An ecological restoration method for partial collapse of half-cut and half-filled roads
By using transverse fiberglass anchors and foam lightweight soil lightweight retaining walls at the high embankment road collapse, combined with vertical prestressed anchors and layered filling technology, foundation disturbance and high cost during the construction of conventional large retaining walls are solved solve the problem and achieve safe, reliable and economical road repair results.
Patent Information
- Application Number
- CN202211217891.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-09-30
- Publication Date
- 2024-10-08
- Estimated Expiration
- 2042-09-30
AI Technical Summary
When high-embankment roads collapse in western mountainous areas, conventional small and medium-sized retaining walls cannot meet the design requirements, resulting in the need to use large-scale retaining walls. However, foundation disturbance of anti-slide piles and high engineering costs become problems during their construction.
Horizontal fiberglass anchors and foam lightweight soil lightweight retaining walls are used, and vertical prestressed anchors are fastened to the foundation. The support layer, EPS lightweight backfill layer and permeable concrete layer are filled in layers to reduce the extrusion of the foundation. Avoid using anti-slide piles to reduce project costs.
The road repair effect is achieved with safe and reliable construction, little foundation disturbance, less material consumption, and low cost, and improves the bearing capacity and stability of the road.
Smart Images

Figure CN115897318B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to an ecological restoration method for partial collapse of a half-cut and half-filled road, belonging to the technical field of geotechnical engineering. Background Art
[0002] In the past thirty years, my country's highway and railway construction has developed rapidly, especially in the western mountainous areas. In order to meet the requirements of the overall road line, many high embankments and high cuttings have appeared. The earthquake action in some areas and the erosion of local heavy rainfall have caused landslides on high earth-filled embankments. Once a road collapses, it not only causes traffic congestion, but also may cause serious loss of life and property.
[0003] The height of the high embankment slope reaches more than ten meters or even more. Conventional small and medium-sized retaining walls can no longer meet the design requirements. Large retaining walls are needed. However, when using large retaining walls to repair collapsed roads, anti-slip pile holes need to be drilled. However, drilling anti-slip piles will disturb the foundation stress, which may cause landslides and collapses during the construction process. Second, the pile length and embedded depth of the anti-slip piles are very high, resulting in excessively high project costs. Therefore, a construction solution with small disturbance to the foundation stress and low project cost is urgently needed. Summary of the invention
[0004] The technical problem to be solved by the present invention is to provide an ecological restoration method for partial collapse of a half-cut and half-filled road, so as to overcome the shortcomings of the prior art.
[0005] The technical solution of the present invention is: an ecological restoration method for partial collapse of a half-cut and half-filled road, the method comprising the following steps:
[0006] S01. Use transverse fiberglass anchor rods for temporary support on the collapsed surface of the original road, fasten the foam lightweight soil lightweight retaining wall to the original foundation through vertical prestressed anchor rods at the boundary line of the original road, and fix the end of the transverse fiberglass anchor rod exposed on the collapsed surface to the foam lightweight soil lightweight retaining wall;
[0007] S02. The support layer, EPS lightweight backfill layer and permeable concrete layer are filled in layers from bottom to top between the lightweight retaining wall of foam lightweight soil and the collapsed surface.
[0008] Furthermore, the foam lightweight soil lightweight retaining wall includes a foundation and a wall body. The foundation is cast with C30 reinforced concrete with a thickness of 30 cm. A Φ8@10cm×10cm steel mesh is set at 1 / 2 of the inner portion of the slab. The wall body is cast in layers.
[0009] Furthermore, the foamed lightweight soil lightweight retaining wall material includes a foaming agent mixed in concrete without coarse aggregate, the foamed lightweight soil has a bulk density of 8kN / m3, and a cube compressive strength of not less than 1.5MPa.
[0010] Furthermore, the wall body is preset with a Φ100mm drainage hole, and the drainage hole runs through the left and right sides of the wall body.
[0011] Furthermore, n pieces of geogrids are arranged in layers inside the support layer, where n is a positive integer greater than or equal to 1, and the spacing between two adjacent layers of geogrids is 80 cm. Filling materials are used between the geogrids and filled in layers simultaneously with the layered pouring of the wall body. The filling materials are medium-dense to dense crushed stone soil, which is then compacted, and the geogrids are parallel to the horizontal plane.
[0012] Furthermore, the end of the steel-plastic geogrid extends into the interior of the foam lightweight soil lightweight retaining wall.
[0013] Furthermore, the thickness of the EPS lightweight backfill layer is greater than 50 cm.
[0014] Furthermore, the permeable concrete layer is connected to the non-collapsed roadbed through steel rods with a longitudinal spacing of 30 cm to form an integral road surface.
[0015] Furthermore, the foam lightweight soil lightweight retaining wall is in a stepped shape, and a greening geocell is arranged on the stepped upper surface of the foam lightweight soil lightweight retaining wall, and the greening geocell is filled with planting soil.
[0016] The beneficial effects of the present invention are as follows: compared with the prior art, the present invention uses a lightweight foam soil retaining wall, which reduces the extrusion of the lightweight foam soil retaining wall on the foundation, so that vertical prestressed anchor rods can be used instead of anti-slip piles, so that this scheme basically does not disturb the foundation, and the construction is safe and reliable. In addition, since there is no need to drill anti-slip pile holes, the amount of retaining wall material used is small and the cost is lower. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] Figure 1 It is a schematic structural diagram of an embodiment of the present invention. DETAILED DESCRIPTION
[0018] In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inside", "outside" and the like indicate positions or positional relationships based on the positions or positional relationships shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific position, be constructed and operated in a specific position, and therefore cannot be understood as limiting the present invention; the terms "first", "second", and "third" are only used for descriptive purposes, and cannot be understood as indicating or implying relative importance. In addition, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be an indirect connection through an intermediate medium, or it can be a connection between the two elements. For those of ordinary skill in the art, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0019] In order to better understand the above technical solution, the above technical solution will be described in detail below in conjunction with the accompanying drawings and specific implementation methods.
[0020] refer to Figure 1 , Figure 1 1 is the original road, 16 is the rock and soil fracture surface, in order to reduce the disturbance to the foundation 6 during construction and use and reduce the project cost, this embodiment adopts an ecological restoration method for the partial collapse of the half-cut and half-filled road, the method includes the following steps:
[0021] S01. A transverse fiberglass anchor rod 4 is used for temporary support on the collapsed surface 3 of the original road. A foam light soil lightweight retaining wall 5 is fastened to the original foundation through a vertical prestressed anchor rod 11 at the original road boundary line. The end of the transverse fiberglass anchor rod 4 exposed from the collapsed surface 3 is fixedly connected to the foam light soil lightweight retaining wall 5.
[0022] S02. A support layer 8, an EPS lightweight backfill layer 12 and a permeable concrete layer 13 are sequentially filled in layers from bottom to top between the foam lightweight soil lightweight retaining wall 5 and the collapsed surface 3.
[0023] The present invention uses a foam lightweight soil lightweight retaining wall 5, which reduces the extrusion of the foam lightweight soil lightweight retaining wall 5 on the foundation, so that vertical prestressed anchor rods 11 can be used instead of anti-slip piles, so that this solution basically does not disturb the foundation 6, and the construction is safe and reliable. In addition, since there is no need to drill anti-slip pile holes, the amount of retaining wall material used is small and the cost is lower.
[0024] In order to make the foam lightweight soil lightweight retaining wall 5 meet the structural strength requirements, the foam lightweight soil lightweight retaining wall 5 further includes a foundation 6 and a wall body 7. The foundation 6 is cast with C30 reinforced concrete with a thickness of 30 cm, and a Φ8@10cm×10cm steel mesh is set at 1 / 2 of the plate; the wall body 7 is cast in layers.
[0025] In order to increase the adhesion, sealing and leakproofness of the foamed light soil light retaining wall 5, the foamed light soil light retaining wall 5 is made of concrete without coarse aggregate and a foaming agent is mixed therein, the foamed light soil has a bulk density of 8kN / m3, and a cubic compressive strength of not less than 1.5MPa. The foaming agent has good surface activity, can reduce the surface tension of the liquid, and can play the role of adhesion, sealing and leakproofness after foaming and curing.
[0026] In order to prevent water from accumulating between the wall body 7 and the foundation 6 and causing the foam lightweight soil lightweight retaining wall 5 to be squeezed and collapsed, and to increase the durability of the foam lightweight soil lightweight retaining wall 5, the wall body 7 is further preset with a Φ100mm drainage hole 10, and the drainage hole 10 runs through the left and right sides of the wall body 7.
[0027] In order to facilitate construction, further, n pieces of geogrids 9 are arranged in layers inside the support layer 8, n is a positive integer greater than or equal to 1, the distance between two adjacent layers of geogrids 9 is 80 cm, and the geogrids 9 are filled in layers at the same time as the wall body 7 is cast in layers. The filling material is medium-dense to dense crushed stone soil, which is then compacted, and the geogrids 9 are parallel to the horizontal plane.
[0028] In order to increase the bearing capacity of the repaired road, further, the end of the steel-plastic geogrid 9 extends into the interior of the foam lightweight soil lightweight retaining wall 5.
[0029] Furthermore, the thickness of the EPS lightweight backfill layer 12 is greater than 50 cm. The EPS lightweight backfill layer 12 has the characteristics of light weight, high strength, strong chemical stability and water stability, and good mechanical properties, which can reduce the deadweight of the upper road structure, reduce the pressure of the foam lightweight soil lightweight retaining wall 5, and can better solve the excessive settlement and differential settlement of the newly built roadbed.
[0030] Furthermore, the permeable concrete layer 13 is connected to the uncollapsed roadbed 2 by steel rods 14, with a longitudinal spacing of 30 cm, to form an integral road surface. The steel rods make the connection between the newly repaired road surface and the uncollapsed roadbed 2 more stable, avoiding cracks between the newly repaired road surface and the uncollapsed roadbed 2.
[0031] Furthermore, the foamed lightweight soil light retaining wall 5 is stepped, and a greening geocell 15 is arranged on the stepped upper surface of the foamed lightweight soil light retaining wall 5, and the greening geocell 15 is filled with planting soil. The greening geocell 15 can be planted with plants to play a greening role.
[0032] The above contents are further detailed descriptions of the present invention in combination with specific preferred embodiments, and it cannot be determined that the specific implementation of the present invention is limited to these descriptions. For ordinary technicians in the technical field to which the present invention belongs, several simple deductions or substitutions can be made without departing from the concept of the present invention, which should be regarded as falling within the protection scope of the present invention.
Claims
1. An ecological restoration method for partial collapse of a half-cut and half-filled road, characterized in that: The method comprises the following steps: S01. A transverse glass fiber reinforced plastic anchor rod (4) is used for temporary support at the collapsed surface (3) of the original road. A foam light soil lightweight retaining wall (5) is fastened to the original foundation at the boundary line of the original road by means of a vertical prestressed anchor rod (11). The end of the transverse glass fiber reinforced plastic anchor rod (4) exposed from the collapsed surface (3) is fixedly connected to the foam light soil lightweight retaining wall (5); S02, a support layer (8), an EPS lightweight backfill layer (12) and a permeable concrete layer (13) are sequentially filled between the foam lightweight soil lightweight retaining wall (5) and the collapsed surface (3) from bottom to top; The foamed lightweight soil lightweight retaining wall (5) comprises a foundation (6) and a wall body (7). The foundation (6) is cast using C30 reinforced concrete with a thickness of 30 cm. A Φ8@10 cm×10 cm steel mesh is set at 1 / 2 of the inner portion of the slab. The wall body (7) is cast in layers. N pieces of geogrids (9) are arranged in layers inside the support layer (8), where n is a positive integer greater than or equal to 1, and the spacing between two adjacent layers of geogrids (9) is 80 cm. Filling material is used between the geogrids (9) and is filled in layers simultaneously with the layered pouring of the wall body (7). The filling material is medium-dense to dense crushed stone soil, which is then compacted. The geogrids (9) are parallel to the horizontal plane.
2. The ecological restoration method for partial collapse of a half-cut and half-filled road according to claim 1, characterized in that: The foamed lightweight soil lightweight retaining wall (5) is made of concrete without coarse aggregate and mixed with a foaming agent. The foamed lightweight soil has a bulk density of 8 kN / m 3 , the cube compressive strength is not less than 1.5MPa.
3. The ecological restoration method for partial collapse of a half-cut and half-filled road according to claim 1, characterized in that: The wall body (7) is provided with a Φ100 mm drainage hole (10), and the drainage hole (10) runs through the wall body (7) on the left and right.
4. The ecological restoration method for partial collapse of a half-cut and half-filled road according to claim 1, characterized in that: The end of the steel-plastic geogrid (9) extends into the interior of the foam lightweight soil lightweight retaining wall (5).
5. The ecological restoration method for partial collapse of a half-cut and half-filled road according to claim 1, characterized in that: The thickness of the EPS lightweight backfill layer (12) is greater than 50 cm.
6. The ecological restoration method for partial collapse of a half-cut and half-filled road according to claim 1, characterized in that: The permeable concrete layer (13) is connected to the non-collapsed roadbed (2) via steel rods (14) with a longitudinal spacing of 30 cm to form an integral road surface.
7. The ecological restoration method for partial collapse of a half-cut and half-filled road according to claim 4, characterized in that: The foamed lightweight soil lightweight retaining wall (5) is in a stepped shape, and a greening geocell (15) is arranged on the stepped upper surface of the foamed lightweight soil lightweight retaining wall (5), and the greening geocell (15) is filled with planting soil.