A BIM-based air conditioning system control method with pre-action optimization function
By introducing weather forecast and personnel event modules into the BIM model, combining fuzzy control and harmonic reaction method, optimizing the flow of the air-conditioning water system pipeline and the number of host machines, the problems of low management efficiency and uneven cold distribution of air-conditioning system are solved, and Efficient operation and maintenance of air conditioning systems and energy consumption optimization.
Patent Information
- Application Number
- CN202210753730.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-06-29
- Publication Date
- 2024-11-08
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
The existing air conditioning system has low management efficiency, the chiller unit is often in an inefficient state, the cold volume distribution is uneven, and the entire complex system cannot be effectively adjusted, resulting in waste of energy consumption and reduced equipment life.
Using BIM-based method, the weather forecast module and personnel event module are added, and the operation and maintenance plan is associated with the BIM model, and the fuzzy control and harmonic reaction method are used to adjust the flow rate of the air-conditioning water system pipeline and the number of host machines to achieve the pre-action optimization of the air-conditioning system. .
It improves the operation and maintenance efficiency of the air conditioning system, reduces the operation and maintenance costs, reduces the operation and intensity of on-site personnel, and realizes effective regulation and energy consumption optimization of the entire air conditioning system.
Smart Images

Figure CN115930382B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of air-conditioning systems, and in particular to a BIM-based air-conditioning system control method with a pre-action optimization function. Background Art
[0002] With the development of economy, more and more buildings are not only complex in structure, but also have larger and larger scale of air conditioning and electromechanical equipment, facing a large number of professional management problems of air conditioning and electromechanical equipment. Relying on traditional preventive maintenance management system and temporary maintenance management methods to manage, it cannot meet the needs of intelligent operation and maintenance of electromechanical equipment.
[0003] The main problems are:
[0004] 1) Although the air conditioning system is managed by a dedicated person, there are still prominent problems such as reliance on experience, low efficiency, high workload, and no consideration of energy waste to ensure operation.
[0005] 2) The chiller is often operated in a non-efficient state. The chiller is often operated in a low-load state, and the host operating parameters and number of units are unreasonable, resulting in a decrease in the efficiency of the chiller.
[0006] 3) The cold water of the air conditioning system is supplied to each terminal area by the water distributor. Due to the pipeline characteristics of the fluid and the load characteristics of the air conditioner, there is an uneven distribution of cooling capacity between areas, and there is also an imbalance between supply and demand in the same area. In actual operation, the air conditioning effect in unfavorable areas and the air conditioning effect in high-load time periods are used as the standard, resulting in a huge waste of cooling capacity in favorable areas and low-load time periods.
[0007] In response to these current situations, people have proposed different solutions. Path one mainly starts from the main components of the air-conditioning equipment to solve the problem of efficient operation: Application No. 202210079266.4 proposes to control the speed of the air-conditioning fan to increase or decrease the multiple of the base speed; Application No. 202122442136.6 provides an air-conditioning unit angle adjustment device; Application No. 202010326616.3 proposes an air-conditioning refrigerant automatic adjustment device, control method, etc.; Path two mainly starts with the operation adjustment of the air-conditioning system and proposes an adjustment strategy: Application No. 201810653262.6 adjusts the sub-air outlets according to the number of personnel distribution and changes. The number of air conditioners can be controlled, and then the output of the air conditioner can be controlled to avoid the water-cooled central air conditioner being unable to effectively adjust the air outlet according to the changes in personnel; Application No. 201310272830.5 proposes to receive the results of the air conditioner monitoring by the sensor according to the preset time period to determine whether the air conditioner is running at a low consumption; Application No. 201910855943.5 proposes to intelligently control the operation mode of the fresh air fan according to information such as outdoor temperature, indoor environment and indoor personnel to improve the user's comfort in the air-conditioned environment; at the same time, it effectively reduces the power consumption of the air conditioner to avoid the reduction of its service life due to continuous operation. Although these ideas can solve some problems, there are mainly the following problems:
[0008] 1) Feedback control is made based on the actual temperature, humidity, and carbon dioxide concentration, which delays the resolution of the problem. This is seriously out of line with the actual needs of the tight production and life of enterprises and institutions;
[0009] 2) Only local regulation and control of the air-conditioning system can be performed, and it is impossible to truly achieve regulation and control of the entire complex air-conditioning system.
[0010] Building Information Modeling (BIM) is an intelligent multi-dimensional model of a building, which connects the data, processes and resources of different stages in the life cycle of a construction project (including the design, construction, delivery and management process of the building), and is a complete description of the construction project object. With the development of BIM, it has brought great influence and promotion in the design and construction of construction projects, and has made it possible to efficiently manage a large number of complex mechanical and electrical equipment. Summary of the invention
[0011] The technical problem to be solved by the present invention is to provide a BIM-based air conditioning system control method with pre-action optimization function in view of the deficiencies of the above-mentioned prior art. The BIM-based air conditioning system control method with pre-action optimization function combines BIM technology to intuitively display the real-time status parameters of air conditioning equipment, record equipment information, maintenance and repair plans and effects in daily operation and maintenance of property management, and optimize the performance of the air conditioning system based on pre-action such as weather and changes in the number of personnel, reasonably reduce operation and maintenance costs, improve operation and maintenance efficiency, greatly improve efficiency, and reduce the operation intensity of on-site personnel.
[0012] In order to solve the above technical problems, the technical solution of the present invention is:
[0013] 1. A BIM-based air conditioning system control method with pre-action optimization function, comprising the following steps:
[0014] Step S1: When making a BIM model of an air conditioning system, two custom modules are added to the components related to operation and maintenance: a weather forecast module and a personnel event module;
[0015] Step S2: import the prepared air conditioning system BIM model including the weather forecast module and the personnel event module into the BIM system platform and software;
[0016] Step S3: when using the planning software to prepare the air conditioning system operation and maintenance plan, by adding a new column, fill in the identifier or keyword of the component custom attribute in the BIM model of the component involved in the air conditioning operation and maintenance corresponding to the planned task;
[0017] Step S4: Import the prepared operation and maintenance plan file into the software platform or system involving BIM technology through the import function;
[0018] Step S5: In the software platform and system involving BIM technology, add an air conditioning water system pipe network flow allocation module and an air conditioning host number allocation module, and realize automatic association between the operation and maintenance plan and the BIM model components through the imported operation and maintenance plan file and BIM model;
[0019] Furthermore, the method for quickly associating the air conditioning system operation and maintenance plan with the BIM model also includes the following process:
[0020] Step S6: air conditioning water system pipe network flow allocation, using fuzzy control technology, in the software platform involving BIM technology, according to the association between the operation and maintenance plan and the BIM model components, predetermine the opening adjustment time and opening adjustment size of the bypass valve between the water distributor and the water collector, as well as the opening and adjustment time of the chilled water flow regulating valve of each corresponding chilled water branch, determine the maximum chilled water flow available for the corresponding air conditioning system, and present the associated components and information in the BIM model in turn according to the air conditioning operation and maintenance plan;
[0021] Step S7, the air conditioner host number allocation module sets the temperature rise and fall range △T and the reference temperature T0 of the increase or decrease units, calculates the temperature of the air conditioner return water under the maximum available flow rate, and determines the time to increase or decrease the units.
[0022] Furthermore, in step S1, when making the BIM model of the air-conditioning system, a custom attribute is added under the "identification data" of the component, the custom attribute is named, and the identifier or keyword associated with the operation and maintenance plan is filled in the custom attribute.
[0023] Furthermore, in step S1, the weather forecast module obtains local meteorological parameters such as temperature, humidity and wind speed at a future time through a wireless network.
[0024] Furthermore, in step S1, the personnel event module manually inputs the events scheduled in the work plan and the time of occurrence and end, and obtains half an hour delay and modification authority.
[0025] Furthermore, in step S2, the air-conditioning BIM model is imported into the BIM system platform and software by developing a plug-in in the modeling tool software.
[0026] Furthermore, in step S3, the future air conditioning load changes caused by the weather forecast module and the personnel event module are calculated using the harmonic response method, and are saved in digital form in a newly added new column.
[0027] Furthermore, in step S6, the supply and return water temperature difference of each loop is used as the controlled variable, and the supply and return water temperature difference of each loop at the current flow is calculated according to the weather forecast module and the personnel event module, and the deviation and the deviation change rate from the set temperature difference value are calculated, and then the water pump frequency (or number) at the water supply end of the corresponding loop is adjusted, and the water flow rate of the corresponding loop is dynamically adjusted, so that the supply and return water temperature difference tends to be consistent, close to the set temperature difference, and the maximum chilled water flow Lmax of the adjustment loop is obtained.
[0028] Furthermore, in step S7, the required load Q of the air conditioning system is calculated in step 3. For the water system of the air conditioning system, the cooling capacity of the air conditioning system is Q = 4.1868 × Lmax × (T1-T2), where: T1 is the chilled water outlet temperature, which is 7°C; Lmax is the maximum chilled water flow obtained in step 6. The future time T2 is calculated as the chilled water return temperature;
[0029] The relationship between the air conditioning system load and the unit cooling capacity is calculated using the following formula: Q = K × (N × C), where K is the proportional constant, N is the cooling capacity of the chiller, and C is the number of chillers currently in operation.
[0030] The conditions for adding a machine are to meet the following two conditions at the same time:
[0031] ①Q≥K×(N×C) K=85%
[0032] ②T2≥T0+△T
[0033] The conditions for reducing the number of machines are to meet the following two conditions at the same time:
[0034] ①Q1≤K×((N-1)×C) K=65%
[0035] ②T2≤T0
[0036] This allows the time to add or remove units to be determined in advance to meet the comfort requirements of the air-conditioning system.
[0037] By adopting the above technical solution, the present invention has the following beneficial effects:
[0038] 1. Realized the rapid association between air-conditioning system operation and maintenance plan and BIM model.
[0039] 2. Realize the future air conditioning load changes caused by the weather forecast module and the personnel event module,
[0040] 3. Through the allocation of air conditioning water system pipe network flow and the number of air conditioning hosts, the air conditioning system regulation with pre-action optimization function is realized
[0041] 4. This system provides statistics and records of air conditioning system control with pre-action optimization function, providing important reference for subsequent operation improvement and personnel training. BRIEF DESCRIPTION OF THE DRAWINGS
[0042] Figure 1 The present invention is a flow chart of a method for controlling an air conditioning system with a pre-action optimization function based on BIM. DETAILED DESCRIPTION
[0043] The specific embodiments of the present invention are further described below in conjunction with the accompanying drawings. It should be noted that the description of these embodiments is used to help understand the present invention, but does not constitute a limitation of the present invention. In addition, the technical features involved in the various embodiments of the present invention described below can be combined with each other as long as they do not conflict with each other.
[0044] Take a comprehensive office building project in Fuzhou as an example: the building situation is: 12 floors are above ground, 1 underground garage, the total construction area is 13515m2, of which the air-conditioned area is 7375m2, and the room categories are mainly offices, conference rooms, halls and other rooms. This air-conditioning design determines the following air-conditioning system through scheme comparison: the second floor and the seventh to twelfth floors of the office building all use fan coil units plus fresh air air treatment methods, among which, the first floor office 1 to office 7 use fan coil units plus fresh air air treatment methods, and the third to sixth floors office 1 to office 10 also use fan coil units plus fresh air air treatment methods; the first floor entrance hall, service hall, multi-functional hall and the third to sixth floors conference rooms use full air systems. The room load is calculated using the harmonic response method, and it is finally concluded that the maximum load of the entire building occurs at 17 o'clock, with a load of 1279kW. The air conditioning water system is a double-pipe closed system with a single pump. The water system is divided into four zones: Zone A: the first floor, Zone B: the second floor, Zone C: the third to sixth floors, and Zone D: the seventh to twelfth floors. The water pipes in each zone are horizontally and vertically aligned. The cold source design determines two water-cooled chillers based on the air conditioning load of the office building. The cooling capacity of the YBWC150A chiller is 545kW.
[0045] A BIM-based air conditioning system control method with pre-action optimization function comprises the following steps:
[0046] Step S1: When making a BIM model of an air conditioning system, two custom modules are added to the components related to operation and maintenance: a weather forecast module and a personnel event module;
[0047] Step S2: import the prepared air conditioning system BIM model including the weather forecast module and the personnel event module into the BIM system platform and software;
[0048] Step S3: when using the planning software to prepare the air conditioning system operation and maintenance plan, by adding a new column, fill in the identifier or keyword of the component custom attribute in the BIM model of the component involved in the air conditioning operation and maintenance corresponding to the planned task;
[0049] Step S4: Import the prepared operation and maintenance plan file into the software platform or system involving BIM technology through the import function;
[0050] Step S5: In the software platform and system involving BIM technology, add the air conditioning water system pipe network flow allocation module and the air conditioning host number allocation module, and realize the automatic association between the operation and maintenance plan and the BIM model components through the imported operation and maintenance plan file and BIM model.
[0051] Furthermore, the method for quickly associating the air conditioning system operation and maintenance plan with the BIM model also includes the following process:
[0052] Step S6, air conditioning water system pipe network flow allocation, using fuzzy control technology, in the software platform involving BIM technology, according to the association between the operation and maintenance plan and the BIM model components, pre-determine the opening adjustment time and opening adjustment size of the bypass valve between the manifold and the collector, as well as the opening and adjustment time of the chilled water flow regulating valve of each corresponding chilled water branch, determine the corresponding maximum chilled water flow available for the air conditioning system, and present the related components and information in the BIM model in turn according to the air conditioning operation and maintenance plan.
[0053] Step S7, the air conditioning host number allocation module sets the return water temperature rise and fall range △T = 2°C and the reference temperature T0 = 12°C for increasing or decreasing the units, calculates the control air conditioning return water temperature under the maximum available flow rate, and determines the time to increase or decrease the units.
[0054] Furthermore, in step S1, when making the BIM model of the air-conditioning system, a custom attribute is added under the "identification data" of the component, the custom attribute is named, and the identifier or keyword associated with the operation and maintenance plan is filled in the custom attribute.
[0055] Furthermore, in step S1, the weather forecast module obtains local meteorological parameters such as temperature, humidity and wind speed at a future time through a wireless network.
[0056] Furthermore, in step S1, the personnel event module manually inputs the events scheduled in the work plan and the time of occurrence and end, and obtains half an hour delay and modification authority.
[0057] Furthermore, in step S2, the air-conditioning BIM model is imported into the BIM system platform and software by developing a plug-in in the modeling tool software.
[0058] Furthermore, in step S3, the future air conditioning load change caused by the weather forecast module is calculated using the harmonic response method and saved in digital form in a newly added new column.
[0059] Tables 1 and 2 below show the load calculation results for the north exterior wall of the conference room on the 5th floor:
[0060]
[0061] Table 1 Load calculation of the north exterior wall of the conference room on the 5th floor
[0062]
[0063] Table 2 Summary of loads for the entire building
[0064] Furthermore, in step S6, the supply and return water temperature difference of each loop is 5°C as the controlled variable, and the supply and return water temperature difference of each loop at the current flow is calculated according to the weather forecast module. The deviation 5-△τ and the deviation change rate = 1-△τ / 5 from the set temperature difference are calculated, and then the water flow of the corresponding loop is dynamically adjusted by adjusting the water pump frequency (or number) at the water supply end of the corresponding loop, so as to achieve the consistency of the supply and return water temperature difference and close to the set temperature difference, and obtain the maximum chilled water flow Lmax of the adjustment loop. In this example, since the outdoor temperature change is mainly considered, the flow regulation of each system does not change significantly.
[0065] Furthermore, in step S7, the required load Q of the air conditioning system is calculated in step 3. For the water system of the air conditioning system, the cooling capacity of the air conditioning system is Q = 4.1868 × Lmax × (T1-T2), where: T1 is the chilled water outlet temperature, which is 7°C; Lmax is the maximum chilled water flow obtained in step 6. The future time T2 is calculated as the chilled water return temperature;
[0066] The relationship between the air conditioning system load and the unit cooling capacity is calculated using the following formula: Q = K × (N × C), where K is the proportional constant, N is the cooling capacity of the chiller, and C is the number of chillers currently in operation.
[0067] The conditions for adding a machine are to meet the following two conditions at the same time:
[0068] ①Q≥K×(N×C) K=85%
[0069] ②T2≥T0+△T
[0070] The conditions for reducing the number of machines are to meet the following two conditions at the same time:
[0071] Q1≤K×((N-1)×C) K=65%
[0072] ②T2≤T0
[0073] In this example, one host is started at 7 o'clock, and it is expected that one more host will be added around 8:30 to meet the comfort requirements of the air-conditioning system.
[0074] The present invention has the following beneficial effects:
[0075] 1. Realized the rapid association between air-conditioning system operation and maintenance plan and BIM model.
[0076] 2. Realize the future air conditioning load changes caused by the weather forecast module and the personnel event module,
[0077] 3. Through the allocation of air conditioning water system pipe network flow and the number of air conditioning hosts, the air conditioning system regulation with pre-action optimization function is realized
[0078] 4. This system provides statistics and records of air conditioning system control with pre-action optimization function, providing important reference for subsequent operation improvement and personnel training.
[0079] The embodiments of the present invention are described in detail above with reference to the accompanying drawings, but the present invention is not limited to the described embodiments. For those skilled in the art, various changes, modifications, substitutions and variations of these embodiments are made without departing from the principles and spirit of the present invention, and still fall within the scope of protection of the present invention.
Claims
1. A BIM-based air conditioning system control method with pre-action optimization function, characterized in that: The following steps are involved: Step S1: When making a BIM model of an air conditioning system, two custom modules are added to the components related to operation and maintenance: a weather forecast module and a personnel event module; Step S2, importing the prepared air conditioning system BIM model including the weather forecast module and the personnel event module into the BIM system platform and software; Step S3: when using the planning software to prepare the air conditioning system operation and maintenance plan, by adding a new column, fill in the identifier or keyword of the component custom attribute in the BIM model of the component involved in the air conditioning operation and maintenance corresponding to the planned task; Step S4: Import the prepared operation and maintenance plan file into the software platform or system involving BIM technology through the import function; Step S5: In the software platform and system involving BIM technology, add an air conditioning water system pipe network flow allocation module and an air conditioning host number allocation module, and realize automatic association between the operation and maintenance plan and the BIM model components through the imported operation and maintenance plan file and BIM model; Furthermore, the method for quickly associating the air conditioning system operation and maintenance plan with the BIM model also includes the following process: Step S6: air conditioning water system pipe network flow allocation, using fuzzy control technology, in the software platform involving BIM technology, according to the association between the operation and maintenance plan and the BIM model components, predetermine the opening adjustment time and opening adjustment size of the bypass valve between the water distributor and the water collector, as well as the opening and adjustment time of the chilled water flow regulating valve of each corresponding chilled water branch, determine the maximum chilled water flow available for the corresponding air conditioning system, and present the associated components and information in the BIM model in turn according to the air conditioning operation and maintenance plan; Step S7, the air conditioner host number allocation module sets the temperature rise and fall range △T and the reference temperature T0 of the increase or decrease units, calculates the temperature of the air conditioner return water under the maximum available flow rate, and determines the time to increase or decrease the units; Wherein, in the step S7, the required load Q of the air conditioning system is calculated in step 3. For the water system of the air conditioning system, the cooling capacity of the air conditioning system is Q=4.1868×Lmax×(T1-T2), where: T1 is the chilled water outlet temperature, which is 7°C; Lmax is the maximum chilled water flow obtained in step 6; T2 calculated at the future time is the chilled water return temperature; The relationship between the air conditioning system load and the unit cooling capacity is calculated using the following formula: Q = K × (N × C), where K is the proportional constant, N is the cooling capacity of the chiller, and C is the number of chillers currently in operation. The conditions for adding a machine are to meet the following two conditions at the same time: ①Q≥K×(N×C)K=85% ②T2≥T0+△T The conditions for reducing the number of machines are to meet the following two conditions at the same time: ①Q1≤K×((N-1)×C)K=65% ②T2≤T0 Thus, the time to increase or decrease the units can be determined in advance to meet the comfort requirements of the air conditioning system.
2. The BIM-based air conditioning system control method with pre-action optimization function according to claim 1 is characterized in that: In the step S1, when making the BIM model of the air-conditioning system, a custom attribute is added under the "identification data" of the component, the custom attribute is named, and the identifier or keyword associated with the operation and maintenance plan is filled in the custom attribute.
3. The BIM-based air conditioning system control method with pre-action optimization function according to claim 1 is characterized in that: In step S1, the weather forecast module obtains local temperature, humidity and wind speed meteorological data at a future time through a wireless network.
4. The BIM-based air conditioning system control method with pre-action optimization function according to claim 1, characterized in that: In step S1, the personnel event module manually inputs the events scheduled in the work plan and the time of occurrence and end, and obtains half an hour delay and modification authority.
5. The BIM-based air conditioning system control method with pre-action optimization function according to claim 1 is characterized in that: In step S2, the air-conditioning BIM model is imported into the BIM system platform and software by developing a plug-in in the modeling tool software.
6. The BIM-based air conditioning system control method with pre-action optimization function according to claim 1 is characterized in that: In step S3, the future air conditioning load changes caused by the weather forecast module and the personnel event module are calculated using the harmonic response method, and are saved in digital form in a newly added new column.
7. The BIM-based air conditioning system control method with pre-action optimization function according to claim 1 is characterized in that: In step S6, the supply and return water temperature difference of each loop is used as the controlled variable, and the supply and return water temperature difference of each loop at the current flow rate is calculated according to the weather forecast module and the personnel event module, and the deviation and the deviation change rate from the set temperature difference value are calculated, and then the water pump frequency or number of the water supply end of the corresponding loop is adjusted, and the water flow rate of the corresponding loop is dynamically adjusted, so that the supply and return water temperature difference tends to be consistent and close to the set temperature difference, and the maximum chilled water flow rate Lmax of the adjustment loop is obtained.