Building vertical opening construction platform and use method thereof
By installing a first lifting mechanism, a second lifting mechanism, and a lifting platform inside the vertical opening, the problem of fixed height of traditional construction platforms is solved, enabling flexible adjustment of the construction platform and cost reduction.
Patent Information
- Application Number
- CN202310460280.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-04-25
- Publication Date
- 2025-11-04
- Estimated Expiration
- 2043-04-25
AI Technical Summary
When constructing vertical openings using traditional ground-mounted scaffolding or cantilevered steel platforms, the construction platform can only be fixed in a specific position and its height cannot be flexibly adjusted, causing inconvenience to workers.
The construction platform design includes a first lifting mechanism, a second lifting mechanism, and a lifting platform. By alternately connecting multiple connecting structures, the height of the lifting platform can be flexibly adjusted.
The construction platform can be adjusted to a high degree of flexibility, which facilitates construction by workers and reduces construction costs.
Smart Images

Figure CN116717067B_ABST
Abstract
Description
TECHNICAL FIELD
[0001] The present application relates to the technical field of building engineering, in particular to a building vertical hole construction platform and a use method thereof. BACKGROUND
[0002] In the process of building construction, especially in the process of super high-rise building construction, the traditional horizontal and vertical structure synchronous construction technology is gradually eliminated, and the vertical structure priority construction has become a trend. Super high-rise buildings usually adopt tube-in-tube or frame-tube structure. These two structures need to construct the inner tube or core tube first, and then construct the outer tube or outer frame. Multiple vertical holes are often set between the shear walls or structural columns of super high-rise buildings. When the vertical holes need to install mechanical and electrical equipment, air pipes, drainage pipes or perform decoration work, a working platform is often set up by using a landing scaffold or a cantilever steel structure.
[0003] However, when the landing scaffold or the cantilever steel platform is used to construct the vertical hole, the construction platform can only be fixed at a specific position of the vertical hole. When the workers stand on the construction platform to work, the height of the construction platform cannot be flexibly adjusted, which is not convenient for the workers to work. SUMMARY
[0004] The technical problem to be solved by the present application is that when the landing scaffold or the cantilever steel platform is used to construct the vertical hole, the construction platform can only be fixed at a specific position of the hole. When the workers stand on the construction platform to work, the height of the construction platform cannot be flexibly adjusted, which is not convenient for the workers to work.
[0005] In order to solve the above technical problems, the purpose of the present application is to provide a building vertical hole construction platform, which comprises a first lifting mechanism, a second lifting mechanism and a lifting platform arranged in a vertical hole. The inner side of the vertical hole is fixed with a plurality of connecting structures, and each connecting structure is arranged in sequence and spaced from top to bottom. The first end of the first lifting mechanism and the first end of the second lifting mechanism are connected to the lifting platform.
[0006] The second end of the first lifting mechanism and the second end of the second lifting mechanism are respectively detachably connected with two connecting structures spaced above and below. The first lifting mechanism drives the lifting platform to rise, so that the second end of the second lifting mechanism is switched to the connecting structure above the second end of the first lifting mechanism, so that the second lifting mechanism drives the lifting platform to rise. Or the first lifting mechanism drives the lifting platform to descend, so that the second end of the second lifting mechanism is switched to the connecting structure below the second end of the first lifting mechanism, so that the second lifting mechanism drives the lifting platform to descend.
[0007] As a preferred solution, the first hoisting mechanism comprises four first hoisting ropes arranged at four corners of the lifting platform, and each first hoisting rope is connected with a first electric hoist at an end away from the lifting platform, and each first electric hoist is detachably connected to the connecting structure.
[0008] The second hoisting mechanism comprises four second hoisting ropes arranged at four corners of the lifting platform, and each second hoisting rope is connected with a second electric hoist at an end away from the lifting platform, and each second electric hoist is detachably connected to the connecting structure.
[0009] As a preferred solution, each floor of the building is provided with a steel structure beam body at a position around the vertical opening, each steel structure beam body is provided with a binding hole, and the second end of the first hoisting mechanism and the second end of the second hoisting mechanism are provided with hooks, and each hook is hung on the corresponding binding hole.
[0010] As a preferred solution, the outer side of each steel structure beam body is bound with a rope sleeve, and each hook is hung on the corresponding rope sleeve.
[0011] As a preferred solution, two cable wind ropes are symmetrically arranged on both sides of the lifting platform, and each cable wind rope extends downward at an angle and is bound to the corresponding connecting structure at an end away from the lifting platform.
[0012] As a preferred solution, the lifting platform comprises a bottom plate and a guardrail arranged around the periphery of the bottom plate, and the bottom periphery of the guardrail is provided with a skirting board.
[0013] As a preferred solution, the guardrail comprises vertical rods arranged at intervals around the periphery of the bottom plate, and a horizontal rod is connected between two adjacent vertical rods, and the lower end of each vertical rod is detachably connected to the edge of the bottom plate.
[0014] A use method of the building vertical opening construction platform described above, comprising the following steps:
[0015] Step S1, connecting the second end of the first hoisting mechanism to the connecting structure at the top of the vertical opening, so that the lifting platform is located at the top of the vertical opening;
[0016] Step S2, constructing the first position of the vertical opening;
[0017] Step S3, driving the lifting platform to descend to the first set position by the first hoisting mechanism;
[0018] Step S4, connecting the second end of the second hoisting mechanism to the connecting structure below the second end of the first hoisting mechanism;
[0019] Step S5, the second end of the first hoisting mechanism is detached from the connection structure above the second end of the second hoisting mechanism, a second position of the vertical hole is constructed, and the second position is below the first position;
[0020] Step S6, the lifting platform is driven to descend to a second set position by the second hoisting mechanism;
[0021] Step S7, the second end of the first hoisting mechanism is connected to the connection structure below the second end of the second hoisting mechanism;
[0022] Step S8, the second end of the second hoisting mechanism is detached from the connection structure above the second end of the first hoisting mechanism, a third position of the vertical hole is constructed, and the third position is below the second position;
[0023] Step S9, steps S3 to S8 are cycled until the lifting platform descends to the bottom of the vertical hole.
[0024] As a preferred solution, the step S1, the step S4 and the step S7 all include that a cable wind rope is tied on the connection structure below the lifting platform;
[0025] The step S2 and the step S3, the step S5 and the step S6, and the step S8 and the step S9 all include that the cable wind rope is detached from the connection structure below the lifting platform.
[0026] As a preferred solution, the step S1 includes that the second end of the first hoisting mechanism is connected to the connection structure at the top of the vertical hole, including the following steps:
[0027] Step S11, the lifting platform is assembled at the bottom of the vertical hole;
[0028] Step S12, the first end of the first hoisting mechanism and the first end of the second hoisting mechanism are both connected to the lifting platform;
[0029] Step S13, the second end of the first hoisting mechanism and the second end of the second hoisting mechanism are alternately connected to each connection structure, so that the lifting platform ascends to the top of the vertical hole.
[0030] Compared with the prior art, the present application has the following beneficial effects:
[0031] The vertical opening construction platform of the present invention includes a first lifting mechanism, a second lifting mechanism, and a lifting platform disposed within the vertical opening. Multiple connecting structures are fixed to the inner side of the vertical opening, arranged sequentially and at intervals from top to bottom. The first end of both the first and second lifting mechanisms is connected to the lifting platform. The second ends of the first and second lifting mechanisms are detachably connected to two vertically spaced connecting structures, respectively. The first lifting mechanism drives the lifting platform upwards, causing the second end of the second lifting mechanism to switch to the connecting structure located above the second end of the first lifting mechanism, thus causing the second lifting mechanism to drive the lifting platform upwards; or the first lifting mechanism drives the lifting platform downwards, causing the second end of the second lifting mechanism to switch to the connecting structure located below the second end of the first lifting mechanism, thus causing the second lifting mechanism to drive the lifting platform downwards. Therefore, the vertical opening construction platform of the present invention, by alternately connecting the first and second lifting mechanisms to the connecting structures, can flexibly adjust the height of the lifting platform, facilitating worker construction. Attached Figure Description
[0032] Figure 1 This is a schematic diagram showing the lifting platform in the middle of the vertical opening;
[0033] Figure 2 This is a schematic diagram of the construction process of the lifting platform at the top of the vertical opening;
[0034] Figure 3 A schematic diagram showing the top floor of the vertical opening after the lifting platform has been completed and lowered.
[0035] Figure 4 The front view shows the connection between the lifting platform and the lifting mechanism.
[0036] Figure 5 An isometric view of the connection between the lifting platform and the jacking mechanism;
[0037] Figure 6 This is a top view of the lifting platform;
[0038] Figure 7 for Figure 6 Enlarged view at point D;
[0039] Figure 8 for Figure 6 Enlarged view at point C;
[0040] Figure 9 for Figure 5 Top view at point E in the middle;
[0041] Figure 10 for Figure 5 Side view at point E in the middle;
[0042] Figure 11 for Figure 4 Enlarged view of point B in the middle;
[0043] Figure 12 For Figure 4 the sectional view at B;
[0044] Figure 13 For Figure 4 the sectional view at B;
[0045] Figure 14 For Figure 1 the enlarged view at A;
[0046] Figure 15 For Figure 1 the enlarged view at F;
[0047] In the figure, 1, first hoisting mechanism; 11, first hoisting rope; 12, first electric hoist; 2, second hoisting mechanism; 21, second hoisting rope; 22, second electric hoist; 3, lifting platform; 31, bottom plate; 311, cross beam; 312, longitudinal beam; 313, anti-skid steel plate; 314, longitudinal rib plate; 315, first angle iron; 316, second angle iron; 317, third angle iron; 318, U-shaped bolt; 319, nut; 32, guardrail; 321, vertical rod; 322, horizontal rod; 323, first connecting plate; 324, second connecting plate; 325, first screw rod; 326, second screw rod; 33, skirting board; 4, steel structure beam body; 41, rope sleeve; 5, cable wind rope; 6, vertical hole; 7, air pipe. DETAILED DESCRIPTION
[0048] The specific embodiments of the present application will be further described in conjunction with the accompanying drawings and examples. The following examples are used to illustrate the present application, but not to limit the scope of the present application.
[0049] In the description of the present application, it should be understood that the terms "upper", "lower", "left", "right", "top", "bottom", etc. indicate the orientation or positional relationship shown in the drawings, and are only for the convenience of describing the present application and simplifying the description, and do not indicate or imply that the devices or elements referred to must have a particular orientation, be constructed and operated in a particular orientation, and therefore cannot be understood as a limitation on the present application. It should be understood that the terms "first", "second", etc. are used to describe various information in the present application, but these information should not be limited to these terms, and these terms are only used to distinguish the same type of information from each other. For example, the "first" information can also be referred to as "second" information without departing from the scope of the present application, and similarly, the "second" information can also be referred to as "first" information.
[0050] As Figure 1As shown, the preferred embodiment of the building vertical opening construction platform of the present application comprises a first lifting mechanism 1, a second lifting mechanism 2 and a lifting platform 3 arranged in the vertical opening 6, the inner side of the vertical opening 6 is fixed with a plurality of connecting structures, each connecting structure is arranged in sequence and spaced from top to bottom; the first end of the first lifting mechanism 1 and the first end of the second lifting mechanism 2 are both connected with the lifting platform 3; the second end of the first lifting mechanism 1 and the second end of the second lifting mechanism 2 are respectively detachably connected with the two connecting structures spaced from top to bottom; the first lifting mechanism 1 drives the lifting platform to rise, so that the second end of the second lifting mechanism 2 is switched to the connecting structure above the second end of the first lifting mechanism 1, so that the second lifting mechanism 2 drives the lifting platform 3 to rise; or the first lifting mechanism 1 drives the lifting platform 3 to descend, so that the second end of the second lifting mechanism 2 is switched to the connecting structure below the second end of the first lifting mechanism 1, so that the second lifting mechanism 2 drives the lifting platform 3 to descend. Therefore, the building vertical opening construction platform of the present application can flexibly adjust the height of the construction platform by alternately connecting the first lifting mechanism 1 and the second lifting mechanism 2 to the connecting structure, which is convenient for workers to work. In addition, when using the floor type scaffold, the height of the scaffold body increases continuously as the construction floor increases, the load of the bottom scaffold body also increases, and a large amount of steel is consumed, the construction process is complex and the construction cost is high; when using the cantilever type steel platform, the embedded steel bars are usually used to connect the scaffold to the wall, during the construction process of the shear wall, before pouring concrete in the shear wall, one end of the embedded steel bar is welded with the steel bar frame in the wall according to the design drawing, so as to position each embedded part and connect it to the steel bar frame in the shear wall, after pouring concrete in the shear wall, the other end of the embedded part extends out of the shear wall to connect the scaffold, after the completion of the scaffold construction, in order to avoid the rust of the embedded steel bar leading to the rust of the steel bar frame in the shear wall, the extending end of the embedded steel bar also needs to be treated to prevent rust, the construction process is complex and the construction cost is high; the building vertical opening construction platform of the present application has lower construction cost than the floor type scaffold and the cantilever type steel platform.
[0051] Specifically, as shown in Figure 4 、 Figure 5 、 Figure 11 The first lifting mechanism 1 comprises four first lifting ropes 11 arranged at the four corners of the lifting platform 3, one end of each first lifting rope 11 away from the lifting platform 3 is connected with a first electric hoist 12, and each first electric hoist 12 is detachably connected with each connecting structure;
[0052] The second lifting mechanism 2 includes four second lifting ropes 21 located at the four corners of the lifting platform 3. Each second lifting rope 21 has a second electric hoist 22 connected to its end furthest from the lifting platform 3. Each second electric hoist 22 can be detachably connected to its respective connecting structure. In this embodiment, four first lifting ropes 11, four first electric hoists 12, four second lifting ropes 21, and four second electric hoists 12 are provided. The four first lifting ropes 11 and four second lifting ropes 21 are respectively located at the four corners of the base plate.
[0053] Among them, such as Figure 14 As shown, each floor of the building has steel structural beams 4 located around the vertical openings 6. Each steel structural beam 4 has binding holes. The second end of the first lifting mechanism 1 and the second end of the second lifting mechanism 2 are equipped with hooks, which are respectively attached to the corresponding binding holes. The steel structural beams 14 are the steel beam nodes around the floor openings of the high-rise building. No additional construction is required. The steel structural beams 14 are used as lifting points, and in conjunction with electric hoists, the lifting platform 3 is raised and lowered. No drilling or pre-embedding is required, and the stability is good.
[0054] Specifically, each steel structure beam 4 has a rope loop 41 tied to its outer side, and each hook is attached to the corresponding rope loop 41, forming a connecting structure. The rope loop 41 is a steel wire rope, which is detachably connected to the steel structure beam 4. After construction is completed, the steel wire rope can be removed from the steel structure beam 4, allowing it to be reused, further reducing the construction cost of the vertical opening construction platform of this invention.
[0055] To ensure the stability of the lifting platform, in this embodiment, as follows: Figure 1 , Figure 2 , Figure 3 , Figure 15 As shown, two guy ropes 5 are symmetrically arranged on both sides of the lifting platform 3. The end of each guy rope 5 away from the lifting platform 3 extends downward at an angle and is tied to the corresponding connecting structure. Specifically, one of the two guy ropes 5 is located on one side of the lifting platform 3, and the other guy rope 5 is located on the other side of the lifting platform 3. The two guy ropes 5 are arranged symmetrically about the center of the lifting platform 3, thereby ensuring the stability of the lifting platform 3.
[0056] In this embodiment, the lifting platform 3 includes a base plate 31 and a protective railing 32 arranged around the periphery of the base plate 31. A kick plate 33 is provided on the bottom periphery of the protective railing 32. The kick plate can prevent materials or debris from falling outside the lifting platform 3, thus ensuring construction safety.
[0057] The guardrail 32 includes vertical bars 321 arranged at intervals around the periphery of the base plate 31. A horizontal bar 322 is connected between each pair of adjacent vertical bars 321. The lower end of each vertical bar 321 can be detachably connected to the edge of the base plate 31.
[0058] Specifically, as shown in Figures 4 to 10 The bottom plate 31 includes a cross beam 311 and a longitudinal beam 312, which enclose a square frame, and the cross beam 311 and the longitudinal beam 312 are connected by a second angle iron 316 and a third angle iron 317. To ensure the stability of the bottom plate 31, a plurality of longitudinal rib plates 314 are connected to the cross beam 311 in the axial direction, and the longitudinal rib plates 314 are connected to one side of the cross beam 311 by a first angle iron 315. Figure 9 、 Figure 10 The vertical rod 321 is two parallel and spaced steel pipes, and the lower part of each steel pipe is welded with a first connecting plate 323. Specifically, the first connecting plate 323 is provided with two spaced first mounting holes, and the lower part of each steel pipe is provided in and welded in the first mounting hole. The cross beam 311 is arranged between the two steel pipes, and the lower end of the first connecting plate 323 abuts against the upper end of the cross beam 311. The lower end of each steel pipe is sleeved with a second connecting plate 324. Specifically, the second connecting plate is provided with two spaced second mounting holes, and the two second mounting holes are coaxially arranged with the corresponding first mounting holes. The lower end of each steel pipe is provided in the corresponding second mounting hole. The first connecting plate 323 and the second connecting plate 324 are connected with a first screw 325 and a second screw 326. The lower end of the first screw 325 and the lower end of the second screw 326 are both provided through the second connecting plate 324 and connected with a nut. By screwing the nut, the first connecting plate and the second connecting plate can be moved closer to each other to clamp the cross beam 311, or the first connecting plate and the second connecting plate can be moved away from each other, so that the vertical rod 321 can be removed from the cross beam 311.
[0059] In this embodiment, as shown in Figures 11 to 13 The end of the cross beam 311 is provided with a U-shaped bolt 318, and the threaded end of the U-shaped bolt 318 is provided through the cross beam 311 and connected with a nut 319, so that the U-shaped bolt 318 is detachably connected to the cross beam 311. The first hoisting rope 11 and the second hoisting rope 21 are both connected to the U-shaped bolt. Specifically, the U-shaped bolt is arranged at an angle of 80° with the cross beam 311, and the first hoisting rope and the second hoisting rope are both made of an 8-fold safety factor and a 20mm fiber core steel wire rope.
[0060] An embodiment of a method for using the building vertical opening construction platform described above, comprising the following steps:
[0061] Step S1, connecting the second end of the first hoisting mechanism 1 to the connecting structure located at the top of the vertical opening 6, so that the lifting platform 3 is located at the top of the vertical opening 6;
[0062] Step S2, the first position of the vertical hole 6 is constructed; specifically, before construction, the components and their accessories that need to be installed are transported to the floor where they need to be installed by construction elevators or manually and placed next to the lifting platform 3. The construction content includes water pipes or air pipes 7, and the height of the lifting platform 3 can be adjusted by the first lifting mechanism 1 during construction to facilitate worker operation.
[0063] Step S3, the lifting platform 3 is lowered to the first set position by the first lifting mechanism 1; specifically, after the top air pipe 7 or drain pipe and other construction is completed, the lifting platform 3 is lowered to the lower limit position of the first lifting mechanism.
[0064] Step S4, the second end of the second lifting mechanism 2 is connected to the connecting structure below the second end of the first lifting mechanism 1;
[0065] Step S5, the second end of the first lifting mechanism 1 is removed from the connecting structure above the second end of the second lifting mechanism 2, and thereafter, the height of the lifting platform 2 is adjusted step by step downward by the second lifting mechanism 2, thereby facilitating the worker to construct the second position of the vertical hole 6, which is below the first position;
[0066] Step S6, the lifting platform 3 is lowered to the second set position by the second lifting mechanism 2; specifically, after the second position is constructed, the second lifting mechanism 2 falls to the limit position.
[0067] Step S7, the second end of the first lifting mechanism 1 is connected to the connecting structure below the second end of the second lifting mechanism 2;
[0068] Step S8, the second end of the second lifting mechanism 2 is removed from the connecting structure above the second end of the first lifting mechanism 1, and the third position of the vertical hole 6 is constructed, which is below the second position;
[0069] Step S9, steps S3 to S8 are repeated until the lifting platform 3 is lowered to the bottom of the vertical hole 6.
[0070] Among them, steps S1, S4 and S7 all include binding the cable wind rope 5 to the connecting structure below the lifting platform 3;
[0071] Between steps S2 and S3, between steps S5 and S6, and between steps S8 and S9, the cable wind rope 5 is removed from the connecting structure below the lifting platform 3.
[0072] In this embodiment, in step S1, the second end of the first lifting mechanism 1 is connected to the connecting structure at the top of the vertical hole 6, which includes the following steps:
[0073] Step S11, assembling the lifting platform 3 at the bottom of the vertical hole 6;
[0074] Step S12, connecting the first end of the first lifting mechanism 1 and the first end of the second lifting mechanism 2 on the lifting platform 3;
[0075] Step S13, alternately connecting the second end of the first lifting mechanism 1 and the second end of the second lifting mechanism 2 on each connecting structure, so as to lift the lifting platform 3 to the top of the vertical hole 6. Specifically, the process of lifting the lifting platform is similar to the operation method of lowering the lifting platform 2.
[0076] In summary, the building vertical hole construction platform of the present application comprises a first lifting mechanism 1, a second lifting mechanism 2 and a lifting platform 3 arranged in the vertical hole 6. The inner side of the vertical hole 6 is fixed with a plurality of connecting structures, and each connecting structure is arranged in sequence and spaced from top to bottom. The first end of the first lifting mechanism 1 and the first end of the second lifting mechanism 2 are connected to the lifting platform 3. The second end of the first lifting mechanism 1 and the second end of the second lifting mechanism 2 are respectively detachably connected to the two connecting structures spaced above and below. The first lifting mechanism 1 drives the lifting platform to rise, so that the second end of the second lifting mechanism 2 is switched to the connecting structure above the second end of the first lifting mechanism 1, so that the second lifting mechanism 2 drives the lifting platform 3 to rise. Or the first lifting mechanism 1 drives the lifting platform 3 to descend, so that the second end of the second lifting mechanism 2 is switched to the connecting structure below the second end of the first lifting mechanism 1, so that the second lifting mechanism 2 drives the lifting platform 3 to descend. Therefore, the building vertical hole construction platform of the present application can flexibly adjust the height of the construction platform by alternately connecting the first lifting mechanism 1 and the second lifting mechanism 2 on the connecting structure, which is convenient for workers to work. Moreover, the building vertical hole construction platform of the present application has lower construction cost compared with the floor type scaffold and cantilever type steel platform.
[0077] The above is only the preferred embodiment of the present application, and it should be pointed out that for ordinary skilled in the art, without departing from the technical principles of the present application, a number of improvements and replacements can be made, which should be considered as the protection scope of the present application.
Claims
1. A construction platform for vertical openings in a building, characterized in that, It includes a first lifting mechanism (1), a second lifting mechanism (2), and a lifting platform (3) set in a vertical opening (6). Multiple connecting structures are fixed on the inner side of the vertical opening (6), and the connecting structures are arranged at intervals from top to bottom. The first end of the first lifting mechanism (1) and the first end of the second lifting mechanism (2) are both connected to the lifting platform (3). The second end of the first lifting mechanism (1) and the second end of the second lifting mechanism (2) are detachably connected to two connecting structures spaced vertically apart. The first lifting mechanism (1) drives the lifting platform to rise, so that the second end of the second lifting mechanism (2) switches to the connecting structure located above the second end of the first lifting mechanism (1), so that the second lifting mechanism (2) drives the lifting platform (3) to rise; or the first lifting mechanism (1) drives the lifting platform (3) to fall, so that the second end of the second lifting mechanism (2) switches to the connecting structure located below the second end of the first lifting mechanism (1), so that the second lifting mechanism (2) drives the lifting platform (3) to fall. The first lifting mechanism (1) includes four first lifting ropes (11) arranged at the four corners of the lifting platform (3). Each first lifting rope (11) is connected to a first electric hoist (12) at the end away from the lifting platform (3). Each first electric hoist (12) can be detachably connected to each of the connecting structures. The second lifting mechanism (2) includes four second lifting ropes (21) set at the four corners of the lifting platform (3). Each second lifting rope (21) is connected to a second electric hoist (22) at the end away from the lifting platform (3). Each second electric hoist (22) can be detachably connected to each of the connecting structures. The lifting platform (3) includes a base plate (31) and a guardrail (32) arranged around the periphery of the base plate (31); The base plate (31) includes a crossbeam (311) and a longitudinal beam (312), which together form a square frame. A U-bolt (318) is inserted through the end of the crossbeam (311), and the threaded end of the U-bolt (318) passes through the crossbeam (311) and is screwed with a nut (319), thereby detachably connecting the U-bolt (318) to the crossbeam (311). The first hoisting rope (11) and the second hoisting rope (21) are both connected to the U-bolt (318).
2. The construction platform for vertical openings in a building according to claim 1, characterized in that, Each floor of the building is provided with a steel structure beam (4) at the position around the vertical opening (6). Each steel structure beam (4) is provided with a binding hole. The second end of the first lifting mechanism (1) and the second end of the second lifting mechanism (2) are provided with hooks. Each hook is respectively hung on the corresponding binding hole.
3. The construction platform for vertical openings in a building according to claim 2, characterized in that, Each of the steel structure beams (4) is bound with a rope loop (41) on its outer side, and each of the hooks is hung on the corresponding rope loop (41).
4. The construction platform for vertical openings in a building according to claim 1, characterized in that, Two guy ropes (5) are symmetrically arranged on both sides of the lifting platform (3). The end of each guy rope (5) away from the lifting platform (3) extends downward at an angle and is tied to the corresponding connecting structure.
5. The construction platform for vertical openings in a building according to claim 1, characterized in that, The bottom perimeter of the guardrail (32) is provided with a kick plate (33).
6. The construction platform for vertical openings in a building according to claim 5, characterized in that, The guardrail (32) includes vertical bars (321) arranged at intervals around the periphery of the base plate (31), and a horizontal bar (322) is connected between two adjacent vertical bars (321). The lower end of each vertical bar (321) can be detachably connected to the edge of the base plate (31).
7. A method of using the construction platform for a vertical opening in a building as described in any one of claims 1 to 6, characterized in that, Includes the following steps: Step S1: Connect the second end of the first lifting mechanism (1) to the connecting structure located at the top of the vertical opening (6), so that the lifting platform (3) is located at the top of the vertical opening (6); Step S2: Construct the first position of the vertical opening (6); Step S3: Drive the lifting platform (3) to descend to the first set position through the first lifting mechanism (1); Step S4: Connect the second end of the second lifting mechanism (2) to the connection structure located below the second end of the first lifting mechanism (1); Step S5: Remove the second end of the first lifting mechanism (1) from the connecting structure located above the second end of the second lifting mechanism (2), and carry out construction on the second position of the vertical opening (6), which is located below the first position; Step S6: Drive the lifting platform (3) to descend to the second set position via the second lifting mechanism (2); Step S7: Connect the second end of the first lifting mechanism (1) to the connecting structure located below the second end of the second lifting mechanism (2); Step S8: Remove the second end of the second lifting mechanism (2) from the connecting structure located above the second end of the first lifting mechanism (1), and carry out construction on the third position of the vertical opening (6), which is located below the second position; Step S9, repeat steps S3 to S8 until the lifting platform (3) descends to the bottom of the vertical opening (6); In step S1, connecting the second end of the first lifting mechanism (1) to the connecting structure located at the top of the vertical opening (6) includes the following steps: Step S11: Assemble the lifting platform (3) at the bottom of the vertical opening (6); Step S12: Connect the first end of the first lifting mechanism (1) and the first end of the second lifting mechanism (2) to the lifting platform (3); Step S13: Alternately connect the second end of the first lifting mechanism (1) and the second end of the second lifting mechanism (2) to each of the connecting structures so that the lifting platform (3) rises to the top of the vertical opening (6).
8. The method of using the construction platform for vertical openings in a building according to claim 7, characterized in that, Step S1, step S4 and step S7 all include tying the guy rope (5) to the connecting structure located below the lifting platform (3); The steps between S2 and S3, between S5 and S6, and between S8 and S9 all include removing the guy rope (5) from the connecting structure located below the lifting platform (3).
Citation Information
Patent Citations
Operating platform for mounting external window of building
CN2581615Y