A method for controlling blasting shock during construction of tunnels adjacent to highways

Through the design of segmented blasting and arc-shaped shock absorbing trenches, digital electronic detonators and water drills are used to reduce the vibration impact of tunnel blasting on the highway, solve the problem of the impact of earthquakes on the highway during tunnel excavation, and achieve safety and efficiency. improvement.

CN116222331BActive Publication Date: 2024-10-22CHINA RAILWAY 16TH BUREAU GRP CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202211566357.7
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-12-07
Publication Date
2024-10-22
Estimated Expiration
2042-12-07

AI Technical Summary

Technical Problem

During the tunnel excavation process, the vibrations generated by blasting will affect nearby roads, leading to road cracks and operational safety issues. It is difficult for existing technology to effectively reduce the impact of vibrations on surrounding roads.

Method used

The method of blasting is divided into sections, and a digital electronic detonator is used to set the differential interval time. An arc-shaped shock-absorbing trench is excavated between the tunnel and the highway, and a hydraulic drill is used to excavate the shock-absorbing trench to reduce seismic wave propagation and vibration transmission.

Benefits of technology

It effectively breaks rocks, reduces blasting vibration, improves blasting safety, reduces the impact on surrounding roads, and improves excavation efficiency and safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN116222331B_ABST
    Figure CN116222331B_ABST
Patent Text Reader

Abstract

The invention belongs to the technical field of blasting shock absorption control, and specifically is a blasting shock absorption control method for construction of tunnels adjacent to highways; by adopting a method of zoning and segmenting blasting and utilizing a reasonable micro-difference interval time of digital electronic detonators, rocks can be effectively crushed while reducing blasting vibration; a shock absorption ditch is excavated, and the cross section of the shock absorption ditch is set to an arc section, which can reflect a part of the seismic waves generated by tunnel blasting to the ground and underground, and change the propagation direction of the seismic waves of the tunnel blasting in the rock and soil, thereby improving the safety of blasting and reducing the impact on surrounding highways.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of blasting shock reduction control, in particular to a blasting shock reduction control method for construction of a tunnel adjacent to a highway. Background Art

[0002] With the construction of highways, especially those built in mountainous areas, tunnel excavation is often necessary. Common tunnel excavation methods include drilling and blasting, shield tunneling and driving. The drilling and blasting method is widely used in tunnel excavation because of its strong adaptability to geological conditions and low excavation cost.

[0003] A Chinese patent with the publication number CN102506622B discloses a tunnel electronic millisecond electric detonator full-section blasting vibration control construction method, which involves blasting vibration control technology. According to the geological conditions of the tunnel engineering, excavation section, excavation method, excavation cycle footage, drilling equipment and blasting equipment, and blasting vibration requirements, the full-section blasting vibration reduction control drilling and blasting design is carried out; wherein, the drilling and blasting design is to achieve single sound of the slot hole, auxiliary hole and bottom plate hole, group the surrounding holes, and set the detonator delay of each blast hole to achieve blasting staggered vibration reduction; design the use process of electronic millisecond electric detonators and use them according to the process; during construction, analyze the vibration waveform obtained by blasting effect and blasting monitoring, feedback information to guide construction, and continuously adjust blasting parameters. This blasting construction method can significantly reduce the vibration of full-section blasting.

[0004] During the tunnel excavation blasting process, the blasting produces a large vibration, and the vibration waves spread in all directions, affecting the roads near the tunnel, affecting the driving of vehicles on the road, and even causing cracks in the road, affecting the structure of the road and the safety of its operation.

[0005] To this end, the present invention provides a method for controlling blasting shock absorption during construction of a tunnel adjacent to a highway. Summary of the invention

[0006] In order to make up for the deficiencies of the prior art, at least one technical problem raised in the background technology is solved.

[0007] The technical solution adopted by the present invention to solve the technical problem is: a method for controlling blasting shock absorption in tunnel construction adjacent to a highway described in the present invention, the blasting construction method comprises the following steps:

[0008] S1: Design blasting plan based on the concept of zoned and segmented blasting and use the middle partition wall method for construction;

[0009] S2: Design the blasting sequence and select the order of detonation of the sections: the upper section of the pilot tunnel I, the lower section of the pilot tunnel II, the upper section of the pilot tunnel III and the lower section of the pilot tunnel IV;

[0010] S3: Drill blast holes on the cross section according to the blast hole layout diagram, install digital electronic detonators inside the blast holes, and set the micro-difference blasting interval time;

[0011] S4: Arrange the shock-absorbing trench along the contour line of the tunnel excavation and use a water-grinding drill to excavate the shock-absorbing trench;

[0012] S5: blast the tunnel in sections and sections according to the blasting sequence of S2;

[0013] S6: Clean up the rubble after tunnel blasting and complete the tunnel blasting;

[0014] The digital electronic detonator in this embodiment adopts a fully parallel network circuit. According to the requirements of the manufacturer, a special detonator is used to program the network according to a certain procedure. The authorization code is downloaded through a password, and the detonation is sequentially performed according to the detonation sequence designed in the blasting hole layout diagram. The delay and micro-difference time of the digital electronic detonator are key factors that determine the micro-difference blasting effect. Reasonable micro-difference interval time can effectively break the rock and reduce the blasting vibration effect. However, due to the complexity of the blasting process and the complexity of the rock mass, there is still no unified standard for the selection of micro-difference interval time. Since the propagation of seismic waves is affected by many factors, it is difficult to obtain an accurate seismic wave period through simple calculation in actual engineering. The seismic wave propagation period measured by the blasting vibration instrument in this project is 13.8ms, and the half period is 7ms. When the delay time between blast holes is set to half a period, the peaks and troughs of two adjacent blasting seismic waves can be superimposed and vibration-reduced. Therefore, the micro-difference time of the slot hole is set to 7ms; the auxiliary hole interval time is 11ms, and the peripheral hole interval time is 3ms, so that the rock is effectively broken and the blasting vibration is reduced at the same time.

[0015] Preferably, after the excavation of the upper section I, the lower section II, the upper section III and the lower section IV of the guide tunnel is completed, support is carried out in time; the section distance between the upper section I and the lower section II is greater than or equal to 10m, and the longitudinal distance between the upper section I and the upper section III, and between the lower section II and the lower section IV is greater than or equal to 20m; the section distance between the lower section II and the lower section IV is greater than or equal to 10m; the tunnel section is excavated into four separated parts and blasting is carried out in sections and zones, thereby reducing the vibration generated during blasting; at the same time, the intervals opened effectively isolate the impact of blasting on other parts, thereby improving the safety of blasting and reducing the impact on surrounding roads.

[0016] Preferably, the distance between the shock-absorbing ditch and the highway is greater than or equal to 10m, the excavation depth of the shock-absorbing ditch is 1m, and the cross-section of the shock-absorbing ditch is arc-shaped, the cross-section of the shock-absorbing ditch is plastered with cement concrete, and the thickness of the plastering is 3cm, the bottom surface of the shock-absorbing ditch is paved with glass fiber needle felt, the top surface of the glass fiber needle felt is paved with spring shock absorbers, and the top of the spring shock absorbers is covered with waterproof membrane and ordinary sand in turn; the cross-section of the shock-absorbing ditch is set to an arc-shaped section because the arc-shaped section can reflect a part of the seismic waves generated by the tunnel blasting to the ground and underground, thereby changing the propagation direction of the seismic waves generated by the tunnel blasting in the rock and soil, and the laid glass fiber needle felt effectively reduces the noise generated by the blasting; the spring shock absorber reduces the vibration transmission of the blasting, thereby further reducing the impact of the blasting on the surrounding roads.

[0017] Preferably, the water grinding drill comprises a body and a drill bit, the bottom end of the motor shaft of the body is bolted with the drill bit, a plurality of notches are arranged around the bottom surface of the drill bit, a crushing knife is rotatably installed inside the notch, a sliding hole is arranged on the middle top surface of the notch, the top end of the sliding hole passes through the top wall of the drill bit, a connecting rod is slidably installed inside the sliding hole, the bottom end of the connecting rod is rotatably connected to the top of the crushing knife, a plurality of the top ends of the connecting rods are fixedly connected with ring plates, the inner ring of the ring plates is sleeved on the top outer ring of the drill bit, and a plurality of push rods are slidably installed on the outer ring of the top wall of the drill bit , and the push rod passes through the top wall of the drill bit, the top of the push rod is fixedly connected to the bottom wall of the ring plate, and the bottom ends of the push rods are fixedly connected with push plates, the outer ring of the push plate is slidably matched with the inner wall of the drill bit, and the outer ring of the push rod is provided with a spring, and the two ends of the spring are respectively fixedly connected to the inner top surface of the drill bit and the top surface of the push plate; the cross-section of the crushing knife in this embodiment is crescent-shaped, and the top is arc-shaped; during operation, when it is necessary to blast and excavate the tunnel, in order to reduce the impact of the vibration generated during blasting on the surrounding roads, it is necessary to dig a shock-absorbing trench between the tunnel and the surrounding roads, and The tunnel is excavated in the mountainous wild area, and the depth and diameter of the shock-absorbing trench are small, which is not suitable for excavation by large equipment such as excavators. At the same time, the soil in the wild is relatively hard, and water-grinding drills are usually used for excavation. When excavating the shock-absorbing trench, the motor of the main body drives the drill bit to rotate, and the staff operates the drill bit to move downward. The drill bit drills holes on the contour line of the tunnel. When the drill bit drills into the ground, the soil column in the middle of the drill bit is close to the top wall inside the drill bit, pushing the push plate to slide upward, pushing the push rod to slide upward out of the top wall of the drill bit, compressing the spring, and pushing the push rod The ring plate moves upward, driving the connecting rod to slide upward along the sliding hole, driving the crushing knife to rotate in the slot, so that the blade of the crushing knife is close to the bottom of the soil column and squeezes it to cut off the bottom of the soil column; when the soil column is cut off, the staff operates the drill bit to move upward, so that the thrust on the push plate disappears, the spring resets, drives the push plate, push rod and ring plate to slide downward, and pushes the connecting rod to slide downward, so that the crushing knife turns into the inside of the slot and releases the soil column; thereby reducing the workload of the staff for knocking off the soil column in the later stage, and then improving the excavation efficiency of the shock-absorbing ditch.

[0018] Preferably, a groove is provided at the bottom of the crushing knife, and an expansion tooth is rotatably installed inside the groove. The outer ring of the rotating shaft of the expansion tooth is provided with a torsion spring, and the side of the expansion tooth close to the inside of the drill bit fits with the inner wall of the groove; when working, when the blade of the crushing knife approaches and squeezes the bottom of the soil column, the blade of the crushing knife cuts into the bottom of the soil column, so that the expansion tooth is inserted into the bottom of the soil column, and when the outer wall of the soil column is squeezed to the bending part of the expansion tooth, the expansion tooth is pushed to rotate inside the groove, so that the expansion tooth and the crushing knife open the incision of the soil column and cut off the soil column, thereby further improving the efficiency of cutting off the soil column.

[0019] Preferably, magnets are embedded in the interior of a side of the expansion tooth close to the interior of the drill bit and the interior of a side of the groove away from the interior of the drill bit, the magnets on both sides repel each other, a plurality of round rollers are rotatably installed on the bottom surface of the expansion tooth, a panel is fixedly connected to the bottom surface of the side of the expansion tooth close to the interior of the drill bit, and a side of the panel close to the round roller is horizontally aligned with the bottom surface of the round roller; during operation, when the expansion tooth slides into the incision of the soil column, the expansion tooth is squeezed and rotated, so that the magnets on both sides are close to each other, and the panel further opens the incision of the soil column, so that the incision of the soil column and the round roller slide in cooperation, which improves the smoothness of the expansion tooth sliding into the incision of the soil column, thereby improving the process of cutting off the soil column; when the expansion tooth moves out of the incision of the soil column, the magnets on both sides repel each other, pushing the expansion tooth to reset, so that the expansion tooth hits the inner wall of the groove, and concrete debris on the surface of the expansion tooth and the surface of the round roller is shaken off, thereby improving the surface cleanliness of the expansion tooth and the round roller.

[0020] Preferably, a serrated groove is provided on one side of the crushing cutter close to the inside of the drill bit; during operation, when the crushing cutter contacts the outer ring of the soil column, the drill bit drives the crushing cutter to rotate, and the side wall of the serrated groove slides and rubs against the outer ring of the soil column, thereby improving the efficiency of the crushing cutter cutting into the soil column.

[0021] Preferably, the inner ring and the outer ring bottom surfaces of the ring plate are both fixedly connected with elastic ring sheets, the bottom end of the elastic ring sheet is fixedly connected with the top surface of the drill bit, the top outer ring of the drill bit is fixedly connected with an annular oil tank, the outer ring of the annular oil tank is sleeved on the inner ring of the ring plate, and the interior of the annular oil tank is filled with lubricating oil, the top outer ring of the connecting rod is sleeved with a cylinder, the bottom surface of the cylinder is fixedly connected to the top surface of the drill bit, the top of the cylinder is provided with an annular groove, the bottom of the annular groove is connected to the interior of the cylinder, and an oil pipe is connected between the annular groove and the annular oil tank; during operation, the elastic ring sheet arranged at the same time isolates the connecting rod from the push rod to prevent external dust from falling onto the surface of the connecting rod and affecting the sliding of the connecting rod in the sliding hole; when the drill bit rotates, the annular oil tank generates centrifugal force, so that the internal lubricating oil flows to the oil pipe under the influence of the centrifugal force, the lubricating oil enters the interior of the annular groove through the oil pipe, and the lubricating oil flows to the surface of the connecting rod, thereby reducing the friction between the connecting rod and the remaining sliding holes, thereby improving the smoothness of the connecting rod when sliding.

[0022] Preferably, a tapered tube is fixedly connected to the outer ring of the bottom of the annular oil tank, the interior of the tapered tube is connected to the interior of the annular oil tank, the end of the tapered tube is connected to the oil pipe, and a plurality of groups of tapered rubber sheets are fixedly connected around the interior of the tapered tube; during operation, when the drill bit rotates, the annular oil tank generates centrifugal force, so that the lubricating oil inside flows toward the oil pipe under the influence of the centrifugal force, and the lubricating oil squeezes the tapered rubber sheet, so that the tapered rubber sheet is bent under the force, and the tapered tube is opened, so that the lubricating oil flows into the oil pipe; when the drill bit stops rotating, the pressure of the lubricating oil on the tapered rubber sheet is reduced, so that the tapered rubber sheet is reset, and the tapered tube is blocked and closed, thereby reducing the probability of the lubricating oil entering the oil pipe, thereby improving the utilization rate of the lubricating oil and reducing waste.

[0023] The beneficial effects of the present invention are as follows:

[0024] 1. The invention discloses a method for controlling shock absorption during blasting in tunnel construction adjacent to a highway. By adopting a method of zoning and segmenting blasting and utilizing the reasonable micro-difference interval time of digital electronic detonators, the rock can be effectively crushed while reducing blasting vibration. The excavated shock absorbing trench has an arc-shaped cross section, which can reflect a part of the seismic waves generated by the tunnel blasting to the ground and underground, and change the propagation direction of the seismic waves generated by the tunnel blasting in the rock and soil, thereby improving the safety of the blasting and reducing the impact on the surrounding highways.

[0025] 2. The method for controlling shock absorption during blasting during construction of a tunnel adjacent to a highway described in the present invention comprises the following steps: a main body, a drill bit, a crushing knife, a connecting rod, a ring plate, a push rod, a push plate and a spring are arranged; the soil column in the middle of the drill bit is close to the top wall inside the drill bit, and through the linkage of the push plate, the push rod and the ring plate, the connecting rod is driven to slide upward along the sliding hole, and the crushing knife is driven to rotate in the slot, so that the blade of the crushing knife approaches and squeezes the bottom of the soil column, and the bottom of the soil column is cut off; when the soil column is cut off, the drill bit moves upward, so that the thrust exerted on the push plate disappears, and the spring is reset, driving the push plate, the push rod, the ring plate and the connecting rod to slide downward and reset, so that the crushing knife is transferred into the inside of the slot to release the soil column; thereby reducing the workload of the staff for knocking off the soil column in the later stage, and thereby improving the excavation efficiency of the shock-absorbing ditch. BRIEF DESCRIPTION OF THE DRAWINGS

[0026] The present invention will be further described below in conjunction with the accompanying drawings.

[0027] Figure 1 is a three-dimensional diagram of the first embodiment of the present invention;

[0028] Figure 2 is a cross-sectional view of a drill bit according to an embodiment of the present invention;

[0029] Figure 3 yes Figure 2 A partial enlarged view of the middle part;

[0030] Figure 4 yes Figure 3 A partial enlarged view of point B in the middle;

[0031] Figure 5 yes Figure 2 A partial enlarged view of point C in the middle;

[0032] Figure 6 is a cross-sectional view of a cylinder according to a second embodiment of the present invention;

[0033] Figure 7 This is the hole arrangement diagram of the middle partition wall method blasting of the present invention;

[0034] Figure 8 It is a flow chart of the construction method of the present invention;

[0035] In the figure: 1, body; 2, drill bit; 3, notch; 4, crushing knife; 5, sliding hole; 6, connecting rod; 7, ring plate; 8, push rod; 9, push plate; 10, spring; 11, groove; 12, expansion tooth; 13, magnet; 14, round roller; 15, panel; 16, serrated groove; 17, elastic ring sheet; 18, annular oil tank; 19, cylinder; 20, ring groove; 21, oil pipe; 22, tapered pipe; 23, tapered rubber sheet; 24, cotton thread. DETAILED DESCRIPTION

[0036] In order to make the technical means, creative features, objectives and effects achieved by the present invention easy to understand, the present invention is further explained below in conjunction with specific implementation methods.

[0037] Embodiment 1

[0038] like Figures 7 and 8 As shown, a method for controlling blasting vibration reduction in tunnel construction adjacent to a highway according to an embodiment of the present invention, the blasting construction method comprises the following steps:

[0039] S1: Design blasting plan based on the concept of zoned and segmented blasting and use the middle partition wall method for construction;

[0040] S2: Design the blasting sequence and select the order of detonation of the sections: the upper section of the pilot tunnel I, the lower section of the pilot tunnel II, the upper section of the pilot tunnel III and the lower section of the pilot tunnel IV;

[0041] S3: Drill blast holes on the cross section according to the blast hole layout diagram, install digital electronic detonators inside the blast holes, and set the micro-difference blasting interval time;

[0042] S4: Arrange the shock-absorbing trench along the contour line of the tunnel excavation and use a water-grinding drill to excavate the shock-absorbing trench;

[0043] S5: blast the tunnel in sections and sections according to the blasting sequence of S2;

[0044] S6: Clean up the rubble after tunnel blasting and complete the tunnel blasting;

[0045] The digital electronic detonator in this embodiment adopts a fully parallel network circuit. According to the requirements of the manufacturer, a special detonator is used to program the network according to a certain procedure. The authorization code is downloaded through a password, and the detonation is sequentially performed according to the detonation sequence designed in the blasting hole layout diagram. The delay and micro-difference time of the digital electronic detonator are key factors that determine the micro-difference blasting effect. Reasonable micro-difference interval time can effectively break the rock and reduce the blasting vibration effect. However, due to the complexity of the blasting process and the complexity of the rock mass, there is still no unified standard for the selection of micro-difference interval time. Since the propagation of seismic waves is affected by many factors, it is difficult to obtain an accurate seismic wave period through simple calculation in actual engineering. The seismic wave propagation period measured by the blasting vibration instrument in this project is 13.8ms, and the half period is 7ms. When the delay time between blast holes is set to half a period, the peaks and troughs of two adjacent blasting seismic waves can be superimposed and vibration-reduced. Therefore, the micro-difference time of the slot hole is set to 7ms; the auxiliary hole interval time is 11ms, and the peripheral hole interval time is 3ms, so that the rock is effectively broken and the blasting vibration is reduced at the same time.

[0046] After the excavation of the upper section I, the lower section II, the upper section III and the lower section IV of the guide tunnel is completed, support is carried out in time; the section distance between the upper section I and the lower section II of the guide tunnel is greater than or equal to 10m, and the longitudinal distance between the upper section I and the upper section III of the guide tunnel, and between the lower section II and the lower section IV of the guide tunnel is greater than or equal to 20m; the section distance between the lower section II and the lower section IV of the guide tunnel is greater than or equal to 10m; the tunnel section is excavated into four separated parts and blasting is carried out in sections and zones, thereby reducing the vibration generated during blasting; at the same time, the intervals opened effectively isolate the impact of blasting on other parts, thereby improving the safety of blasting and reducing the impact on surrounding roads.

[0047] The distance between the shock-absorbing ditch and the highway is greater than or equal to 10m, the excavation depth of the shock-absorbing ditch is 1m, and the cross-section of the shock-absorbing ditch is arc-shaped. The cross-section of the shock-absorbing ditch is plastered with cement concrete, and the thickness of the plastering is 3cm. The bottom surface of the shock-absorbing ditch is paved with glass fiber needle felt, and the top surface of the glass fiber needle felt is paved with spring shock absorbers, and the top of the spring shock absorbers is covered with waterproof membrane and ordinary sand in turn; the cross-section of the shock-absorbing ditch is set to an arc-shaped section because the arc-shaped section can reflect a part of the seismic waves generated by the tunnel blasting to the ground and underground, thereby changing the propagation direction of the seismic waves generated by the tunnel blasting in the rock and soil, and the laid glass fiber needle felt effectively reduces the noise generated by the blasting; the spring shock absorber reduces the vibration transmission of the blasting, thereby further reducing the impact of the blasting on the surrounding roads.

[0048] like Figure 1 to Figure 2 As shown, the water grinding drill includes a body 1 and a drill bit 2, the drill bit 2 is bolted to the bottom end of the motor shaft of the body 1, a plurality of notches 3 are arranged around the bottom surface of the drill bit 2, a crushing knife 4 is rotatably installed inside the notch 3, a sliding hole 5 is arranged on the middle top surface of the notch 3, the top end of the sliding hole 5 passes through the top wall of the drill bit 2, a connecting rod 6 is slidably installed inside the sliding hole 5, the bottom end of the connecting rod 6 is rotatably connected to the top of the crushing knife 4, a plurality of ring plates 7 are fixed to the top ends of the connecting rods 6, the inner ring of the ring plate 7 is sleeved on the top outer ring of the drill bit 2, and a plurality of ring plates 7 are slidably installed on the outer ring of the top wall of the drill bit 2 A push rod 8 is provided, and the push rod 8 passes through the top wall of the drill bit 2. The top end of the push rod 8 is fixedly connected to the bottom wall of the ring plate 7. The bottom end of the push rod 8 is fixedly connected to a push plate 9. The outer ring of the push plate 9 is slidably matched with the inner wall of the drill bit 2. The outer ring of the push rod 8 is provided with a spring 10. The two ends of the spring 10 are respectively fixedly connected to the inner top surface of the drill bit 2 and the top surface of the push plate 9; the cross-section of the crushing knife 4 in this embodiment is crescent-shaped, and the top is arc-shaped; when working, when it is necessary to blast and excavate the tunnel, in order to reduce the impact of the vibration generated during blasting on the surrounding roads, it is necessary to excavate a reduction hole between the tunnel and the surrounding roads. The vibration-absorbing trench is used for digging tunnels in mountainous wild areas, and the depth and diameter of the vibration-absorbing trench are small, which is not suitable for digging by large equipment such as excavators. At the same time, the soil in the wild is relatively hard, and a water-grinding drill is usually used for digging. When digging the vibration-absorbing trench, the motor of the main body 1 drives the drill bit 2 to rotate, and the staff operates the drill bit 2 to move downward. The drill bit 2 drills holes on the contour line of the tunnel. When the drill bit 2 drills into the ground, the soil column in the middle of the drill bit 2 is close to the top wall inside the drill bit 2, pushing the push plate 9 to slide upward, pushing the push rod 8 to slide upward out of the top wall of the drill bit 2, so that the spring 10 is compressed, and the push rod 8 pushes The ring plate 7 moves upward, driving the connecting rod 6 to slide upward along the sliding hole 5, driving the crushing knife 4 to rotate in the slot 3, so that the blade of the crushing knife 4 is close to and squeezed to the bottom of the soil column, and the bottom of the soil column is cut off; when the soil column is cut off, the staff operates the drill bit 2 to move upward, so that the thrust on the push plate 9 disappears, the spring 10 resets, drives the push plate 9, the push rod 8 and the ring plate 7 to slide downward, and pushes the connecting rod 6 to slide downward, so that the crushing knife 4 is rotated into the inside of the slot 3, and the soil column is released; thereby reducing the workload of the staff for knocking off the soil column in the later stage, thereby improving the excavation efficiency of the shock-absorbing ditch.

[0049] like Figure 3As shown, a groove 11 is provided at the bottom of the crushing knife 4, and an expansion tooth 12 is rotatably installed inside the groove 11. The outer ring of the rotating shaft of the expansion tooth 12 is provided with a torsion spring, and the side of the expansion tooth 12 close to the inside of the drill bit 2 fits with the inner wall of the groove 11; when working, when the blade of the crushing knife 4 approaches and squeezes the bottom of the soil column, the blade of the crushing knife 4 cuts into the bottom of the soil column, so that the expansion tooth 12 is inserted into the bottom of the soil column. When the outer wall of the soil column is squeezed to the bending part of the expansion tooth 12, the expansion tooth 12 is pushed to rotate inside the groove 11, so that the expansion tooth 12 and the crushing knife 4 open the cut of the soil column and cut off the soil column, thereby further improving the efficiency of cutting off the soil column.

[0050] like Figure 3 to Figure 4 As shown, the inside of the side of the expansion tooth 12 close to the inside of the drill bit 2 and the inside of the side of the groove 11 away from the inside of the drill bit 2 are both inlaid with magnets 13, and the magnets 13 on both sides repel each other. A plurality of round rollers 14 are rotatably installed on the bottom surface of the expansion tooth 12, and a panel 15 is fixedly connected to the bottom surface of the side of the expansion tooth 12 close to the inside of the drill bit 2, and a side of the panel 15 close to the round roller 14 is horizontally aligned with the bottom surface of the round roller 14; when working, when the expansion tooth 12 slides into the cutout of the soil column, the expansion tooth 12 is squeezed and rotated, so that the magnets on both sides 13 are close to each other, and the panel 15 further expands the incision of the soil column, so that the incision of the soil column and the round roller 14 are slidably matched, which improves the smoothness of the expansion tooth 12 sliding into the incision of the soil column, thereby improving the flow of cutting the soil column; when the expansion tooth 12 moves out of the incision of the soil column, the magnets 13 on both sides repel each other, pushing the expansion tooth 12 to reset, so that the expansion tooth 12 hits the inner wall of the groove 11, and shakes off the concrete debris on the surface of the expansion tooth 12 and the surface of the round roller 14, thereby improving the surface cleanliness of the expansion tooth 12 and the round roller 14.

[0051] like Figures 2 to 3 As shown, a serrated groove 16 is provided on one side of the crushing knife 4 close to the inside of the drill bit 2; during operation, when the crushing knife 4 contacts the outer ring of the soil column, the drill bit 2 drives the crushing knife 4 to rotate, and the side wall of the serrated groove 16 slides and rubs against the outer ring of the soil column, thereby improving the efficiency of the crushing knife 4 cutting into the soil column.

[0052] like Figure 5As shown, the inner and outer ring bottom surfaces of the ring plate 7 are fixedly connected with elastic ring sheets 17, the bottom end of the elastic ring sheet 17 is fixedly connected to the top surface of the drill bit 2, the top outer ring of the drill bit 2 is fixedly connected with an annular oil tank 18, the outer ring of the annular oil tank 18 is sleeved on the inner ring of the ring plate 7, the interior of the annular oil tank 18 is filled with lubricating oil, the top outer ring of the connecting rod 6 is sleeved with a cylinder 19, the bottom surface of the cylinder 19 is fixedly connected to the top surface of the drill bit 2, the top of the cylinder 19 is provided with an annular groove 20, the bottom of the annular groove 20 is connected to the interior of the cylinder 19, and the annular groove 20 An oil pipe 21 is connected to the annular oil tank 18; during operation, the elastic ring sheet 17 is arranged to isolate the connecting rod 6 from the push rod 8 to prevent external dust from falling onto the surface of the connecting rod 6 and affecting the sliding of the connecting rod 6 in the sliding hole 5; when the drill bit 2 rotates, the annular oil tank 18 generates centrifugal force, so that the internal lubricating oil flows toward the oil pipe 21 under the influence of the centrifugal force, and the lubricating oil enters the inside of the annular groove 20 through the oil pipe 21, and the lubricating oil flows to the surface of the connecting rod 6, reducing the friction between the connecting rod 6 and the sliding hole 5, thereby improving the smoothness of the connecting rod 6 when sliding.

[0053] like Figure 5 As shown, a conical tube 22 is fixedly connected to the bottom outer ring of the annular oil tank 18, the interior of the conical tube 22 is connected to the interior of the annular oil tank 18, the end of the conical tube 22 is connected to the oil pipe 21, and a plurality of groups of conical rubber sheets 23 are fixedly connected around the interior of the conical tube 22; during operation, when the drill bit 2 rotates, the annular oil tank 18 generates centrifugal force, so that the lubricating oil inside flows to the oil pipe 21 under the influence of the centrifugal force, and the lubricating oil squeezes the conical rubber sheet 23, so that the conical rubber sheet 23 is bent by the force, and the conical tube 22 is opened, so that the lubricating oil flows into the oil pipe 21; when the drill bit 2 stops rotating, the pressure of the lubricating oil on the conical rubber sheet 23 is reduced, so that the conical rubber sheet 23 is reset, and the conical tube 22 is blocked and closed, thereby reducing the probability of the lubricating oil entering the oil pipe 21, thereby improving the utilization rate of the lubricating oil and reducing waste.

[0054] Embodiment 2

[0055] like Figure 6 As shown, compared with Example 1, another embodiment of the present invention is: a plurality of cotton threads 24 are fixedly connected to the inner wall of the cylinder 19, and the cotton threads 24 slide with the outer wall of the connecting rod 6; during operation, when the lubricating oil flows into the inside of the cylinder 19, the lubricating oil wets the cotton threads 24, and the cotton threads 24 insert the lubricating oil teeth into the top of the connecting rod 6, so that the lubricating oil teeth are inserted and slide to wet the entire connecting rod 6, thereby further improving the sliding smoothness of the connecting rod 6.

[0056] During work: when digging the shock-absorbing ditch, the motor of the body 1 drives the drill bit 2 to rotate, and the staff operates the drill bit 2 to move downward. The drill bit 2 drills and excavates on the contour line of the tunnel. When the drill bit 2 reaches the bottom, the soil column in the middle of the drill bit 2 is close to the top wall inside the drill bit 2, pushing the push plate 9 to slide upward, pushing the push rod 8 to slide upward out of the top wall of the drill bit 2, so that the spring 10 is compressed, and the push rod 8 pushes the ring plate 7 to move upward, driving the connecting rod 6 to slide upward along the sliding hole 5, driving the crushing knife 4 to rotate in the notch 3, so that the blade of the crushing knife 4 is close to the bottom of the soil column and squeezed. When the blade of the crushing knife 4 cuts into the bottom of the soil column, the expansion tooth 12 is inserted into the bottom of the soil column. When the outer wall of the soil column is squeezed to the bending part of the expansion tooth 12, the expansion tooth 12 is pushed to rotate inside the groove 11, so that the expansion tooth 12 and the crushing knife 4 open the cut of the soil column and cut off the bottom of the soil column.

[0057] At the same time, when the drill bit 2 rotates, the annular oil tank 18 generates centrifugal force, so that the lubricating oil inside is affected by the centrifugal force and flows to the oil pipe 21, and the lubricating oil squeezes the conical rubber sheet 23, so that the conical rubber sheet 23 is bent by force, and the conical tube 22 is opened, so that the lubricating oil flows into the oil pipe 21, and the lubricating oil enters the inside of the annular groove 20 through the oil pipe 21, and the lubricating oil flows to the surface of the connecting rod 6, reducing the friction between the connecting rod 6 and the sliding hole 5, thereby improving the smoothness of the connecting rod 6 when sliding;

[0058] When the soil column is cut off, the staff operates the drill bit 2 to move upward, so that the thrust on the push plate 9 disappears, the spring 10 resets, drives the push plate 9, the push rod 8 and the ring plate 7 to slide downward, and pushes the connecting rod 6 to slide downward, so that the crushing knife 4 turns into the inside of the groove 3, and the soil column is released; thereby reducing the workload of the staff for breaking the soil column in the later stage, and then improving the excavation efficiency of the shock-absorbing ditch.

[0059] The above-mentioned front, back, left, right, top and bottom are all based on the figures in the specification. Figure 1 As a benchmark, according to the person's observation perspective, the side of the device facing the observer is defined as the front, the left side of the observer is defined as the left, and so on.

[0060] In the description of the present invention, it should be understood that the terms "center", "longitudinal", "lateral", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as limiting the scope of protection of the present invention.

[0061] The above shows and describes the basic principles, main features and advantages of the present invention. It should be understood by those skilled in the art that the present invention is not limited to the above embodiments. The above embodiments and descriptions are only for explaining the principles of the present invention. Without departing from the spirit and scope of the present invention, the present invention may have various changes and improvements, which fall within the scope of the present invention. The scope of protection of the present invention is defined by the attached claims and their equivalents.

Claims

1. A method for controlling blasting shock during construction of a tunnel adjacent to a highway, characterized in that: The blasting construction method includes the following steps: S1: Design blasting plan based on the concept of zoned and segmented blasting and use the middle partition wall method; S2: Design the blasting sequence, and select the order of detonation of the sections: the upper half section of the pilot tunnel I, the lower half section of the pilot tunnel II, the upper half section of the pilot tunnel III and the lower half section of the pilot tunnel IV; S3: Drill blast holes on the cross section according to the blast hole layout diagram, install digital electronic detonators inside the blast holes, and set the micro-difference blasting interval time; S4: Arrange the shock-absorbing trench along the contour line of the tunnel excavation and use a water-grinding drill to excavate the shock-absorbing trench; S5: blast the tunnel in sections and sections according to the blasting sequence of S2; S6: Clean up the rubble after tunnel blasting and complete the tunnel blasting; The water-grinding drill comprises a body (1) and a drill bit (2), the drill bit (2) being bolted to the bottom end of the motor shaft of the body (1), a plurality of notches (3) being arranged around the bottom surface of the drill bit (2), a crushing knife (4) being rotatably mounted inside the notch (3), a sliding hole (5) being arranged on the top surface of the middle portion of the notch (3), the top end of the sliding hole (5) penetrating the top wall of the drill bit (2), a connecting rod (6) being slidably mounted inside the sliding hole (5), the bottom end of the connecting rod (6) being rotatably connected to the top of the crushing knife (4), and a plurality of ring plates being fixedly connected to the top ends of the connecting rods (6). (7), the inner ring of the ring plate (7) is sleeved on the top outer ring of the drill bit (2), a plurality of push rods (8) are slidably mounted on the outer ring of the top wall of the drill bit (2), and the push rods (8) penetrate the top wall of the drill bit (2), the top ends of the push rods (8) are fixedly connected to the bottom wall of the ring plate (7), the bottom ends of the plurality of push rods (8) are fixedly connected to a push plate (9), the outer ring of the push plate (9) is slidably matched with the inner wall of the drill bit (2), the outer ring of the push rod (8) is sleeved with a spring (10), and the two ends of the spring (10) are respectively fixedly connected to the inner top surface of the drill bit (2) and the top surface of the push plate (9); The bottom of the crushing knife (4) is provided with a groove (11), an expansion tooth (12) is rotatably mounted inside the groove (11), a torsion spring is arranged on the outer ring of the rotating shaft of the expansion tooth (12), and a side of the expansion tooth (12) close to the inside of the drill bit (2) is in contact with the inner wall of the groove (11); The inside of the side of the expansion tooth (12) close to the inside of the drill bit (2) and the inside of the side of the groove (11) away from the inside of the drill bit (2) are both inlaid with magnets (13), and the magnets (13) on both sides repel each other. A plurality of round rollers (14) are rotatably mounted on the bottom surface of the expansion tooth (12). A panel (15) is fixedly connected to the bottom surface of the side of the expansion tooth (12) close to the inside of the drill bit (2), and a side of the panel (15) close to the round roller (14) is horizontally aligned with the bottom surface of the round roller (14); A sawtooth groove (16) is formed on one side of the crushing knife (4) close to the inside of the drill bit (2).

2. The method for controlling blasting shock absorption during construction of a tunnel adjacent to a highway according to claim 1, characterized in that: After the excavation of the upper section I of the guide tunnel, the lower section II of the guide tunnel, the upper section III of the guide tunnel and the lower section IV of the guide tunnel are completed, support shall be carried out in time; the section distance between the upper section I of the guide tunnel and the lower section II of the guide tunnel is greater than or equal to 10m, and the longitudinal distance between the upper section I of the guide tunnel and the upper section III of the guide tunnel, and between the lower section II of the guide tunnel and the lower section IV of the guide tunnel is greater than or equal to 20m.

3. The method for controlling blasting shock absorption during construction of a tunnel adjacent to a highway according to claim 1, characterized in that: The distance between the shock-absorbing ditch and the highway is greater than or equal to 10m, the excavation depth of the shock-absorbing ditch is 1m, and the cross-section of the shock-absorbing ditch is arc-shaped. The cross-section of the shock-absorbing ditch is plastered with cement concrete, and the thickness of the plastering is 3cm. The bottom surface of the shock-absorbing ditch is paved with glass fiber needle felt, and the top surface of the glass fiber needle felt is paved with spring shock absorbers. The top of the spring shock absorber is covered with waterproof membrane and ordinary sand in turn.

4. The method for controlling blasting shock absorption during construction of a tunnel adjacent to a highway according to claim 1, characterized in that: The inner and outer ring bottom surfaces of the ring plate (7) are both fixedly connected with elastic ring sheets (17), the bottom end of the elastic ring sheet (17) is fixedly connected with the top surface of the drill bit (2), the top outer ring of the drill bit (2) is fixedly connected with an annular oil tank (18), the outer ring of the annular oil tank (18) is sleeved on the inner ring of the ring plate (7), the interior of the annular oil tank (18) is filled with lubricating oil, the top outer ring of the connecting rod (6) is sleeved with a cylinder (19), the bottom surface of the cylinder (19) is fixedly connected to the top surface of the drill bit (2), the top of the cylinder (19) is provided with an annular groove (20), the bottom of the annular groove (20) is connected to the interior of the cylinder (19), and an oil pipe (21) is connected between the annular groove (20) and the annular oil tank (18).

5. The method for controlling blasting shock absorption during construction of a tunnel adjacent to a highway according to claim 4, characterized in that: A conical tube (22) is fixedly connected to the outer ring of the bottom of the annular oil tank (18); the interior of the conical tube (22) is connected to the interior of the annular oil tank (18); the end of the conical tube (22) is connected to the oil pipe (21); and a plurality of groups of conical rubber sheets (23) are fixedly connected around the interior of the conical tube (22).

6. The method for controlling blasting shock absorption during construction of a tunnel adjacent to a highway according to claim 5, characterized in that: A plurality of cotton threads (24) are fixedly connected to the inner wall of the cylinder (19), and the cotton threads (24) are slidably engaged with the outer wall of the connecting rod (6).