floor using the second construction elevator 19. After that, they are horizontally moved outside the building and transported away. After the floor slabs are cut and demolished, the beams, walls, and columns are cut and hoisted.

[0071] Secondary structure demolition of the mid-rise building on building structure 7: First, use a crusher to break the secondary structure, namely the masonry infill wall, then use a loader to collect the debris and load it into a transport truck, and then use the transport truck to transport it to the construction elevator and down to the ground.

[0072] The mechanical and electrical equipment and interior decoration materials of the lower building on the building structure 7 are removed: First, the exterior decoration materials such as windows and curtain walls are removed using the operating platform. Inside the building, the decoration materials are removed manually. Then, the removed decoration materials are transported horizontally to the second construction elevator 19 using a forklift and transported downwards to the ground.

[0073] Step four: After the demolition work on the upper, middle and lower floors is completed simultaneously, an opening 25 is made in the floor slab of the next floor, and a horizontal limiting structure is installed around the opening 25 to create conditions for the downward movement of the supporting column 8. The second construction elevator 19 is used to move the various working equipment on each working floor to the corresponding next working floor in sequence, and the flip platform on the operating bracket 5 is retracted. The supporting mechanism 1 is lowered synchronously so that the entire high-rise building demolition equipment is lowered one floor to the next working floor. The construction operation in step three is repeated to achieve the demolition of the structure, secondary mechanism, electromechanical equipment and interior decoration materials of the next floor.

[0074] Step 5: When the building structure 7 is demolished down to the remaining four floors, the entire high-rise building demolition equipment is dismantled using a truck crane, and the remaining part of the building is demolished using conventional demolition methods.

[0075] In summary, the high-rise building demolition equipment and method described in this application achieve factory-like demolition operations, improving efficiency, ensuring construction safety, and reducing noise. Furthermore, the operation is unaffected by external weather, increasing available working time. Simultaneously, it improves the working environment, increases worker efficiency, and avoids dust and noise pollution by creating a closed environment. Moreover, throughout the entire demolition process, only a soundproof enclosure 6 covers the top of the building, with no construction machinery such as tower cranes exposed, resulting in minimal noise pollution and environmental safety during the demolition process.

[0076] The above description is merely a preferred embodiment of this application and is not intended to limit this application. Various modifications and variations can be made to this application by those skilled in the art. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of this application should be included within the protection scope of this application.

Claims

1. A high-rise building demolition apparatus, characterized by, It includes at least two sets of supporting mechanism, at least one hoisting mechanism, a transport mechanism, a frame platform, four sets of operating hangers and at least one layer of soundproof cover; two sets of the supporting mechanism are respectively installed in opposite sides of the building structure to be demolished, for driving the high-rise building demolition equipment to lift, so that the high-rise building demolition equipment demolishes the building structure at different heights; the hoisting mechanism is transversely movably installed between the two sets of supporting mechanism, for demolishing the building structure at different positions; four sets of the operating hangers are respectively spaced and detachably installed on the outer walls of the opposite sides of the building structure; the frame platform is installed on the top of the supporting mechanism and the operating hanger; the transport mechanism is installed on the building structure, for transporting the demolished building structure. The soundproof cover is arranged on the outside of the operating hanger and the top of the frame platform; the support mechanism comprises at least one support column, a screw jack, an upper support beam, a lower support beam and an electric push cylinder; the support column is installed on the building structure in a lifting manner and can drive the lower support beam to pass through the hole on the building structure downward; the lower support beam is hingedly connected between the lower parts of the two opposite inner walls of the support column in an openable and closable manner, for fixing the support column on the building structure or passing through the hole on the building structure by the support column; the electric push cylinder is fixedly installed on the support column and is used to drive the lower support beam to open or close, so that the lower support beam is fixed on the building structure or passes through the hole on the building structure; the screw jack is fixedly installed on the inner walls of the support column at the top and bottom ends, and is used to drive the upper support beam to rise and fall on the screw jack; the upper support beam is installed on the sliding block of the screw jack; when the screw jack is rotated in a normal direction, the upper support beam moves downward relative to the screw jack until the upper support beam moves to the upper layer, so that the upper support beam bears all the loads on the support mechanism; when the lower support beam is driven to turn and close by the electric push cylinder, the screw jack is reversed, and the upper support beam is fixed on the upper layer, so that the support column and the screw jack move downward and drive the closed lower support beam to pass through the hole on the middle layer and then open until the lower support beam is clamped in the hole on the lower layer, so that the lower support beam bears all the loads on the support mechanism; the support column comprises two profiles and a plurality of connecting plates, the two profiles are arranged in parallel and at intervals and are connected by the plurality of connecting plates arranged at intervals in the height direction, and the symmetry axis between the two profiles is arranged at an angle of 45° with the column grid axis on the building structure; the lower support beam comprises a wedge block, a first support part and a second support part; the first support part and the second support part are hingedly connected to the gaps between the two profiles at intervals and can turn in the direction of mutual contraction and closing or mutual expansion and opening; the wedge block can move into or out of the gap between the first support part and the second support part, for clamping in the gap between the first support part and the second support part to make the lower support beam clamped on the hole or moving out of the gap between the first support part and the second support part to make the lower support beam pass through the hole; the driving end of the electric push cylinder is in transmission connection with the wedge block, for driving the wedge block to rise and fall relative to the support column, so that the wedge block moves into or out of the gap between the first support part and the second support part, and the first support part and the second support part turn in the direction of mutual contraction and closing or mutual expansion and opening, so that the two lower support beams can pass through the hole or be clamped on the hole.

2. The high-rise building demolition apparatus according to claim 1, wherein, The hoisting mechanism comprises a track beam, a steel rail and a travelling crane; each set of the supporting mechanism is provided with a top supporting plate on the top thereof; the track beam is installed between two top supporting plates, and the steel rail is installed on the track beam; and the travelling crane is installed on the steel rail in a transversely movable manner.

3. The high-rise building demolition apparatus according to claim 1, wherein, The transportation mechanism comprises a first construction elevator and a second construction elevator; the first construction elevator is attached to the outer wall of the building structure; the second construction elevator is installed vertically in an elevator shaft inside the building structure, and the second construction elevator comprises a top-open cage, one side of the cage is provided with a frame door which can be opened and closed, and the inner wall of the bottom is provided with a detachable tray.

4. The high-rise building demolition apparatus according to claim 1, wherein, The frame platform is a frame structure formed by a plurality of bailey beams and a plurality of connecting nodes.

5. The high-rise building demolition apparatus according to claim 1, wherein, The operation hanger comprises a plurality of operation platforms connected in sequence from top to bottom, the operation platforms are arranged between the outer walls of the middle layer and the lower layer, and each operation platform is hingedly connected with a flap platform on the side close to the building structure.

6. The high-rise building demolition apparatus according to claim 1, wherein, The soundproof cover is arranged on the outside of the operation hanger and the top of the frame platform in an openable and closable manner.

7. A method of demolishing a high-rise building, characterized by, The high-rise building demolition equipment is used for demolition, comprising the following steps: Step one: installing a first construction elevator outside the building structure, transporting a roof to the top of the building by the first construction elevator for installation, and demolishing part of the structure at the top of the building; Step two: installing the high-rise building demolition equipment on the top of the building by the roof crane, transporting various equipment and tools required for the operation to the top of the building, and then demolishing the roof crane; Step three: simultaneously performing structural demolition, secondary structural demolition, decoration and electromechanical demolition on the three upper, middle and lower layers of the building connected in sequence from top to bottom in a parallel flow operation manner: Performing structural demolition on the upper layer of the building structure: first placing a cutting seam on the upper layer, then cutting the upper layer into blocks by cutting mechanical equipment, then hoisting the cut floor slabs to the second construction elevator by the travelling crane, transporting the floor slabs to the ground floor by the second construction elevator, then performing external transport, and then cutting and hoisting the beams, walls and columns in the upper layer of the building; Performing secondary structural demolition on the middle layer of the building structure: first crushing the masonry infill wall in the secondary structure by a crusher, then collecting and loading the crushed debris into a transport bucket by a shovel truck, then transporting the transport bucket to the first construction elevator and downward to the ground; Performing electromechanical equipment and internal decoration material demolition on the lower layer of the building structure: first demolishing the decoration materials on the building by the operation platform, then horizontally transporting the demolished decoration materials to the second construction elevator by a forklift, and then transporting them downward to the ground. Step four, when the three working layers of superstructure, midstructure and substructure are completed, a hole is opened on the building floor of the next floor; each working equipment on each working layer is moved to the corresponding next working layer in sequence through the second construction elevator, and the flap platform on the operation hanger is folded, and the support mechanism is lowered synchronously, so that the whole high-rise building demolition equipment is lowered to the next working layer, and the construction operation in step three is repeated to realize the demolition of the mechanical and electrical equipment and internal decoration materials of the next floor, the demolition of the secondary mechanism, and the demolition of the structure.

Citation Information

Patent Citations

  • Scattered thing of construction stage handling is fitted up and cage device on chassis can be dismantled

    CN204873427U

  • Rapid lifting tool for battery module

    CN212151341U

  • All-weather antipolluting denolishing work method

    JP1995054503A

  • Disassembling method of structure

    JP2011069117A