Column installation auxiliary tooling and column installation method
By designing auxiliary tooling for column installation and utilizing a combination of universal wheels and switch magnets, the column can be quickly positioned and installed vertically, solving the problem of difficulty in ensuring the verticality of the column, shortening the installation time, reducing welding marks, and improving production efficiency.
Patent Information
- Application Number
- CN202310503725.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-05-06
- Publication Date
- 2025-09-19
- Estimated Expiration
- 2043-05-06
AI Technical Summary
When installing the columns on a roll-on/roll-off ship, verticality is difficult to ensure, resulting in a long lifting time and the need for temporary welding of diagonal braces for storage, which increases the number of processes and welding traces, affecting production efficiency.
A column installation auxiliary tooling is designed, which includes a U-shaped mounting part, a universal wheel and a switch magnet. After the universal wheel is moved to a preset position, the switch magnet adsorbs the deck, and the column enters from the tooling opening. After the bottom is positioned, the verticality is adjusted on the operating platform, eliminating the need for diagonal bracing.
The columns can be quickly positioned and installed vertically, which shortens the installation time of the entire dock, reduces dependence on crane accuracy, avoids welding marks, and improves installation efficiency.
Smart Images

Figure CN116424518B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of ships, and in particular to a column installation auxiliary tool and a column installation method. Background Art
[0002] There are over 300 decks on a RoRo ship, including both fixed and movable decks. To ensure deck height and facilitate installation, numerous columns are installed between adjacent decks. The verticality of the columns is crucial, and guide slots are provided on the sides of the columns. During installation, the decks enter through these slots and slide down to their installation positions. Due to the large size of the decks, and the fact that each deck is equipped with at least four columns for simultaneous guidance, any deviation from the verticality of the columns can prevent the decks from being lowered. Therefore, to ensure verticality, the cranes used for hoisting the columns have poor operating precision, resulting in extremely long hoisting times. This extends the platform assembly and docking period, impacting the normal operation of the RoRo ship. Furthermore, because the columns are shipped in batches, diagonal braces are often welded onboard to store the columns before installation due to a lack of suitable storage space. After the columns are installed, the diagonal braces are removed, leaving numerous weld marks on the hull, commonly known as "stubs," which require subsequent polishing, adding unnecessary processing steps.
[0003] Therefore, it is urgent to design a column installation auxiliary tooling and a column installation method to solve the above problems. Summary of the Invention
[0004] One purpose of the present invention is to provide a column installation auxiliary tool that can quickly position and install the column to be vertical, and can be used to install columns at multiple column installation positions on the same floor, eliminating the need for diagonal bracing and shortening the installation time of the entire dock.
[0005] To achieve this object, the present invention adopts the following technical solutions:
[0006] Column installation auxiliary tooling, including:
[0007] A base comprising a U-shaped mounting member, universal wheels, and a switch magnet. The universal wheels are mounted on the four corners of the U-shaped mounting member. The relative positions of the universal wheels and the U-shaped mounting member in the vertical direction are adjustable. The switch magnets are mounted on the four corners of the U-shaped mounting member.
[0008] A U-shaped frame is vertically mounted on the upper side of the U-shaped mounting member;
[0009] The U-shaped operating platform is installed on the upper end of the U-shaped frame.
[0010] Optionally, the universal wheel is connected to the U-shaped mounting member via a stud.
[0011] Optionally, the U-shaped frame is divided into a first frame with a height of H1, a second frame with a height of H2 and a third frame with a height of H3. The first frame and the second frame are stacked to form a third frame, H3=H1+H2, and the column installation auxiliary tooling is assembled using any one of the first frame, the second frame and the third frame.
[0012] Optionally, the base further includes a reinforcing plate, and the four corners of the U-shaped frame are correspondingly mounted with the reinforcing plate, one end of the reinforcing plate is mounted on the U-shaped mounting piece, and the other end is connected to the corner of the U-shaped frame.
[0013] Optionally, the U-shaped operating platform includes a horizontal plate and a reinforcing vertical plate, the reinforcing vertical plate is installed on the lower side of the horizontal plate, and the U-shaped frame is connected to the horizontal plate.
[0014] Optionally, the column installation auxiliary tooling further includes a railing and a ladder, the railing is U-shaped and is installed on the outer periphery of the U-shaped operating platform, and the ladder can lead to the U-shaped operating platform.
[0015] Another object of the present invention is to provide a column installation method that can quickly position and install the column to be vertical, and can be used to install columns at multiple column installation positions on the same floor, eliminating the need for diagonal bracing and shortening the installation time of the entire dock.
[0016] To achieve this object, the present invention adopts the following technical solutions:
[0017] The column installation method uses the above-mentioned column installation auxiliary tooling, and the above-mentioned column installation method includes:
[0018] S1: Push the column installation auxiliary tooling to a preset position, adjust the universal wheel upward relative to the U-shaped mounting piece to separate it from the deck, and turn on the switch magnet so that the switch magnet is attracted to the deck;
[0019] S2: Hoist the column so that the column enters through the opening of the column installation auxiliary tooling;
[0020] S3: Aligning and positioning the bottom of the column, welding two backrest components on the bottom positioning plate, so that the two adjacent sides of the bottom of the column respectively abut against the two backrest components, and then welding two more backrest components on the bottom positioning plate so that the backrest components respectively abut against the remaining two sides of the bottom of the column;
[0021] S4: measuring the verticality of the column on the U-shaped operating platform and adjusting the upper end position of the column to adjust the column to a vertical position;
[0022] S5: Welding a support plate on the U-shaped operating platform to clamp the upper end of the column, and tack welding the four sides of the bottom of the column to the corresponding support assembly;
[0023] S6: Check the verticality of the columns again. If they meet the accuracy standards, remove the support plate on the U-shaped operating platform.
[0024] S7: Turn off the switch magnet, adjust the universal wheel downward so that the universal wheel contacts the deck, the switch magnet is released, and the column installation auxiliary tooling is pushed on the deck to the installation position of the next column.
[0025] Optionally, between the above S2 and the above S3, there is included S21: installing a limiting member at the opening position of the above U-shaped operating platform to close the above opening position; between the above S6 and the above S7, there is included S61: removing the above limiting member.
[0026] Optionally, in the above S4, a plumb bob is used to measure the verticality of the above-mentioned column, and a jack or a flower basket is fixed to the side of the above-mentioned U-shaped operating platform so that the free end of the above-mentioned jack or the above-mentioned flower basket abuts against the side of the above-mentioned column to adjust the verticality of the above-mentioned column.
[0027] Optionally, in the above S5, a slope is provided on one end of the backer in the backer assembly facing the side surface of the column, and the side surface of the column and the slope are fixed by full penetration welding.
[0028] The beneficial effects of the present invention are:
[0029] The present invention provides a column installation auxiliary tool. A universal wheel and a switch magnet are installed on a U-shaped installation part. After the column installation auxiliary tool is moved to a position to be installed by moving the universal wheel, the universal wheel is adjusted to rise so that the switch magnet is adsorbed on the deck. The column enters from an opening of the column installation auxiliary tool for rough positioning. After the bottom of the column is positioned, the U-shaped operating platform facilitates the verticality adjustment of the top of the column, and the column is quickly positioned and installed to be vertical. The column can be installed at multiple column installation positions on the same layer, eliminating the need for setting diagonal braces and shortening the installation time of the entire dock.
[0030] The present invention also provides a column installation method, by adopting the above-mentioned column installation auxiliary tooling, after the universal wheel drives the column installation auxiliary tooling to a preset position, the universal wheel is adjusted upward so that the switch magnet is adsorbed on the deck, which can not only stably install at the preset position but also realize switching of multiple installation positions; after the column is hoisted and enters from the opening of the column installation auxiliary tooling, the bottom falls to the positioning position, and after the side of the column abuts the backrest, the overall verticality of the column is measured on the U-shaped operating platform. The operating platform is convenient for adjusting the top on the premise that the bottom of the column is positioned to ensure that the overall verticality of the column is qualified, and then the bottom is welded to the backrest, and the top is welded to the back plate. After stabilization, the verticality is measured again, the back plate is removed, and the installation auxiliary tooling is moved to the next positioning position. During the entire process, the column installation auxiliary tooling first gives the column a rough positioning, and the U-shaped operating platform provides a base point for vertical adjustment, reducing the dependence on the crane during vertical adjustment, avoiding the situation where the crane adjustment accuracy is poor and needs repeated adjustment, and improving the speed of column vertical adjustment. It can also be used to install columns in multiple column installation positions, eliminating the need for the setting of diagonal braces and shortening the installation time of the entire dock. BRIEF DESCRIPTION OF THE DRAWINGS
[0031] Figure 1 Schematic diagram of the structure of the column installation auxiliary tooling provided by an embodiment of the present invention;
[0032] Figure 2 is a structural schematic diagram of a base provided by an embodiment of the present invention;
[0033] Figure 3 It is a structural schematic diagram of a U-shaped operating platform provided by an embodiment of the present invention;
[0034] Figure 4 It is a structural schematic diagram of a U-shaped frame provided by an embodiment of the present invention;
[0035] Figure 5 It is a structural schematic diagram of the column and backrest assembly provided by an embodiment of the present invention.
[0036] In the picture:
[0037] 10. Base; 11. U-shaped mounting member; 111. Main body; 112. Protrusion; 12. Universal wheel; 13. Switch magnet; 14. Reinforcement plate; 15. Stud;
[0038] 20. U-shaped frame; 21. First frame; 22. Second frame; 23. Third frame;
[0039] 30. U-shaped operating platform; 31. Horizontal plate; 32. Reinforced vertical plate;
[0040] 40. Railing; 50. Ladder; 200. Column; 210. Backrest assembly; 211. Backrest; 2111. Inclined surface. DETAILED DESCRIPTION
[0041] The present invention will be further described in detail below with reference to the accompanying drawings and examples. It will be understood that the specific embodiments described herein are intended only to illustrate the present invention and are not intended to limit the present invention. It should also be noted that, for ease of description, the accompanying drawings only illustrate portions relevant to the present invention, not all structures.
[0042] In the description of the present invention, unless otherwise expressly specified or limited, the terms "connected," "connected," and "fixed" should be understood in a broad sense. For example, they may refer to fixed connections, detachable connections, or integration; mechanical connections or electrical connections; direct connections or indirect connections through an intermediate medium; and internal communication between two components or interaction between two components. Those skilled in the art will understand the specific meanings of the above terms in the present invention in specific circumstances.
[0043] In the present invention, unless otherwise expressly specified or limited, a first feature being "above" or "below" a second feature may include the first and second features being in direct contact, or may include the first and second features being in contact not directly but through another feature between them. Furthermore, a first feature being "above," "above," and "above" a second feature may include the first feature being directly above or obliquely above the second feature, or may simply mean that the first feature is higher in level than the second feature. A first feature being "below," "below," and "below" a second feature may include the first feature being directly below or obliquely below the second feature, or may simply mean that the first feature is lower in level than the second feature.
[0044] In the description of this embodiment, terms such as "upper," "lower," "left," and "right" are used to refer to positions or locations based on those shown in the accompanying drawings. These terms are intended solely to facilitate description and simplify operation, and are not intended to indicate or imply that the devices or components referred to must have, be constructed, or operate in a specific orientation. Therefore, they should not be construed as limitations on the present invention. Furthermore, the terms "first" and "second" are used solely for descriptive purposes and have no special meaning.
[0045] This embodiment provides a column installation auxiliary tool, which can quickly position and install the column 200 to a vertical state, and can be used to install columns 200 at multiple column installation positions on the same layer, eliminating the need for diagonal bracing and shortening the installation time of the entire dock. Figure 1 and Figure 2As shown, the column installation auxiliary tooling includes a base 10, a U-shaped frame 20 and a U-shaped operating platform 30. The base 10 includes a U-shaped mounting part 11, a universal wheel 12 and a switch magnet 13. The four corners of the U-shaped mounting part 11 are equipped with universal wheels 12. The relative position of the universal wheel 12 and the U-shaped mounting part 11 in the vertical direction is adjustable. The four corners of the U-shaped mounting part 11 are equipped with switch magnets 13; the U-shaped frame 20 is installed on the upper side of the U-shaped mounting part 11 in the vertical direction; the U-shaped operating platform 30 is installed on the upper end of the U-shaped frame 20.
[0046] The column installation auxiliary tooling is implemented by installing a universal wheel 12 and a switch magnet 13 on a U-shaped mounting part 11. After the column installation auxiliary tooling is moved to the position to be installed by moving the universal wheel 12, the universal wheel 12 is adjusted to rise so that the switch magnet 13 is adsorbed onto the deck (the bottom deck is the inner bottom plate. As the decks are installed layer by layer, the bottom of the column 200 of the lower deck needs to be installed on the installed deck of the lower layer. The deck is a metal part). The column 200 enters from the opening of the column installation auxiliary tooling for rough positioning. After the bottom of the column 200 is positioned, the U-shaped operating platform 30 facilitates the vertical adjustment of the top of the column 200, quickly positioning and installing the column 200 to be vertical, and can be used to install the column 200 at multiple column installation positions on the same layer, eliminating the need for the setting of diagonal braces and shortening the installation time of the entire dock.
[0047] Alternatively, as Figure 2 As shown, the U-shaped mounting member 11 includes a main body 111 and a protrusion 112. The main body 111 is U-shaped, and the protrusions 112 are arranged along the four corners of the main body 111. The switch magnet 13 is mounted on the main body 111, and the universal wheel 12 is connected to the protrusion 112. This arrangement rationally arranges the positions of the universal wheel 12 and the switch magnet 13, providing a larger mounting surface. In other embodiments, the positions of the universal wheel 12 and the switch magnet 13 can be interchanged, which is not limited here.
[0048] Optionally, the universal wheel 12 is connected to the U-shaped mounting member 11 via a stud 15 , and the position of the universal wheel 12 relative to the U-shaped mounting member 11 in the vertical direction can be adjusted by screwing the stud 15 .
[0049] Preferably, if Figure 1 and Figure 2 As shown, the base 10 also includes reinforcement plates 14, mounted at each of the four corners of the U-shaped frame 20. One end of the reinforcement plate 14 is attached to the U-shaped mounting member 11, and the other end is connected to the corner of the U-shaped frame 20. This arrangement improves the mounting strength of the U-shaped frame 20. Specifically, the reinforcement plates 14 are mounted on the protrusions 112, spaced apart from the bolts. Optionally, the U-shaped frame 20 and the base 10 are connected by welding.
[0050] During the actual installation process of the columns 200, the height of the column installation auxiliary tooling will be made lower than the height of the columns 200 on that layer to ensure that the top of the column 200 is higher than the U-shaped operating platform 30 to play a limiting role. However, if the column 200 is too high, the height of the column installation auxiliary tooling needs to be changed to ensure that most of the columns 200 are roughly positioned to ensure stability. The height of each layer of columns 200 is different, and the height of the column installation auxiliary tooling used on different layers will also be different. In this embodiment, there are three heights of the column installation auxiliary tooling, and three U-shaped frames 20 with different heights need to be designed, which is more complicated to manufacture.
[0051] In order to solve the above problems, Figure 4 As shown, in this embodiment, the U-shaped frame 20 is divided into a first frame 21 with a height of H1, a second frame 22 with a height of H2, and a third frame 23 with a height of H3. The first frame 21 and the second frame 22 are stacked to form the third frame 23, where H3 = H1 + H2. The column installation auxiliary tooling can be assembled using any of the first frame 21, the second frame 22, and the third frame 23. With this arrangement, when manufacturing the U-shaped frame 20, only the first frame 21 and the second frame 22 need to be manufactured. The third frame 23 is connected by welding, eliminating the need to produce a separate frame. Optionally, the first frame 21 and the second frame 22 are both welded together using connecting rods.
[0052] Preferably, the U-shaped operating platform 30 includes a horizontal plate 31 and a reinforcing vertical plate 32. The reinforcing vertical plate 32 is installed on the lower side of the horizontal plate 31. The U-shaped frame 20 is connected to the horizontal plate 31. Through the above arrangement, the strength of the U-shaped operating platform 30 can be improved.
[0053] Preferably, the opening edges of the horizontal plate 31 are all provided with reinforcing vertical plates 32 , so that the area of the column 200 abutting against the side wall of the column 200 after entering the horizontal plate 31 is increased, thereby improving the stability of rough positioning.
[0054] Preferably, the column installation auxiliary tooling further includes a railing 40 and a ladder 50. The railing 40 is U-shaped and installed on the outer periphery of the U-shaped operating platform 30, and the ladder 50 can lead to the U-shaped operating platform 30. Through the above arrangement, it is convenient for operators to enter the U-shaped operating platform 30, and the railing 40 ensures the safety of the operators.
[0055] This embodiment also provides a column installation method. By using the above-mentioned column installation auxiliary tooling, the column 200 can be quickly positioned and installed vertically, and the column 200 can be installed at multiple column installation positions on the same layer, eliminating the need for the setting of diagonal braces and shortening the installation time of the entire dock.
[0056] The column installation method includes:
[0057] S1: Push the column installation auxiliary tooling to the preset position, adjust the universal wheel 12 upward relative to the U-shaped mounting member 11 to separate from the deck, and turn on the switch magnet 13 so that the switch magnet 13 is attracted to the deck. This step ensures that the entire column installation auxiliary tooling is firmly positioned.
[0058] S2: Hoist the column 200 so that the column 200 enters through the opening of the column installation auxiliary tooling;
[0059] S3: The bottom of the column 200 is aligned and positioned. Two support assemblies 210 are welded to the bottom positioning plate. The two adjacent sides of the bottom of the column 200 are respectively abutted against the two support assemblies 210. Two more support assemblies 210 are welded to the bottom positioning plate so that the support assemblies 210 respectively abut the remaining two sides of the bottom of the column 200. The bottom positioning plate is the part of the inner bottom plate or deck used to install the column 200. Its strength is higher than other parts of the inner bottom plate or deck. First, two support assemblies 210 are welded so that the two connected sides of the bottom of the column 200 are abutted in place. Then, two more support assemblies 210 are welded to limit the four sides of the bottom of the column 200. At this time, the four sides of the bottom of the column 200 are in abutment with the corresponding support assemblies 210 rather than in a connected state. Due to the high height of the column 200, when the verticality of the column 200 is subsequently adjusted at the top, the amount of fine-tuning can be guaranteed without damaging the support assemblies 210.
[0060] S4: Measure the verticality of the column 200 on the U-shaped operating platform 30 and adjust the upper end position of the column 200 to adjust the column 200 to a vertical position. In this embodiment, the verticality accuracy of the four sides of the column 200 is sufficient when it leaves the factory, so the verticality of only three sides needs to be measured.
[0061] S5: Weld a backing plate onto the U-shaped operating platform 30 to hold the upper end of the column 200 in place. The four sides of the bottom of the column 200 are tack welded to the corresponding backing assembly 210. This step is to secure the vertically adjusted column 200 in place and prevent it from shaking. The backing plate can be welded to a suitable location on the horizontal plate 31 or the reinforcing plate 32.
[0062] S6: Recheck the verticality of column 200. If it meets the accuracy standard, remove the support plate on U-shaped operating platform 30. Simply smash the support plate when removing it. If there are any holes on U-shaped operating platform 30, no action is required (just ensure there are no holes on column 200 or the deck).
[0063] S7: Turn off the switch magnet 13, adjust the universal wheel 12 downward, so that the universal wheel 12 contacts the deck, and the switch magnet 13 is lifted off. The column installation auxiliary tool is pushed on the deck to the installation position of the next column 200. This step realizes the sequential installation of columns 200 at different positions on the same floor.
[0064] The column 200 installation method adopts the above-mentioned column installation auxiliary tooling. After the universal wheel 12 drives the column installation auxiliary tooling to the preset position, the universal wheel 12 is adjusted upward so that the switch magnet 13 is adsorbed on the deck, which can not only stably install at the preset position but also realize switching of multiple installation positions; after the column 200 is hoisted and enters from the opening of the column installation auxiliary tooling, the bottom falls to the positioning position, and after the side of the column 200 abuts the backrest assembly 210, the overall verticality of the column 200 is measured on the U-shaped operating platform 30. The operating platform is convenient for adjusting the top on the premise that the bottom of the column 200 is positioned to ensure that the overall verticality of the column 200 is qualified, and then the bottom is welded to the backrest assembly 210 and the top is welded to the back plate. After stabilization, the verticality is measured again, the back plate is removed, and the installation auxiliary tooling is moved to the next positioning position. During the entire process, the column installation auxiliary tooling first gives the column 200 a rough positioning, and the U-shaped operating platform 30 provides a base point for the vertical adjustment, reducing the dependence on the crane during vertical adjustment, avoiding the situation where the crane adjustment accuracy is poor and needs repeated adjustment, and improving the speed of adjusting the verticality of the column 200. It can also be used to install the column 200 at multiple column installation positions, eliminating the need for the setting of diagonal braces and shortening the installation time of the entire dock.
[0065] Preferably, between S2 and S3, there is a step S21: installing a stopper at the opening of the U-shaped operating platform 30 to close the opening; and between S6 and S7, there is a step S61: removing the stopper. The above arrangement prevents the upright column 200 from tipping over toward the opening when inside the U-shaped operating platform 30, thereby improving safety.
[0066] Optionally, in S4, a plumb bob is used to measure the verticality of column 200. A jack or basket is secured to the side of the U-shaped operating platform 30 so that the free end of the jack or basket abuts the side of column 200 to adjust the verticality of column 200. A plumb bob is a common device for measuring verticality, and its use is not described here. The jack and basket allow for convenient adjustment of the top position of column 200. Optionally, the jack or basket is secured to the U-shaped operating platform 30 by welding.
[0067] like Figure 5As shown, in order to improve the stable connection between the backrest assembly 210 and the bottom of the column 200, the thickness of the backrest 211 in the backrest assembly 210 will be more than 15 mm. Ordinary welding cannot weld to the inside of the backrest assembly 210. After long-term use, if corrosion occurs, it will lead to a loose connection. In order to solve the above problem, in S5, the backrest 211 is provided with a bevel 2111 at one end facing the side of the column 200, and the side of the column 200 is fixed to the bevel 2111 by full penetration welding. The setting of the bevel 2111 can provide sufficient welding space for welding, ensuring that the two are fully welded at the welding section after welding, thereby improving the reliability of the connection between the two.
[0068] Preferably, if Figure 5 As shown, the backrest assembly 210 may include at least two backrests 211 to ensure the balance of the corresponding side connections of the column 200.
[0069] Obviously, the above embodiments of the present invention are merely examples for the purpose of clearly illustrating the present invention and are not intended to limit the embodiments of the present invention. A person skilled in the art would be able to make various obvious changes, readjustments, and substitutions without departing from the scope of protection of the present invention. It is not necessary and impossible to enumerate all embodiments here. Any modifications, equivalent substitutions, and improvements made within the spirit and principles of the present invention shall be included within the scope of protection of the claims of the present invention.
Claims
1. The column installation method is characterized in that: A column installation auxiliary tool is used, and the column installation auxiliary tool comprises: A base (10) comprises a U-shaped mounting member (11), a universal wheel (12) and a switch magnet (13), wherein the universal wheel (12) is mounted on each of the four corners of the U-shaped mounting member (11), the relative position of the universal wheel (12) and the U-shaped mounting member (11) in the vertical direction is adjustable, and the switch magnet (13) is mounted on each of the four corners of the U-shaped mounting member (11); A U-shaped frame (20) is mounted vertically on the upper side of the U-shaped mounting member (11); A U-shaped operating platform (30) is installed on the upper end of the U-shaped frame (20); The column installation method includes: S1: Push the column installation auxiliary tooling to a preset position, adjust the universal wheel (12) upward relative to the U-shaped installation member (11) to separate from the deck, and turn on the switch magnet (13) so that the switch magnet (13) is adsorbed on the deck; S2: hoisting the column (200) so that the column (200) enters through the opening of the column installation auxiliary tooling; S3: The bottom of the column (200) is aligned and positioned, and two backrest components (210) are welded on the bottom positioning plate, so that the adjacent two sides of the bottom of the column (200) are respectively abutted against the two backrest components (210), and then two backrest components (210) are welded on the bottom positioning plate so that the backrest components (210) are respectively abutted against the remaining two sides of the bottom of the column (200); S4: measuring the verticality of the column (200) on the U-shaped operating platform (30), and adjusting the upper end position of the column (200) so that the column (200) is adjusted to a vertical position; S5: Welding a backing plate on the U-shaped operating platform (30) to clamp the upper end of the column (200), and positioning welding the four sides of the bottom of the column (200) to the corresponding backing assembly (210); S6: Check the verticality of the column (200) again, and remove the support plate on the U-shaped operating platform (30) after it meets the accuracy standard; S7: Turn off the switch magnet (13), adjust the universal wheel (12) downward so that the universal wheel (12) contacts the deck, the switch magnet (13) is vacated, and the column installation auxiliary tooling is pushed on the deck to the installation position of the next column (200).
2. The column installation method according to claim 1, characterized in that: The universal wheel (12) is connected to the U-shaped mounting member (11) via a stud (15).
3. The column installation method according to claim 1, characterized in that: The U-shaped frame (20) is divided into a first frame (21) with a height of H1, a second frame (22) with a height of H2, and a third frame (23) with a height of H3. The first frame (21) and the second frame (22) are stacked to form the third frame (23), where H3 = H1 + H2. The column installation auxiliary tooling is assembled using any one of the first frame (21), the second frame (22), and the third frame (23).
4. The column installation method according to claim 1, characterized in that: The base (10) further comprises a reinforcing plate (14), and the four corners of the U-shaped frame (20) are correspondingly mounted with the reinforcing plate (14), one end of the reinforcing plate (14) is mounted on the U-shaped mounting member (11), and the other end is connected to the corner of the U-shaped frame (20).
5. The column installation method according to any one of claims 1 to 4, characterized in that: The U-shaped operating platform (30) comprises a horizontal plate (31) and a reinforcing vertical plate (32), wherein the reinforcing vertical plate (32) is installed on the lower side of the horizontal plate (31), and the U-shaped frame (20) is connected to the horizontal plate (31).
6. The column installation method according to any one of claims 1 to 4, characterized in that: The column installation auxiliary tool further comprises a handrail (40) and a ladder (50); the handrail (40) is U-shaped and is installed on the outer periphery of the U-shaped operating platform (30); and the ladder (50) can lead to the U-shaped operating platform (30).
7. The column installation method according to claim 1, characterized in that: The process between S2 and S3 includes S21: installing a limiting member at the opening of the U-shaped operating platform (30) to close the opening; and the process between S6 and S7 includes S61: removing the limiting member.
8. The column installation method according to claim 1, characterized in that: In S4, a plumb bob is used to measure the verticality of the column (200), and a jack or a flower basket is fixed to the side of the U-shaped operating platform (30) so that the free end of the jack or the flower basket abuts against the side of the column (200), thereby adjusting the verticality of the column (200).
9. The column installation method according to claim 1, characterized in that: In S5, a slope (2111) is provided on one end of the backrest (211) of the backrest assembly (210) facing the side of the column (200), and the side of the column (200) and the slope (2111) are fixed by full penetration welding.
Citation Information
Patent Citations
Tool vehicle for mounting solid-sealed polar pole
CN208986464U