Construction technology of exterior wall insulation metal integrated panel

The installation process of the metal insulation board is simplified by the rotating rod and clamping rod structure. Combined with foam glue and aerogel filling, the problems of complex installation and poor firmness in the existing technology are solved, and efficient and firm installation of the metal insulation board is achieved, and waterproof and moisture-proof protection is provided.

CN116657774BActive Publication Date: 2025-09-26ANHUI JUZHONG CONSTR GRP CO LTD
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202310342203.8
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-04-03
Publication Date
2025-09-26
Estimated Expiration
2043-04-03

AI Technical Summary

Technical Problem

The existing metal insulation panels require manual tightening of screws during installation, which increases the workload and difficulty, and the installation firmness is poor.

Method used

The rotating rod and the clamping rod structure are used to rotate in the groove of the metal plate. The clamping rod is driven by the rotating bar and the curved rod to insert into the grid plate slot, combined with the thermal insulation foam and elastic polyurethane aerogel filling, and finally fixed to the exterior wall with bolts.

Benefits of technology

It simplifies the installation process, improves efficiency and firmness, and provides waterproof and moisture-proof protection through the sealing cover.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN116657774B_ABST
    Figure CN116657774B_ABST
Patent Text Reader

Abstract

The present invention relates to a construction process for an external wall thermal insulation metal integrated panel, comprising the following steps: S1, placing an installation frame; S2, installing one of the metal plates on the installation frame; S3, fixing the metal plate on the installation frame; S4, filling with thermal insulation foam; S5, filling with elastic polyurethane aerogel; S6, fixing another metal plate on the installation frame by repeating step S3; S7, fixing the installation frame to the external wall; manually rotating a turning rod directly using a cross bar in a first groove on the metal plate, driving a clamping rod to be inserted into a first clamping groove on a grid plate through a turning bar and a curved rod, and then fixing the mounting frame to the external wall through bolts at four corners of the mounting frame, so that when installing the metal plate on the grid plate, the operation is simpler and more convenient, and while improving the installation work efficiency, the clamping rod increases the contact area between the grid plate and the grid plate, and the installation of the metal plate is also more secure.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of total stations, and in particular to a construction process for an external wall thermal insulation metal integrated panel. Background Art

[0002] Metal insulation integrated panel is a kind of exterior wall insulation decorative integrated panel, which is also composed of a finishing layer and an insulation layer. The reason why it is called metal insulation decorative integrated panel is mainly because its finishing layer uses metallic paint, and the metallic paint used in metal insulation decorative integrated panel is mainly fluorocarbon metallic paint, that is, metal powder is added to fluorocarbon paint;

[0003] At present, when installing the thermal insulation metal integrated panel on the outside, a grid-shaped metal sheet is laid on the exterior wall, and the metal thermal insulation panels are respectively fixed on the metal sheet with screws in sequence. In this way, during installation, each metal thermal insulation panel needs to be manually tightened with tools, which increases the workload of installing the metal thermal insulation panel and reduces the installation efficiency. In addition, the screws are large in size, which increases the installation difficulty during the tightening process and the installation firmness of the metal panel is also poor. Therefore, the installation process of the existing metal thermal insulation panel needs to be improved. Summary of the Invention

[0004] In order to solve the problems raised in the above background technology, the present invention provides a construction process for an exterior wall thermal insulation metal integrated panel.

[0005] The construction process of the exterior wall insulation metal integrated panel provided by the present invention adopts the following technical solutions:

[0006] The construction process of the exterior wall insulation metal integrated panel includes the following steps:

[0007] S1. Place the installation frame;

[0008] S2. Install one of the metal plates on the installation frame: Insert one of the metal plates into the installation frame;

[0009] S3. Fix the metal plate to the mounting frame by rotating the rotating rod on the I-shaped sleeve in the first groove of the metal plate, driving the rotating bar at one end of the rotating rod. The rotating bar is then rotated in the second groove of the mesh plate. The curved rods at both ends of the rotating bar push the two clamping rods into the first clamping grooves of the groove walls at both ends of the second groove.

[0010] S4, thermal insulation foam filling: fill thermal insulation foam between the installation frame, the grid plate and one of the metal plates;

[0011] S5. Elastic polyurethane aerogel filling: after the foam glue is dried, the elastic polyurethane aerogel is filled;

[0012] S6. Fix another metal plate on the mounting frame by repeating step S3;

[0013] S7. Fix the installation frame to the exterior wall by fastening the frame to the exterior wall with screws through the threaded holes at the four corners of the frame.

[0014] Preferably, after fixing the metal plate in step S3 and step S7, the insertion rod is pressed into the slot on the rotating rod to drive the cross bar to be inserted into the two limit blocks.

[0015] Preferably, in step S3 and step S7, after the rotating rod is limited, the sealing cover is inserted into the first groove.

[0016] Preferably, during the process of inserting the sealing cover, the card is driven to slide from the guide groove to the second card groove to clamp the sealing cover.

[0017] Preferably, the card is an elastic rubber sheet, and the inner groove wall of the guide groove is an inclined surface. When the sealing cover is inserted into the first groove, the card is smoothly clamped into the second card slot due to the guidance of the guide groove on the card and the elastic deformation ability of the card itself.

[0018] Preferably, the rotating rod and the inserting rod are both quadrilateral rods, and the limiting block is a U-shaped block.

[0019] Preferably, the outer diameter of the outer edge of the sealing cover is 1.3 times the inner diameter of the first groove.

[0020] Preferably, in step S1, the grid plate and the mounting frame are integrally formed.

[0021] Preferably, in step S1 , a mounting groove for inserting the metal plate is provided on the mounting frame, and the size of the mounting groove is the same as that of the metal plate.

[0022] Preferably, in step S3, the I-shaped sleeve movably passes through the groove wall of the first groove, and the rotating rod is fixed and passes through the middle of the I-shaped sleeve.

[0023] In summary, the present invention has the following beneficial technical effects:

[0024] The present invention inserts the metal plate into the installation frame, fills it with thermal insulation foam and elastic polyurethane aerogel, and then manually rotates the rotating rod directly in the first groove of the metal plate using a cross bar. The rotating bar and the curved rod drive the clamping rod to be inserted into the first clamping groove of the grid plate, and then the mounting frame can be fixed to the exterior wall by bolts at the four corners of the mounting frame. This makes it easier and more convenient to install the metal plate on the grid plate, improves the installation work efficiency, and increases the contact area between the clamping rod and the grid plate, making the installation of the metal plate more secure.

[0025] After the card rod is inserted into the card slot, the rod can be moved in the slot at the end of the rotating rod to drive the cross bar to be inserted into the two limit blocks, which plays a limiting role, making the metal plate more firmly fixed on the grid plate. At the same time, the cross bar can be used to easily rotate the rotating rod;

[0026] After the metal plate is installed, a sealing cover can be inserted into the first groove to play a waterproof and moisture-proof role to provide protection; when the sealing cover is inserted into the first groove, it drives the card to slide from the guide groove into the second card slot for clamping, thereby fixing the sealing cover in the first groove to improve the protection quality. BRIEF DESCRIPTION OF THE DRAWINGS

[0027] Figure 1 This is a structural diagram of a construction process for an integrated metal panel for exterior wall insulation according to an embodiment of the present invention;

[0028] Figure 2 This is an enlarged view of the structure at point A of the construction process of the external wall thermal insulation metal integrated panel in an embodiment of the present invention;

[0029] Figure 3 Schematic diagram of the internal structure of the installation frame of the exterior wall thermal insulation metal integrated panel construction process according to an embodiment of the present invention;

[0030] Figure 4 This is an enlarged view of the structure at point B of the construction process of the external wall thermal insulation metal integrated panel in an embodiment of the present invention;

[0031] Figure 5 This is a structural diagram of a metal plate after a sealing cover is installed on the metal plate in a construction process of an integrated metal plate for exterior wall insulation according to an embodiment of the present invention;

[0032] Figure 6 2. This is a structural diagram of the exterior wall thermal insulation metal integrated panel construction process after the sealing cover is pulled out in an embodiment of the present invention;

[0033] Figure 7 It is an enlarged view of the structure at point C of the construction process of the external wall insulation metal integrated panel in an embodiment of the present invention.

[0034] Explanation of the accompanying drawings: 1. Installation frame; 101. Insert rod; 102. Cross bar; 2. Metal plate; 201. Slot; 202. Limit block; 3. First groove; 301. Card; 302. Second card slot; 303. Guide groove; 4. Sealing cover; 5. Grid plate; 6. Rotating rod; 7. Second groove; 8. Rotating bar; 9. Curved rod; 10. Card rod; 11. First card slot; 12. I-shaped sleeve. Implementation Method

[0035] The following is combined with Figure 1-7 The present invention is described in further detail.

[0036] The embodiment of the present invention discloses a construction process for an external wall thermal insulation metal integrated panel. Figure 1-7 The construction process of the external wall insulation metal integrated panel includes the following steps:

[0037] S1. Place the installation frame 1 so that it is convenient for installing the metal plate 2. The mesh plate 5 and the installation frame 1 are integrally formed, which omits the installation process between the mesh plate 5 and the installation frame 1, thereby improving the installation efficiency of the integrated plate;

[0038] S2. Install one of the metal plates 2 on the mounting frame 1: Insert one of the metal plates 2 into the mounting frame 1. The mounting frame 1 has a mounting slot for inserting the metal plate 2. The size of the mounting slot is the same as the size of the metal plate 2. Inserting the metal plate 2 into the mounting slot with the same size can improve the installation quality of the metal plate 2 on the grid plate 5.

[0039] S3. Fix the metal plate 2 on the mounting frame 1 in the following manner: in the first groove 3 on the metal plate 2, the operator rotates the rotating rod 6 on the I-shaped sleeve 12 in the first groove 3, driving the rotating bar 8 at one end of the rotating rod 6. The I-shaped sleeve 12 moves through the groove wall of the first groove 3. The rotating rod 6 is fixed through the middle of the I-shaped sleeve 12. The I-shaped sleeve 12 can not only limit the rotating rod 6, but also will not hinder the normal rotation of the rotating rod 6. In the second groove 7 on the grid plate 5, the rotating bar 8 is rotated, and the two clamping rods 10 are pushed into the first clamping grooves 11 of the groove walls at both ends of the second groove 7 through the curved rods 9 at both ends of the rotating bar 8. The rotating rod 6 is rotated in the first groove 3 to drive the rotating bar 8 to rotate in the second groove 7 on the grid plate 5, and the clamping rod is pushed through the two curved rods 9. 10 is inserted into the first slot 11 to realize the installation and fixing of the metal plate 2 on the grid plate 5, and the insertion rod 101 is pressed in the slot 201 on the rotating rod 6 to drive the cross bar 102 to be inserted into the two limit blocks 202. After the card rod 10 is inserted into the first slot 11, the insertion rod 101 can be moved in the slot 201 on the rotating rod 6, driving the cross bar 102 on the insertion rod 101 to be inserted into the two limit blocks 202, limiting the card rod 10, and improving the installation firmness of the metal plate 2. The rotating rod 6 and the insertion rod 101 are both quadrilateral column rods, and the limit block 202 is a U-shaped block. While the insertion rod 101 can move in the slot 201 at the end of the rotating rod 6, the insertion rod 101 can also drive the rotating rod 6 to rotate, so that the operator can rotate the rotating rod 6 through the cross bar 102, and the operation is more labor-saving;

[0040] S4, thermal insulation foam filling: filling thermal insulation foam between the installation frame 1, the grid plate 5 and one of the metal plates 2;

[0041] S5. Elastic polyurethane aerogel filling: after the foam glue is dried, the elastic polyurethane aerogel is filled;

[0042] S6. Fix another metal plate 2 on the mounting frame 1 by repeating step S3 and inserting the sealing cover 4 into the first groove 3. Inserting the sealing cover 4 into the first groove 3 can play a waterproof role in the first groove 3. In the process of inserting the sealing cover 4, the card 301 is driven to slide from the guide groove 303 to the second groove 302 to clamp the sealing cover 4. The card 301 is an elastic rubber sheet, and the inner groove wall of the guide groove 303 is an inclined surface. In the process of inserting the sealing cover 4 into the first groove 3, due to the guidance of the guide groove 303 on the card 301 and the elastic deformation ability of the card 301 itself, it is smoothly clamped into the second groove 302, and then the sealing cover 4 is fixed in the first groove 3 to prevent the sealing cover 4 from falling off, and the protection effect is better. The outer edge diameter of the sealing cover 4 is 1.3 times the inner diameter of the first groove 3. After the sealing cover 4 is inserted into the first groove 3, its edge is driven to press against the metal plate 2, so that the sealing cover 4 has a better sealing performance.

[0043] S7. Fix the installation frame 1 to the exterior wall by fastening the frame 1 to the exterior wall through the threaded holes at the four corners of the frame 1 with bolts. This way, the thermal insulation metal integrated panel can be installed on the exterior wall.

[0044] The above are all preferred embodiments of the present invention, and are not intended to limit the scope of protection of the present invention. Therefore, any equivalent changes made based on the structure, shape, and principle of the present invention should be included in the scope of protection of the present invention.

Claims

1. The construction process of the external wall insulation metal integrated panel is characterized by: The following steps are involved: S1. Arrange the installation frame (1), wherein the grid plate (5) and the installation frame (1) are integrally formed; S2. Install one of the metal plates (2) on the installation frame (1): insert one of the metal plates (2) into the installation frame (1); S3. Fixing the metal plate (2) on the mounting frame (1) is performed by: in the first groove (3) on the metal plate (2), the operator rotates the rotating rod (6) on the shaped sleeve (12) in the first groove (3), driving the rotating bar (8) at one end of the rotating rod (6), rotating the rotating bar (8) in the second groove (7) on the grid plate (5), and pushing the two clamping rods (10) into the first clamping grooves (11) of the groove walls at both ends of the second groove (7) through the curved rods (9) at both ends of the rotating bar (8); S4, filling with thermal insulation foam: filling thermal insulation foam between the installation frame (1), the grid plate (5) and one of the metal plates (2); S5. Elastic polyurethane aerogel filling: after the foam glue is dried, the elastic polyurethane aerogel is filled; S6. Fix another metal plate (2) on the mounting frame (1) by repeating step S3; S7. Fix the installation frame (1) to the exterior wall by fastening the installation frame (1) to the exterior wall through the threaded holes at the four corners of the installation frame (1).

2. The construction process of the exterior wall thermal insulation metal integrated panel according to claim 1 is characterized by: After fixing the metal plate (2) in step S3 and step S7, the insertion rod (101) is pressed into the slot (201) on the rotating rod (6), driving the cross rod (102) to be inserted into the two limit blocks (202).

3. The construction process of the exterior wall thermal insulation metal integrated panel according to claim 2 is characterized by: In the steps S3 and S7, after the rotating rod (6) is limited, the sealing cover (4) is inserted into the first groove (3).

4. The construction process of the exterior wall thermal insulation metal integrated panel according to claim 3 is characterized by: During the process of inserting the sealing cover (4), the card (301) is driven to slide from the guide groove (303) to the second card groove (302) to clamp the sealing cover (4).

5. The construction process of the exterior wall thermal insulation metal integrated panel according to claim 4 is characterized in that: The card (301) is an elastic rubber sheet, and the inner groove wall of the guide groove (303) is an inclined surface. When the sealing cover (4) is inserted into the first groove (3), the card (301) is smoothly clamped into the second card groove (302) due to the guidance of the guide groove (303) on the card (301) and the elastic deformation ability of the card (301) itself.

6. The construction process of the exterior wall thermal insulation metal integrated panel according to claim 2 is characterized by: The rotating rod (6) and the inserting rod (101) are both quadrilateral columnar rods, and the limiting block (202) is a U-shaped block.

7. The construction process of the exterior wall thermal insulation metal integrated panel according to claim 4 is characterized in that: The outer diameter of the outer edge of the sealing cover (4) is 1.3 times the inner diameter of the first groove (3).

8. The construction process of the exterior wall thermal insulation metal integrated panel according to claim 1 is characterized by: In step S1, the grid plate (5) and the mounting frame (1) are integrally formed.

9. The construction process of the exterior wall thermal insulation metal integrated panel according to claim 1 is characterized by: In step S1, a mounting groove for inserting the metal plate (2) is provided on the mounting frame (1), and the size of the mounting groove is the same as the size of the metal plate (2).

10. The construction process of the exterior wall thermal insulation metal integrated panel according to claim 1, characterized in that: In step S3, the I-shaped sleeve (12) movably passes through the groove wall of the first groove (3), and the rotating rod (6) is fixedly passed through the middle of the I-shaped sleeve (12).

Citation Information

Patent Citations

  • Integrated construction technology for heat-preservation plates

    CN108086495A

  • Construction method of building outer wall heat preservation and insulation system

    CN113482182A